Professional Documents
Culture Documents
➢ Profitability is a term for the measure of the amount of profit that can be
obtained from any given projects.
➢ Aim of profitability analysis is to give a measure of the attractiveness of
the project as compared to other different alternative projects and the
choice of the best investment from various alternatives.
➢ Total profit alone cannot be used as the deciding profitability factor to
make the choice of the best investment from various alternatives.
Therefore, there are the most commonly used methods for profitability
evaluation in addition to total profit.
The most commonly used methods for project (profitability) evaluation are
the following
1) Break even analysis
2) Incremental analysis
3) Ratio analysis (Rate of return on investment and Payback period)
4) Discounting cash flow analysis (Net present value, internal rate of
return, and profitability index)
5) Capitalized costs
1) Break Even Analysis
A technique that describes at which production capacity and selling price
more profit is earned or profit loss occurs
➢ Through a graphical plot of fixed cost, variable cost, total production cost
and total income as function of production capacity.
Variable cost
Loss
Fixed charge
➢ Sometimes, Net profit is not constant from year to year; total investment
also changes if additional investments are made during project operation.
1/n σ𝑛
𝑗=1(𝑁𝑃𝑗)
In such a case, ROI = σ𝑛
where
𝑗=1(𝑇𝐶𝐼𝑗)
n is the project period, NPj is net profit in year j, TCIj is TCI in year j
➢ The calculated ROI can be compared with minimum acceptable rate of return to
judge on project profitability.
➢ If ROI is greater than or equal to minimum acceptable rate of return then the project
is acceptable and profitable.
Table: Suggested values for risk and minimum acceptable return on investment
Disadvantages of ROI
The advantage of ROI is its simplicity to make quick profitability analysis
Its disadvantage includes;
✓ The time value of money (interest) is no considered
✓ All projects are assumed to be similar in nature to each other
✓ It does not take into account the fact that profits and costs may vary
significantly over the life of the project
ⅱ) Payback period (PBP)
➢ PBP is the minimum length of time required to recover the original
capital investment.
Depreciable Fixed Capital Investment FCI
payback period (PBP) = =
Annual Cash flo𝑤 Aj
V+Ax
PBP = if interest is not considered
Aj
,where
V is manufacturing fixed capital investment
Ax is nonmanufacturing fixed capital investment
Aj is annual cash flow = Net profit +depreciation
➢ As a rule PBP =2-3 year for small project and 5-7 for large project
➢ If PBP < Target period then the project is acceptable
➢ If PBP > target period then the project is rejected
depreciable FCI+interest on TCI
payback period (PBP) =
Aj
V+Ax+i on TCI
PBP = if interest is considered
Aj
A positive NPV means that the present value of the inflows is greater than
the present value of outflows, so the project makes a profit.
➢ For evaluating a single project, NPV value greater than 0 is acceptable
and the project is profitable. If NPV <0 then the project is unfavorable
➢ For multiple project comparison, calculate NPV for each project and
select the one with the largest NPV.
➢ If NPV >0, then the project provides the return at a rate greater than the
minimum acceptable rate of return (i).
➢ If NPV =0, then the project provides the return at rate that matches the
minimum acceptable rate of return.
➢ If NPV <0, then the project is unfavorable with respect to the minimum
acceptable rate of return
b) Internal rate of return (IRR) or Discounted cash flow rate of return
Internal rate of return is also known as Discounted cash flow rate of return
➢ It is defined as the value of interest (discount) rate (i) at which NPV at
the end of project life is zero.
CFn
NPV =σ𝑛𝑗=1 − 𝑇𝐶𝐼 = 0
1+𝑖 𝑛