Professional Documents
Culture Documents
of Clinker Capacity
Grinding Unit
CONFIDENTIAL
17326 i
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
ACKNOWLEDGEMENT
17326 ii
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
TABLE OF CONTENTS
1 PREAMBLE 1.1-1.3
17326 iii
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
LIST OF ANNEXURES
17326 iv
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
LIST OF ABBREVIATIONS
ABBREVIATION DESCRIPTION
% Percentage
µ Micron
Approx. Approximate
Avg. Average
CO Carbon Monoxide
dB Decibel
Dia Diameter
Ha Hectare
IS Indian Standard
kg Kilogram
km Kilometer
kW Kilo Watt
17326 v
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
ABBREVIATION DESCRIPTION
LV Low Voltage
m Meter
mA Milli Ampere
max. Maximum
mio Million
Misc. Miscellaneous
mm Millimeter
MW Megawatt
NH National Highway
No./nos. Numbers
Para Paragraph
PC Precalciner
PH Preheater
17326 vi
TechnIcal Feasibility Report for Augmentation of Clinker
Capacity of Durg Cment Plant (DCP), Chhattisgarh
Grinding Unit
ABBREVIATION DESCRIPTION
Rs. Rupees
Sn Serial Number
t Tonnes
V Volt
17326 vii
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Project JKLC proposes to enhance the clinker capacity from existing 1.5 mio tpa to
1.98 mio tpa, feasible with available infrastructure, process optimization,
modifications and investment.
Capacity
Product Existing/
Additional Total
Granted
Project Clinker
Proposal (mio tpa) 1.5 0.48 1.98
CPP (MW) 20 - 20
WHR (MW) 8 - 8
ML-2 81o 23’ 00.0” - 81o 24’ 53.0” 21o 24’ 00.0” - 21o 25’ 30.0”
Land details for Cement Plant at Durg and Mines is furnished below:
Land
17326 0.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The cement plant area falls under Seismic Zone –II as per IS 1893 (Part I):
Site
2002. The other climatic conditions of the area are as follows:
Conditions
Temperature : Min 12 oC and Maximum 45 oC
Rainfall : Min 850 mm, Max 1,250 mm
Humidity : Min 7%, Max 85%
Wind velocity : 0.2-5 m/s
Limestone
Reserve 119.45 mio t as on 28.02.2018
(Residual)
In addition, JKLC has also available 500 KVA DG sets for meeting power
requirement during emergency.
17326 0.2
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Water JKLC has approval from Water Resource Department, Raipur for withdrawal of
Demand And 1.64 million cubic meter water per annum from river Shivnath for which the
Availability company has constructed an anicut as per the conditions of the Chhattisgarh
(Contd…) State Government.
Further, there is permission from Central Ground Water Authority for withdrawal
of 320 m3/ day ground water for domestic use.
Kiln : 35 %
Fuel Firing
PC : 65 %
17326 0.3
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Assessment The assessment of kiln and cooler vis-à-vis basis specified in the above Table
of Kiln and is given below:
Cooler
4,500 tpd 6,000 tpd 6,000 tpd
Parameter @ 4.5 rpm @ 5.0 rpm @ 5.5 rpm Remarks
Specific volumetric
5.5 7.3 7.3 Manageable
loading
Last two
cooler fans to
Specific Cooling Air
1.76 1.76 1.76 be replaced
required
with higher
capacity fans
17326 0.4
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Assessment The PH fan is adequate with WHR operation. However, in case of WHR
of PH Fan, stop condition, the fan volumetric capacity marginally exceeds the design
Bag house/ capacity.
ESP
Cooler ESP and ESP Fan volumetric capacity are adequate to meet the
requirement of 6,000 tpd clinker with WHR operation. However, the ESP
fan pressure marginally exceeds the design however with sufficient margin
available in the volumetric capacity of the ESP fan which would
compensate the shortfall in the pressure margin
Raw Mill/ Kiln Bag House and Bag House Fan are adequate to meet the
requirement of 6,000 tpd clinker with WHR in operation. However, in case
of WHR stop condition the Bag house fan is just adequate.
