Professional Documents
Culture Documents
Training Report
On
"Cement Manufacturing Process and Use of Crushers in
Cement Plant”
Submitted to
RAJASTHAN TECHNICAL UNIVERSITY
1
Candidate’s Declaration
I hereby declare that the work, which is being presented in the Practical Training Report
,entitled “Cement Manufacturing Process and Use of Crushers in Cement Plant" in partial
fulfilment for the requirement of course of “Bachelor of Technology” in Deptt. of
Mechanical Engineering and submitted to the Department for a record of my own studies
carried under the Guidance of Shri/ Dr.Prof. Arun Arya. Department of Mechanical
Engineering, Arya College of Engineering and I.T., Jaipur
I have not submitted the matter presented in this Report anywhere for the requirement of any
other course.
2
ACKNOWLEDGEMENT
3
List of Figure
1. JK Cement factory
2. Regional Training Center
3. Drilling Machine
4. Excavator
5. Dumper
6. Dozer
7. Impact Crusher
8. Hammer Crusher
9. Limestone Mining, Crushing, Stacking
10. Belt Conveyor
11. Stacker Machine
12. Piles
13. Reclaimer
14. Raw mill grinding
15. VRM
16. Horizontal Mill
17. CF Silo
18. Preheating section
19. Rotary Kiln
20. Cement mill
21. Double toggle jaw crusher
22. Swing hummer crusher
23. Solid rotor impactor breaker
24. Gyratory Crusher
4
CONTENT
1. Introduction and Overview of J K Cement WORKS
1.1 History & Milestones
1.2 Production Capacity and Financial Performance
2. Management Set- up.
3. Organizational Chart.
4. Regional Training Centre - North
5. Corporate Social Responsibility
6. Introduction to Cement
6.1 History of Cement
6.2 Definition of Cement
6.3 Types and Uses of Cement
6.4 Types of Processes
6.5 Process Overview
6.5.1 Mining
6.5.2 Crushing of Limestone
6.5.3 Prehomogenisation
6.5 .6 Pyroprocessing
5
Introduction to
HR Department
JK Cement Works
Kailash Nagar, Nimbahera
District: Chittaurgarh-312617
(Rajasthan)
6
J.K. Cement is an affiliate of the J.K. Organization, which was founded by Lala Kamlapat Singhania. The J.K. Organization is an
association of industrial and commercial companies and has operations in a broad number of industries.
Our cement operations commenced commercial production in May 1975 at our first plant at Nimbahera in the state of Rajasthan. At
Nimbahera, we started with a single kiln with a production capacity of 0.3 million tons. We added a second kiln in 1979 with
production capacity of 0.42 million tons, and a third kiln in 1982 with a production capacity of 0.42 million tons. We added a
precalciner with a capacity of 0.4 million tons in 1988, which increased our capacity at Nimbahera to 1.54 million tons. During the
years 1998 through 2003, we continued to implement modifications to each of our kilns, which increased our aggregate capacity at
Nimbahera to 2.8 million tons as of September 30, 2005.
We commissioned a second grey cement plant at our Mangrol plant in 2001, with a production capacity of 0.75 million tons. As of
September 30, 2005, we had an aggregate production capacity of 3.55 million tons per annum of grey cement. Our white cement plant
was completed in 1984 with a capacity of 50,000 tons. Our continuing modifications to the plant have increased its production
capacity to 300,000 tons as of September 30, 2005.
Today, J. K. Cement Ltd. is one of the largest cement manufacturers in Northern India. We are also the second largest white cement
manufacturer in India by production capacity. While the grey cement is primarily sold in the northern India market, the white cement
enjoys demand in the export market including countries like South Africa, Nigeria, Singapore, Bahrain, Bangladesh, Sri Lanka,
Kenya, Tanzania, UAE and Nepal.
Our access to high quality limestone reserves that are suitable for production of white cement provides us with a competitive
advantage. Based on geological surveys conducted by independent agencies on our mines between 1996 and 2001, our limestone
reserves for both grey and white cement are expected to meet our existing and planned limestone requirements of 4.0 MnTPA of grey
cement and 0.4 MnTPA of white cement, for approximately 40 years.
