TABLE OF CONTENTS
1 Purpose......................................................................................................................................
2 References.................................................................................................................................
4 Materials...................................................................................................................................
5 Sequence of Work....................................................................................................................
6 Safety.........................................................................................................................................
1 of 3
HVAC Air Leak Test
ABDEL 710 Suite, 7th Floor Trinity Plaza Tower
CONSTRUCTION Gorordo Avenue, Cebu City, Philippines
CORPORATION Tel : (032) 233-5515/ 233-5577
The purpose of method statement is to describe the method of testing HVAC Duct
System for air leak (light test) that will be performed in the scope of Holy Mary Women
& Children Hospital Project at Brgy. Balabag Pavia, Ilo-Ilo City. This statements made
shall be followed by Supervisors & Foremen without omissions.
2 REFERENCES
4 Materials
All materials shall comply with contract specification requirements and approved
material submittals.
5 Sequence of Work
2 of 3
HVAC Air Leak Test
ABDEL 710 Suite, 7th Floor Trinity Plaza Tower
CONSTRUCTION Gorordo Avenue, Cebu City, Philippines
CORPORATION Tel : (032) 233-5515/ 233-5577
6. Safety
1. Prior to commencement, all activities shall be coordinated with the project safety officer,
who will assess the associated risks if any, and monitor the implementation of the
project safety plan and liaise with the construction team to ensure a safe working
environment.
2. The safety officer in charge to ensure that all workers are equipped with their P.P.E
throughout the construction work.
3. The safety officer in charge to organize and conduct necessary periodic toolbox meetings
for supervisory staff and manpower, to ensure the construction team are well aware of
safety requirements.
****************************************************************************
***********
3 of 3