RAB
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi ls 1.00 Rp 15,000,000.00
2 Pemasangan bowplank ls 1.00 Rp 8,000,000.00
3 Pembuatan direksi kit dan gudang material ls 1.00 Rp 7,600,000.00
II PEKERJAAN STRUKTUR
Pondasi
1 Square Pile (350x350) Type A m' 2,916.00 Rp 275,000.00
1 ShearWall 1
Besi D19 Kg
Besi D13 Kg
Bekisting m2
Beton m3
2 ShearWall 2
Besi D19 Kg
Besi D13 Kg
Bekisting m2
Beton m3
Elevasi -5.50
1 Sloof Type S1 (400x800)
- Besi D22 Kg 619.34 Rp 10,000.00
- Besi D19 Kg 77.27 Rp 10,000.00
- Besi D13 Kg 465.30 Rp 10,000.00
- Bekisting m2 26.20 Rp 120,000.00
- Beton m3 4.19 Rp 900,000.00
2 Kolom Type K4 (700x700)
- Besi D22 Kg 910.75 10,000.00
- Besi D13 Kg 404.80 10,000.00
- Bekisting m2 38.64 120,000.00
- Beton (f'c =35 Mpa) m3 4.41 900,000.00
3 Plat Pit Lift
- Besi D19 Kg 3,263.91 10,000.00
- Bekisting m2 63.82 120,000.00
- Beton m3 40.05 900,000.00
Elevasi -4.00
1 Sloof Type S1 (400x800)
- Besi D22 Kg 8,545.46 10,000.00
- Besi D19 Kg 1,066.19 10,000.00
- Besi D13 Kg 7,204.91 10,000.00
- Bekisting m2 413.80 120,000.00
- Beton m3 66.21 900,000.00
2 Sloof Type S2 (350x700)
- Besi D19 Kg 1,766.01 10,000.00
- Besi D16 Kg 250.40 10,000.00
- Besi D13 Kg 938.78 10,000.00
- Bekisting m2 129.97 120,000.00
- Beton m3 16.05 900,000.00
3 Sloof Type S3 (300x500)
- Besi D19 Kg 2,095.09 10,000.00
- Besi D16 Kg 247.55 10,000.00
- Besi D13 Kg 634.83 10,000.00
- Bekisting m2 97.24 120,000.00
- Beton m3 11.22 900,000.00
4 Kolom Type K1 (500x500)
- Besi D19 Kg 3,888.68 10,000.00
- Besi D13 Kg 3,653.48 10,000.00
- Bekisting m2 252.20 120,000.00
- Beton (f'c =35 Mpa) m3 28.13 900,000.00
5 Kolom Type K2A (800x800)
- Besi D22 Kg 2,064.94 10,000.00
- Besi D13 Kg 1,780.92 10,000.00
- Bekisting m2 118.72 120,000.00
- Beton (f'c =40 Mpa) m3 20.16 900,000.00
6 Kolom Type K3 (600x800)
- Besi D22 Kg 5,014.86 10,000.00
- Besi D13 Kg 3,284.02 10,000.00
- Bekisting m2 172.99 120,000.00
- Beton (f'c =30 Mpa) m3 36.72 900,000.00
7 Kolom Type K4 (700x700)
- Besi D22 Kg 2,064.94 10,000.00
- Besi D13 Kg 1,387.19 10,000.00
- Bekisting m2 103.88 120,000.00
- Beton (f'c =35 Mpa) m3 15.44 900,000.00
8 Kolom Type K5 (900x400)
- Besi D19 Kg 216.54 10,000.00
- Besi D13 Kg 189.40 10,000.00
- Bekisting m2 7.63 120,000.00
- Beton (f'c =35 Mpa) m3 1.62 900,000.00
9 Kolom Type K6 (250x250)
- Besi D13 Kg 104.42 10,000.00
- Besi Ø12 Kg 244.02 10,000.00
- Bekisting m2 22.50 120,000.00
- Beton m3 1.41 900,000.00
10 Plat Pit Lift ( Pile Cap )
- Besi D19 Kg 71,197.04 10,000.00
- Bekisting m2 1,146.57 120,000.00
- Beton m3 1,402.24 900,000.00
II PEKERJAAN ARSITEKTUR
1 lantai basement
PEKERJAAN PLAFOND
plafond gypsumboard m2 86.11
PEKERJAAN CAT
cat interior m2 1,097.02
KUSEN
kusen toilet / KM unit 3.00
storage unit 1.00
receiving unit 1.00
r. Panel unit 1.00
r. Pompa unit 1.00
engineering unit 1.00
power house unit 1.00
2 lantai 1
PEKERJAAN LANTAI DAN DINDING
Pekerjaan Pasangan Bata ringan m2 879.63
Plesteran m2 1,759.26
acian m2 1,759.26
benangan m1 1,115.60
tali air m1 51.56
kolom praktis 12x10 m1 211.20
balok praktis 12x10 m1 24.00
granit lantai 60x60 m2 683.07
plint granit lantai 10x60 m1 424.14
Keramik dinding kamar mandi 30 x 60 m2 77.34
PEKERJAAN PLAFOND
plafond gypsumboard m2 711.82
PEKERJAAN CAT
cat interior m2 1,420.06
cat exterior m2 339.20
KUSEN
excelco cafe unit 1.00
server unit 1.00
front office unit 1.00
lugage unit 1.00
toilet unit 4.00
GM unit 1.00
office unit 2.00
locker unit 1.00
canteen unit 1.00
laundry unit 1.00
dry unit 1.00
storage unit 1.00
r. Panel unit 1.00
kitchen unit 2.00
storage unit 1.00
3 lantai 2
PEKERJAAN PLAFOND
plafond gypsumboard m2 330.17
PEKERJAAN CAT
cat interior m2 1,363.87
cat exterior m2 339.20
KUSEN
meeting room unit 7.00
KM unit 2.00
r. panel unit 1.00
r. storage unit 2.00
musholla unit 1.00
3 lantai 3
PEKERJAAN PLAFOND
plafond gypsumboard m2 691.93
PEKERJAAN CAT
cat interior m2 1,363.87
cat exterior m2 339.20
cat plafond 691.93
KUSEN
Pintu Kamar unit 16.00
KM unit 16.00
house keeping unit 1.00
storage unit 1.00
r. panel unit 1.00
satuan harsat
kg 10000
m2 120000
m3 900000
RAB
JUMLAH HARGA
Rp 15,000,000.00
Rp 8,000,000.00
Rp 7,600,000.00
30,600,000.00
Rp 801,900,000.00
6,193,400.00
772,733.33
4,652,960.00
3,144,000.00
3,772,800.00
-
9,107,520.00
4,048,012.80
4,636,800.00
3,969,000.00
-
32,639,050.00
7,658,550.00
36,048,787.50
-
-
-
85,454,600.00
10,661,933.33
72,049,120.00
49,656,000.00
59,587,200.00
-
17,660,083.33
2,504,041.67
9,387,788.80
15,595,800.00
14,449,050.00
-
20,950,900.00
2,475,541.67
6,348,284.80
11,668,800.00
10,098,000.00
-
38,886,800.00
36,534,825.60
30,264,000.00
25,312,500.00
-
20,649,440.00
17,809,209.60
14,246,400.00
18,144,000.00
-
50,148,640.00
32,840,246.40
20,759,040.00
33,048,000.00
-
20,649,440.00
13,871,894.40
12,465,600.00
13,891,500.00
-
2,165,440.00
1,893,964.80
915,840.00
1,458,000.00
-
1,044,160.00
2,440,224.00
2,700,000.00
1,265,625.00
-
711,970,398.00
137,588,520.00
1,262,016,720.00
-
-
-
12,125,012.50
1,083,791.67
6,424,704.00
6,520,800.00
7,722,000.00
-
2,563,420.00
1,366,892.80
2,376,000.00
2,138,400.00
-
494,571.67
88,666.67
190,569.60
378,000.00
441,000.00
-
7,875,388.00
5,815,680.00
756,000.00
-
-
-
18,811,706.67
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
20,649,440.00
13,871,894.40
12,465,600.00
13,891,500.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
44,892,752.50
7,823,366.67
38,796,992.00
34,260,000.00
41,112,000.00
-
26,313,133.33
4,993,041.67
12,984,192.00
28,323,900.00
29,289,487.50
-
11,240,813.33
4,697,443.12
9,576,000.00
6,840,000.00
-
76,701,738.00
63,300,840.00
8,988,570.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,838,435.00
6,834,616.67
39,867,318.40
40,427,520.00
47,738,880.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,455,833.33
4,421,175.20
9,542,400.00
5,367,600.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,838,435.00
6,834,616.67
39,867,318.40
40,427,520.00
47,738,880.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,455,833.33
4,421,175.20
9,542,400.00
5,367,600.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,838,435.00
6,834,616.67
39,867,318.40
40,427,520.00
47,738,880.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,455,833.33
4,421,175.20
9,542,400.00
5,367,600.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
23,514,633.33
14,954,284.80
12,768,000.00
16,128,000.00
-
45,685,573.33
27,247,001.60
18,604,800.00
29,376,000.00
-
18,811,706.67
11,510,553.60
11,172,000.00
12,348,000.00
-
1,968,906.67
1,591,782.40
820,800.00
1,296,000.00
-
76,855,887.50
6,836,041.67
39,887,910.40
40,452,360.00
47,776,140.00
-
20,543,086.67
15,840,281.60
23,272,920.00
28,726,425.00
-
3,415,660.00
1,459,889.60
2,310,900.00
2,348,887.50
-
13,073,263.33
4,315,915.00
9,340,800.00
5,254,200.00
-
746,066.67
575,411.20
580,800.00
475,200.00
-
105,266,370.00
77,019,648.00
5,980,932.00
-
-
-
30,673,440.00
19,216,745.60
11,358,720.00
18,360,000.00
-
17,642,240.00
11,510,553.60
10,348,800.00
12,348,000.00
-
1,843,840.00
1,591,782.40
760,320.00
1,296,000.00
-
376,064.00
1,028,851.20
960,000.00
450,000.00
-
19,912,846.67
12,842,336.00
22,552,200.00
23,321,025.00
-
3,525,093.33
1,595,630.40
2,436,900.00
2,471,287.50
-
13,338,248.33
4,581,101.60
9,902,400.00
5,570,100.00
-
30,901,740.00
5,940,666.67
14,931,820.80
30,835,200.00
34,689,600.00
-
70,856,280.00
65,586,024.00
5,622,642.00
-
-
-
1,496,408.33
359,840.00
725,592.00
1,729,200.00
1,414,800.00
-
1,450,966.67
747,804.00
1,608,000.00
964,800.00
-
7,394,128.00
7,250,400.00
1,934,100.00
12,942,586,347.45
no item pekerjaaan harsat
1 Pekerjaan Pasangan Bata ringan 115,000
2 Plesteran 35,000
3 acian 16,000
4 benangan 14,000
5 tali air 14,000
6 kolom praktis 12x10
7 balok praktis 12x10
8 granit lantai 60x60 150,000
9 plint granit lantai 10x60
10 KM kamar mandi 30x30 103,000
11 rabatan lantai , beton K 250 + wiremesh M8 350,000
12 floor hardener 400,000
13 Keramik dinding kamar mandi 30 x 60 150,000
14 plafond gypsumboard 90,000
15 cat interior 21,000
NO ITEM PEKERJAAN P L AREA T N1 N2 minus KOEF VOLUME TOTAL VOL SAT
1 Pekerjaan Arsitektur
lantai Basement
benangan 897.20 m1
kolom str 3.2 27 4 345.6
dinding
AS - 1 3.2 6 19.2
AS - 2 4 12.8
AS - 3 0.0
AS - 4 27 86.4
AS - 5 0.0
AS - 6 0.0
AS - 7 0.0
AS - 8 20 64.0
AS - 9 6 19.2
balok str 350.0
kusen
kusen toilet / KM 3
storage 1
receiving 1
r. Panel 1
r. Pompa 1
engineering 1
power house 1
lantai 1
benangan 1,115.60 m1
kolom str 3.2 27 4 345.6
dinding kamar
AS - 1 3.2 8 25.6
AS - 2 0.0
AS - 3 0.0
AS - 4 40 128.0
AS - 5 18 57.6
AS - 6 0.0
AS - 7 8 25.6
AS - 8 22 70.4
AS - 9 4 12.8
balok str 450.0
benangan 1,230.80 m1
kolom str 3.2 27 4 345.6
dinding ruangan
AS - 1 3.2 8 25.6
AS - 2 12 38.4
AS - 3 12 38.4
AS - 4 40 128.0
AS - 5 6 19.2
AS - 6 4 12.8
AS - 7 4 12.8
AS - 8 46 147.2
AS - 9 4 12.8
balok str 450 450.0
kusen
meeting room 7