Backed by state-of-the-art technology and highly skilled manpower against the backdrop of India’s infrastructural growth in an
overdrive, we are upbeat about the future. We are confident of contributing heavily in India’s journey of development. We see a world
of concrete ideas on the horizon.
7
1.Overview of J K Cement WORKS
1.1 HISTORY BEHIND J K CEMENT
The initial "J.K." stands for a father- son team, namely: Juggilal Kamlapath Singhania
J .K. organization started in the year 1884 at Calcutta. J .K. started their business as a
Financier, Investor, Trading Supplier of cotton belts and manufacturer of small
machinery parts like ‘V' belts, etc. They established few small cotton textile
industries also.
In the year 1914 they shifted their business from Calcutta to Kanpur where they
established many big industries like J.K. cotton Mills, Straw product Co, Lohia Mach,
J.K. Pulp and Raymond’s Woolen, etc.
In the year 1934 J.K. organization started one more division, as J.K. Synthetics Ltd.
They established various big plants of Nylon, Acrylic fiber, etc. at Kota and Tyre
Cord, Chemical and Pesticides at Jhalawar.
In the year 1974 under the same division one more unit was started for manufacturing
of Grey Cement at Nimbahera.
The present cement factory was commissioned in the year 1974. The plant started its
production from 27th Dec 1974.
Ist plant / kiln was commissioned in 1974 and the capacity of this plant was 900 tonne
per day and 3 lakh tonne per year. After modification in Preheater, its present
capacity is 1200 TPD.
Expansion of this plant took place in the year 1979, when 2nd kiln was commissioned
with a capacity of 1200 tonne per day and 7 lakh tonne per year. After modification in
Preheater its present capacity is 1650 TPD.
Again in the third phase, a kiln was erected in the year 1982 and production of this
kiln was 1350 tonne per day.
In the year 1988 a new technology was introduced in this 3rd Kiln that consisted of
precalcination process, which raised the capacity of this plant to 3400 tonne per day,
which was earlier 1350 tonne per day. In Aug.-2003 after again some modification in
Preheater and Folex cooler its capacity is increased to 4700 TPD.
Besides, J.K. cement plant is having its own diesel generator sets, producing power to
meet the power energy requirements.
Main raw material for cement is LIMESTONE, for limestone we have our own open
cast mines adjoining to the plant. Besides we have developed few more mines at
Maliakhera, Karoonda and Tilakhera for producing 10,000 tonnes limestone per day
as needed.
8
J .K. Cement erected one more plant from Jan. 2001 with the capacity of 1400 tonne
per day at village Mangrol. In Nov.-2003 after modification in Preheater and
installation of Mechanical elevator its capacity increased to 2200 TPD.
Due to power shortage as imposed by Ajmer electricity supply board J.K. established
its own Thermal Power Plant at village Bamania, near Shambhupura, which is
generating 15 M.W. power every day, which is consumed by J.K. Cement Plant.
J K Cement also has a plant of 400TPD installed capacity of White Cement at Gotan,
Nagour (Raj).
Cement Plant at Karnataka of over 5500 TPD and Thermal Power Plant of capacity
30 MW.
Thermal Power Plant at Nimbahera of 22 MW.
Waste Heat Recovery Plant at Nimbahera of 13.2 MW capacity.
J.K. cement is one of the most productive, cost efficient cement producing plant in
the country, a company, believing in corporate responsibility to society, integrity and
fairness. The company’s cement is sold under the J.K. Sarve Shaktiman brand name,
enjoys good brand image and a price premium.
The following types of cements are produced by J K Cement Works.
(a) Ordinary Portland Cement (OPC)
(b) Portland Pozzolana Cement (PPC)
(c) Super Silicate Cement (SSC)
(d) Masonry Cement (MC)
(e) Portland Slag Cement (PSC)
(f) White Cement 7
J. K. Cement manufactures and markets cement and clinker for both domestic as well
as exports markets.
