Professional Documents
Culture Documents
Asset No
Project
Location
Sheet No
Date
Client
1. Disconnect all electric power, including remote disconnects before servicing. Follow proper lockout/tagout procedures
to ensure the power cannot be inadvertently energized. Failure to disconnect power before servicing could result in
death or serious injury. Unless directed differently in the instructions below.
2. You must wait until all surfaces cool down and all moving parts completely standstill.
3. You must ensure that proper PPE (personal protective equipment) is always worn while working.
4. You must set up appropriate SAFETY BARRIERS & SIGNS when performing any work.
5. You must measure and record the system parameters before and after the maintenance
SCHEDULE OF FREQUENCY Annually
EQUIPMENT DESCRIPTION Air Handling Unit/FAHU
Please obtain work permit from the client to carry any of the below tasks.
Turn OFF the FAHU and isolate.
Attach a “Lock Out” tag on the electrical panel.
FILTERS
Primary Filters
Remove and wash primary pleat filters.
Check the clean filters are correctly seated to eliminate all air bypasses.
FAN BELTS
Inspect belts for wear and damage; replace if necessary.
Check for correct belt tension, adjust if necessary.
BEARINGS
Check the condition of Motor & Blower bearings. Apply grease or replace if necessary.
PULLEYS
Check the alignment of the V-belt drive using a straight edge; Correct / re-align as required.
Tighten grub screws on motor pulley and fan pulley.
Inspect pulleys and shafts for corrosion. If rust is found, wire brush the surfaces and treat with rust converter.
FAN
Clean the surfaces of the fan impeller using a damp cloth, if necessary. There should never be any accumulation of dirt
on the fans as this would indicate that the filter system is not being correctly maintained.
Check the flexible discharge connection for any signs of wear and any leaks. Repair if the connections are suspected.
Check for any signs of wear or play on the fan shaft.
ELEGANCIA FACILITY MANAGEMENT SERVICE Management Procedure (IMS)
DRIP PAN
Remove any large dirt particles of foreign matter, which may affect the drainage of the condensate water.
Clean condensate drip pan using a hose pipe and rags and check drains run ‘‘Free”.
UNIT CASING
To provide a clean and neat appearance of the air handling unit for their full life span, clean the external and internal
surfaces of the casing with a damp cloth.
Inspect the surfaces for rust. If rust is found, sand the surface, treat with rust converter and repaint with the original
paint color.
GENERAL
Inspect access door latches and hinges; replace if broken.
Check all air ducts
Check the dampers for free and unobstructed movement; secure mounting of turning vanes; thermal insulation;
acoustic lining; sensing elements and check for any damages.
Restart the unit with the access door open and check for any abnormal noise. Great care should be taken when starting
the unit. (Inform other fellow workers that the unit is about to start)
If abnormalities are found, identify the problem and report to your supervisor.
Check the unit controls and record the parameters.
REPORT ALL DEFECTS TO DUTY SUPERVISOR AND IF THERE IS ANY DOUBT, PLEASE REFER TO THE MANUFACTURERS’ INSTRUCTION MANUAL.
ELEGANCIA FACILITY MANAGEMENT SERVICE Management Procedure (IMS)
SPECIFICATIONS
Voltage
Amperage
Phase
OBSERVATIONS / CONDITION OF THE UNIT
Blower Motor Ampere (A) R Y B
Line Voltage L-1: L-2: L-3:
Chilled Water Pressure In: Out:
Chilled Water Temperature In: Out: