You are on page 1of 2

FEATURE: EMERSON May 2016

Successful control system


cutover at the world’s largest
oil processing plant
By: Majed Al-Khalis, Saudi Aramco Company, Control Systems Engineer in Abqaiq Plants Facility

buildings (PIBs) throughout the plants to


monitor and control plant processes. The
control rooms and PIBs represent the veins
of all Abqaiq operations and consist of
several networks and risk areas.
Distributed over 20 locations, the project
included upgrades to 325 controllers, 105
workstations, and 42 network devices. The
team divided the project into four upgrade
phases: north oil plants, south oil plants,
NGL plants, and utilities plants.
Success meant not having a single
interruption to plant operations, and the
team had to minimise the shutdown time
for some of the risk areas that have tight
operations. As a result of that, a hot cutover
approach was chosen.
The project team capitalised on three
factors to overcome project challenges
and complete the project successfully with

W
ith the capacity to produce that an upgrade and migration cutover was zero operation impact: human resource
over seven million barrels per needed of the plants automation system. development, efficient testing procedures,
day, Saudi Aramco Company Abqaiq Plants team began to plan the and streamlined technologies.
Abqaiq plants comprise the largest oil process of upgrading the existing Emerson
processing and crude stabilisation facility PROVOX DCS, Triplex Regent ESD systems,
in the world. Abqaiq is the main oil and burner management systems to the Human resource development
processing center for Arabian Extra Light latest release of Emerson’s DeltaV DCS,
(AXL) and Arabian Light (AL) crude oils SIS & BMS. Before starting the project, Abqaiq Plants
and produces natural gas liquids (NGL) as The team began the project in October, management took proactive steps to
a bi-product for Saudi Aramco’s daily oil 2011 with a planned completion date of develop a qualified team that included a mix
processing activities. To support both the November, 2015. Although on-budget and of experienced and new personnel across
oil and gas plants, Abqaiq Plants produce on-schedule cutovers at a processing plant project disciplines including automation,
their own electrical power, steam, of this size do not happen often, the project process, electrical, and communication.
instrument air, and water. team completed the cutover activities Several engineers, technicians, and
For a complex of this size, an involuntary two months ahead of schedule by end of operators were sent to vendor courses
shutdown would mean great losses in September, 2015. to increase their knowledge of the new
production and would negatively impact systems. In addition, the project team
the company. In 2008, Abqaiq Plants team simulated new systems process and
recognised potential challenges were on Large complex plans for a hot cutover operation scenarios in Abqaiq advanced
the horizon. The plant’s existing automation technology center. The simulation helped
systems would experience obsolescence Abqaiq Plants complex has three main to ensure new systems readiness
for distributed control system (DCS) divisions: oil, NGL, and utilities. As such and familiarised plants engineers and
controllers and emergency shutdown (ESD) Abqaiq plants are operated from three technicians with them.
processors and cards. In addition, these control rooms: North (north oil plants), South Our team participated in several project
systems would no longer have technical (south oil and NGL plants), and the UCR activities and tests including factory
support or training. (utilities plants). The three control rooms acceptance tests (FAT) which increased the
After some studies, it was determined interconnect with several process interface competency level of all team members.

38 Pipeline Magazine www.pipelineme.com Electronic permissions to Emerson Process Management


from Pipeline May © 2016
FEATURE: EMERSON May 2016

of Guardian Support,
Test procedures which provided Emerson
technology connections,
To assure readiness and and ensured project team
correctness of the new would discover system
system and to achieve a issues if any arose. Not
smooth cutover, Abqaiq only did it help to mitigate
Plants experienced Abqaiq system security and
engineering and operation patch issues, but it also
teams developed testing provided the team insights
procedures. into what Emerson learned
Detailed cutover sequence from other sites’ projects.
and contingency plan
documents were developed
to manage cutover critical Business results and
activities and predict all Distributed over 20 locations, lessons
possible scenarios during
cutover and restoration the project included upgrades to By combining planning
procedures. The team also with methods and

325 105 42
developed a plan to relocate technology, the project
the old DCS to a temporary finished ahead of schedule
cabinet and keep it running and under budget. The
controllers workstations network
to control the plant. This devices resulting reduction in man-
approach helped to optimise hours led to cut costs and
the shutdown period for gave the team more time
critical risk areas such as to observe the new system
AXL Shippers and Steam Production Plants a centralised management system was and close some exception items.
from one week to two hours. It also enabled a used to collect system events and key Saudi Aramco employees, Emerson
fast fallback strategy to the old system, in case performance indicators. Engineers, and contractors worked together
of new systems failure. Abqaiq Plants team came up with an collaboratively with support of Abqaiq Plant
innovative design to enhance the cutover management as one team to achieve the
period of some plant networks through goals of the project safely with not a single
Streamlined technologies installing a parallel connections to old and negative impact on production.
new systems’ networks. The innovative In addition, the young plant employees
The project team took advantage idea enabled the team to test the new have been empowered to lead critical
of the upgrade project to implement system while maintaining old system activities. The education and resulting
current technologies in the system connections. This method decreased confidence delivered several innovations
network, monitoring, and security. These plant downtime period from a potential and noticeable cost avoidances. In essence,
technologies simplified the cutover, project 72 hours to zero and allowed for better Abqaiq Plants management capitalised
execution, and troubleshooting. system testing and recovery. In addition, on the development of people to ensure
For example, zoning and subnets were to stabilise the plant sooner on the new present project success and prepare for
used to segregate different control rooms’ system, critical loops were tuned with the future system support.
networks. This segregation of networks help of Emerson consultants. In the future, Abqaiq Plants will plan
and systems into unique areas enhanced The project team also implemented to upgrade PROVOX IO cards to those of
system security. It also helped to isolate a centralised patch management the DeltaV system. In addition the plant
traffic and errors for easier issue tracing system to install security patches and team will work to enable several enhanced
and network troubleshooting. In addition, antivirus updates. The centralised patch DeltaV features such as Advanced Process
management system enabled the use Control (APC).

40 Pipeline Magazine www.pipelineme.com Electronic permissions to Emerson Process Management


from Pipeline May © 2016

You might also like