Plant Capacity(tones/day)
1 Plant/kiln
st
1200
2 Plant/kiln
nd
1650
3rd Plant/kiln 4700
4rt plant at Mangrol 2100
Total Capacity 10200 TPD
PLA
9
1.2.2 PRODUCTION ANALYSIS TABLE: IN TONS – Nimbahera and Mangrol Plant
10
2. MANAGEMENT SET- UP
2.2 Heads:
Project
Project Head Shri NK Mishra
BU
Unit Head J K Cement, Nimbahera and Mangrol,
Shri S K Rathore
Distt: Chittaurgarh, Rajasthan
President Shri B K Arora J K Cement- White and Grey Plants at
Gotan, Distt: Nagaur, Rajasthan
JK Cement Works, Muddapur,Distt:
Unit Head Shri R B M Tripathi
Bagalkot, Karnataka
3. ORGANISATIONAL CHART
J K Organization
J K Cement Ltd.
Abroad:
12
5. CORPORATE SOCIAL RESPONSIBILITY
13
6. INTRODUCTION TO CEMENT
6.1 HISTORY OF CEMENT
The history of cement is the story of civilization from primitive caves of pre-
historic times to the skyscrapers of the modern age. It is said that the use of cement is
form the period of use of fire. Egyptians utilized gypsum plaster as cementing material as
early as 3000 BC building their monuments.
However, It was in 1824, sixty-eighty years after the discovery of hydraulic properties of
lime Joseph Aspdin patented his product, which was called "Portland Cement" The plants
manufacturing portland cement outside England were commissioned in Belgium and
Germany in 1855. The interest that is evoked in the technology of cement resulted in the
development of Rotary kilns in 1886.
Modern cement is the outcome of the combined research and development efforts of
chemists, technologists and architects. The cement technology is an offshoot of the
overall development in other industries, technology, constructional activities and
knowledge and the availability of raw material.
Cement can be defined as any substance, which can join two or more pieces of some
other substance together to form a unit mass. Cement, as used in construction industries,
is a fine powder which when mixed with water and allowed to set and harden can join
different components or members together to give a mechanically strong structure. Thus
cement can be used as bonding material for bricks or for bonding solid particles of
different sizes (rubber masonry) to form a monolith.
14
Components of Portland Cement
Ordinary Portland Cement is the basic cement and it has three grades namely 33, 43 and 53
respectively. Limestone is the principal raw material for the manufacturing of cement. Our
country has enough reserve of raw material needed in the cement industry. Cement
consumption growth is highly correlated to the GDP growth and serves as a
leading
indicator. More industrial activity and greater purchasing power means more asset formation
and construction and thus more consumption of cement.
Lime 64 63-66
Silica 22 17-25
Alumina 5 3-6
Sulphur 1 1-3
Alkalise 1 0.2-1.0
15
Advantages of OPC Cement
Develops early strength at 3 and 7 days with exceptionally high 28 days strength. Form
work of slabs and beams can be removed much earlier which results in increased speed
of construction.
Unbeatable consistency in quality gives better accountability for mix design
The higher characteristics strength of concrete leads to higher bond strength
minimizing the possibility of slippage of reinforcements.
The dense and least permeable concrete prevents leakage / seepage problems.
Its high fineness offers better workability for a given water cement ratio ensuring very
dense, compact and durable concrete.
Being the low alkali cement it provides insurance against alkali-
aggregate reaction,
this results in durable structures.
Hyd ration
In this experiment, the hydration rate for each type of tricalcium silicate component is measured.
Hydration is the reaction that takes place between cement and water that leads to setting and
hardening. All compounds present in Portland cement clinker are anhydrous, but when brought
into contact with water, they are all attacked or decomposed, forming hydrated compounds. When
the tri- or di- calcium silicates react with water a calcium-silicate-hydrate gel is formed.
This
calcium-silicatehydrate (C-S-H) is the principal hydration product and primary binding phase in
Portland cement.