KM 2
r. panel 1
r. storage 2
musholla 1
lantai 3
pasangan bata ringan 1,502.11 m2
AS - A 117.18 3.2 375.0
AS - B 82 262.4
AS - C 53 169.6
AS - 1 26 83.2
AS - 2 18.5 59.2
AS - 3 0.0
AS - 4 23.23 74.3
AS - 5 24.5 78.4
AS - 6 37 118.4
AS - 7 37 118.4
AS - 8 37 118.4
AS - 9 14 44.8
plesteran 3,004.22 m2
1,502.11 2
acian 3,004.22 m2
benangan 1,717.20 m1
kolom str 3.2 27 4 345.6
dinding ruangan
AS - 1 3.2 24 76.8
AS - 2 18 57.6
AS - 3 24 76.8
AS - 4 40 128.0
AS - 5 44 140.8
AS - 6 44 140.8
AS - 7 44 140.8
AS - 8 46 147.2
AS - 9 4 12.8
balok str 450 450.0
kusen
pintu kamar
suite 6.00
deluxe 10
pintu KM
suite 6.00
deluxe 10
F2 - G2 2
G2 - H2 2
B4
F3 - G3 2
G3 - H3 2
F2 - F3 1.7
B4 G2 - G3 1.7
H2 - H3 1.7
K2 - M2 6.65
K1 - K2 2.15
BA4
L1 - L2 2.3
BA4
1 Jenis Kolom : K4
Lokasi : Elv -5.50
Ukuran Kolom : 0.7 x 0.7 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 6 unit
Tinggi Kolom : 1.5 m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Sloof : 0.4 x 0.8 m (S1)
Kebutuhan Tulangan : 16 x 6 x 3.18 = 305.28 m'
2 Jenis Kolom : K1
Lokasi : Elv -4.00
Ukuran Kolom : 0.5 x 0.5 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 12 D 19 0.019 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 4.5 m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.8 m (BD1)
Kebutuhan Tulangan : 12 x 17 x 6.06 = 1236.2 m'
3 Jenis Kolom : K1
Lokasi : Elv -4.00
Ukuran Kolom : 0.5 x 0.5 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 12 D 19 0.019 m
Jumlah Kolom Sejenis : 8 unit
Tinggi Kolom : 4.5 m
Panjang Lewatan ( L1 ) : 40 d
Kebutuhan Tulangan : 12 x 8 x 5.26 = 504.96 m'
4 Jenis Kolom : K3
Lokasi : Elv -4.00
Ukuran Kolom : 0.6 x 0.8 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 4.5 m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.8 m (BD1)
Kebutuhan Tulangan : 16 x 17 x 6.18 = 1681 m'
6 Jenis Kolom : K5
Lokasi : Elv -4.00
Ukuran Kolom : 0.4 x 0.9 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan : 16 D 19 0.019 m
Jumlah Kolom Sejenis : 1 unit
Tinggi Kolom : 4.5 m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.8 m (BD1)
Kebutuhan Tulangan : 16 x 1 x 6.06 = 96.96 m'
8 Jenis Kolom : K6
Lokasi : Elv -4.00
Ukuran Kolom : 0.25 x 0.25 m
Cover : 0.03 2 sisi : 0.06 m
Tulangan : 4 D 13 0.013 m
Jumlah Kolom Sejenis : 5 unit
Tinggi Kolom : 4.5 m
Panjang Lewatan ( L1 ) : 40 d
Kebutuhan Tulangan : 4 x 5 x 5.02 = 100.4 m'
LANTAI 1
9 Jenis Kolom : K3
Lokasi : Elv +0.50
Ukuran Kolom : 0.6 x 0.8 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 17 x 5.63 = 1531.4 m'
10 Jenis Kolom : K5
Lokasi : Elv +0.50
Ukuran Kolom : 0.4 x 0.9 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan : 16 D 19 0.019 m
Jumlah Kolom Sejenis : 1 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 1 x 5.51 = 88.16 m'
11 Jenis Kolom : K4
Lokasi : Elv +0.50
Ukuran Kolom : 0.7 x 0.7 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 7 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (BD1)
Kebutuhan Tulangan : 16 x 7 x 5.63 = 630.56 m'
LANTAI 2 - LANTAI 4
13 Jenis Kolom : K3
Lokasi : Elv +4.50 - Elv +12.50
Ukuran Kolom : 0.6 x 0.8 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 17 x 5.63 = 1531.4 m'
14 Jenis Kolom : K5
Lokasi : Elv +4.50 - Elv +12.50
Ukuran Kolom : 0.4 x 0.9 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan : 16 D 19 0.019 m
Jumlah Kolom Sejenis : 1 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 1 x 5.51 = 88.16 m'
15 Jenis Kolom : K4
Lokasi : Elv +4.50 - Elv +12.50
Ukuran Kolom : 0.7 x 0.7 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 7 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (BD1)
Kebutuhan Tulangan : 16 x 7 x 5.63 = 630.56 m'
LANTAI 5 - LANTAI 11
13 Jenis Kolom : K3
Lokasi : Elv +16.50 - Elv +44.50
Ukuran Kolom : 0.6 x 0.8 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 17 x 5.63 = 1531.4 m'
14 Jenis Kolom : K5
Lokasi : Elv +16.50 - Elv +44.50
Ukuran Kolom : 0.4 x 0.9 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan : 16 D 19 0.019 m
Jumlah Kolom Sejenis : 1 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (B1)
Kebutuhan Tulangan : 16 x 1 x 5.51 = 88.16 m'
15 Jenis Kolom : K4
Lokasi : Elv +16.50 - Elv +44.50
Ukuran Kolom : 0.7 x 0.7 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 7 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.4 x 0.75 m (BD1)
Kebutuhan Tulangan : 16 x 7 x 5.63 = 630.56 m'
LANTAI ATAP
17 Jenis Kolom : K3
Lokasi : Elv +44.50 - Elv +47.50
Ukuran Kolom : 0.6 x 0.8 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 17 unit
Tinggi Kolom : 2.5 m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.3 x 0.4 m (B4)
Kebutuhan Tulangan : 16 x 17 x 3.78 = 1028.2 m'
18 Jenis Kolom : K5
Lokasi : Elv +44.50 - Elv +47.50
Ukuran Kolom : 0.4 x 0.9 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan : 16 D 19 0.019 m
Jumlah Kolom Sejenis : 1 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.3 x 0.4 m (B4)
Kebutuhan Tulangan : 16 x 1 x 5.16 = 82.56 m'
19 Jenis Kolom : K4
Lokasi : Elv +44.50 - Elv +47.50
Ukuran Kolom : 0.7 x 0.7 m
Cover : 0.05 2 sisi : 0.1 m
Tulangan : 16 D 22 0.022 m
Jumlah Kolom Sejenis : 7 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Ukuran Balok : 0.3 x 0.4 m (B4)
Kebutuhan Tulangan : 16 x 7 x 5.28 = 591.36 m'
20 Jenis Kolom : K6
Lokasi : Elv +44.50
Ukuran Kolom : 0.25 x 0.25 m
Cover : 0.03 2 sisi : 0.06 m
Tulangan : 4 D 13 0.013 m
Jumlah Kolom Sejenis : 2 unit
Tinggi Kolom : 4m
Panjang Lewatan ( L1 ) : 40 d
Kebutuhan Tulangan : 4 x 2 x 4.52 = 36.16 m'
Bekisting : 0.25 x 4 x 4 x 2 =
Beton : 0.25 x 0.25 x 4 x 2 =
14D13 : 36.16 m' x 1.04 kg =
Sengkang Ø12 : 98.928 m' x 1.040 kg =
2.556 m' = 20.448 m'
= 36.288 m'
38.64 m2
4.41 m3
910.75 kg/m
404.8 kg/m
1.756 m' = 42.144 m'
= 53.376 m'
180.2 m2
19.125 m3
2760.9 kg/m
1942.3 kg/m
72 m2
9 m3
1127.7 kg/m
1711.2 kg/m
172.99 m2
36.72 m3
5014.9 kg/m
3284 kg/m
2.556 m' = 61.344 m'
= 108.86 m'
103.88 m2
15.435 m3
2064.9 kg/m
1387.2 kg/m
2.436 m' = 58.464 m'
= 92.544 m'
7.632 m2
1.62 m3
216.54 kg/m
189.4 kg/m
118.72 m2
20.16 m3
2064.9 kg/m
1780.9 kg/m
22.5 m2
1.4063 m3
104.42 kg/m
244.02 kg/m
2.556 m' = 51.12 m'
= 86.72 m'
155.04 m2
32.64 m3
4568.6 kg/m
2724.7 kg/m
6.84 m2
1.44 m3
196.89 kg/m
159.18 kg/m
93.1 m2
13.72 m3
1881.2 kg/m
1151.1 kg/m
2.956 m' = 59.12 m'
= 136.96 m'
106.4 m2
17.92 m3
1881.2 kg/m
1495.4 kg/m
155.04 m2
32.64 m3
4568.6 kg/m
2724.7 kg/m
6.84 m2
1.44 m3
196.89 kg/m
159.18 kg/m
2.556 m' = 51.12 m'
= 90.72 m'
93.1 m2
13.72 m3
1881.2 kg/m
1151.1 kg/m
2.956 m' = 59.12 m'
= 136.96 m'
106.4 m2
17.92 m3
2351.5 kg/m
1495.4 kg/m
155.04 m2
32.64 m3
4568.6 kg/m
2724.7 kg/m
6.84 m2
1.44 m3
196.89 kg/m
159.18 kg/m
2.556 m' = 51.12 m'
= 90.72 m'
93.1 m2
13.72 m3
1881.2 kg/m
1151.1 kg/m
106.4 m2
17.92 m3
2351.5 kg/m
1495.4 kg/m
94.656 m2
20.4 m3
3067.3 kg/m
1921.7 kg/m
2.436 m' = 48.72 m'
= 77.12 m'
6.336 m2
1.44 m3
184.38 kg/m
159.18 kg/m
2.556 m' = 51.12 m'
= 90.72 m'
86.24 m2
13.72 m3
1764.2 kg/m
1151.1 kg/m
8 m2
0.5 m3
37.606 kg/m
102.89 kg/m
RESUME PERHITUNGAN
Kolom Elv -5.50
K4
Bekisting : 38.64 m2
Beton (f'c =35 Mpa) : 4.41 m3
Besi D22 : 910.75 Kg/m
Sengkang D13 : 404.80 Kg/m
K2A K5
Bekisting : 118.72 m2 Bekisting :
Beton (f'c =40 Mpa) : 20.16 m3 Beton (f'c =35 Mpa) :
Besi D22 : 2064.94 Kg/m Besi D19 :
Sengkang D13 : 1780.92 Kg/m Sengkang D13 :
K3 K6
Bekisting : 172.99 m2 Bekisting :
Beton (f'c =30 Mpa) : 36.72 m3 Beton :
Besi D22 : 5014.86 Kg/m Besi D13 :
Sengkang D13 : 3284.02 Kg/m Sengkang Ø12 :
K3 K5
Bekisting : 155.04 m2 Bekisting :
Beton (f'c =30 Mpa) : 32.64 m3 Beton (f'c =35 Mpa) :
Besi D22 : 4568.56 Kg/m Besi D19 :
Sengkang D13 : 2724.70 Kg/m Sengkang D13 :
Kolom Elv +4.50 - +12.50
K2A K4
Bekisting : 106.40 m2 Bekisting :
Beton (f'c =40 Mpa) : 17.92 m3 Beton (f'c =35 Mpa) :
Besi D22 : 2351.46 Kg/m Besi D22 :
Sengkang D13 : 1495.43 Kg/m Sengkang D13 :
K3 K5
Bekisting : 155.04 m2 Bekisting :
Beton (f'c =30 Mpa) : 32.64 m3 Beton (f'c =35 Mpa) :
Besi D22 : 4568.56 Kg/m Besi D19 :
Sengkang D13 : 2724.70 Kg/m Sengkang D13 :
K3 K5
Bekisting : 155.04 m2 Bekisting :
Beton (f'c =30 Mpa) : 32.64 m3 Beton (f'c =35 Mpa) :
Besi D22 : 4568.56 Kg/m Besi D19 :
Sengkang D13 : 2724.70 Kg/m Sengkang D13 :
K4 K6
Bekisting : 86.24 m2 Bekisting :
Beton (f'c =35 Mpa) : 13.72 m3 Beton :
Besi D22 : 1764.22 Kg/m Besi D13 :
Sengkang D13 : 1151.06 Kg/m Sengkang Ø12 :
103.88 m2
15.44 m3
2064.94 Kg/m
1387.19 Kg/m
7.63 m2
1.62 m3
216.54 Kg/m
189.40 Kg/m
22.50 m2
1.41 m3
104.42 Kg/m
244.02 Kg/m
103.88 m2
15.44 m3
2064.94 Kg/m
1387.19 Kg/m
6.84 m2
1.44 m3
196.89 Kg/m
159.18 Kg/m
93.10 m2
13.72 m3
1881.17 Kg/m
1151.06 Kg/m
6.84 m2
1.44 m3
196.89 Kg/m
159.18 Kg/m
93.10 m2
13.72 m3
1881.17 Kg/m
1151.06 Kg/m
6.84 m2
1.44 m3
196.89 Kg/m
159.18 Kg/m
6.34 m2
1.44 m3
184.38 Kg/m
159.18 Kg/m
8.00 m2
0.50 m3
37.61 Kg/m
102.89 Kg/m
Panjang Sloof Melintang (PDF/12) - SLOOF ELV -5.
