Method Statement for Installation


of
“Condensate Ceiling Clean-Out”

TABLE OF CONTENTS

1 Purpose ......................................................................................................................

2 References ................................................................................................................

3 Tools, Materials & Equipment ...................................................................................

4 Pre Requirements before Installation .....................................................................

5 Sequence of Work ....................................................................................................

6 Safety .........................................................................................................................

1 of 4
HVAC Air Leak Test
ABDEL th
710 Suite, 7 Floor Trinity Plaza Tower
CONSTRUCTION Gorordo Avenue, Cebu City, Philippines
CORPORATION Tel : (032) 233-5515/ 233-5577

1 PURPOSE

This method statement covers on-site installation of all condensate UPVC


drain ceiling clean-out for fan coil drains located at all common comfort
rooms.
The mechanical method statement defines the method that will be used
to ensure the purposed of the condensate drain ceiling clean-out for the
condensate drain work system comprising all the pipes, fittings, supports
and hangers, all accessories and components will be installed, as an
integrated piping system.

2 REFERENCES

 Contract Specification
 Approve materials specification
 Approved As-Built Plan

3 Tools, Materials & Equipment

1. Halogen Lamp/ Fog Light 500 6. Sanitary UPVC Fittings (Wye &
Watts Clean-Out)
2. Scaffolding/Ladder 7. Aero Tape
3. Sealant/PVC Cement 8. Polyethylene Tape
4. Rubber Insulations 9. Rubber Cement
5. Sanitary UPVC Pipe S600 10. Pipe Cutter

4 Pre Requirements Before Installation

All materials and documentation relevant to condensate drain ceiling


clean-out piping works will be checked by the site engineers/supervisor
prior to the commence of work ensuring that these are of the correct
type as per approved submittals and approved by the client.

Prior to the commencement of works, areas and access will be inspected


to confirm that they are in a suitable condition for pipe installation works
to commence.
Before commencement any works activity, pre-inspections will be carried
out on all material prior to them leaving the storage area.

2 of 4
HVAC Air Leak Test
ABDEL th
710 Suite, 7 Floor Trinity Plaza Tower
CONSTRUCTION Gorordo Avenue, Cebu City, Philippines
CORPORATION Tel : (032) 233-5515/ 233-5577

5 Sequence of Work

Site supervisors will coordinate with the building admin engineering


team before commencing works to make sure no further damages will
happen.

Ensure that all fan coil units (FCU) that connected to the condensate
drain line are not functioning or not in operation. This will prevent the
flooding during the installation of the ceiling clean-out.

 Make a manhole on ceiling near the condensate ceiling clean-


out to be installed.
 Clear area above ceiling before commences on works such
electrical wires and other obstruction for the works.
 Cut the condensate drain line, drain the remaining condensate
water, clean and dry the cut pipes before connecting the UPVC
WYE fittings then apply adhesive on both ends. Cut a UPVC pipes
around 100mm to 200mm then connect to the fittings and install
the clean-out on the end of the UPVC nipple.
 Cure the adhesive first and then coordinate to the engineering
admin team for the flow test.
 The flow test passes and proceeds to insulate the installed
condensate ceiling clean-out.
 Cut the rubber insulation properly and apply rubber cement for
the connection on both ends. After connected tape it with aero
tape on the jointed end to make sure no condensate water will
flow on the joints.
 Wrap the finished insulated ceiling clean-out with polyethylene
tape.

6. Safety

1. Prior to commencement, all activities shall be coordinated with the


project safety officer, who will assess the associated risks if any, and
monitor the implementation of the project safety plan and liaise with the
construction team to ensure a safe working environment.

2. The safety officer in charge to ensure that all workers are equipped with
their P.P.E throughout the construction work.

3 of 4
HVAC Air Leak Test
ABDEL th
710 Suite, 7 Floor Trinity Plaza Tower
CONSTRUCTION Gorordo Avenue, Cebu City, Philippines
CORPORATION Tel : (032) 233-5515/ 233-5577

3. The safety officer in charge to organize and conduct necessary periodic


toolbox meetings for supervisory staff and manpower, to ensure the
construction team are well aware of safety requirements.

Prepared by:

Engr. Jay-AR Awit


OM/HR Head/SO2

***************************************************************************************