The chemical reactions that take place during hydration are summarized below:-
16
Pozzolana Portland Cement (PPC)
It is cheaply manufactured because it uses flyash /burntclay/ coal waste as the main
ingredient. PPC has a lower heat of hydration which is of advantage in preventing cracks
where large volumes are being cast. PPC accounts for 18.3% of the production. Suitable
for most of the applications as stated in OPC ideally suited for domestic consumption like
plastering, brickwork, mass concreting works like dams, large foundation. This cement
enchances the impermeability and cohesiveness of concrete. As a result durability is
enhanced. It also generates low heat of hydration.
Portland Pozzolana Cement is new generation cement. It contains high reactive Silica
(HRS) to enhance ultimate performance of concrete. Pozzolana is essentially a siliceous
material in finely divided form with the presence of water, that react with Calcium
hydroxide at ordinary temperature liberated during the hydration of Portland Cement to
produce stable, cementitious compounds. These compounds contribute to strength and
water tightness of Cement and are specially suitable for Dams and mass construction
like foundation.
17
6.3 TYPES AND USES OF CEMENT:
(a) Type of Cement:
Grey Cement
White Cement
Portland Pozzolona Cement (PPC) General construction, hydraulic construction & marine.
Oil Well Cement Connecting the steel casing to the walls of gas oil wells at high
temperature and to seal porous formations in petroleum
industry.
Low Heat Portland Cement Where low heat on hydration is required as in mass concrete for
dams.
Super Sulphated Cement In a varity of aggressive conditions like marine works, concrete
sewers carrying industrial effluents.
High Alumina Cement Mainly as refractory cement and as structural material giving
high early strength development in cold regions.
Basically there are two types of process for cement manufacturing that is
18
6.5 PROCESS O VERVIEW
6.5.1 MINING OF LIMESTONE
In cement industry mining is one of the major aspect. Raw material (limestone) required
for the manufacturing of cement is extracted from captive mines. JK Cement have four
mines:
1. Ahirpura Mines
2. Malikhera Mines
3. Tilakhera Mines
4. Karoonda Mines
MINING METHOD
Limestone mining operation traditionally is carried out generally as Opencast mining in
India. However, newly developed Eco-friendly Surface Miners are also used in limestone
mines today in various cement plants. Mining methods includes the following activities:
Resources:
(a) Explosives
Kelvex 600
Ammonium Nitrate
(b)Equipment:
Drilling Machines- for making the deep holes for explosives. (Fig.1)
19
Excavators / Shovels- for loading the material in dumper. (Fig.2)
Dozers-to remove the raw material and to clear the passage. (Fig.4)
(C) Operations:
Limestone from mines is explored by using drilling and blasting techniques. Drilling is done with
the help of DRILLING MACHINE and then explosive is inserted in hole and blasting is done.
Sequential Timer Blasting Machines are used for blasting operations. This timer machine reduces
the problem of noise, ground vibrations and improves fragmentation by introducing inter
row
delays. Noise, dust and illumination surveys are conducted at regular intervals in our mines to
keep the same under control. Instruments used for noise and surveys include Noise Dosimeter and
Gravimetric Dust Sampler respectively. Equipments used in this method of Open cast Mining
includes HM-25 dumpers, POCLAIN & DEMAGE shovels, Hindustan and BEML loaders,
BEMLl dozers etc. The limestone produced by this method are in the form of big boulders having
their physical dimensions may be from 1.5 meter to small fragment size up to few millimeters.
Therefore before taking the limestone to grinding machines, boulder crushing in one or two
stages is required for reducing the size of limestone for preparing suitable feed size to grinding
mills.
20
Fig.1 Drilling Machine Fig.2 Excavator
21
MINING WITH SURFACE MINER
Surface miners were firstly developed for road making and are now used for limestone mining
operation also. Being eco friendly machine, Surface Miners eliminate the problems associated
with drilling, blasting, crushing & loading and the complaints associated with their activities.
The surface miner is a track-mounted machine with a powerful diesel engine and hydraulic
pumps for delivering the power to the cutting drum. The cutting drum is made up of a special
alloy steel with replaceable Tungsten Carbide cutting tools (spikes), which can be quickly
detached or fixed. The drum can be lowered or lifted by hydraulic system with powerful
hydraulic motors thereby varying the depth of cut. Dust is suppressed at the source itself by water
spraying on to the milling drum thereby making it an environment friendly machine. As the cut
materials are of uniform size and the impact on the crusher while crushing is reduced. Whenever,
there is an interstitial reject band encountered, the same is eliminated by loading and dumping it
separately in the specified dump thereby facilitating Selective Mining with this machine.