Coal mill Bag House and Bag House Fan are adequate to meet the
requirement of 6,000 tpd clinker with limited margin available in BH fan
PH Fan, ESP Fan, Raw mill/ kiln bag house fan, Coal mill bag house fan may
be upgraded by tipping of the blades in consultation with OEM to have an
additional margin for sustained operation.
17326 0.5
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Assessment Required
Design
of Storages Material Type Capacity at Remarks
Capacity
6,000 tpd
Limestone Covered 2 x 25,000 t Adequate for
24,696 t
Stock Yard 2.7 days
Silica Sand Covered 10,000 t 2,534 t Adequate for
Flue Dust Stock Yard 1,764 t 17 days
Pond Ash 4,961 t
Raw Meal Silo 15,000 Adequate for
14,688 t
1.6 day
Clinker Silo 45,000 Adequate for
45,000 t
7.5 days
Coal Covered 2 x 50,00 Adequate for
5,053 t
Stock Yard 7 days
17326 0.6
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Environment
Plant practices continuous monitoring of dust and gas emission from the
Protection
main process stacks
Dust emissions from main stacks were found within the limits.
The cooler ESP sometimes indicates emission level close to the limit. It is
suggested to take appropriate measures to keep the emission level always
well within specified limit and taking care of the additional volume handling
capacity after the proposed capacity enhancement. Similar steps shall be
taken to improve the emission level from bag houses by improving the
quality of bags and gas handling capacity.
A standard procedure and practice for regular internal monitoring and
recording of all dust and gaseous emission levels are in place
Nuisance bag filters have been installed at all material transfer points to
control the fugitive dust
NOX emission data reported shows occasionally higher emission than
specified. To maintain the NOX level within the specified limit, JKLC shall
install SNCR system to control NOX to less than 600 mg/Nm3
For control of SOx in the CPP area, FGD system is envisaged to control
SOX less than 100 mg/Nm3. SOx emission level in the Cement Plant is
within permissible limit.
JKLC is taking all necessary measures to control pollution with respect to
water, air, solid waste and also in the development in and around the
factory premises
JKLC practices rain water harvesting (52 rain water harvesting units),
ground water level monitoring, green belt development inside the plant and
nearby villages
Environment The environmental impacts that are likely to arise due to the proposed capacity
Impact enhancement during the operations phase are summarized below:
Management
17326 0.7
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Environment
Impact Sn Attributes Probable Impacts
Management
2 Soil No impact
(Contd..)
3 Ecology No impact
4 Water Resources No increase in water usage pattern is
envisaged as no new equipment shall be
installed for the desired capacity enhancement.
Water withdrawal shall not have any adverse
impact on dynamic reserves by implementation
of rain water harvesting system.
5 Water Quality Treated waste water is being re-used in the
process, greenbelt & dust suppression,
maintain zero liquid discharge. No impact is
expected.
6 Air Quality Impairment of ambient air quality
7 Noise Quality Not applicable as no new equipment is installed
8 Vehicular Increase in vehicular traffic for other raw
Movement material and clinker movement
9 Solid Waste Not applicable
10 Aesthetics Not applicable
11 Site of Cultural, Not applicable, no such structure in the vicinity
Historical &
Scenic
Importance
12 Socio-Economic No impact
condition
17326 0.8
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
17326 0.9
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
17326 0.10
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Design Specific heat consumption for the cement plant is < 715 kcal/ kg clinker.
The operating specific heat consumption of the plant is varying from 710-715
kcal/kg clinker with 5 stage operations which is expected to reduce further by 4-
5 kcal/ kg clinker with enhancement in capacity to 6,000 tpd clinker.
With 4 stage operations, benefit to environment will be higher due to high waste
heat based generation of power corresponding to higher exit temperature from
preheater gases which will be used in WHR Boiler more efficiently. At 6,000 tpd
clinker production with 4 stage operation, generation of power will be even
higher with higher and more efficient heat recovery process thereby reducing
GHG emission to atmosphere to a larger extent. However, the specific heat
consumption at 4 stage operation will be more and expected to be around 725-
730 kcal/ kg clinker.
17326 0.11
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Adequacy of Adequacy with respect to Land, water, power, specific heat & power
Land, water, consumption, emission vis-à-vis design is summarized below:
power etc.
