BREACH LIKE DAMAGE AND OTHER DAMAGES

Division: Dhubri W.R. Division, Sub-Division: Abhayapuri W.R. Sub-Division, District: Bongaigaon

Cost of Restoration Propose Proposed


Cost Total cost
d Length Length of
Name of Apprisal of
Location/Chainage/ Length of of Bank
Sl. No. River Embankment Cause of Damages of Restoratio Remarks
Village/Area Damages Temp.(Rs. Permanent Restorati protection
/Dyke Damages n (Rs. In
In L) (Rs. In L) on (In works(if any)
(Rs.in L) L)
Metre ) (In Metre )

1 Aie Daukhanagar From Ch.0 to 1000M The reach has undergone damages like loss of
to Popragaon free-board, slope etc. mainly due to Water
pressure, rain, human activities
1000M 20.00 5.00 80.00 85.00 1000.00 300.00
2 Sidalsuti to At Jaraguri, village (i.e, Due to encroachment on either side of the
Mererrchar from Ch.0 – 1600m). bundh which damaged the total bundh section,
significantly the height of the dyke
1600M 60.00 40.00 100.00 140.00 1600M Nil
3 Aie Sidalsuti to At Ambari(Ch.15800m- Due to presence of termites that make the
Mererrchar 16270m) bundh section weaker during high flood and
sudden depression/ditch forms, also height
reduced and poses overtopping vulnerability. 470M 20.00 12.00 30.00 42.00 470M Nil
4 Aie Sidalsuti to Santoshpur-Dumerguri Due to regular vehicle plying over the bundh,
Mererrchar (Ch.18400m- 19280m) required free-board against HFL has been
reduced. i.e Vulnerable to overtopping. 880M 20.00 16.00 50.00 66.00 880M Nil
5 Aie Sidalsuti to At This portion also less immune to overtopping as
Mererrchar Nasatra(Ch.23000m- required free-board against HFL has been
23500m). reduced over time and due to heavy vehicle
movement. 500M 10.00 12.00 30.00 42.00 500M Nil
6 Aie 3.5Km Ds of At Madhufal-Sikatari This portion is under severe bank erosion with
Sidalsuti to area for a length of all along damages to P&RD built bundh
Mererrchar 3.5Km
dyke
3500M 80.00 75.00 1000.00 1075.00 3500M 2500.00
5 Champa on R/B of At villages Bamunitilla, This reach of R/B of river Champamoti is under This reach
- moti villages Durgamari for length of significant bank erosion due to formation of sand needs bank
Bamunitilla, 2.0Km bars on the opposite banks protection
Durgamari only (i.e.
2000M 60.00 35.00 100.00 135.00 2000M 2000M)
Total= 9950M 270.00 1585.00
FOR BREACH CLOSING
Division: Dhubri W.R. Division, Sub-Division: Abhayapuri W.R. Sub-Division, District: Bongaigaon
d Length Proposed
Cost
Total cost of Length of
Name of Apprisal Cost of Breach closing
Location/Chainage/ Length of of Breach Breach Bank
Sl. No. River Embankment Cause of Breach of Breach Remarks
Village/Area Breach Temp.(Rs. Permanent closing closing/r protection
/Dyke portion
(Rs.in L) In L) (Rs. In L) (Rs. In L) etiremen works(if any)
t (In (In Metre )
1 Aie Daukhanagar No Breach occurred in this current wave of flood Not
to Popragaon breached
2 Aie Sidalsuti to No Breach occurred in this current wave of flood Not
Mererrchar breached
Total= Nil