Crushing is the process of reducing the size of BOULDERS through crushers. The big
boulders produced during drilling and blasting methods of limestone mining are crushed
in suitable type of crushers. Crushers are of three types:
1. Double Toggle Jaw Crusher (Capacity : 400 TPH): Used as primary crusher.
2. Swing Hammer Crusher (Capacity : 200 TPH) used as secondary crusher.
3. Compound Impactor (Capacity : 800 TPH) combined unit of primary and
secondary crusher.
The crushing is carried out either in single or double stages by using Primary crusher and
Secondary crusher, or in a single stage crushing machine depending upon the size of the
boulder produced while mining. This also depends on the type of grinding mills used for
grinding of raw materials for preparation of finally pulverized raw meal. In our plant, we
have two types of crushers:
22
1. PRIMARY CRUSHER (ONE IMPACT CRUSHER)- Capacity 800 tonnes / hr.
(Fig.5)
23
Fig.6 Hammer Crusher
These crushers are used for reduction of size of limestone boulders to a suitable feed size
acceptable to the different types of grinding machines installed in plants. The crushers are mainly
installed at the plant site. The limestone produced in the mine is transported to crusher site with
the help of dumpers and tippers of different capacities. In some mines the crushers are installed at
mine site and crushed limestone is transported to plant stockpile with the help of Belt conveyor/
Ropeway. Fig.7 below illustrates the raw limestone mining and crushing at a limestone mine of a
cement plant.
24
6.5.3 PREHOMOGENISATION
The crushed limestone is then transported to stacker reclaimer site with the help of BELT
CONVEYOR (Fig.8) installed at different plant site. Finally the crushed limestone is
pre-
blended with the help of stacker and reclaimer systems. The crushed limestone travelling on the
belt conveyors is stacked in layers through STACKER MACHINE (Fig.9) and PILES (Fig.10)
are formed. (Pile is the arrangement of one layer of raw material over the another in a
longitudinal form).The stacked materials is then cut in slices with the help of a RECLAIMING
MACHINE (Fig.11) which mixes the layers of stacked limestone which reduces the variation in
quality of limestone as compared to the large variations obtained in the limestone obtained from
mines. The full fledge stack pile ready for reclaiming and feeding to raw mill hoppers can be seen
in the above figure. In our plant at Nimbahera, we have the following type of stacker and
reclaimer:
Stacker:
Type of Pile: Longitudinal.
Details of Piles: 20000 – 30000 tonnes per pile. Height of pile up to 11.00 meters.
Rated capacity: 1000 tonnes per hour. It varies from plant to plant depending upon the
production requirement.
The stacker moves on longitudinal rails.
Reclaimer
Type: Bridge Scrapper Type.
25
Rated Capacity : 600 tonnes per hour It will vary from plant to plant depending on
the production requirement (in TPD).
Working Principle: Cuts Stack Pile in slice from parallel to face of pile. Shifting
material
(limestone) to belt with the help of scrapper.
The feed size of the vertical mill is 40 mm and it saves 20% energy as compared to Ball
mill. The rotating size of Atox mill is 25-27 rpm. For ball mill the feed size is 25 mm. In
ball mill the material is grinded through the impact of balls inside the mill. The rotating
speed of ball mill is 16-17 rpm.
In our plant we have four mills codified as RM1, RM2, RM3, and RM4. The grinding
capacity of each mill is as follows:
RM1-90 tonnes / hour.
27
RM2-110 tonnes / hour.
RM3-110 tonnes / hour.
RM4-200-210 tonnes / hour.
In case of raw grinding the fineness of output 20-24 % residue on 90 µ and 3.5 – 4.5 %
residue on 212 µ.