After
Design
Proposed
Sn Parameter Unit (1.5 Remarks
Enhancement
MTPA)
(1.98 MTPA)
1 Land Area Hectare 130 130 No change
Water
2 KLD 3,050 3,050 No change
Requirement
Increase in power
demand by 3.1 MW
Power is expected but grid
3 MW 13.6 16.7
Requirement connection will not
be increased due to
WHR Power
Further saving of
~0.5 kWh/t clinker
Specific
kWh/t is expected with
4 Power 58.2 53.5
clinker proposed process
Consumption
optimization
measures
Expected saving of
~ 4-5 kcal/kg
Specific Fuel kcal/kg clinker with the
5 <715 ~710
Consumption clinker proposed
optimization
measures
There shall be
slight increase in
dust emission due
to higher
production level.
Particulate 3 JKLC to ensure
6 mg/Nm <30 <30
Matter particulate
emission to less
3
than 30 mg/Nm by
enhancing the bag
house volume/ ESP
field.
The Capex towards efficiency improvement/ optimization measures for the smooth & sustained
operation of the plant at 6,000 tpd clinker are given in Table below:
17326 0.12
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Investment
Section Description (Lakh Rs)
CONCLUSION:
Based on the above assessment, it can be concluded that the clinker line has the potential to
produce 6,000 tpd, which may be achieved by de-bottlenecking/ optimization of process
parameters and minor up-gradation in the equipment. The expenses for de-bottlenecking/
optimization and improvement measures envisaged to produce 6,000 tpd clinker is estimated as
Rs 1,550 Lakh.
17326 0.13
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
With increase in production to 6,000 tpd, plant key performance parameters namely Specific
heat consumption is expected to reduce about 4-5 kcal/ kg clinker and Specific power
consumption is expected to reduce about 0.5 kWh/t clinker. Saving in fuel and power shall also
help in reduction of CO2 emission.
At 6,000 tpd clinker production, there shall be enhanced power generation through Waste Heat
Recovery System installed in the Cement Plant. Hence, the project activity will displace
equivalent amount of electricity generation in fossil fuel based thermal power plant, thereby
reducing GHG emission to atmosphere.
Based on assessment of clinkerisation section, total annual clinker capacity of Durg Cement
Plant of JKLC of 1.98 mio tpa clinker (6,000 tpd) is feasible with proposed de-bottlenecking/
optimization measures. JKLC, hence, may reckon the plant clinker capacity as 1.98 mio tpa.
17326 0.14
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
CHAPTER 1: PREAMBLE
1.1 INTRODUCTION
JKLC is also in the process of setting up a Thermal Power Plant (TPP) of 20 MW in the existing
premises of Integrated Cement Manufacturing Unit to meet the major power requirement of the
Plant in an uninterrupted and economical manner. The CPP is scheduled to commence
operation from December 2018.
Ministry of Environment & Forest (MoEF), Vide letter no. J – 11011/1170/2007 – IA (I) dated
13.05.2009 & 04.09.2015 (Validity extended for five years with effect from 12.05.2014 i.e upto
12.05.2019) had accorded approval for environmental clearance of the Cement Project at
Malpuri Khurd, Durg, Chhattisgarh.
The aforesaid unit/ activities of the Cement Project have also consent from Chhattisgarh
Environment Conservation Board (CECB) vide their letter no. 1343/TS/CECB/2011 dated
04.06.2011 & 5079/TS/CECB/2016 dated 20.12.2016 (validity extended for five years from date
of issue) as per details given in Table below:
17326 1.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
1.2 PROJECT
JKLC has already been granted environment clearance to set up 1.5 mio tpa clinker capacity
under phase 2 which would expire in May 2019. However, it is noted that due to paucity of
funds, they may not go for expansion of the cleared capacity. Instead, JKLC is looking forward
to exploit the inherent potential of the operating cement plant to enhance the clinker production
with marginal investment so as to sustain and compete in the market place.
