MINIMUM TEST
REQUIREMENTS
C O N S T R U C T I O N M AT E R I A L S
AND TESTING
FR
10 kg
MINIMUM QUANTITY/VOLUME OF
MNIMUM TESTING
MATERIALS MATERIALS FOR EACH SAMPLE
REQUIREMENTS
SUBMITTED
2. Asphaltic material 1 sample per 40T or 200 drums 5L
5L
20 kg
70 kg
50 kg
20 kg
50 kg
50 kg
Prepared by: Dr. KVS Caingles and Engr. RC Galdo, M.Eng
FR
MNIMUM TESTING MINIMUM QUANTITY/VOLUME OF
MATERIALS
REQUIREMENTS MATERIALS FOR EACH SAMPLE SUBMITTED
6. Non – Reinforced 2 pipes min./0.5% of
2 pipes
Concrete Pipes no. of pipes
2 pipes
3 units
1 meter
2 meters
1m x 2m
1can – 4liters
1 set (3 cylinders)
1 set (3 beams)
MINIMUM QUANTITY/VOLUME
MNIMUM TESTING
MATERIALS OF MATERIALS FOR EACH
REQUIREMENTS
SAMPLE SUBMITTED
17. Joint – filler (pre – molded) 1 – 400mm x 400mm
1. When cement is placed in contact with the aggregate, batches may be rejected unless mixed
within _____ hours of such contact.
a) 1.5 hours c) 0.5 hours
b) 2.0 hours d) 2.5 hours
2. When mixed at the site or in a central mixing plant, the mixing time shall not be less than
______ nor more than ____ unless mixer performance test prove adequate mixing of concrete in a
shorter time period.
a) 30 seconds nor more than 90 seconds
b) 50 seconds nor more than 90 seconds
c) 60 seconds nor more than 120 seconds
d) 90 seconds nor more than 120 seconds
3. The flow of water shall be uniform and all water should be in the drum by the end of the first
____ seconds of the mixing period.
a) 45 seconds c) 15 seconds
b) 30 seconds d) 20 seconds
4. Concrete not place within ____ minutes from the time the ingredients were
charged into the mixing drum shall be not used.
a) 120 minutes c) 60 minutes
b) 150 minutes d) 90 minutes
5. When concrete is delivered in truck mixers, additional water may be added to the
batch and additional mixing performed to increase the slump to meet the specified
requirement if permitted by the Engineer, provided all these operation are
performed within ____ after the initial mixing operation and the water and cement
ratio is not exceeded.
a) 30 minutes c) 45 minutes
b) 15 minutes d) 60 minutes
DPWH Standard Specifications for Public Works and Highway (2004 edition), Volume II