28
6.5.5 HOMOGENISATION
The raw material grounded in the raw mill is thoroughly blended in C.F Silos of capacity
10000 tonnes or more. The blending is performed by introducing the compressed air and
sliding of bed of fine raw meal due to operation of different chutes for a certain interval
from C.F Silo to discharge bin. The characteristics of blending raw meal should satisfy
the requirement of standard deviation in the range of (+/-) 0.8 to 1.0 in LSF of raw meal.
The moisture content of raw meal powder is less than 0.7 %. The properly blended raw
meal is now ready for burning the same to produce cement clinker in cement rotary kiln.
The grounded raw material is sent to CF SILO (CONTINOUS FLOW SILO) (fig.14),
where the raw material is blended properly.
Fig.14 CF Silo
6.5.6 PYROPROCESSING
The modern pyroprocessing system comprises the following important three sections:
1. Preheating and precalcining.
2. Clinkerisation and
3. Cooling.
The PREHEATING section (fig.15) is 90-100 meters tall and comprises of battery of
cyclones arranged one over the other in series. The modern preheaters are comprising of
5-6 stage of low pressure cyclone as compared to conventional 4 stages of cyclone
preheaters. The riser ducts of top stage cyclones are connected with powerful induced
29
draft fan also known as preheater fan, smoke gas fan etc. Precalcining of raw meal is
carried out in separate vessel vertically held and placed in between preheating and
clinkerisation section known as Pre-Calciner.
The CLINKERISATION reaction is carried out in a ROTARY KILN (fig.16 & 16.a).
The rotary kiln is a long cylindrical shell provided with refractory bricks from inside
which prevents the heat loss from the kiln and protects the steel shell from any damage
due to exposure to high temperature maintained inside the kiln. The kiln is inclined at an
angle of about 3-4° from horizontal from preheating to the cooling end. The kilns are
mounted on tyres and rotated at a speed of 1.5-4.5 rpm depending upon type of kiln. The
dry and properly blended raw meal is lifted either by Air lift or mechanically by Bucket
Elevator from the bottom of raw meal blending / storage silo to the top of the preheater,
and fed at the top stage of cyclone inlet duct with the help of screw conveyor and rotary
air lock. Raw meal weigh-feeders are installed for continuous weigh of raw meal for
feeding the same to pre-heater at a constant rate.
30
CHEMICAL TRANSFORMATIONS
During heating of the raw meal to the burning temperature 1350oC to 1450oC (clinkerization or
sintering) certain physio-chemical processes take place. These include Dehydration of the
argillaceous minerals; decomposition of the carbonates (decarbonisation or expulsion of CO 2
commonly known as calcination); reactions in solid phase and reactions with the participation of one
liquid phase and crystallizations at the temperature range of 850 C -900 C.
o o
These processes are influenced by chemical factors in the raw meal (such as its chemical
composition), by mineralogical factors (its mineralogical composition), by physical factors (fineness
or particle size in the raw meal), homogeneity and other factors. The complete course of these
endothermic reactions plays a decisive role in quality of the resulting cement.
In pre-heater kiln, the first five transformations shows in figure 17 will take place in pre-heater
tower. The decomposition of limestone and other carbonates will primarily take place in the
calciner vessel where the calcination temperature is maintained by injection of fuel. The last two
transformations will take place in the rotary kiln.
The carbonate Ca CO decomposes between 800 C – 900 C to form CaO. Quartz and clay will
3
O O
have started decomposing slightly before that to liberate free reactive Al2O3and SiO 2
The CaO being formed at this stage, now reacts with SiO2to form C S and later with more CaO to
2
components such as CA, C A and others, which will decompose at higher temperature at later
12 7
stage.
C S content is seen to grow steadily during the heating and reach maximum content at approx.
2
1300 C which is a point where liquid phase appears. The major part of C S is then transformed to
O
2
C S in the liquid phase on further increase in temperature and the final content of C S in the
3 2
Combustible fuels eg., coal, liquid fuel oil, or natural gas are used for providing heat
for
converting raw meal into clinker.