1 Jenis Sloof : S1
Lokasi : -5.50
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
m'
m'
m'
0.1 m
0.15 m
x 4 = 16.00 m2
x 4 = 2.56 m3
= 372.32 kg/m
= 46.45 kg/m
= 273.13 kg/m
Panjang Sloof Memanjang (PDF/12) - SLOOF ELV -5.50
Jenis Sloof : S1
Lokasi : -5.50
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
= 10.20 m2
= 1.63 m3
= 247.02 kg/m
= 30.82 kg/m
= 192.17 kg/m
Panjang Sloof Melintang (PDF/13) - SLOOF ELV -4.00
1 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
2 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
3 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
4 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
5 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
6 Jenis Sloof : S2
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 5 D 19 0.019 m
7 Jenis Sloof : S2
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 5 D 19 0.019 m
8 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
9 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jumlah Sloof Sejenis : 1
Panjang Penjangkaran : 0.75 t
Panjang Sloof : F2 - G2 2 √
10 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
11 Jenis Sloof : S2
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 5 D 19 0.019 m
12 Jenis Sloof : S2
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 5 D 19 0.019 m
13 Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
14 Jenis Sloof : S2
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 5 D 19 0.019 m
14 = 79.80 m2
14 = 12.77 m3
= 1729.14 kg/m
= 215.74 kg/m
= 1446.68 kg/m
2
m
3 = 20.70 m2
3 = 3.31 m3
= 434.97 kg/m
= 54.27 kg/m
= 353.51 kg/m
3
m
3 = 11.70 m2
3 = 1.87 m3
= 273.87 kg/m
= 34.17 kg/m
= 204.85 kg/m
4
m
2 = 8.40 m2
2 = 1.34 m3
= 193.32 kg/m
= 24.12 kg/m
= 157.11 kg/m
5
2 = 14.60 m2
2 = 2.34 m3
= 304.30 kg/m
= 37.97 kg/m 6
= 264.68 kg/m
1 = 16.83 m2
1 = 2.08 m3
= 232.83 kg/m
= 33.01 kg/m
= 59.90 kg/m
8
m
1 = 4.00 m2
1 = 0.64 m3
= 93.08 kg/m
= 11.61 kg/m
= 68.28 kg/m
9
m
1 = 4.00 m2
1 = 0.64 m3
= 93.08 kg/m
= 11.61 kg/m
= 68.28 kg/m
6
m
1 = 43.80 m2
1 = 7.01 m3
= 805.50 kg/m
= 100.50 kg/m
= 721.52 kg/m 11
m
2 x 1.836 m' = 44.064 m'
= 18.624 m'
1 = 11.31 m2
1 = 1.40 m3
= 160.24 kg/m
= 22.72 kg/m
= 88.11 kg/m
12
13
5 = 62.00 m2
5 = 9.92 m3
= 1217.20 kg/m
= 151.87 kg/m
= 1054.48 kg/m
14
1 = 58.91 m2
1 = 7.28 m3
= 785.58 kg/m
= 111.39 kg/m
= 425.86 kg/m
15
16
17
18
19
20
21
Panjang Sloof Memanjang (PDF/13) - SLOOF ELV -4.00
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Bekisting : 1 + 0.3 x 2 x 1
Beton : 0.3 x 0.5 x 2 x 1
D19 : 28.5 m' x 2.233 kg
D16 : 4.75 m' x 1.583 kg
Sengkang D13 : 18.804 m' x 1.040 kg
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Bekisting : 1 + 0.3 x 5 x 1
Beton : 0.3 x 0.5 x 5 x 1
D19 : 64.5 m' x 2.233 kg
D16 : 10.75 m' x 1.583 kg
Sengkang D13 : 42.668 m' x 1.040 kg
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jumlah Sloof Sejenis : 2
Panjang Penjangkaran : 0.75 t
Panjang Sloof : D6 - D7 1.45 √
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Bekisting : 1 + 0.3 x 13 x 1
Beton : 0.3 x 0.5 x 13 x 1
D19 : 160.5 m' x 2.233 kg
D16 : 26.75 m' x 1.583 kg
Sengkang D13 : 104.14 m' x 1.040 kg
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S3
Lokasi : -4.00
Ukuran Sloof : 0.3 x 0.5 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m
Tulangan Tarik 4 D 19 0.019 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jenis Sloof : S1
Lokasi : -4.00
Ukuran Sloof : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m
Tulangan Tarik 6 D 22 0.022 m
Jumlah Sloof Sejenis : 1
Panjang Penjangkaran : 0.75 t
Panjang Sloof : M5 - M6 1.5 √
S2
Bekisting : 129.97
Beton : 16.05
D19 : 1766.01
D16 : 250.40
Sengkang D13 : 938.78
S3
Bekisting : 97.24
Beton : 11.22
x 2.236 m' = 22.36 m' D19 : 2095.09
= 27.04 m' D16 : 247.55
Sengkang D13 : 634.83
= 3.90 m2
= 0.62 m3
= 91.29 kg/m
= 11.39 kg/m
= 68.28 kg/m
x 2.236 m' = 58.136 m'
= 70.304 m'
= 9.70 m2
= 1.55 m3
= 195.11 kg/m
= 24.34 kg/m
= 171.62 kg/m
x 2.236 m' = 62.608 m'
= 75.712 m'
= 53.00 m2
= 8.48 m3
= 1056.10 kg/m
= 131.77 kg/m
= 909.46 kg/m
x 1.436 m' = 11.488 m'
= 3.008 m'
= 2.60 m2
= 0.30 m3
= 63.65 kg/m
= 7.52 kg/m
= 19.56 kg/m
= 6.50 m2
= 0.75 m3
= 144.05 kg/m
= 17.02 kg/m
= 44.37 kg/m
= 7.15 m2
= 0.83 m3
= 157.45 kg/m
= 18.60 kg/m
= 48.14 kg/m
= 43.80 m2
= 7.01 m3
= 848.46 kg/m
= 105.86 kg/m
= 750.52 kg/m
x 2.236 m' = 17.888 m'
= 21.632 m'
= 8.10 m2
= 1.30 m3
= 209.43 kg/m
= 26.13 kg/m
= 161.34 kg/m
x 2.236 m' = 17.888 m'
= 21.632 m'
= 5.80 m2
= 0.93 m3
= 146.78 kg/m
= 18.31 kg/m
= 107.56 kg/m
x 1.436 m' = 63.184 m'
= 16.544 m'
= 16.64 m2
= 1.92 m3
= 353.09 kg/m
= 41.72 kg/m
= 106.81 kg/m
= 3.70 m2
= 0.59 m3
= 87.71 kg/m
= 10.94 kg/m
= 68.28 kg/m
= 3.40 m2
= 0.54 m3
= 82.34 kg/m
= 10.27 kg/m
= 64.06 kg/m
= 4.70 m2
= 0.75 m3
= 105.61 kg/m
= 13.18 kg/m
= 78.56 kg/m
= 2.47 m2
= 0.29 m3
= 60.97 kg/m
= 7.20 kg/m
= 19.56 kg/m
x 1.436 m' = 43.08 m'
= 11.28 m'
= 11.05 m2
= 1.28 m3
= 237.85 kg/m
= 28.10 kg/m
= 72.96 kg/m
x 1.436 m' = 60.312 m'
= 15.792 m'
= 16.38 m2
= 1.89 m3
= 347.73 kg/m
= 41.09 kg/m
= 103.04 kg/m
= 16.90 m2
= 1.95 m3
= 358.45 kg/m
= 42.35 kg/m
= 108.31 kg/m
= 17.55 m2
= 2.03 m3
= 371.85 kg/m
= 43.94 kg/m
= 112.07 kg/m
x 2.236 m' = 53.664 m'
= 64.896 m'
= 9.50 m2
= 1.52 m3
= 191.53 kg/m
= 23.90 kg/m
= 157.11 kg/m
x 2.236 m' = 17.888 m'
= 21.632 m'
= 3.00 m2
= 0.48 m3
= 75.18 kg/m
= 9.38 kg/m
= 53.78 kg/m
PERHITUNGAN
+ 164.80 = 413.80 m2
+ 26.37 = 66.21 m3
+ 3401.00 = 8545.46 Kg/m
+ 424.33 = 1066.19 Kg/m
+ 2865.52 = 7204.91 Kg/m
= 129.97 m2
= 16.05 m3
= 1766.01 Kg/m
= 250.40 Kg/m
= 938.78 Kg/m
= 97.24 m2
= 11.22 m3
= 2095.09 Kg/m
= 247.55 Kg/m
= 634.83 Kg/m
Panjang Balok Melintang (PDF/14) - BALOK ELV -0.30
1 Jenis Balok : B1
Lokasi : -0.30
Ukuran Balok : 0.4 x 0.75 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
2 Jenis Balok : B2
Lokasi : -0.30
Ukuran Balok : 0.3 x 0.6 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 19 0.019 m
Tulangan Badan : 2 D 13 0.013 m TUMPUAN
Tulangan Tarik : 3 D 19 0.019 m
TUMPUAN
LAPANGAN
m
2 x 2.136 m' = 68.352 m'
= 41.664 m'
3 = 35.34 m2
3 = 5.58 m3
= 772.61 kg/m
= 69.59 kg/m 2
= 416.56 kg/m
TUMPUAN
LAPANGAN
2 = 19.80 m2
2 = 2.38 m3
= 256.34 kg/m
= 31.20 kg/m
= 105.49 kg/m
Panjang Balok Memanjang (PDF/14) - BALOK ELV -0.30
Jenis Balok : BR1
Lokasi : -0.30
Ukuran Balok : 0.4 x 0.7 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 4 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 3 D 19 0.019 m
Jenis Balok : B1
Lokasi : -0.30
Ukuran Balok : 0.4 x 0.75 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
B2
Bekisting : 19.80
Beton : 2.38
D19 : 256.34
D13 : 31.20
Sengkang D13 : 105.49
BR1
Bekisting : 3.15
Beton : 0.49
D19 : 49.46
D16 : 8.87
Sengkang D13 : 19.06
x 2.036 m' = 12.216 m'
= 3.15 m2
= 0.49 m3
= 49.46 kg/m
= 8.87 kg/m
= 19.06 kg/m
= 19.00 m2
= 3.00 m3
= 439.89 kg/m
= 38.79 kg/m
= 225.91 kg/m
PERHITUNGAN
+ 19.00 = 54.34 m2
+ 3.00 = 8.58 m3
+ 439.89 = 1212.50 Kg/m
+ 38.79 = 108.38 Kg/m
+ 225.91 = 642.47 Kg/m
= 19.80 m2
= 2.38 m3
= 256.34 Kg/m
= 31.20 Kg/m
= 105.49 Kg/m
= 3.15 m2
= 0.49 m3
= 49.46 Kg/m
= 8.87 Kg/m
= 19.06 Kg/m
Panjang Balok Melintang (PDF/15) - BALOK ELV +0.50
1 Jenis Balok : BD1
Lokasi : 0.50
Ukuran Balok : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m TUMPUAN
Tulangan Tarik : 3 D 22 0.022 m
TUMPUAN
LAPANGAN
m
2 x 2.236 m' = 40.248 m'
= 31.536 m'
3 = 20.70 m2
3 = 3.31 m3
= 375.50 kg/m
= 62.31 kg/m
= 282.22 kg/m
TUMPUAN
LAPANGAN
m
2 x 2.236 m' = 22.36 m'
= 17.52 m'
3 = 11.70 m2
3 = 1.87 m3
= 274.81 kg/m
= 42.21 kg/m
= 163.26 kg/m
TUMPUAN
LAPANGAN
m
2 x 2.236 m' = 71.552 m'
= 56.064 m'
11 = 136.40 m2
11 = 21.82 m3
= 2053.67 kg/m
= 363.59 kg/m
= 1851.54 kg/m
TUMPUAN
LAPANGAN
4 = 44.06 m2
4 = 6.07 m3
= 522.73 kg/m
= 96.90 kg/m
= 252.05 kg/m
TUMPUAN
5
LAPANGAN
4 = 143.88 m2
4 = 19.84 m3
= 1468.55 kg/m
= 288.48 kg/m
= 779.05 kg/m
6
7
8
9
10
Jenis Balok : BD1
Lokasi : 0.50
Ukuran Balok : 0.4 x 0.8 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 22 0.022 m
