You are on page 1of 5

138 Anticorrosive Rubber Lining

Rubber Lining of Pipes


In the case of pipes, the sandblasted inner sur-
faces are coated by pouring with adhesive solutions.
For this purpose the pipes are laid obliquely on two
“A” frame stands of different height, say 3 ft and/or
2½ ft. While pouring the adhesive through the pipe,
the pipe is rotated slowly and the excess is collected
in a container at the opposite end. This operation
is repeated twice in each case, the coating of the
adhesive solution being allowed to dry. Next, a pre-
viously formed tube of rubber having length of at
least 50 cm longer than that of the pipe is closed at
both ends. At one end a small opening is made by
pinching and the tube is inflated with air. The tube
is then drawn into the coated pipe with the aid of
a rope made of nylon or cotton duck. The air pres-
sure is then increased by additional pumping of air
through the pinched hole to allow the tube to be
pressed well on the wall of the pipe. The two closed
ends of the tube are then cut open and one of the
protruding ends is folded and pressed into contact
with the whole area of the flange of the mild steel
pipe (Fig. 15.7).
√ √ The other end of the pipe remains free when the
mild steel pipe is firmly clamped. A bell-shaped rub-
√ √ ber bung of low hardness (45 degrees A) is slowly
drawn into the pipe from the end where the rubber is
Figure 15.6  Sheet-laying procedure. folded and fixed onto the flange by means of a cable
attached to an electric winch motor. The diameter
air. The overlap joints should be finally rerolled. The of this rubber bung is about 10% greater than the
sheets should be marked by segments with a chalk inside diameter of the pipe to be lined and is coated
stick, each segment being marked after rolling to dif- with lubricants such as talc and soft soap to reduce
ferentiate rolled as well as unrolled surfaces. the friction when it is drawn through. When the
bung moves, it presses the rubber tube against the
wall of the mild steel pipe and expels the air trapped
Procedure of Tank Inspection between the tube and the pipe. Finally, the free end
Before Lining of the tube is then pressed onto the other flange with
a roller and stitched. The lined pipe is now ready
After fabrication of the tank, the metal surface should for autoclave vulcanization. Recommended maxi-
be inspected for any pitting or projections, which should mum lengths of straight pipe for satisfactory lin-
be leveled out by grinding. This visual inspection should ing are given in Table 15.3. There is no standard
be done before the tank is hydraulically tested since rust for the maximum length of straight pipes of vari-
formed immediately after the hydraulic test will camou- ous diameters for lining. Since lengthy pipes with
flage the defects on the surface. Any leaks at the metal smaller diameters cannot be accessed for inspection
joints found during hydraulic testing should be repaired and testing, the maximum lengths of straight pipes
before the start of rubber lining and not during the oper- are recommended based on normal and convenient
ation. Before the start of rubber lining the tank should industrial practice.
be properly earthed. The lining operator should check The conventional method of lining pipes involves
the earthing beforehand. the use of rubber bungs. In this method, the green
15: Manufacturing Rubber Sheets and Application Procedures 139

Figure 15.7  Rubber lining of long pipe using a rubber bung tool.

Figure 15.8  Rubber lining of short pipe using a vacuum. (1) Hose made from ebonite closed at one end. (2) Iron
pipe. (3) Soft rubber cover with hose connection to the pump. (4) Iron bell with hose connection to the pump. (5)
Vacuum pump.

Table 15.3  Recommended Maximum Lengths of Straight Pipes for Lining


Nominal Bore (mm) Maximum Length Between Flanges (mm)
25 1000
40 2000
50 3000
65 4000
80 5000
100 and above 6000

(unvulcanized) rubber sheet is made in the form of The disadvantages of this process are (1) folding
a tube called a slew and the tube is drawn into the of the slew during the passage of the bung, (2) air
coated pipe. The tube length is longer than the length entrapment, and (3) low productivity.
of the pipe. The bung diameter is also larger than that To overcome these disadvantages, a special process
of the pipe. The rubber bung is drawn from one end using a vacuum technique can be adopted (Fig. 15.8).
of the tube toward the other end using a winch motor. In western countries this process is popular. The tube or
The travel of the bung presses the tube against the wall slew is closed at one end and drawn into the coated pipe.
of the pipe and expels the air trapped between the rub- The open end of the tube is stuck to the flange of the pipe
ber and the pipe. After this process, the lined pipe is and closed with a soft rubber cover, which is connected
cured. to a vacuum pump by a hose. A metallic cover, which is
140 Anticorrosive Rubber Lining