In view of the above, JKLC proposes to enhance the clinker capacity from present existing 1.5
mio tpa to 1.98 mio tpa which is feasible with available infrastructure, process optimization and
modification and investment. The project proposal is stated as under:
Capacity
Product Total after Remarks
Existing/
Additional Proposed
Granted
Project Enhancement
Proposal Clinker (mio tpa) 32%
1.5 0.48 1.98
enhancement
CPP (MW) 20 - 20
No change
WHR (MW) 8 - 8
Having already achieved the guaranteed parameters with respect to production level, JKLC has
entrusted HOLTEC to carry out the technical feasibility study and report with a view to ascertain
the adequacy of installed machineries for a production level of 1.98 mio tpa clinker capacity on
sustained basis, so that MoEF may be approached for enhancing the name plate capacity of the
existing cement plant to 1.98 mio tpa.
JK Lakshmi Cement Limited is a profit making and dividend paying Flagship Company of
Eastern Zone of JK Group.
The company had started the cement business in the year 1982 by setting up a plant with a
capacity of 5 lakh tonnes per annum at Jaykaypuram, Basantgarh, Distt. Sirohi, Rajasthan. Over
the years, the capacity has gradually been enhanced to the present level of 109 lakh tonnes
per annum at the following locations:
Capacity Lakh tonnes per annum
Sn Location Cement Capacity
1. Sirohi Cement Plant, Rajasthan - IU 46.36
2. Grinding Unit, Kalol, Gujarat - GU 9.00
3. Grinding Unit, Jhajjar, Haryana - GU 13.14
4. Grinding Unit, Surat, Gujarat - GU 13.50
5. Durg Cement Plant, Chhattisgarh - IU 27.00
Total 109.00
17326 1.2
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Apart from expanding the cement capacity and in order to be self-sufficient for its power
requirement, the company has set up 54 MW (3 X 18 MW) thermal power plants and also a 15
MW waste heat recovery power plant at its existing plant at Jaykaypuram, Basantgarh, Dist.
Sirohi, Rajasthan.
The company has set up a 8 MW waste heat recovery based power plant at their Durg unit and
are in the process of setting up a 20 MW CPP at their Durg unit to meet most of the power
requirement of existing Cement Production Line.
HOLTEC’s ensemble of 900+ clients, in over 90+ countries, includes cement producers,
equipment & service providers, EPC & construction firms, infrastructure developers, investing &
funding bodies and all other relevant stakeholders. Since its inception, HOLTEC has delivered
significant value to its clientele through 4,000+ consulting assignments.
1.5 METHODOLOGY
A HOLTEC specialist visited the plant site during 15-16thMarch, 2018. The various activities
carried out during the plant visit are:
1.6 REPORT
This report covers the assessment of plant potential capacity based on the data and feedback
received from JKLC during plant visit undertaken on 15-16thMarch, 2018.
This study draws extensively from HOLTEC’s database on plant designs norms, cement
industry standards & practices etc.
17326 1.3
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Annexure 1.1
SCOPE OF WORK
Site Visit
Visit to the plant site by a HOLTEC specialist to study the available infrastructure, installed plant
& machinery, operational parameters.
Coverage
The coverage proposed shall include assessment of plant operations, equipment specifications,
storages and environmental protection measures with basic objective of establishing the plant
potential capacity. The following areas would be covered with respect to specifications, output
etc., encompassing:
During the visit, HOLTEC specialist shall collect details of current operational parameters such
as clinker output, heat & power consumption, emission levels, etc as mentioned under coverage
above.
Based on the findings of site visit and analysis of data collected, HOLTEC shall prepare
Technical Feasibility Report on potential clinker capacity which is feasible with available
infrastructure, process optimization and minor modification/ investment.
Deliverable
HOLTEC will submit 1 hard + 1 soft copy of Technical Feasibility Report. This will include:
Preamble
Plant Location and Infrastructure
Capacity Assessment and Environmental Protection
17326 1.1.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
The Integrated Cement Manufacturing Unit is located at about 35 km from Durg city & 35 km
from Raipur city.
2.2 LAND
The Integrated Cement Manufacturing Unit is spread in an area measuring 130 ha. Out of 130
ha, an area of 50.6 ha is marked as greenbelt/ plantation area.
JKLC has mining leases spread across 519.774 ha. The green cover for mining lease ML 1 is
70.8 ha. ML-2 of 252 ha out of the above is new lease and is yet to be operational.
