Professional Documents
Culture Documents
Rhett Hassell
Senior Geotechnical Engineer
Northern Star Resources
Page 1
“We installed a lot ground support, why didn’t it work”
• This picture shows an ore Damage to ore drive following M+1.6 event
drive that was damaged
from a M+1.6 seismic
events.
• It took 3 months of
painful rehab to get back
to the stope brow and
re-start stoping.
• We invested a lot of
money on ground
support that ultimately
did not work.
• Was it a design or
implementation issue?
Page 2
Sometimes more is not the answer
• Observations from this event
plus others has shown how
critical it is to get the
implementation of the design
correct.
• The following slides
summarises some of the issues
we have identified and
proposed solutions
Page 3
Cable bolts – Barrel & Wedge
• >30 cable plates were counted on the Failed barrel & wedges at low loads
floor following the seismic event. Most
had failed at loads well below design.
• Cable bolts are there to do the heavy
lifting during a seismic event.
• The cable should break before the
barrel/wedge/plate.
• Failure was caused by corrosion on the
internal surface of the barrel/outside
of the wedge.
• This prevents sliding of the wedges
and causes the cable to shear through Some worked
the wedge teeth at low loads.
Page 6
Cable bolts – splaying wires
• If premature failure of the barrel and wedge anchor does occur
splaying of the cable strands may prevent the
barrel/wedge/plate sliding off the strand.
• Splaying cables is possible but manually intensive.
• Requires mechanical assistance if it is going to be taken up by
the Australian mining industry.
Page 7
Cable bolts – metal epoxy
• We are currently investigating if
placing a metal epoxy/glue behind
the wedge to act as a barrier in case
of premature failure is a viable
option.
Page 8
Cable bolts – Plate capacity
• Need to match the cable bolt plate with the cable bolt capacity.
• The previously used plate hole was too large for the barrel and wedge
anchor and we had instances of the barrel punching through the plate.
• Completed some simple static testing to determine the best
pate/barrel & wedge combination.
Failed plate where the barrel has punched through the plate.
Page 9
Cable bolts – grout encapsulation
• Pressure grouting vs Retreat grouting
• We saw two main benefits with retreat grouting:
• Fill encapsulation to the collar (pressure grouting leaves 0.1-0.3m ungrouted). This
should result in reduced load transfer for the barrel/wedge/plate assemblage.
• Operationally much quicker than pressure grouting
• But how to ensure it is being done correctly:
• Training and dedicated cable bolt crew.
• Audits. Is there grout on the floor. Working out the time required to fill a hole and
timing operators
Page 11
Resin encapsulation
• Engineer “I’ve calculated how much resin I need by working out the volume of the drill
hole minus the volume of the bolt, oh and I’ll add 30% for good measure”
Page 12
Resin encapsulation
• Engineer “I’ve calculated how much resin I need by working out the volume of the drill
hole minus the volume of the bolt, oh and I’ll add 30% for good measure”
• Jumbo Operator “Trying to get these resin cartridges into this hole is causing me a lot of
grief and is too slow. I’ll use a bigger bit to make life easier”
Page 13
Resin encapsulation
The result
Resin
Page 14
Resin encapsulation
• Pumpable resin
may provide the
solution.
Page 15
The next advancement - Acoustic Testing?
Page 16
Thankyou & comments/questions
Page 17