Tulangan Badan : 2 D 19 0.019 m TUMPUAN
Tulangan Tarik : 3 D 22 0.022 m
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Tulangan Badan (Ø10) :
Tulangan Tarik (D16) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
D16 :
x 2.236 m' = 29.068 m' Ø10 :
= 11.388 m' Sengkang Ø10 :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Tulangan Badan (Ø10) :
Tulangan Tarik (D16) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
x 2.236 m' = 62.608 m' D16 :
= 49.056 m' Ø10 :
Sengkang Ø10 :
13 Jenis Balok :
Lokasi :
Ukuran Balok :
x 2.236 m' = 20.124 m' Cover :
= 7.884 m' Tulangan Tekan :
Tulangan Badan :
= 10.60 m2 Tulangan Tarik :
= 1.70 m3
= 166.56 kg/m Tulangan Tekan :
= 29.03 kg/m Tulangan Badan :
= 145.26 kg/m Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Kebutuhan Tulangan :
Tulangan Tekan (D16) :
Tulangan Badan (Ø10) :
Tulangan Tarik (D16) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
D16 :
Ø10 :
Sengkang Ø10 :
14 Jenis Balok :
Lokasi :
x 2.236 m' = 80.496 m' Ukuran Balok :
= 63.072 m' Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Tulangan Tekan :
x 2.236 m' = 26.832 m' Tulangan Badan :
= 10.512 m' Tulangan Tarik :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
D16 :
Ø10 :
Sengkang Ø10 :
15 Jenis Balok :
Lokasi :
Ukuran Balok :
Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
x 2.236 m' = 58.136 m' Tulangan Tekan :
= 45.552 m' Tulangan Badan :
Tulangan Tarik :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
D16 :
Ø10 :
Sengkang Ø10 :
16 Jenis Balok :
Lokasi :
Ukuran Balok :
Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Bekisting :
Beton :
D16 :
Ø10 :
Sengkang Ø10 :
= 3.88 m2
= 0.53 m3
= 63.07 kg/m
= 10.53 kg/m
= 21.00 kg/m
x 1.836 m' = 33.048 m'
= 8.66 m2
= 1.19 m3
= 108.41 kg/m
= 19.71 kg/m
= 47.74 kg/m
x 1.836 m' = 11.016 m'
= 5.61 m2
= 0.77 m3
= 105.82 kg/m
= 16.94 kg/m
= 34.37 kg/m
x 1.836 m' = 51.408 m'
= 27.39 m2
= 3.78 m3
= 312.18 kg/m
= 58.74 kg/m
= 148.94 kg/m
0
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
1
0.75 t
D'2 - D'7 10.4 √
TUMPUAN
4 x 6.28 = 25.12 m'
LAPANGAN
2 x 5.52 = 11.04 m'
2 x 11.0 = 22 m'
3 x 11.0 = 33 m'
Ø 10 - 100 0.1 m
1.176 m'
2.6 : 0.1 = 26 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
2.6 : 0.15 = 18 bh x 1 x 1.176 m' =
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
1
0.75 t
E1 - E7 12.8 √
TUMPUAN
4 x 7.48 = 29.92 m'
LAPANGAN
2 x 6.72 = 13.44 m'
2 x 13.4 = 26.8 m'
3 x 13.4 = 40.2 m'
Ø 10 - 100 0.1 m
1.176 m'
3.2 : 0.1 = 32 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
3.2 : 0.15 = 22 bh x 1 x 1.176 m' =
0.8 + 0.25 x 12.8 x 1 = 13.44 m2
0.25 x 0.4 x 12.8 x 1 = 1.28 m3
83.56 m' x 2.23 kg = 186.62 kg/m
26.8 m' x 0.62 kg = 16.54 kg/m
101.136 m' x 0.62 kg = 62.40 kg/m
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
2
0.75 t
I'1 - I'7 13.2 √
TUMPUAN
4 x 7.68 = 30.72 m'
LAPANGAN
2 x 6.92 = 13.84 m'
2 x 13.8 = 27.6 m'
3 x 13.8 = 41.4 m'
Ø 10 - 100 0.1 m
1.176 m'
3.3 : 0.1 = 33 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
3.3 : 0.15 = 22 bh x 1 x 1.176 m' =
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
1
0.75 t
L1 -L7 13.15 √
TUMPUAN
4 x 7.655 = 30.62 m'
LAPANGAN
2 x 6.895 = 13.79 m'
2 x 13.8 = 27.5 m'
3 x 13.8 = 41.25 m'
Ø 10 - 100 0.1 m
1.176 m'
3.2875 : 0.1 = 33 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
3.2875 : 0.15 = 22 bh x 1 x 1.176 m' =
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
1
0.75 t
L'2 -L'7 11.2 √
TUMPUAN
4 x 6.68 = 26.72 m'
LAPANGAN
2 x 5.92 = 11.84 m'
2 x 11.8 = 23.6 m'
3 x 11.8 = 35.4 m'
Ø 10 - 100 0.1 m
1.176 m'
2.8 : 0.1 = 28 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
2.8 : 0.15 = 19 bh x 1 x 1.176 m' =
BD3
0.50
0.25 x 0.4 m
0.035 2 sisi : 0.07 m
4 D 16 0.016 m
2 Ø 10 0.01 m TUMPUAN
3 D 16 0.016 m
2 D 16 0.016 m
2 Ø 10 0.01 m LAPANGAN
3 D 16 0.016 m
1
0.75 t
L"2 -L"7 2.05 √
TUMPUAN
4 x 2.105 = 8.42 m'
LAPANGAN
2 x 1.345 = 2.69 m'
2 x 2.7 = 5.3 m'
3 x 2.7 = 7.95 m'
Ø 10 - 100 0.1 m
1.176 m'
0.5125 : 0.1 = 6 bh x 2 x 1.176 m' =
Ø 10 - 150 0.15 m
1.176 m'
0.5125 : 0.15 = 4 bh x 1 x 1.176 m' =
BD2
Bekisting : 236.03 = 236.03
Beton : 32.54 = 32.54
D19 : 2631.31 = 2631.31
D16 : 499.30 = 499.30
Sengkang D13 : 1298.42 = 1298.42
BD3
Bekisting : 79.80 = 79.80
Beton : 7.60 = 7.60
D16 : 1124.08 = 1124.08
Ø10 : 98.97 = 98.97
Sengkang Ø10 : 370.78 = 370.78
61.152 m'
21.168 m'
75.264 m'
25.872 m'
77.616 m'
25.872 m'
77.616 m'
25.872 m'
65.856 m'
22.344 m'
14.112 m'
4.704 m'
m2
m3
Kg/m
Kg/m
Kg/m
m2
m3
Kg/m
Kg/m
Kg/m
m2
m3
Kg/m
Kg/m
Kg/m
Melintang
1 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
2 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
3 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Memanjang
4 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
5 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
6 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
7 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
8 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Tulangan Tekan : 3 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m LAPANGAN
Tulangan Tarik : 5 D 22 0.022 m
9 Jenis Balok : B1
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
x 2.116 m' = 12.696 m' Beton :
D19 :
= 19.46 m2 D13 :
= 3.06 m3 Sengkang D13 :
= 512.43 kg/m
= 43.32 kg/m 2 Jenis Balok :
= 231.00 kg/m Lokasi :
Ukuran Balok :
Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
x 2.116 m' = 21.16 m'
= 12.92 m' Bekisting :
Beton :
D19 :
D13 :
x 2.116 m' = 8.464 m' Sengkang D13 :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
x 2.116 m' = 67.712 m' D19 :
= 41.344 m' D13 :
Sengkang D13 :
x 2.116 m' = 23.276 m'
= 163.18 m2
= 25.69 m3
= 3597.36 kg/m
= 324.08 kg/m
= 1926.75 kg/m
= 19.93 m2
= 3.14 m3
= 457.52 kg/m
= 40.60 kg/m
= 238.09 kg/m
= 9.87 m2
= 1.55 m3
= 227.20 kg/m
= 20.14 kg/m
= 119.05 kg/m
x 2.116 m' = 76.176 m'
= 46.512 m'
= 39.48 m2
= 6.22 m3
= 846.04 kg/m
= 77.05 kg/m
= 462.01 kg/m
x 2.116 m' = 55.016 m'
= 33.592 m'
= 37.60 m2
= 5.92 m3
= 877.46 kg/m
= 77.39 kg/m
= 447.83 kg/m
x 2.116 m' = 50.784 m'
= 31.008 m'
= 8.93 m2
= 1.41 m3
= 211.53 kg/m
= 18.56 kg/m
= 102.67 kg/m
Melintang
B2
Lt.2 - Lt.4
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
D2 - F2 6.675 √
TUMPUAN
5 x 4.8825 = 24.4125 m'
LAPANGAN
3 x 3.7175 = 11.1525 m'
2 x 7.650 = 15.3 m'
3 x 7.650 = 22.95 m'
D 13 - 150 0.15 m
1.836 m'
1.66875 : 0.15 = 12 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
1.66875 : 0.2 = 9 bh x 1 x 1.836 m' =
B2
Lt.2 - Lt.4
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
H2 - M2 21.8 √
TUMPUAN
5 x 12.445 = 62.225 m'
LAPANGAN
3 x 11.28 = 33.84 m'
2 x 22.775 = 45.55 m'
3 x 22.775 = 68.325 m'
D 13 - 150 0.15 m
1.836 m'
5.45 : 0.15 = 37 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
5.45 : 0.2 = 28 bh x 1 x 1.836 m' =
1.3 + 0.35 x 21.8 x 4 = 143.88 m2
0.35 x 0.65 x 21.8 x 4 = 19.84 m3
657.56 m' x 2.23 kg = 1468.55 kg/m
182.2 m' x 1.04 kg = 189.49 kg/m
749.088 m' x 1.04 kg = 779.05 kg/m
B2
Lt.2 - Lt.4
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
C2 - D2 6.6 √
TUMPUAN
5 x 4.845 = 24.225 m'
LAPANGAN
3 x 3.68 = 11.04 m'
2 x 7.575 = 15.15 m'
3 x 7.575 = 22.725 m'
D 13 - 150 0.15 m
1.836 m'
1.65 : 0.15 = 11 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
1.65 : 0.2 = 9 bh x 1 x 1.836 m' =
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.436 m'
16.524 m' Kebutuhan Sengkang 2 Kaki : 0.3875 : 0.2
Bekisting : 1 + 0.3
Beton : 0.3 x 0.5
D19 : 20.84 m' x 2.23
D13 : 4.6 m' x 1.04
Sengkang D13 : 11.488 m' x 1.04
2 Jenis Balok : B3
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
135.864 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
51.408 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.2
Bekisting : 1.3 + 0.35
Beton : 0.35 x 0.65
D19 : 84.72 m' x 2.23
D13 : 19.95 m' x 1.04
Sengkang D13 : 60.588 m' x 1.04
3 Jenis Balok : B3
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