Land details for JKCL Cement Plant at Durg and Mines is furnished below:
17326 2.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
Road
The approximate distances of major towns from the cement plant are:
Raipur : 35 km
Bilaspur : 120 km
Nagpur : 275 km
Durg : 35 km
Rail
The Plant does not have railway siding at present. Provision of railway siding and allied utilities
kept shall help reduce the logistics cost, improve the net realization, augment market reach.
Bhilai – Nandini rail link is close to the plant site near Ahiwara at a distance of about 2 km. The
nearest Railway station is Kumhari located at a distance of 20 km from the plant site. Charoda
Rly. Siding is located at a distance of about 30 km from plant site and is presently utilized for
bringing imported coal/ pet coke for plant operations. Railway approvals for setting up the siding
have been obtained.
Air
The nearest domestic airport for the plant is at Raipur at a distance of about 45 km. Plant site
with Raipur airport is well connected with road network.
Sea
Plant site is well connected with sea linkage network. Nearest sea port is located at
Vishakhapatnam. Vishakhapatnam sea port is about 600 km from plant site. Paradwip sea port
is located at a distance of about 670 km. Mumbai sea port at Nhava Sheva, Navi Mumbai, is
located at about 1,100 km.
Pet coke, imported coal and gypsum is currently imported via Vishakhapatnam sea port and
Reliance Industries, Gujarat and brought to plant site by rail till Devbaloda Charoda railway
siding located at about 30 km from the plant site. From Devbaloda Charoda railway siding,
material is brought by road transport.
17326 2.2
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
JKLC has been granted mining leases for mineral Limestone near Nandini-Khundini and
Ghikuria villages of Dhamdha tehsil, Durg district, Chhattisgarh. The limestone areas can be
located in Survey of India Toposheet No. 64 G/7 and is bounded by following coordinates:
ML-2 81o 23’ 00.0” - 81o 24’ 53.0” 21o 24’ 00.0” - 21o 25’ 30.0”
17326 2.3
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
The ML areas are located about 36 km East-Northeast of Durg town and can be approached
from Durg by following the Durg-Raipur NH-53 upto Powerhouse Flyover and then following the
Nandini road leads to ML areas.
JKLC has been granted mineral concession for limestone over total area of 519.774 ha in Durg
district, Chhattisgarh. The status of mineral concession area is summarized below;
Total 519.774
Source: JKLC
Land Status
17326 2.4
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
Distance
Source
Sn Material Source Locality from plant Remarks
Category
(km)
Raw Material
01 Limestone Captive Near village Nandini- 6 The crusher is located
Mineral Khundini & Ghikuria, within ML-1 and limestone
Concession Tehsil-Dhamdha, District after crushing is
Durg transported to plant Trucks.
02 Silica Sand Outsource Rajim village, Gariaband 80 Transport by road
district, Chhattisgarh
03 Pond Ash Outsource NSPCL, Bhilai 35 Transport by road from
NSPCL Thermal Power
Plant, Bhilai.
04 Flue dust Outsource BSP, Bhilai 35 Transport by road from
Bhilai Steel Plant.
Fuel
01 Coal Outsource SECL coal from open 150 Coal is transported to plant
market by road.
02 Coal Outsource Imported 30* Import through Vizag port
and transport by rail upto
Charoda Rly. Siding and
then by road upto plant.
03 Pet Coke Outsource Imported 30* Import through Vizag port
and transport by rail upto
Charoda Rly. Siding and
then by road upto plant.
*- Distance from rail head to plant
Table: Details of input materials
17326 2.5
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
2.7 UTILITIES
Power
JKLC has an agreement with Chhattisgarh State Power Distribution Company Limited
(CSPDCL) for a contract demand of 31.11 MVA (29.55 MW at 95% power factor) at 220 KV for
Cement Plant and Mines at 220 KV.
JKLC has installed 8 MW (gross) WHRS which is operational. Further, JKLC is in the process
of installing 20 MW CPP scheduled to be commissioned in December 2018.
In addition, JKLC has also available 500 KVA DG sets for meeting power requirement during
emergency.
