CLIENT Francis Tauro

AISHU ENGINEER'S ENGINEER Shivanand S M


QUTATION FOR HOUSE CONSTRUCTION IN BANGALORE DATE April - 04 - 2021

HOUSE CONSTRUCTION MEASUREMENT


Sl No. Roof Location Width in ft Length in ft Area in sqf
1 Ground Floor Roof = 26 47 = 1222
2 First Floor Roof = 26 47 = 1222
3 Second Floor Roof = 13 15 = 195
TOTAL AREA IN SQF = 2639
Note: - Area of construction calculated as per client provided drawing. It will be revised once architectural plan is finalized at construction time

CONSTRUCTION MATERIALS AGREED


Sl No. MATERIAL FOR MATERIAL COMPANY/BRAND REMARK
Construction work Cement Ultratec
a.Foundation RCC Steel TATA/JSW Fe500
1 b.Structure Concrete
M-Sand Standard
c.Walls
d.Plastring P-Sand Standard
Blocks 6" & 4" Standard
Pipes National/VIP
Box Goldmedal
2 Electrical Wor
Wire Havels
Plates & Switches Goldmedal Modular Type
Bolders Standard
3 Size Stone Masonry Work Size Stone Standard
CLIENT Francis Tauro
AISHU ENGINEER'S ENGINEER Shivanand S M
QUTATION FOR HOUSE CONSTRUCTION IN BANGALORE DATE April - 04 - 2021

Sl No. MATERIAL FOR MATERIAL COMPANY/BRAND REMARK


Pipes Ashirvadh
Wall mixture/Diverter Jaguar (Basic Price)
4 Plumbing Shower & Fittings Cera/Hindware/Onida (Basic Price) Equivalent
SS Taps, Angle/Piller cock Cera/Hindware/Onida (Basic Price) Equivalent
Comode Indian/Westren Type Cera/Hindware/Onida (Basic Price) Equivalent
Wall putty Birla White
Internal Primer Asian Paints
5 Painting-internal
Emulsion Tractor Shine from Asian Paint
Oil Paints Asian Paints
Primer Asian Paints
6 Painting-External Emulsion Apex Shine from Asian Paint
Texture in elevation wall Oil Paint
Granite Up to 90Rs.
7 Tiles Work Vetrified Up to 50Rs.
Dadoing Toilet/Bath/Kitchen/Front wall Up to 40Rs.
Main Door Teak Frame 6"x4" Shutter 1.5" Antiq Fittings Polish
Room Doors Ready Frame & Flush Doors SS Fittings Paint
8 Doors & Windows Windows MS Grils & UPVC 3 Track with Mesh Paint
Ventilation MS Grils with Glass Paint
Locks Main Door - Europa & Room Door - Matiz Equivalent
CLIENT Francis Tauro
AISHU ENGINEER'S ENGINEER Shivanand S M
QUTATION FOR HOUSE CONSTRUCTION IN BANGALORE DATE April - 04 - 2021

Sl No. MATERIAL FOR MATERIAL COMPANY/BRAND REMARK


Side wall (2 Side) 4' Block & Plastring
Front Wall 4" Briks & Plastring
9 Compound & Staircase Gate MS Gate
Railings SS Railing Basic Price
Parking tiles At car parking location
RCC Sump up to 8000 ltrs
Pump 1 Hp One number
10 Sump & Tanks in Top
Syntex Tank 2000 lts
Borehole Not considered

Rates considered for quatation


1 Cement = 380 Rs/Bag 7 M-Sand = 900 Rs/Ton
2 RC Steel = 68 Rs/kg 8 P-Sand = 1300 Rs/Ton
3 Block 6" = 36 Rs/No 9 S S Railing = 700 Rs/Rf
4 Block 4" = 28 Rs/No 10 Jelly 20mm = 800 Rs/ton
5 Teak Wood = 3200 Rs/cft 11 Jelly 40mm = 700 Rs/ton
6 MS Steel = 55 Rs/kg 12 Size = 10 Rs/no

Estimated Amount for the above work = 4486300 Rs Only


Note: - Total amount is exclusive of VAT, Service and GST