Professional Documents
Culture Documents
Trade-Offs
Constraints Finger Pier Transporter Linear Importance
Terminal Terminal Terminal Factor
Economic (Land
Area Cost) 543,836,498.40 375,698,691.75 302,462,644.74 10
[Php]
Sustainability
(Service Life) 20 12 20 9
[Years]
Risk Assessment
(Delayed and
Cancelled Flights
22.52 11.40 20.77 10
Percentage)
[%]
Uncertainty (Land
Cost with 560,042,826.05 379,380,538.93 305,426,778.66 9
Inflation)
[Php]
Functionality
(Congestion 20.04 31.78 21.26 10
Percentage)
[ %]
Safety (Noise
Control) [dB] 73.80 67.80 79.80 9
Normalized Data
Show below is the summarized table of normalized values of respective trade-offs considered in the
design project.
Table 3.2: Normalized Data
Context I Trade-Offs
Constraints Finger Pier Transporter Linear
Terminal Terminal Terminal
Economic
(Land Area Cost) 1 7.27 10
[Php]
Sustainability
(Service Life of Passenger Boarding 10 1 10
Bridge)
[Years]
Risk Assessment (Delayed and
Cancelled Flights Percentage) 1 10 2.42
[%]
Uncertainty
(Land Cost with Inflation) 1 7.39 10
[Php]
Functionality
(Congestion Percentage) 10 1 9.06
[%]
Safety
(Noise Control) 5.50 10 1
[dB]
Table 3.4 shows the weight for economic constraint, risk assessment constraint, and functionality
constraint to be 0.18 each while the remaining constraints is weighted 0.15 each. Ultimately, the
highest weighted sum was calculated to be 7.09, in favour of the trade-off “Linear Terminal”. This data
shows that the linear terminal configuration is the most efficient design to be used in the project.
Table 3.4: 2nd Weighted Sum of Various Percentage
Table 3.5 on the other hand, shows the weight for economic constraint, safety constraint, and
functionality constraint to be 0.18 each while the remaining constraints is weighted 0.15 each.
Ultimately, the highest weighted sum was calculated to be 7.14, in favor of the trade-off “Linear
Terminal”. This data shows that the linear terminal configuration is the most efficient design to be used
in the project.
Table 3.5: 3rd Weighted Sum of Various Percentage
Overall Assessment
The weighted percentage of the transportation engineering context concluded the Linear Terminal
Configuration to be the leading tradeoff. The Linear Terminal tradeoff governed in all of the weighted
sum of various percentages. Initially, the designers recommended the Linear Terminal Configuration as
the best transportation engineering tradeoff for the design project, and after the final design, Linear
Terminal still govern and has been deemed to be the most recommended design to be used.
Sensitivity Analysis
Sensitivity Analysis for Context I: Transportation Engineering
Economic vs. Functionality
The figure and table below show the variation of the project cost to the functionality of the project when
increased by percentage. It can be concluded that when the construction cost increases, the
congestion from each configuration reduces. The conclusion is if the land area is increasing it requires
the land cost to increase as well. Therefore, the congestion lessens due to the increase in land area
which is a result of the increase of land cost. The relationship between the overall cost and congestion
rate can be used for each trade-off of the design project.
Table: Economic vs. Functionality for Transportation Engineering
Finger Pier Transporter Linear
Terminal Terminal
Percentage Terminal
Increase
Cost Congestion Cost Congestion Cost Congestion
Rate Rate Rate
0.30
0.25
0.05
-
0% 5% 10% 15% 20% 25%
INCREASE in COST (%)
375.698.69 302.462.64
0% 543.836.49 560.042.82 311.476.
1,75 4,74
8,40 6,05 386.894.512,76 031,55
5% 571.028.323,32 588.044.967,35 394.483.626,34 406.239.238,40 317.585.776,9 327.049.833,1
8 3
20%
672.051.391,26 450.838.430,10 464.273.415,32 362.955.173,6 373.771.237,8
652.603.798,08
9 6
25%
679.795.623,00 700.053.532,57 469.623.364,69 483.618.140,96 378.078.305,9 389.345.039,4
3 4
0.30
INFLATION PRICE (Php)
0.25
0.05
-
0% 5% 10% 15% 20% 25%
INCREASE in COST (%)
67.8 302,462,644
73.80 0 .74 79.80
0% 543,836,498.40 375,698,691.75
68.23
10% 598,220,148 413,268,5 332,708,909
.24 63.01 60.93 57.97 .21
347,832,041
.45 58.00
15% 625,411,973 432,053,4
.16 53.56 95.51 49.27
362,955,173
.69
652,603,798 450,838,4
20% .08 42.85 30.10 39.42 46.40
378,078,305
.93
25% 679,795,623 469,623,3
.00 32.14 64.69 29.57 34.80
70.00
60.00
50.00 Finger Pier Terminal
Transporter Terminal
40.00
Linear Terminal
30.00
20.00
10.00
-
0% 5% 10% 15% 20% 25%
INCREASE in COST (%)