PRESERVATION Inspection & Test Record

PRES-L-01 Pre-Fabricated Pipe Spool

Project Name:
Tag No:
Description:

Subsystem:
System:

Location: ModelNo: Manufacturer:


SerialNo: LayoutDwg: Calibration Date:

Item Description Period OK N/A PL Comments


1 ONGOING INSPECTION CHECK LIST
1.01 Confirm material are clean and, stored indoor. All materials such as: Tubing, Piping components of Ongoing
≤ 2 inches, Pipe Fittings of ≤ 1.5 inches, all stainless steel and other exotic materials fitting and
flanges, Valves of ≤ 1.5 inches, Specialty item of ≤ 2 inches, Spring support, Special tools, all stud
and anchor bolts etc. shall be stored in this condition.
1.02 Material stored outside shall be well covered such as tarpaulin to prevent rain water, particle/dust Ongoing
and dirt from accumulating. Material shall be laid on wooden beams clearly above soil and shall be
stacked in a slope for facilitate self-draining. Materials shall not touch ground or water pool at any
case. The following material shall be stored in this condition:
- Austenitic or Duplex stainless-steel pipes may be stored outdoor in original packaging.
Provide sheet covering as required when original package is removed.
- Piping component of > 2 inches.
- Pipe fittings of > 1.5 inches.
- Valves of > 1.5 inches.
- Specialty item of > 2 inches
1.03 Pipe storage area must be self-draining, concrete paved or decked. Ongoing
1.04 The warehouse will properly mark the pipe and fittings in order to keep the different alloys Ongoing
separated. Stainless steel and other exotic piping spool and materials shall be stored separately
from Carbon Steel Materials.
1.05 After unloading of shop fabricated pipe, an inspection should be made to ensure pipe spools are Ongoing
not damaged and all end covers are in place. Any missing end covers shall be replaced.
1.06 All random length pipes shall be identified as specified. Ongoing

1.07 Protection covers and plugs shall be of original packing for all materials. If water or dirt ingress due Ongoing
to damaged or improperly secured covers, the pipes shall be cleaned and covered with durable
end caps.
1.08 Check equipment is free from mechanical damage. Ongoing
1.09 Confirm all paint/surface coatings are free from damage. Ongoing
1.10 Plastic wrapping shall be removed for outdoor storage. Ongoing
1.11 Ensure material that is installed is protected suitably from any ongoing construction activities to Ongoing
prevent any damage.
1.12 Confirm preservation tag or label is fitted & updated. Ongoing

2 MONTHLY INSPECTION CHECK LIST


2.01 The end protection shall be inspected and securely installed in monthly basis, and repair them as Monthly
necessary.
Comments:

Note: Tick all check item under OK - Satisfactory; N/A - Not Applicable; Punch items(s) are to be PL.

Contractor Company
Data Input
Performed By Checked By Checked By Accepted By Witnessed By

Company / Dept.: Construction Spv. / CCMS Coord./


QC Inspector QC Inspector QC Lead Operation
Pre-Comm. Eng. Operator

Name:

Signature:

Date:

11