also connected to the pump, is put over the other end of Surface Preparation for Rubber
the pipe. The air inside the tube is sucked out through Lining
the soft rubber cover at one end and at the same time
the air between the tube and the pipe is removed via The advent of the sophisticated protective rubber
the metallic cover. The vacuum thus created should be lining has brought about the necessity to acquire a
adjusted in such a fashion that the tube is kept balanced, wider knowledge of precise end conditions that must
and at a suitable moment the vacuum inside the tube be fulfilled at the metal surface to achieve the utmost
is released. On release of the vacuum, air flows into adhesion and bonding of the lining material to the
the tube at controlled parameters and presses the tube metal. The performance of any type of lining is very
against the wall of the pipe. By this process it can be much dependent on the cleanliness of the surface. The
ensured that no air remains trapped. This procedure is environment in which the equipment, storage tanks,
suitable for pipes of smaller lengths. For long-distance or road tankers are located determines to a great
piping systems, small pipes need to be flange joined. extent the type of lining that should be specified; for
example, a tank that is located in a harbor terminal
will have to be rubber lined adopting a precured rub-
Storage of Rubber-Lined Pipes ber sheet with a self-curing adhesive bonding solu-
tion. If maximum life expectancy of a rubber lining
The following precautions are to be taken while is expected, it should be firmly adhered to the metal.
storing rubber-lined pipes prior to erection and The key to the lifespan and effectiveness of lined
commissioning: equipment exposed to a corrosive environment is its
design and construction. The design and construc-
• The outside surfaces of the rubber-lined pipes tion include not only the structural design enabling
should be protected against atmospheric cor- maneuverability during lining operation, but also the
rosion, such as rusting, with an anticorrosive surface preparation. Proper surface preparation plays
weather-resistant coating based on chlorosulfo- a vital role in the ultimate protection against corro-
nated polyethylene or neoprene. A primer coat of sion. For film formation of the adhesive coating of
red oxide is given. In many installations, epoxy even thickness all over and for uniform wetting and
coating or chlorinated rubber-based coating is drying, removal of surface contaminants is all that is
also applied if cost considerations are not signifi- required.
cant. It is, however, recommended that a suitable
white paint is applied to the outer surface as this
will reduce the heat transmitted through the rub- Methods of Surface Preparation
ber lining and the adhesive bonding beneath it.
Several methods for preparing the metal surfaces
• The pipes should be stored in stands at least before rubber lining are as follows:
about 3 ft above ground level for handling with-
out damage. • Cleaning with hand tools,
• It is advisable to avoid direct exposure to sun • Cleaning with power tools,
and the lined pipes should be protected under
suitable shelters against extreme climatic condi- • Cleaning by sandblasting,
tions. However, this is not possible in huge tanks • Cleaning by waterblasting,
in port terminals and therefore a weather-resis- • Cleaning with steam, high-pressure water, and
tant coating is given. chemicals, and
• The pipes should be covered with tarpaulin if • Pickling with acid.
stacked outdoors and free air flow should be
ensured to avoid hot air packets to prevent pre- Cleaning by hand tools is the oldest process. Today
mature oxidation. this is employed only when power tools are not avail-
• The ideal measure will be that the rubber-lined able and where the surface is inaccessible to power
surface is always kept wet with water to arrest tools and is too small. The generally used hand tools
the likely deterioration from ultraviolet rays and are wire brush, scraper blades, chipping hammer, and
ozone attack during storage. emery or sand paper. Handheld electric or pneumatic
15: Manufacturing Rubber Sheets and Application Procedures 141

Table 15.4  Swedish Standard SIS 05 5900 1967

Sa1 Light blast cleaning to remove mill scale, rust, and paint
Sa2 Widely known as commercial blast
Sa2.5 Very thorough blast cleaning to achieve near white metal. Inferior to Sa3
Sa3 Blast cleaning to visually clean steel. Surface to be completely free from oil, grease,
mill scale, and rust