40.392 m' Kebutuhan Sengkang 2 Kaki : 0.425 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
16.524 m' Kebutuhan Sengkang 2 Kaki : 0.425 : 0.2
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 10.475 m'
= 3.465 m'
= 4.6 m'
= 6.9 m'
150 0.15 m
200 0.2 m
x 1.55 x 1 = 2.02 m2
x 1.55 x 1 = 0.23 m3
kg = 46.54 kg/m
kg = 4.78 kg/m
kg = 11.95 kg/m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 13.6 m'
= 4.665 m'
= 6.65 m'
= 9.975 m'
150 0.15 m
200 0.2 m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 11.975 m'
= 3.69 m'
= 5.35 m'
= 8.025 m'
150 0.15 m
200 0.2 m
x 1.7 x 2 = 5.61 m2
x 1.7 x 2 = 0.77 m3
kg = 105.82 kg/m
kg = 11.13 kg/m
kg = 34.37 kg/m
Memanjang
1 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
2 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
3 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
5 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
Tulangan Tekan : 3 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m LAPANGAN
Tulangan Tarik : 3 D 16 0.016 m
6 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
7 Jenis Balok : B5
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
TUMPUAN
LAPANGAN
m
1 = 10.24 m2
1 = 0.77 m3
= 169.69 kg/m
= 16.35 kg/m
= 40.30 kg/m
TUMPUAN
LAPANGAN
TUMPUAN
LAPANGAN
2 = 21.12 m2
2 = 1.58 m3
= 349.20 kg/m
= 33.69 kg/m
= 82.88 kg/m
TUMPUAN
LAPANGAN
1 = 10.52 m2
1 = 0.79 m3
= 173.99 kg/m
= 16.78 kg/m
= 41.44 kg/m
TUMPUAN
LAPANGAN
1 = 10.92 m2
1 = 0.82 m3
= 180.13 kg/m
= 17.40 kg/m
= 43.14 kg/m
TUMPUAN
LAPANGAN
m
1 = 1.68 m2
1 = 0.13 m3
= 38.26 kg/m
= 3.15 kg/m
= 7.38 kg/m
TUMPUAN
LAPANGAN
m
2 = 16.64 m2
2 = 1.25 m3
= 280.42 kg/m
= 26.78 kg/m
= 64.71 kg/m
Memanjang
Jenis Balok : BT
Lokasi : Lt.2 - Lt.4
Ukuran Balok : 0.3 x 0.4 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 16 0.016 m
Tulangan Badan : 2 D 13 0.013 m TUMPUAN
Tulangan Tarik : 3 D 16 0.016 m
B2
Bekisting : 193.94 m2
Beton : 31.92 m3
D19 : 2054.31 Kg/m
D13 : 316.16 Kg/m
Sengkang D13 : 1267.87 Kg/m
B3
Bekisting : 19.26 m2
Beton : 2.61 m3
D19 : 341.57 Kg/m
D13 : 36.66 Kg/m
Sengkang D13 : 109.33 Kg/m
B5
Bekisting : 79.52 m2
Beton : 5.96 m3
D16 : 1345.58 Kg/m
Ø10 : 128.21 Kg/m
Sengkang Ø10 : 313.90 Kg/m
= 4.84 m2
= 0.53 m3
= 74.61 kg/m
= 11.65 kg/m
= 45.89 kg/m
Melintang
1 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.75 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
2 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
3 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Memanjang
4 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
5 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
6 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
7 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
8 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Tulangan Tekan : 3 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m LAPANGAN
Tulangan Tarik : 5 D 22 0.022 m
9 Jenis Balok : B1
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.4 x 0.74 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 8 D 22 0.022 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 5 D 22 0.022 m
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
x 2.136 m' = 12.816 m' Beton :
D19 :
= 19.67 m2 D13 :
= 3.11 m3 Sengkang D13 :
= 514.18 kg/m
= 43.46 kg/m 2 Jenis Balok :
= 233.06 kg/m Lokasi :
Ukuran Balok :
Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
x 2.116 m' = 21.16 m'
= 12.92 m' Bekisting :
Beton :
D19 :
D13 :
x 2.116 m' = 8.464 m' Sengkang D13 :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
Kebutuhan Sengkang 2 Kaki :
Bekisting :
Beton :
x 2.116 m' = 67.712 m' D19 :
= 41.344 m' D13 :
Sengkang D13 :
x 2.116 m' = 23.276 m'
= 163.18 m2
= 25.69 m3
= 3597.36 kg/m
= 324.08 kg/m
= 1926.75 kg/m
= 19.93 m2
= 3.14 m3
= 457.52 kg/m
= 40.60 kg/m
= 238.09 kg/m
= 9.87 m2
= 1.55 m3
= 227.20 kg/m
= 20.14 kg/m
= 119.05 kg/m
x 2.116 m' = 76.176 m'
= 46.512 m'
= 39.48 m2
= 6.22 m3
= 846.04 kg/m
= 77.05 kg/m
= 462.01 kg/m
x 2.116 m' = 55.016 m'
= 33.592 m'
= 37.60 m2
= 5.92 m3
= 877.46 kg/m
= 77.39 kg/m
= 447.83 kg/m
x 2.116 m' = 50.784 m'
= 31.008 m'
= 8.93 m2
= 1.41 m3
= 211.53 kg/m
= 18.56 kg/m
= 102.67 kg/m
Melintang
B2
Lt.5 - Lt.11
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
D2 - F2 6.675 √
TUMPUAN
5 x 4.8825 = 24.4125 m'
LAPANGAN
3 x 3.7175 = 11.1525 m'
2 x 7.650 = 15.3 m'
3 x 7.650 = 22.95 m'
D 13 - 150 0.15 m
1.836 m'
1.66875 : 0.15 = 12 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
1.66875 : 0.2 = 9 bh x 1 x 1.836 m' =
B2
Lt.5 - Lt.11
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
H2 - M2 21.8 √
TUMPUAN
5 x 12.445 = 62.225 m'
LAPANGAN
3 x 11.28 = 33.84 m'
2 x 22.775 = 45.55 m'
3 x 22.775 = 68.325 m'
D 13 - 150 0.15 m
1.836 m'
5.45 : 0.15 = 37 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
5.45 : 0.2 = 28 bh x 1 x 1.836 m' =
1.3 + 0.35 x 21.8 x 4 = 143.88 m2
0.35 x 0.65 x 21.8 x 4 = 19.84 m3
657.56 m' x 2.23 kg = 1468.55 kg/m
182.2 m' x 1.04 kg = 189.49 kg/m
749.088 m' x 1.04 kg = 779.05 kg/m
B2
Lt.5 - Lt.11
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
C2 - D2 6.6 √
TUMPUAN
5 x 4.845 = 24.225 m'
LAPANGAN
3 x 3.68 = 11.04 m'
2 x 7.575 = 15.15 m'
3 x 7.575 = 22.725 m'
D 13 - 150 0.15 m
1.836 m'
1.65 : 0.15 = 11 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
1.65 : 0.2 = 9 bh x 1 x 1.836 m' =
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.436 m'
16.524 m' Kebutuhan Sengkang 2 Kaki : 0.3875 : 0.2
Bekisting : 1 + 0.3
Beton : 0.3 x 0.5
D19 : 20.84 m' x 2.23
D13 : 4.6 m' x 1.04
Sengkang D13 : 11.488 m' x 1.04
2 Jenis Balok : B3
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
135.864 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
51.408 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.2
Bekisting : 1.3 + 0.35
Beton : 0.35 x 0.65
D19 : 84.72 m' x 2.23
D13 : 19.95 m' x 1.04
Sengkang D13 : 60.588 m' x 1.04
3 Jenis Balok : B3
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
40.392 m' Kebutuhan Sengkang 2 Kaki : 0.425 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
16.524 m' Kebutuhan Sengkang 2 Kaki : 0.425 : 0.2
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 10.475 m'
= 3.465 m'
= 4.6 m'
= 6.9 m'
150 0.15 m
200 0.2 m
x 1.55 x 1 = 2.02 m2
x 1.55 x 1 = 0.23 m3
kg = 46.54 kg/m
kg = 4.78 kg/m
kg = 11.95 kg/m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 13.6 m'
= 4.665 m'
= 6.65 m'
= 9.975 m'
150 0.15 m
200 0.2 m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 11.975 m'
= 3.69 m'
= 5.35 m'
= 8.025 m'
150 0.15 m
200 0.2 m
x 1.7 x 2 = 5.61 m2
x 1.7 x 2 = 0.77 m3
kg = 105.82 kg/m
kg = 11.13 kg/m
kg = 34.37 kg/m
Memanjang
1 Jenis Balok : B5
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
2 Jenis Balok : B5
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
3 Jenis Balok : B5
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
5 Jenis Balok : B5
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
Tulangan Tekan : 3 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m LAPANGAN
Tulangan Tarik : 3 D 16 0.016 m
6 Jenis Balok : B5
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
TUMPUAN
LAPANGAN
m
1 = 10.24 m2
1 = 0.77 m3
= 169.69 kg/m
= 16.35 kg/m
= 40.30 kg/m
TUMPUAN
LAPANGAN
TUMPUAN
LAPANGAN
2 = 21.12 m2
2 = 1.58 m3
= 349.20 kg/m
= 33.69 kg/m
= 82.88 kg/m
TUMPUAN
LAPANGAN
1 = 10.52 m2
1 = 0.79 m3
= 173.99 kg/m
= 16.78 kg/m
= 41.44 kg/m
TUMPUAN
LAPANGAN
1 = 10.92 m2
1 = 0.82 m3
= 180.13 kg/m
= 17.40 kg/m
= 43.14 kg/m
TUMPUAN
LAPANGAN
m
2 = 16.64 m2
2 = 1.25 m3
= 280.42 kg/m
= 26.78 kg/m
= 64.71 kg/m
Memanjang
Jenis Balok : BT
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.3 x 0.4 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 5 D 16 0.016 m
Tulangan Badan : 2 D 13 0.013 m TUMPUAN
Tulangan Tarik : 3 D 16 0.016 m
B2
Bekisting : 193.94 m2
Beton : 31.92 m3
D19 : 2054.31 Kg/m
D13 : 316.16 Kg/m
Sengkang D13 : 1267.87 Kg/m
B3
Bekisting : 19.26 m2
Beton : 2.61 m3
D19 : 341.57 Kg/m