31
Our plant uses a mixture of petro coke (75-85%) and remaining coal obtained from
Indian / South African coal mines. The coal obtained in the form of lump containing upto
10% moisture is ground to suitable fineness in vertical roller mills or closed circuit tube
mills at different cement manufacturing facilities. The cooler exhaust/ part of preheater
gases are used for drying away the moisture from coal while grinding the same in the
airswept VRM or tube mills. The figure16 represents a typical pyroprocessing kiln with
planetary coolers in a dry process 4-stage suspension preheater kiln equipped with folax
cooler.
Conversion of raw meal into cement clinker is accomplished in steps in various zones of
kiln circuit. The pulverized fuel (about 35-40% of total fuel to be fed to kiln system) is
pushed into the burning zone of rotary kiln through a specially designed burner pipe
along with the primary air known as Primary air. The high temperature persisting in
burning zone makes the fine coal to burn near the tip of burner pipe and helps in flame
shape formation.
The combustion gases generated from burning of purlverized coal in clinkerisation zone
of the kiln flow towards the inlet of PH fan under the influence of the induced draft
created in the kiln circuit. While flowing from burning zone towards the inlet of fan after
passing through Kiln Precalciner–Preheater circuit, the high temperature combustion gas
transfer its heat to the finally derived raw meal which is fed to the inlet duct of 1st stage
twin cyclone and falls towards the bottom end of preheater after passing through all
stages of cyclones under the influence of hot gases flowing in the circuit. The moisture
and other volatile contents present are completely driven away and thus raw meal attains
between preheater and kiln. The precalciner is fired with 55-60 % of total pulverized fuel
for increasing the precalcination degree of raw meal upto 90-95% before the same is fed
to kiln for accomplishing the clinkerisation reaction. The remaining 5-10% degree of
calcination of raw meal is performed in the kiln before the meal enters in to the burning
zone. Thus burning zone in rotary kiln receives complete decarbonated material, the part
of which is transformed into liquid after achieving appropriate melting temperature of
some of the raw meal components and powdery form of raw meal gets converted into
nodulized clinker form. The final clinkerisation of raw meal is achieved between the
temperature range of 1350-1450oC depending upon the raw meal characteristics. The
high temperature clinker nodules varying in size then fall out of the kiln and enter the
32
cooler and then COOLING of hot clinker is done. In our plant there are three kiln, out of
which 2 kiln are provided with planetary coolers and one kiln is equipped with Folax
grate cooler .The modern Folax grate coolers are provided with fixed and moving grate plates.
Below the grate are provided number of air chambers which receive atmospheric cold air with
the help of number of high pressure discharge fans in different compartments. The
pressurized air flows through the holes provided in the grate plates cools the clinker
which is travelling in the form of granules on the grate plates. The clinker is cooled down
to a temperature of 100-150oC while leaving the outlet end of the cooler. The cold
clinker is crushed continuously in a suitable clinker crusher provided at the outlet end of
the cooler before the same is discharged on the clinker transportation system for
transporting the same to clinker storage Silo stock/ Pile.
33
The Ball / Tube mills (in open circuit or closed circuit mode) are used for clinker
grinding in cement plant worldwide. However, the energy requirement of Ball Mills
being compartively higher for cement grinding, new types of energy efficient equipments
like Vertical Roller Mills, Roll Presses / Roller Presses in combination with Ball Mill /
Closed Circuit Ball Mills, Horro Mills etc., are now being used for grinding cement
clinker. Our plant is using ball mill grinding machines for cement grinding. We have 6
ball mills codified as CM1, CM2, CM3, CM4, CM5, CM6. The capacity of these
cement mills are as follows:
The cement grinding unit along with dust collector, cement storage silo and the despatch
section are illustrated in the figure 19.
The pulverized different types of cements are stored in different silos installed with
different capacities. Depending upon the market requirements the cement is loaded in
bulk or packed in 50KG bags with the help of conventional rotary packers or electronic
packers, loaded on to trucks / wagons and finally despatched to the required destinations.
Purpose:
To pack cement in appropriate packages suitable for consumption at site.