Water
Water is required for equipment cooling, drinking, sanitation, horticulture, etc. The total daily
water requirement for Cement Plant, WHR, TPP, Mines, Drinking & Sanitation etc is given in
Table below:
Quantity
Area
(m3/day)
Cement Plant 1,150
Horticulture 1,000
Mines 100
Drinking & Sanitation 250
Waste Heat Recovery (8 MW Gross) 150
CPP (20 MW) 400
Total 3,050
JKLC has approval from Water Resource Department, Raipur for withdrawal of 1.64 million
cubic meter water per annum from Shivnath river located at about 14 km. JKLC has constructed
an anicut as per condition of the Chhattisgarh Government and has installed pumping facility
and connected the plant with water pipe line.
Further, there is permission from Central Ground Water Authority for withdrawal of 320 m3/ day
ground water for domestic use.
Fuel
The cement production line is utilizing pet coke, South African coal and local coal from SECL
mines as fuel.
17326 2.6
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
J K Lakshmi Cement Ltd.
Considering availability of coal from international market from countries such as South Africa,
Indonesia etc. and E auction from coalfields as well as arrangement of pet coke from local /
international market, fuel availability is not foreseen as a constraint.
2.8 COMMUNICATION
Communication facilities such as telefax, STD, ISD and Internet are available at the Plant site.
2.9 MANPOWER
Skilled manpower is available to operate the Plant in an efficient manner. JKLC plant is
operational since March 2015.
The location of project is about 1 km away from Malpuri Khurd & Khasadih with the nearest
town being Bhilai & Raipur at 30 km & 35 km away respectively. Ahiwara is located at about 4
km distance. The area is scantily populated.
Social Amenities
Educational facilities are available near the project site at Ahiwara and Kumhari. Higher
education and professional educational facilities are available at Bhilai, Raipur and Durg.
Additionally, health centers, shopping centers, recreational facilities are available within a radius
of 35 km.
Residential Infrastructure
In view of the proximity to major cities, staff is accommodated in the nearby cities.
17326 2.7
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
3.1 INTRODUCTION
JKLC has an Integrated Cement Manufacturing Unit having installed clinker capacity of 1.5
mio tpa at Durg, Chhattisgarh.
Key details of the Integrated Cement Manufacturing Unit are furnished below:
The main machinery suppliers for the Integrated Cement Manufacturing Unit are furnished
below:
Sn Package Supplier
Pyro-processing
10 FL Smidth Pvt. Ltd.
(Preheater, Kiln, Cooler)
17326 3.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Sn Package Supplier
This chapter covers the description of installed plant & machinery and storage facilities at
JKLC’s Integrated Cement Manufacturing Unit at Durg, Chhattisgarh. It also gives the design
data of specific heat and power consumption at 4,500 tpd.
Description of major plant and machinery with vintage, design capacities and make are given
below in Table 3.1
EQUIPMENT SPECIFICATIONS
Vintage
Operation No. Description Design Capacity Make
(Year)
17326 3.2
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
EQUIPMENT SPECIFICATIONS
Vintage
Operation No. Description Design Capacity Make
(Year)
3
Volume Flow: 6,99,720 m /hr
Gas Temp: 343 0C
Pressure: -133
Cooler 1 ESP 2015
Precipitator Current: 800 mA
Gas Density: 0.542 kg/m3
3
Emission: < 30 mg/Nm
50 tph coal
@12% residues
on 90 micron or
Coal Mill 1 Vertical Roller Mill 2015 25 tph UBE-Loesche
petcoke@3%
residues on 90
micron
Gas Volume: 2,20,000 m3/hr
0 0
Operating Temp: 80 C Normal, 90 C
Peak
Filtering Area: 3,653 m2
Filtering media: Poly Acrylo Netrile
Bag
1 Coal Mill 2015 Space Needle Felt Gm/2-2% SS Fiber
House
Ass Mixture NT Static & Silicon
Finished
Bag Size: 152 mm ID X 4270 mm LG.