D13 : 36.66 Kg/m
Sengkang D13 : 109.33 Kg/m
B5
Bekisting : 77.84 m2
Beton : 5.84 m3
D16 : 1307.33 Kg/m
Ø10 : 125.07 Kg/m
Sengkang Ø10 : 306.53 Kg/m
= 4.84 m2
= 0.53 m3
= 74.61 kg/m
= 11.65 kg/m
= 45.89 kg/m
Melintang
1 Jenis Balok : BA3
Lokasi : Atap
Ukuran Balok : 0.4 x 0.6 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 3 D 19 0.019 m
Memanjang
4 Jenis Balok : BA3
Lokasi : Atap
Ukuran Balok : 0.4 x 0.6 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 6 D 19 0.019 m
Tulangan Badan : 2 D 16 0.016 m TUMPUAN
Tulangan Tarik : 3 D 19 0.019 m
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
x 1.836 m' = 22.032 m' Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
x 1.836 m' = 9.18 m' Kebutuhan Sengkang 2 Kaki :
= 16.56 m2 Bekisting :
= 2.48 m3 Beton :
= 258.18 kg/m D19 :
= 41.33 kg/m D13 :
= 97.38 kg/m Sengkang D13 :
2 Jenis Balok :
Lokasi :
Ukuran Balok :
Cover :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Tulangan Tekan :
Tulangan Badan :
Tulangan Tarik :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Kebutuhan Tulangan :
Tulangan Tekan (D19) :
Tulangan Badan (D16) :
Tulangan Tarik (D19) :
Sengkang Tumpuan :
Panjang Sengkang 2 Kaki :
x 1.836 m' = 14.688 m' Kebutuhan Sengkang 2 Kaki :
Sengkang Lapangan :
Panjang Sengkang 2 Kaki :
x 1.836 m' = 5.508 m' Kebutuhan Sengkang 2 Kaki :
= 9.36 m2 Bekisting :
= 1.40 m3 Beton :
= 182.81 kg/m D19 :
= 27.08 kg/m D13 :
= 63.01 kg/m Sengkang D13 :
= 109.12 m2
= 16.37 m3
= 1453.36 kg/m
= 247.32 kg/m
= 630.12 kg/m
x 1.836 m' = 47.736 m'
= 23.36 m2
= 3.50 m3
= 301.10 kg/m
= 51.93 kg/m
= 137.48 kg/m
x 1.836 m' = 33.048 m'
= 16.96 m2
= 2.54 m3
= 234.10 kg/m
= 39.27 kg/m
= 95.47 kg/m
x 1.836 m' = 33.048 m'
= 8.40 m2
= 1.26 m3
= 116.21 kg/m
= 19.48 kg/m
= 47.74 kg/m
x 1.836 m' = 44.064 m'
= 33.60 m2
= 5.04 m3
= 436.57 kg/m
= 75.05 kg/m
= 189.03 kg/m
= 7.60 m2
= 1.14 m3
= 107.84 kg/m
= 17.89 kg/m
= 42.01 kg/m
Panjang
Melintang
B2
Lt.5 - Lt.11
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
D2 - F2 6.675 √
TUMPUAN
5 x 4.8825 = 24.4125 m'
LAPANGAN
3 x 3.7175 = 11.1525 m'
2 x 7.650 = 15.3 m'
3 x 7.650 = 22.95 m'
D 13 - 150 0.15 m
1.836 m'
1.66875 : 0.15 = 12 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
1.66875 : 0.2 = 9 bh x 1 x 1.836 m' =
B2
Lt.5 - Lt.11
0.35 x 0.65 m
0.04 2 sisi : 0.08 m
5 D 19 0.019 m
2 D 13 0.013 m TUMPUAN
3 D 19 0.019 m
3 D 19 0.019 m
2 D 13 0.013 m LAPANGAN
4 D 19 0.019 m
4
0.75 t
H2 - M2 21.8 √
TUMPUAN
5 x 12.445 = 62.225 m'
LAPANGAN
3 x 11.28 = 33.84 m'
2 x 22.775 = 45.55 m'
3 x 22.775 = 68.325 m'
D 13 - 150 0.15 m
1.836 m'
5.45 : 0.15 = 37 bh x 2 x 1.836 m' =
D 13 - 200 0.2 m
1.836 m'
5.45 : 0.2 = 28 bh x 1 x 1.836 m' =
1.3 + 0.35 x 21.8 x 4 = 143.88 m2
0.35 x 0.65 x 21.8 x 4 = 19.84 m3
657.56 m' x 2.23 kg = 1468.55 kg/m
182.2 m' x 1.04 kg = 189.49 kg/m
749.088 m' x 1.04 kg = 779.05 kg/m
Panjang Balok (PDF/18) - BALOK ATAP +44.50
Memanja
1 Jenis Balok : B3
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.3 x 0.5
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.436 m'
16.524 m' Kebutuhan Sengkang 2 Kaki : 0.4625 : 0.2
Bekisting : 1 + 0.3
Beton : 0.3 x 0.5
D19 : 22.94 m' x 2.23
D13 : 5.2 m' x 1.04
Sengkang D13 : 15.796 m' x 1.04
2 Jenis Balok : B3
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
135.864 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
51.408 m' Kebutuhan Sengkang 2 Kaki : 0.5875 : 0.2
Bekisting : 1.3 + 0.35
Beton : 0.35 x 0.65
D19 : 84.72 m' x 2.23
D13 : 19.95 m' x 1.04
Sengkang D13 : 60.588 m' x 1.04
3 Jenis Balok : B3
Lokasi : Lt.5 - Lt.11
Ukuran Balok : 0.35 x 0.65
Cover : 0.04 2 sisi : 0.08
Tulangan Tekan : 5 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 3 D 19
Tulangan Tekan : 3 D 19
Tulangan Badan : 2 D 13
Tulangan Tarik : 4 D 19
Sengkang Tumpuan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
Kebutuhan Sengkang 2 Kaki : 0.475 : 0.15
Sengkang Lapangan : D 13 -
Panjang Sengkang 2 Kaki : 1.836 m'
Kebutuhan Sengkang 2 Kaki : 0.475 : 0.2
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 11.225 m'
= 3.915 m'
= 5.2 m'
= 7.8 m'
150 0.15 m
200 0.2 m
x 1.85 x 1 = 2.41 m2
x 1.85 x 1 = 0.28 m3
kg = 51.23 kg/m
kg = 5.41 kg/m
kg = 16.43 kg/m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 13.6 m'
= 4.665 m'
= 6.65 m'
= 9.975 m'
150 0.15 m
200 0.2 m
m
m
0.019 m
0.013 m TUMPUAN
0.019 m
0.019 m
0.013 m LAPANGAN
0.019 m
= 12.475 m'
= 3.99 m'
= 5.75 m'
= 8.625 m'
150 0.15 m
200 0.2 m
x 1.9 x 2 = 6.27 m2
x 1.9 x 2 = 0.86 m3
kg = 112.07 kg/m
kg = 11.96 kg/m
kg = 42.01 kg/m
Memanjang
1 Jenis Balok : B5
Lokasi : Atap
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
2 Jenis Balok : B5
Lokasi : Atap
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
3 Jenis Balok : B5
Lokasi : Atap
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
4 Jenis Balok : B5
Lokasi : Atap
Ukuran Balok : 0.2 x 0.3 m
Cover : 0.025 2 sisi : 0.05 m
Tulangan Tekan : 4 D 16 0.016 m
Tulangan Badan : 2 Ø 10 0.01 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
B3
Bekisting :
Beton :
D19 :
D13 :
Sengkang D13 :
B5
Bekisting :
Beton :
m D16 :
Ø10 :
2 x 0.92 m' = 47.84 m' Sengkang Ø10 :
3 = 30.96 m2
3 = 2.32 m3
= 467.39 kg/m
= 49.42 kg/m
= 120.91 kg/m
TUMPUAN
LAPANGAN
TUMPUAN
LAPANGAN
3 = 32.64 m2
3 = 2.45 m3
= 538.55 kg/m
= 52.01 kg/m
= 129.42 kg/m
TUMPUAN
LAPANGAN
1 = 10.52 m2
1 = 0.79 m3
= 173.99 kg/m
= 16.78 kg/m
= 41.44 kg/m
UME PERHITUNGAN
256.96 m2
38.54 m3
3090.17 Kg/m
594.07 Kg/m
1493.18 Kg/m
187.94 m2
25.91 m3
1991.28 Kg/m
253.14 Kg/m
1031.10 Kg/m
20.31 m2
2.75 m3
352.51 Kg/m
38.12 Kg/m
121.45 Kg/m
82.52 m2
6.19 m3
1333.82 Kg/m
132.28 Kg/m
325.83 Kg/m
1 Jenis Balok : B4
Rumah Lift
Lokasi : Atap
Ukuran Balok : 0.3 x 0.4 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 3 D 16 0.016 m
Tulangan Badan : 2 D 13 0.013 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
2 Jenis Balok : B4
Lokasi : Rumah Lift
Atap
Ukuran Balok : 0.3 x 0.4 m
Cover : 0.04 2 sisi : 0.08 m
Tulangan Tekan : 3 D 16 0.016 m
Tulangan Badan : 2 D 13 0.013 m TUMPUAN
Tulangan Tarik : 2 D 16 0.016 m
TUMPUAN
LAPANGAN
m
2 x 1.2 m' = 12 m' Kebutuhan Sengkang 2 Kaki :
4 = 8.80 m2
4 = 0.96 m3
= 89.17 kg/m
= 21.63 kg/m
= 41.46 kg/m
TUMPUAN
LAPANGAN
BA4
Bekisting : 13.40 m2
Beton : 1.07 m3
D16 : 145.10 Kg/m
Ø10 : 19.50 Kg/m
Sengkang Ø10 : 55.28 Kg/m
x 1.12 m' = 31.36 m'
= 6.65 m2
= 0.53 m3
= 62.40 kg/m
= 8.95 kg/m
= 26.26 kg/m
= 4.60 m2
= 0.37 m3
= 55.92 kg/m
= 7.16 kg/m
= 19.35 kg/m
Panjang Sloof ( PDF/12)
Jenis As Panjang (m)
F2 - G2 2
S1 G2 - H2 2
F2-3 1.7
J'7 - K7 2.85 14
K7 - L7 1.95
L7 - M7 3.45 3
B1
B3
F4 - I4 6.2 5 G3 - G4 2.35 2
B1 I4 - J4 6.2 6 B5 G4 - G7 5.25 1
J4 - K4 6.2 7 H1 - H2 1.7 2
B3
K4 - M4 6.2 8 H3 - H4 2.35 3
D5 - F5 6.675 3 B5 H4 - H7 5.25 2
B2
H5 - M5 21.8 3 I1 - I4 7 1
B1
D6 - F6 6.675 4 I4 - I7 5 1
B2
H6 - M6 21.8 4 B5 I'1 - I'7 13.20 1
D7 - E7 3.45 2 J1 - J4 7 2
B1
E7 - F7 1.95 2 J4 - J7 5 2
F7- I7 6.2 9 B5 J'1 -J'7 13.2 2
B1 I7 - J7 6.2 10 K1 - K4 7 3
B1
J7 - K7 6.2 11 K4 - K7 5 3
K7 - L7 1.95 3 B5 L1 -L7 13.15 1
L7 - M7 3.45 3 B5 L'2 - L'7 13.65 1
B1 C1 - D1 6.2 12 M2 - M4 4.75 1
B1
C2 - D2 6.6 1 M4 - M7 5 4
C3 - D3 6.6 2 D1 - D4 7.3 2
B2 B1
C5 - D5 6.6 3 D4 - D7 5.3 2
C6 - D6 6.6 4 B5 D'2 - D'7 10.4 2
C4 - D4 6.2 13
B1
C7 - D7 6.2 14
Dimensi Sloof
S1 0.4 X 0.9
S2 0.35 X 0.7
S3 0.3 X 0.5
Dimensi Balok
B1 0.4 X 0.75
B2 0.3 X 0.6
B3 0.3 X 0.5
B4 0.3 X 0.4
B5 0.2 X 0.3
Dimensi Balok
BL 0.3 X 0.5
BA1 0.4 X 0.75
BA2 0.35 X 0.65
BA3 0.4 X 0.6
BA4 0.2 X 0.4
Dimensi Balok
BD1 0.4 X 0.8
BD2 0.35 X 0.65
BD3 0.25 X 0.4
BR1 0.4 X 0.7
BR2 0.3 X 0.4
BT 0.3 X 0.4
B.Bordes 0.3 X 0.4
BK 0.3 X 0.5
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah plat pit lift FL. -5.50 )
1 Lokasi : Denah plat pit lift FL. -5.50
P: 7.78 m
L: 4.68 m
Tebal Selimut : 10 cm 0.01 m
Tebal pile cap : 1.1 m
Arah Y : 47 bh x 2 = 94 bh
Berat Tul Y : 94 bh x 7.78 m x 2.233 Kg = 1632.232
→ Bekisting
Luas : 36.41 m2 + 17.11 m2 + 10.30 m2 = 63.82
→ Beton 40.0542 m3
