You are on page 1of 17

Improving ground support QA/QC to prevent premature

failure during seismic events

Rhett Hassell
Senior Geotechnical Engineer
Northern Star Resources

Page 1
“We installed a lot ground support, why didn’t it work”
• This picture shows an ore Damage to ore drive following M+1.6 event
drive that was damaged
from a M+1.6 seismic
events.
• It took 3 months of
painful rehab to get back
to the stope brow and
re-start stoping.
• We invested a lot of
money on ground
support that ultimately
did not work.
• Was it a design or
implementation issue?

Page 2
Sometimes more is not the answer
• Observations from this event
plus others has shown how
critical it is to get the
implementation of the design
correct.
• The following slides
summarises some of the issues
we have identified and
proposed solutions

Page 3
Cable bolts – Barrel & Wedge
• >30 cable plates were counted on the Failed barrel & wedges at low loads
floor following the seismic event. Most
had failed at loads well below design.
• Cable bolts are there to do the heavy
lifting during a seismic event.
• The cable should break before the
barrel/wedge/plate.
• Failure was caused by corrosion on the
internal surface of the barrel/outside
of the wedge.
• This prevents sliding of the wedges
and causes the cable to shear through Some worked
the wedge teeth at low loads.

Page 4 Failed wedge


Greasing of Barrel & Wedge Anchors
• Grease is to be applied to the surface between the inside of the barrel and the outside of the wedge.
• We recommended an anti-seize grease (Molybond GOG)
• Relying on the operators to install is problematic but slowly changing the culture.

Barrel & wedge anchors to be greased before installation


Page 5
Cable bolts - tensioning
• Cable bolts were previously tensioned to
2000kPa. Equivalent to ~2-4t of force. This is
regarded as low strand tension (see adjacent
Figure).
• For full teeth penetration 10-12t of force is
required.
• Alan Thompson “To avoid slippages during use,
it is important that the cable bolt is fully
stressed at time of installation to a force equal
to 0.5 TUlt ( ~125kN for a 15.2mm diameter
pre-stressing strand).
• We changed the cable bolt tensioner to cut out
over 10t.

Page 6
Cable bolts – splaying wires
• If premature failure of the barrel and wedge anchor does occur
splaying of the cable strands may prevent the
barrel/wedge/plate sliding off the strand.
• Splaying cables is possible but manually intensive.
• Requires mechanical assistance if it is going to be taken up by
the Australian mining industry.

Page 7
Cable bolts – metal epoxy
• We are currently investigating if
placing a metal epoxy/glue behind
the wedge to act as a barrier in case
of premature failure is a viable
option.

Page 8
Cable bolts – Plate capacity
• Need to match the cable bolt plate with the cable bolt capacity.
• The previously used plate hole was too large for the barrel and wedge
anchor and we had instances of the barrel punching through the plate.
• Completed some simple static testing to determine the best
pate/barrel & wedge combination.

Failed plate where the barrel has punched through the plate.

Page 9
Cable bolts – grout encapsulation
• Pressure grouting vs Retreat grouting
• We saw two main benefits with retreat grouting:
• Fill encapsulation to the collar (pressure grouting leaves 0.1-0.3m ungrouted). This
should result in reduced load transfer for the barrel/wedge/plate assemblage.
• Operationally much quicker than pressure grouting
• But how to ensure it is being done correctly:
• Training and dedicated cable bolt crew.
• Audits. Is there grout on the floor. Working out the time required to fill a hole and
timing operators

No encapsulation of the cable bolt at the collar Retreat grouting training.


Page 10
Install as much of the ground support as possible during the development
cycle
• Previous ground support standards had a development
standard
• Mesh grade to grade with dynamic followed.
• This was followed by an upgrade to ground support
prior to stoping.
• Mesh below grade, cable bolting and shotcrete to
protect ground support below grade.
• Lag of 30m between the upgraded ground support and
the stoping front.
• Unfortunately the damage from seismic events doesn’t
always conform to the stoping lag distance.
• Operationally it was painful to get jumbo resources
back into a stoping area. Damage to the rock mass where no ground support was installed.

• All current ground support standards install all the


jumbo ground support during the development cycle.

Page 11
Resin encapsulation
• Engineer “I’ve calculated how much resin I need by working out the volume of the drill
hole minus the volume of the bolt, oh and I’ll add 30% for good measure”

Page 12
Resin encapsulation
• Engineer “I’ve calculated how much resin I need by working out the volume of the drill
hole minus the volume of the bolt, oh and I’ll add 30% for good measure”

• Jumbo Operator “Trying to get these resin cartridges into this hole is causing me a lot of
grief and is too slow. I’ll use a bigger bit to make life easier”

Page 13
Resin encapsulation
The result

Resin

Page 14
Resin encapsulation
• Pumpable resin
may provide the
solution.

Page 15
The next advancement - Acoustic Testing?

Page 16
Thankyou & comments/questions

How do we support the floor?

Page 17

You might also like