50 Kg bags
Bulk handling of cement has started at selected places .Bulk cement loading in
close container is available at our Mangrol Plant
White Cement:
50 Kg and small size packs as per market demand
34
Packers:
Mechanical Packers
Electronic Packers
cement is loaded in trucks and railway wagons and finally sent to destinations.
product (i.e. cement in this case). The concept of quality has undergone a sea change
from mere quality control of the product to total quality management (T.Q.M.) with
emphasis on quality defined as “totality of features and characteristics of product /
services that bears on its ability to satisfy the stated and implied needs”
The quality of the product depends on variety of factors such as technology, quality of
raw materials and fuels, operation and quality control procedures to produced consistent
product.
The broad quality parameters of cement relate to chemical and physical properties as per
IS Code are as mentioned below:
CHEMICAL PROPERTIES:
Loss on ignition [LOI]
Insoluble residue [IR]
Sulphur trioxide [SO3]
Magnesium oxide [MgO]
Total chloride [Cl]
Lime saturation factor [LSF]
Alumina modulus [AM]
.
35
PHYSICAL PROPERTIES
Fineness
Consistency
Setting time – initial and final
Soundness
Compressive strengths (3 days, 7 days and 28 days)
Heat of hydration
Drying shrinkage [for PPC]
7.1 : CRUSHER
Purpose:
Size reduction from 1.0M * 1.4M * 1.1M boulder to 25mm size limestone pieces.
Daily requirement of crushed material:
1.6 to 1.7 times the production capacity of clinker (approx. 5600 tonnes per day
for 1.0 million tonnes plant).
Common type of Crushers:
Double Toggle Jaw Crusher (Capacity : 400 TPH): Used as primary crusher.
Swing Hammer Crusher (Capacity : 200 TPH) used as secondary crusher.
Compound Impactor (Capacity : 800 TPH) combined unit of primary and
secondary
crusher.
Reclaimer Stacker:
Type of Pile: Longitudinal.
Details of Piles: 20000 – 30000 tonnes per pile. Height of pile upto 11.00 meters.
Rated capacity: 1000 tonnes per hour. It varies from plant to plant depending upon the
production requirement
Rated Capacity : 600 tonnes per hour It will vary from plant to plant depending on
the production
requirement (in TPD
36
Working Principle:
Cuts Stack Pile in slice from parallel to face of pile.
Shifting material (limestone) to belt with the help of scrapper.
37
7.1B : Swing – Hammer Crushers
Operating Principles:
As for the solid rotor impactor, this crusher type contains one or sometimes
two heavy rotors horizontally mounted inside a rigid frame, which is lines
throughout with replaceable liner plates.
7.1
7.2
38
Contrary to the solid rotor impactor, the rotor of the swing-hammer crusher is made
of a series of discs, between which the hammers are freely suspended. When the rotor
revolves at high speed, the hammers are flung outwards due to the centrifugal force.
The material is either fed to the crusher via a feed ramp, similar to the solid-rotor
impactor, via feed rollers – or entered directly on top of the rotor. The latter feed
arrangement is normally only applicable for low capacity, double –rotor machines
where the material is crushed against a centrally mounted anvil between the rotors.
When the feed material enters the crusher, it is initially struck by the hammer and
then projected against the breaker plates at the opposite side of the feed opening.
The disc construction of the rotor allows undersize feed material to penetrate the
rotor, thus reducing the amount of material being hit by the hammers. Contrary to the
solid–rotor impactor, where the breaker plates normally are suspended from the roof
of the crusher, the breaker plates of a swing – hammer crusher are usually placed
directly on the crusher frame walls.
39
7.1C : Solid-Rotor Impactor Breakers
7.3
40
7.1D : GYRATORY CRUSHER:
41
42
8.CONCLUSION
The summer internship in JK CEMENT plant in Nimbaher was a great opportunity
to understand how manufacturing process of cement is done . On a personal front it
was an invaluable opportunity for me to have a practical experience of a cement
manufacturing plant.
9.REFERENCE
Books and Authors
R G Blezard, The Hostory of Calcareous Cement in P C Hewlett
A C Davis, Hundred Years of Portland Cement
WEB SITE
www.jkcement.com
www.rtcnorthindia.org
www.crushermill.com
www.mineral-grinder.com
www.unique-machinery.com
43
44