RESUME PERHITUNGAN
PLAT PIT LIFT
PDF/20 Besi D19 : 3263.905 Kg
Bekisting : 63.82 m2
Beton : 40.05421 m3
Kg/m
Kg/m
m2
Denah Plat Basement FL. -4.00 PERHITUNGAN KEBUTUHAN TULANGAN ( Dena
Area C1 - D1 C7 - D7 1 1 Lokasi : C1 - D1 C7 - D7
P: 15.00 m P: 15.00 m
L: 9.56 m L: 9.56 m
Tebal Selimut : 10 cm
Area D1 - F1 D7 - F7 2 Tebal pile cap : 1.1 m
P: 15.00 m Jumlah area sejenis : 2 unit
L: 9.56 m
→ Penulangan Double Atas Bawah
Area F1 - I1 F7 - I7 3 Arah X : D 19
P: 15.00 m Arah Y : D 19
L: 7.88 m Kebutuhan :
Arah X : 150 bh x
Area I1 - J1 I7 -J7 4 Berat Tul X : 600 bh x
P: 15.00 m
L: 7.88 m Arah Y : 96 bh x
Berat Tul Y : 384 bh x
Area J1 - K1 J7 -K7 5
P: 15.00 m → Bekisting 143.44 m2 +
L: 7.69 m Luas : 197.48 m2 x
→ Bekisting 115.31 m2 +
Luas : 165.23 m2 x
→ Beton
P: 15.00 m
L: 8.50 m
Tebal pile cap : 1.1 m
Volume Beton : 15.00 m x
PENGURANGAN VOID
1 Lokasi : D1 - E1 D2 - E2
P: 5.4 m
L: 2.4 m
Tebal Selimut : 20 cm
Jumlah area sejenis : 1 unit
Arah Y : 16 bh x
Berat Tul Y : 32 bh x
→ Bekisting 12.96 m2 +
Luas : 13.58 m2 x
→ Beton
P: 5.40 m
L: 2.40 m
Tebal Selimut : 0.02 cm
Volume Beton : 5.40 m x
TUHAN TULANGAN ( Denah Plat Basement FL. -4.00 ) PERHITUNGAN KEBUTUH
PDF/21 1
0.01 m
→
- 100 0.1 m
- 100 0.1 m
2 x 2 = 600 bh
9.56 m x 2.233 Kg = 12813.75 Kg/m
2 x 2 = 384 bh
15.00 m x 2.233 Kg = 12864 Kg/m
0.01 m
→
- 100 0.1 m
- 100 0.1 m
2 x 1 = 300 bh
7.69 m x 2.233 Kg = 5150.625 Kg/m
2 x 1 = 154 bh
15.00 m x 2.233 Kg = 5159 Kg/m
PENGURANGAN VOID
PDF/23
0.02 m
- 150 0.15 m
- 150 0.15 m
2 x 1 = 72 bh
2.40 m x 0.617 Kg = 106.6176 Kg/m
2 x 1 = 32 bh
5.40 m x 0.617 Kg = 106.6176 Kg/m
Arah Y : 79 bh x 2 x 2 = 316 bh
Berat Tul Y : 316 bh x 15.00 m x 2.233 Kg = 10586 Kg/m
Beton
P: 15.00 m
L: 8.50 m
Tebal pile cap : 1.1 m
Volume Beton : 15.00 m x 8.50 m x 1.1 m = 280.5 m3
Arah Y : 85 bh x 2 x 1 = 170 bh
Berat Tul Y : 170 bh x 15.00 m x 2.233 Kg = 5695 Kg/m
Beton
P: 15.00 m
L: 8.50 m
Tebal pile cap : 1.1 m
Volume Beton : 15.00 m x 8.50 m x 1.1 m = 140.25 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Basement FL. -4.00 )
1 Lokasi : A1 - AA'1 A2 - AA'2
P: 3.6 m
L: 1.8 m
Tebal Selimut : 10 cm 0.01 m
Tebal pile cap : 1.1 m
Jumlah area sejenis : 3 unit
Arah Y : 18 bh x 2 x 3 =
Berat Tul Y : 108 bh x 3.60 m x 2.233 Kg =
→ Beton
P: 15.00 m
L: 8.50 m
Tebal pile cap : 1.1 m
Volume Beton : 15.00 m x 8.50 m x 1.1 m =
Arah Y : 36 bh x 2 x 1 =
Berat Tul Y : 72 bh x 3.60 m x 2.233 Kg =
→ Beton
P: 15.00 m
L: 8.50 m
Tebal pile cap : 1.1 m
Volume Beton : 15.00 m x 8.50 m x 1.1 m =
Dilebihkan 1/4Lo
t FL. -4.00 ) RESUME PERHITUNGAN
PDF/21 PLAT BASEMENT
Besi D19 : 71197.04 Kg
Bekisting : 1146.57 m2
Beton : 1402.241 m3
216 bh
868.32 Kg/m
108 bh
868.32 Kg/m
18.36 m2
55.08 m2
420.75 m3
t FL. -4.00 )
PDF/21
72 bh
578.88 Kg/m
72 bh
578.88 Kg/m
28.80 m2
28.8 m2
140.25 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 1 FL. -0.30 )
1 Lokasi : C4 - D4 C7 - D7
P: 7.40 m
L: 6.40 m
Tebal Plat : 20 cm 0.02 m
Jumlah area sejenis : 1 unit
Arah Y : 43 bh x 2 x 1 =
Berat Tul Y : 86 bh x 7.40 m x 0.617 Kg =
→ Beton
P: 7.00 m
L: 6.00 m
Tebal Plat : 0.02 cm
Volume Beton : 7.00 m x 6.00 m x 0.02 m =
RESUME PERHITUNGAN
PLAT LANTAI 1 TYPE D
Besi Ø10 : 787.5388 Kg
Bekisting : 48.46 m2
Beton : 0.84 m3
FL. -0.30 )
PDF/22
100 bh
394.88 Kg/m
86 bh
392.6588 Kg/m
48.46 m2
48.464 m2
0.84 m3
3 Denah Plat Lantai 1 FL. +0.50 PERHITUNGAN KEBUTUHAN TULANGAN ( Dena
Area D1 - F1 D7 - F7 1 Lokasi : D1 - F1 D7 - F7
P: 14.00 m P: 14.40 m
L: 7.68 m L: 7.88 m
Tebal Plat : 20 cm
Area F1 - I1 F7 - I7 Jumlah area sejenis : 1 unit
P: 14.00 m
L: 7.88 m → Penulangan Double Atas Bawah
Arah X : Ø 10
Area I1 - J1 I7 -J7 Arah Y : Ø 10
P: 14.00 m Kebutuhan :
L: 7.88 m Arah X : 96 bh x
Berat Tul X : 192 bh x
Area J1 - K1 J7 -K7
P: 14.00 m Arah Y : 53 bh x
L: 7.69 m Berat Tul Y : 106 bh x
Arah Y : 17 bh x
Berat Tul Y : 68 bh x
→ Bekisting 10.63 m2 +
Luas : 11.17 m2 x
→ Beton
P: 4.25 m
L: 2.50 m
Tebal Selimut : 0.02 cm
Volume Beton : 4.25 m x
UTUHAN TULANGAN ( Denah Plat Lantai 1 FL. -0.50 ) PERHITUNGAN KEBUTU
PDF/23 1 Lokasi :
P:
L:
0.02 m Tebal Plat :
Jumlah area sejenis :
2 x 1 = 106 bh Arah Y :
14.40 m x 0.617 Kg = 941.7888 Kg/m Berat Tul Y :
→ Beton
P:
L:
Tebal Selimut :
7.68 m x 0.02 m = 2.149 m3 Volume Beton :
PENGURANGAN VOID
PDF/23 1 Lokasi :
P:
L:
0.02 m Tebal Plat :
Jumlah area sejenis :
2 x 2 = 68 bh Arah Y :
4.25 m x 0.617 Kg = 178.313 Kg/m Berat Tul Y :
0.09 m2 x 0.05 m2 = 11.17 m2 → Bekisting
2 = 22.33 m2 Luas :
→ Beton
P:
L:
Tebal Selimut :
2.50 m x 0.02 m = 0.425 m3 Volume Beton :
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 1 FL. -0.50 ) PER
F1 - I1 F7 - I7 PDF/23 1
14.40 m
7.88 m
20 cm 0.02 m
2 unit
96 bh x 2 x 2 = 384 bh
384 bh x 7.88 m x 0.617 Kg = 1865.808 Kg/m
53 bh x 2 x 2 = 212 bh
212 bh x 14.40 m x 0.617 Kg = 1883.578 Kg/m
→
14.00 m
7.88 m
0.02 cm
14.00 m x 7.88 m x 0.02 m = 4.41 m3
PENGURANGAN VOID
D1 - E1 D2 - E2 PDF/23
5.40 m
2.40 m
20 cm 0.02 m
1 unit
36 bh x 2 x 1 = 72 bh
72 bh x 2.40 m x 0.617 Kg = 106.6176 Kg/m
16 bh x 2 x 1 = 32 bh
32 bh x 5.40 m x 0.617 Kg = 106.6176 Kg/m
12.96 m2 + 0.11 m2 x 0.05 m2 = 13.58 m2
13.58 m2 x 1 = 13.584 m2
5.40 m
2.40 m
0.02 cm
5.40 m x 2.40 m x 0.02 m = 0.2592 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 1 FL. -0.50 )
Lokasi : F1 - I1 F7 - I7 PDF/23
P: 14.40 m
L: 7.69 m
Tebal Plat : 20 cm 0.02 m
Jumlah area sejenis : 1 unit
Arah Y : 52 bh x 2 x 1 = 104 bh
Berat Tul Y : 104 bh x 14.40 m x 0.617 Kg = 924.0192 Kg/m
Beton
P: 14.00 m
L: 7.69 m
Tebal Selimut : 0.02 cm
Volume Beton : 14.00 m x 7.69 m x 0.02 m = 2.1525 m3
RESUME PERHITUNGAN
PLAT LANTAI 1 TYPE D
Besi Ø10 : 7670.174 Kg
Bekisting : 527.51 m2
Beton : 9.9873 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 1 FL. -0.50 )
1 Lokasi : K1 - M1 K7 -M7
P: 14.40 m
L: 7.20 m
Tebal Plat : 20 cm 0.02 m
Jumlah area sejenis : 1 unit
Arah Y : 48 bh x 2 x 1 =
Berat Tul Y : 96 bh x 14.40 m x 0.617 Kg =
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.02 cm
Volume Beton : 14.00 m x 7.00 m x 0.02 m =
-0.50 )
PDF/23
192 bh
852.9408 Kg/m
96 bh
852.9408 Kg/m
105.41 m2
105.408 m2
1.96 m3
4 Denah Plat Lantai 2 FL. +4.50 - Lantai 4 FL. +12.50 PERHITUNGAN KEBUTUHAN TULA
Area C1 - D1 C7 - D7 1 Lokasi : C1 - D1
P: 14.00 m P: 14.40
L: 8.06 m L: 8.26
Tebal Plat : 12
Area D1 - F1 D7 - F7 Jumlah area sejenis : 1
P: 14.00 m
L: 7.68 m → Penulangan Double Atas Bawah
Arah X : Ø
Area F1 - I1 F7 - I7 Arah Y : Ø
P: 14.00 m Kebutuhan :
L: 7.88 m Arah X : 96
Berat Tul X : 192
Area I1 - J1 I7 -J7
P: 14.00 m Arah Y : 56
L: 7.88 m Berat Tul Y : 112
PENGURAN
1 Lokasi : D1 - E1
P: 4.25
L: 2.50
Tebal Plat : 12
Jumlah area sejenis : 2
Arah Y : 17
Berat Tul Y : 68
→ Bekisting 10.63
Luas : 10.95
→ Beton
P: 4.25
L: 2.50
Tebal Selimut : 0.01
Volume Beton : 4.25
UNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 2 - 4 ) PERHITUNG
C7 - D7 PDF/24 1
m
m
cm 0.012 m
unit
→
10 - 150 0.15 m
10 - 150 0.15 m
bh x 2 x 1 = 192 bh
bh x 8.26 m x 0.617 Kg = 978.8088 Kg/m
bh x 2 x 1 = 112 bh
bh x 14.40 m x 0.617 Kg = 995.0976 Kg/m
→
m
m
cm
m x 7.00 m x 0.01 m = 1.176 m3
PENGURANGAN VOID
D2 - E2 PDF/24 1
m
m
cm 0.012 m
unit
→
10 - 150 0.15 m
10 - 150 0.15 m
bh x 2 x 2 = 116 bh
bh x 2.50 m x 0.617 Kg = 178.93 Kg/m
bh x 2 x 2 = 68 bh
bh x 4.25 m x 0.617 Kg = 178.313 Kg/m
m2 + 0.05 m2 x 0.03 m2 = 10.95 m2 →
m2 x 2 = 21.898 m2
→
m
m
cm
m x 2.50 m x 0.01 m = 0.255 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 2 - 4 )
Lokasi : D1 - F1 D7 - F7 PDF/24
P: 14.40 m
L: 7.68 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 52 bh x 2 x 1 = 104 bh
Berat Tul Y : 104 bh x 14.40 m x 0.617 Kg = 924.0192 Kg/m
Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.00 m x 0.01 m = 1.176 m3
PENGURANGAN VOID
Lokasi : D1 - E1 D2 - E2 PDF/24
P: 5.40 m
L: 2.40 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 16 bh x 2 x 1 = 32 bh
Berat Tul Y : 32 bh x 5.40 m x 0.617 Kg = 106.6176 Kg/m
Bekisting 12.96 m2 + 0.06 m2 x 0.03 m2 = 13.33 m2
