JASA SEWA WATER TREATMENT PACKAGE PILOT

WATERFLOOD STRUKTUR BENTAYAN (BNT)


FIELD RAMBA ZONA 4 PT PERTAMINA EP

No Doc : WBNT-20-G0-SC-001
PROJECT SCHEDULE Rev : A1
Page : 1 - 3

PEMILIK PROYEK : PT. PERTAMINA EP


LOKASI : STRUKTUR BENTAYAN - FIELD RAMBA
NO KONTRAK : 4650016309

A1 12 Juli 2022 ISSUED FOR REVIEW MF AG HP ASH WDN

CHECKED APPROVED CHECKED APPROVED


REV DATE DESCRIPTION PREPARED
PT. IOS PT. PERTAMINA EP
JASA SEWA WATER TREATMENT PACKAGE PILOT
WATERFLOOD STRUKTUR BENTAYAN (BNT)
FIELD RAMBA ZONA 4 PT PERTAMINA EP

No Dokumen : WBNT-20-G0-SC-001
RIWAYAT PERBAIKAN (REVISI) Revisi : A1
Halaman : 2 - 3

REV DATE DESCRIPTION

A1 12 JULI 2022 Revisi: Penambahan logo SKK Migas, Judul Project, Nama lokasi, Penambahan
Stempel Pertamina, penambahan inisial & paraf, No PO, Isi Project schedule
PT INTEGRA OILFIELD SERVICES JASA SEWA WTP UNTUK PILOT WATERFLOOD STRUKTUR BENTAYAN (BNT) FIELD RAMBA ZONA 4 PT PERTAMINA EP FIELD RAMBA
MASTER SCHEDULE ZONA 4
ID Task Name Juli Agustus September Oktober
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18
-4 -1 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 63 66 69 72 75 78 81 84 87 90 93 96 99 102 105 108 111 114 117 120 123
1 Kick Off Kick Off
2 Data Collection Data Collection
3 Engineering Engineering
4 Procurement
5 Pump Pump
6 DGF (Dissolved Gas Floatation) DGF (Dissolved Gas Floatation)
7 Compressore Compressore
8 Filter Filter
9 Fabrication
10 Buffer Tank Buffer Tank
11 Treated Water Tank Treated Water Tank
12 Backwash Tank Backwash Tank
13 Oil Tank Oil Tank
14 Sand Filter Sand Filter
15 Carbon Filter Carbon Filter
16 Hydrotest & FOW Test Hydrotest & FOW Test
17 Assembly Equipment to Ski Assembly Equipment to Skid
18 Pipe Spool & Valve Installation Pipe Spool & Valve Installation
19 Pre Inspection Pre Inspection
20 Personil Preparation (HSE, SIM L) Personil Preparation (HSE, SIM L)
Delievery Bentayan Site Delivery to Bentayan Site
21
22 ETA at Bentayan Site ETA at Bentayan Site
23 Unloading Unloading
24 DGF DGF
25 Buffer Tank Package Buffer Tank Package
26 Treated Water Tnak Treated Water Tnak
27 Office + Lab Office + Lab
28 Filter Package Filter Package
29 BackWash Tank BackWash Tank
30 Clearing Area Clearing Area
31 Layout Marking Layout Marking
32 Positioning
33 Treated Water Tank Treated Water Tank
34 Backwash Tank Backwash Tank
35 Buffer Tank Pacakge Buffer Tank Pacakge
36 Filter Pacakage Filter Pacakage
37 Office + Lab Office + Lab
38 Leveling Leveling
39 Intake Pump Installation Intake Pump Installation
40 Pipeline Intake to WTIP Installation Pipeline Intake to WTIP Installation
41 Interconnection Piping Interconnection Piping
42 Cable Power Intake Pump to CP Cable Power Intake Pump to CP
Cable Power Installation to CP
43 Cable Power Installation to CP
Gas line Tie In
44 Gas line Tie In
Water Line Tie In
45 Water Line Tie In

Power Control Panel Test


46 Power Control Panel Test
PreCommissioning
47 PreCommissioning
Comissioning
48 Comissioning
Start Up
49 Start Up

Project: MS PEP Bentayan Task Progress Summary External Tasks Deadline


Date: 12/07/22 Split Milestone Project Summary External Milestone

Page 3