power tools for cleaning include sanders, pneumatic of light streak discoloration. At least 95% of the sur-
scalers, needle guns, and rotary steel brushes. face shall have the appearance of a white metal sur-
Sandblasting is by far the best and most practical face finish and the reminder shall be limited to light
method and for large areas this is the method fol- discoloration.
lowed. For outdoor blasting operation, coarse river A commercially blasted surface finish corresponds
sand is used. For indoor blasting, steel shots are used. to Swedish standard Sa2 third quality (Table 15.4).
Sandblasting is the cheapest method and is widely The finish is defined as one from which oil, grease,
used. Sandblasting is done using compressed air at dirt, rust, mill scale, and foreign matter have been
an output pressure of 6 kg/cm2. Low pressure reduces completely removed from the surface, except for
blasting efficiency considerably. slight shadows streaks or discoloration and pitting.
The high and low points of the blasted surface are In the case of old tanks, the surface might have been
called the “peaks and valleys” and are an important pitted, allowing slight residues settling at the bottom
factor for anchoring of the adhesive coating. The of the pits. These should be removed by brushing.
sandblasting nozzles generally in use will have either
1/4″, 5/16″, or 3/8″ diameter. Where sufficient air is
available at the correct uniform pressure, the larger- Waterblasting
sized nozzles are preferred to smaller ones for more
area coverage. Waterblasting will remove substances such as
The sandblasting operation can be continuous or loose and blistered paints, loose rust, grease, and
intermittent. For continuous sandblasting, the flow other accumulated residue. Since waterblasting will
of sand should be continuous. For rubber linings of not produce a surface equivalent to that produced by
large storage tanks, sandblasting is done intermit- sandblasting, it is nevertheless an economical method
tently, simultaneously followed by primer coats. For of cleaning for lining applications.
productivity, the sandblasting equipment may have Cleaning with steam, hot water using chemi-
double hopper arrangements. cal additives is adopted in connection with other
Blasted surface qualities are often specified by methods. This method is known as “sweating.” For
users of rubber-lined equipment. A white surface fin- example, preparatory to relining of a tank handling
ish after blasting corresponds to Swedish standard caustic soda for its service life, it is good practice
Sa3 [5] or BS standard 7079 [6] and to first quality first to thoroughly clean with steam or high-pressure
[7,8]. This white finish is defined as a surface with hot water before sandblasting. A 5% by weight phos-
a gray white, uniform metallic color slightly rough- phoric acid solution in water added to the steam or
ened to form a suitable anchor pattern (peaks and high-pressure water will neutralize any alkali resi-
valleys) for primer coat and subsequent lining. The dues. Care, however, should be taken by the operator
finished surface should be free of all oil, grease, dirt, to avoid exposure to fumes and spillage, and stan-
visible mill scale, rust corrosion products, oxides or dard precautionary methods and measures should be
remaining adhesive or paint coatings, or any other strictly followed. At times authentic information as
foreign matter. to the use of acidic water handling in cleaning opera-
A near white surface finish corresponds to Swedish tions is not provided by the equipment suppliers. In
standard Sa2½ or BS4232 second quality. This fin- this case, such cleaning operations should not be
ish is defined as one that is free from all oil, grease, resorted to without seeking expert advice. Pickling is
dirt, mill scale, rust, corrosion products, oxides, or done to clean the surface of small metal parts using
remaining coatings, except for very slight shadows dilute hydrochloric or sulfuric acids in pickling tanks
142 Anticorrosive Rubber Lining

that are rubber lined. The acid pickling process will [3] M.G. Fontana, N.D. Greene (Eds.), Corrosion
yield a fresh metal surface suitable for bonding with Engineering, second ed., McGraw-Hill, New
rubber for manufacturing metal rubber-bonded com- York, NY, USA, 1978, p. 264.
ponents. This process is followed mainly in the man- [4] S. Johnson, Across the Bench–Cleaning Moulds:
ufacture of rubber-bonded components. Part II, Mould Making Technology, 2004. Article
110406 http://mouldmakingtechnology.com/
articles/110406.html.
References [5] SIS 05 59 00, Preparation of Steel Substrates
before Application of Paints and Related Products–

[1] 
Compounding and Properties of Bayprene Visual Assessment of Surface Cleanliness, 1967.
Garde Neoprene Rubbers, Technical Information [6] BS 7079, Preparation of Steel Substrates before
Bulletin, Bayer AG, Leverkusen, Germany, Application of Paints and Related Products, 1990.
1976. [7] A. Blanc, M. Mc Evoy, R. Plank (Eds.),

[2] 
ASTM D1646, Standard Test Methods for Architecture and Construction in Steel, Taylor &
Rubber–Viscosity, Stress Relaxation and Francis, London, UK, 1993, p. 352.
Pre-vulcanisation Characteristics (Mooney [8] Talleres Reunidos SA, Spain. http://www.taresa.
Viscometer), 2007. es/fiche.html.

You might also like