Luas : 13.33 m2 x 1 = 13.3344 m2
Beton
P: 5.40 m
L: 2.40 m
Tebal Selimut : 0.01 cm
Volume Beton : 5.40 m x 2.40 m x 0.01 m = 0.15552 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 2 - 4 )
1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.88 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 2 unit
Arah Y : 53 bh x 2 x 2 =
Berat Tul Y : 212 bh x 14.40 m x 0.617 Kg =
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.00 m x 0.01 m =
RESUME PERHITUNGAN
PLAT LANTAI 2-4 TYPE A
Besi Ø10 : 10526.64 Kg
Bekisting : 641.83 m2
Beton : 6.65 m3
-4) PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 2 - 4
PDF/24 1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.69 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
212 bh Arah Y : 52 bh x 2 x
1883.578 Kg/m Berat Tul Y : 104 bh x 14.40 m x
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
2.352 m3 Volume Beton : 14.00 m x 7.00 m x
RHITUNGAN
AI 2-4 TYPE A
( Denah Plat Lantai 2 - 4 ) PERHITUNGAN KEBUTUHAN TULANGAN ( D
PDF/24 1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.20 m
Tebal Plat : 12 cm
Jumlah area sejenis : 1 unit
1 = 104 bh Arah Y : 48 bh x
0.617 Kg = 924.0192 Kg/m Berat Tul Y : 96 bh x
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
0.01 m = 1.176 m3 Volume Beton : 14.00 m x
BUTUHAN TULANGAN ( Denah Plat Lantai 2 - 4 )
PDF/24
0.012 m
- 150 0.15 m
- 150 0.15 m
2 x 1 = 192 bh
7.20 m x 0.617 Kg = 852.9408 Kg/m
2 x 1 = 96 bh
14.40 m x 0.617 Kg = 852.9408 Kg/m
PENGURAN
1 Lokasi : D1 - E1
P: 4.25
L: 2.50
Tebal Plat : 12
Jumlah area sejenis : 2
Arah Y : 17
Berat Tul Y : 68
→ Bekisting 10.63
Luas : 10.95
→ Beton
P: 4.25
L: 2.50
Tebal Selimut : 0.01
Volume Beton : 4.25
UNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 5 - 11 ) PERHITUNG
C7 - D7 PDF/25 1
m
m
cm 0.012 m
unit
→
10 - 150 0.15 m
10 - 150 0.15 m
bh x 2 x 1 = 192 bh
bh x 8.26 m x 0.617 Kg = 978.8088 Kg/m
bh x 2 x 1 = 112 bh
bh x 14.40 m x 0.617 Kg = 995.0976 Kg/m
→
m
m
cm
m x 7.00 m x 0.01 m = 1.176 m3
PENGURANGAN VOID
D2 - E2 PDF/25 1
m
m
cm 0.012 m
unit
→
10 - 150 0.15 m
10 - 150 0.15 m
bh x 2 x 2 = 116 bh
bh x 2.50 m x 0.617 Kg = 178.93 Kg/m
bh x 2 x 2 = 68 bh
bh x 4.25 m x 0.617 Kg = 178.313 Kg/m
m2 + 0.05 m2 x 0.03 m2 = 10.95 m2 →
m2 x 2 = 21.898 m2
→
m
m
cm
m x 2.50 m x 0.01 m = 0.255 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 5 - 11 )
Lokasi : D1 - F1 D7 - F7 PDF/25
P: 14.40 m
L: 7.68 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 52 bh x 2 x 1 = 104 bh
Berat Tul Y : 104 bh x 14.40 m x 0.617 Kg = 924.0192 Kg/m
Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.00 m x 0.01 m = 1.176 m3
PENGURANGAN VOID
Lokasi : D1 - E1 D2 - E2 PDF/25
P: 5.40 m
L: 2.40 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 16 bh x 2 x 1 = 32 bh
Berat Tul Y : 32 bh x 5.40 m x 0.617 Kg = 106.6176 Kg/m
Bekisting 12.96 m2 + 0.06 m2 x 0.03 m2 = 13.33 m2
Luas : 13.33 m2 x 1 = 13.3344 m2
Beton
P: 5.40 m
L: 2.40 m
Tebal Selimut : 0.01 cm
Volume Beton : 5.40 m x 2.40 m x 0.01 m = 0.15552 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 5 - 11 )
1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.88 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 2 unit
Arah Y : 53 bh x 2 x 2 =
Berat Tul Y : 212 bh x 14.40 m x 0.617 Kg =
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.00 m x 0.01 m =
RESUME PERHITUNGAN
PLAT LANTAI 2-4 TYPE A
Besi Ø10 : 10526.64 Kg
Bekisting : 641.83 m2
Beton : 6.65 m3
- 11 ) PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai 5 - 1
PDF/25 1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.69 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
212 bh Arah Y : 52 bh x 2 x
1883.578 Kg/m Berat Tul Y : 104 bh x 14.40 m x
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
2.352 m3 Volume Beton : 14.00 m x 7.00 m x
RHITUNGAN
AI 2-4 TYPE A
( Denah Plat Lantai 5 - 11 ) PERHITUNGAN KEBUTUHAN TULANGAN ( D
PDF/25 1 Lokasi : D1 - F1 D7 - F7
P: 14.40 m
L: 7.20 m
Tebal Plat : 12 cm
Jumlah area sejenis : 1 unit
1 = 104 bh Arah Y : 48 bh x
0.617 Kg = 924.0192 Kg/m Berat Tul Y : 96 bh x
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
0.01 m = 1.176 m3 Volume Beton : 14.00 m x
UTUHAN TULANGAN ( Denah Plat Lantai 5 - 11 )
PDF/25
0.012 m
- 150 0.15 m
- 150 0.15 m
2 x 1 = 192 bh
7.20 m x 0.617 Kg = 852.9408 Kg/m
2 x 1 = 96 bh
14.40 m x 0.617 Kg = 852.9408 Kg/m
Arah Y : 16 bh x
Berat Tul Y : 32 bh x
→ Bekisting 12.96 m2 +
Luas : 13.33 m2 x
→ Beton
P: 5.40 m
L: 2.40 m
Tebal Selimut : 0.01 cm
Volume Beton : 5.40 m x
UHAN TULANGAN ( Denah Plat Lantai Atap FL. +44.50 ) PERHITUNGAN KEBUTUHA
PDF/26 1 Lokasi :
P:
L:
0.012 m Tebal Plat :
Jumlah area sejenis :
2 x 1 = 106 bh Arah Y :
14.40 m x 0.617 Kg = 941.7888 Kg/m Berat Tul Y :
→ Beton
P:
L:
Tebal Selimut :
7.68 m x 0.01 m = 1.2894 m3 Volume Beton :
- 150 0.15 m
- 150 0.15 m
2 x 1 = 72 bh
2.40 m x 0.617 Kg = 106.6176 Kg/m
2 x 1 = 32 bh
5.40 m x 0.617 Kg = 106.6176 Kg/m
0.06 m2 x 0.03 m2 = 13.33 m2
1 = 13.3344 m2
96 bh x 2 x 2 = 384 bh
384 bh x 7.88 m x 0.617 Kg = 1865.808 Kg/m
53 bh x 2 x 2 = 212 bh
212 bh x 14.40 m x 0.617 Kg = 1883.578 Kg/m
→
14.00 m
7.88 m
0.01 cm
14.00 m x 7.88 m x 0.01 m = 2.646 m3
RESUME PERHITUNGAN
PLAT LANTAI ATAP TYPE A
7085.63 Kg
546.55 m2
6.25 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai Atap FL. +44.50 )
Lokasi : F1 - I1 F7 - I7 PDF/26
P: 14.40 m
L: 7.69 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 52 bh x 2 x 1 = 104 bh
Berat Tul Y : 104 bh x 14.40 m x 0.617 Kg = 924.0192 Kg/m
Beton
P: 14.00 m
L: 7.69 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.69 m x 0.01 m = 1.2915 m3
PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lantai Atap FL. +44.50 )
1 Lokasi : K1 - M1 K7 -M7
P: 14.40 m
L: 7.20 m
Tebal Plat : 12 cm 0.012 m
Jumlah area sejenis : 1 unit
Arah Y : 48 bh x 2 x 1 =
Berat Tul Y : 96 bh x 14.40 m x 0.617 Kg =
→ Beton
P: 14.00 m
L: 7.00 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.00 m x 0.01 m =
. +44.50 )
PDF/26
192 bh
852.9408 Kg/m
96 bh
852.9408 Kg/m
104.72 m2
104.7168 m2
1.176 m3
Denah Plat Lantai Rumah Lift +47.00 PERHITUNGAN KEBUTUHAN TULANGAN ( Denah Plat Lanta
Area F2 - H2 F3 - H3 1 Lokasi : D1 - F1 D7 - F7
P: 2.40 m P: 2.80 m
L: 5.40 m L: 9.60 m
Tebal Plat : 10 cm 0.01
Area K1 - M1 K2 - M2 Jumlah area sejenis : 1 unit
P: 2.50 m
L: 7.00 m → Penulangan Double Atas Bawah
Arah X : Ø 10 -
Arah Y : Ø 10 -
Kebutuhan :
Arah X : 14 bh x 2
Berat Tul X : 28 bh x 9.60
Arah Y : 48 bh x 2
Berat Tul Y : 96 bh x 2.80
→ Beton
P: 14.00 m
L: 7.68 m
Tebal Selimut : 0.01 cm
Volume Beton : 14.00 m x 7.68
RESUME PERHITUNGAN
PLAT LANTAI ATAP RUMAH LIFT TYPE C
Besi Ø10 : 739.41 Kg
Bekisting : 60.42 m2
Beton : 2.15 m3
GAN ( Denah Plat Lantai Atap Rumah Lift FL. +47.00) PERHITUNGAN KEBUTUHAN TULANGAN ( Denah
PDF/27 1 Lokasi : D1 - F1 D7 - F7
P: 2.90 m
L: 11.20 m
m Tebal Plat : 10 cm
Jumlah area sejenis : 1 unit
x 1 = 96 bh Arah Y : 56 bh x
m x 0.617 Kg = 165.8496 Kg/m Berat Tul Y : 112 bh x
→ Beton
P: 14.00 m
L: 7.68 m
Tebal Selimut : 0.01 cm
m x 0.01 m = 1.0745 m3 Volume Beton : 14.00 m x
AN TULANGAN ( Denah Plat Lantai Atap Rumah Lift FL. +47.00)
PDF/27
0.01 m
- 200 0.2 m
- 200 0.2 m
2 x 1 = 30 bh
11.20 m x 0.617 Kg = 207.312 Kg/m
2 x 1 = 112 bh
2.90 m x 0.617 Kg = 200.4016 Kg/m
NO LOKASI
1 Denah plat pit lift Fl. -5.50
P: 7.78 m
L: 4.68 m
Area D1 - F1 D7 - F7
P: 15.00 m
L: 9.56 m
Area F1 - I1 F7 - I7
P: 15.00 m
L: 7.88 m
Area I1 - J1 I7 -J7
P: 15.00 m
L: 7.88 m
Area J1 - K1 J7 -K7
P: 15.00 m
L: 7.69 m
Area K1 - M1 K7 -M7
P: 15.00 m
L: 8.50 m
Area F1 - I1 F7 - I7
P: 14.00 m
L: 7.88 m
Area I1 - J1 I7 -J7
P: 14.00 m
L: 7.88 m
Area J1 - K1 J7 -K7
P: 14.00 m
L: 7.69 m
Area K1 - M1 K7 -M7
P: 14.00 m
L: 7.00 m
Area D1 - F1 D7 - F7
P: 14.00 m
L: 7.68 m
Area F1 - I1 F7 - I7
P: 14.00 m
L: 7.88 m
Area I1 - J1 I7 -J7
P: 14.00 m
L: 7.88 m
Area J1 - K1 J7 -K7
P: 14.00 m
L: 7.69 m
Area K1 - M1 K7 -M7
P: 14.00 m
L: 7.00 m
Area K1 - M1 K2 - M2
P: 2.50 m
L: 7.00 m
Dilebihkan 1/4Lo