No. of Bags: 1792
Emission: < 30 mg/Nm3
Ball Mills - 100
tph for PPC @
2 nos., Ball Mills
Clinker 3,500 blaine LNVT / UBE-
3 1 no., Vertical Roller 2015
Grinding VRM – 130 tph Loesche
Mill
for slag @
3,600 blaine
17326 3.3
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Material Handling
Luffing Boom Stacker, 1,000 tph Bridge type reclaimer, 600 tph
Limestone
capacity (FL Smidth Make) capacity (FL Smidth Make)
Correctives (Silica Sand, Point Stacking by tipper
By Pay Loader (Manual)
Pond Ash, Flue Dust) conveyor
Stacker, 150 tph (FL Smidth Reclaimer, 100 tph (FL Smidth
Coal
Make) Make)
Point Stacking by tipper
Gypsum By Pay Loader (Manual)
conveyor
Stacker, 250 tph (FL Smidth Reclaimer, 200 tph (FL Smidth
Slag
Make) Make)
Mechanical Transport (Bucket Mechanical Transport (Bucket
Cement
Elevator) Elevator)
Table 3.2: Details Of Main Material Handling Equipment
The details of storages available in the Cement Plant are given below:
Storages
Material Type Capacity
17326 3.4
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Storages
Material Type Capacity
Electrical
The power to plant loads is distributed via Load Centers, located close to the electrical loads in
the different process departments.
6.6 kV is envisaged to feed the plant HT loads. The single bus switchboards in the load centers
are fed from the Main Substation.
The power at 6.6 kV is stepped down to 415 V at these load centers through 6.6/ 0.433 kV
distribution transformers and connected to LT switchboards to cater to LT loads of the plant.
Radial system of plant power distribution has been considered as it is economical, safer and
allows expansion if needed.
The main Electrical and Control items considered are as given below:
Sn Item Make
1 HT Switchgear Siemens
2 LT Switchgear Siemens
3 HT Motors Siemens
4 LT Motors Siemens
5 Distributed Control System (DCS) FLS
Distributed control system comprising of programmable controllers and operator stations with
peripherals considered for remote operation of plant from a central control room.
Necessary field sensors installed to monitor process variables like pressure, temperature, flow,
level, speed etc. The sensors are linked to Plant Control System through field transmitters/
transducers to display the parameters on Operation Station and exercise the desired controls.
The Plant is provided with Gas Analyzers at various locations for process optimization and
safety. The list of analyzers is given below:
17326 3.5
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Sn Location Type
The details of material handling of various materials for clinker production line are as follows:
The average section wise specific power consumption (Design) as collected from the plant
during the site visit is as follows:
Design
Sn Area Sp. Power Consumption (kWh/MT)
1 Crusher 2
4 Pyro processing 21
17326 3.6
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
This section covers status of statutory approvals/ clearances for the Cement Project, Waste
Heat Recovery Power Generation (WHR) and Thermal Power Project (TPP) at Durg,
Chhattisgarh.
The Table below provides the status of these required approvals/ clearances based on data
received from JKLC:
The statutory approvals/ clearances required to operate Cement Project & WHR Project at
Durg, Chhattisgarh have been obtained and are in place.
Necessary permissions and approvals for height, regular blast, Gram Panchayat, Town &
Country Planning, installation of Electrical equipment, construction labour, GST registration,
PF registration, minimum wages act etc are available.
17326 3.9
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
4.1 INTRODUCTION
The Cement Plant is having a modern dry process rotary kiln technology with single string-5
stage preheater and inline calciner.
Considering efficient plant & machinery installed and infrastructure available in the plant, it is felt
that the Clinker Production Line has potential to produce more by process optimization and
minor modification/ investment.
Having already achieved the guaranteed parameters with respect to production level, JKLC has
entrusted HOLTEC to carry out the technical feasibility study with a view to ascertain the
adequacy of installed machineries for a production level of 1.98 mio tpa clinker (6,000 tpd)
capacity on sustained basis, so that MoEF may be approached for enhancing the name plate
capacity of the plant to 1.98 mio tpa.
This chapter covers the technical assessment of the JKLC’s Cement Manufacturing Unit at
Durg, Chhattisgarh entailing the technical specifications of the plant & machinery, quality control
systems, vis-à-vis the proposed capacity enhancement for a sustained operation.
It assesses following aspects for the proposed capacity enhancement of the existing plant:
JKLC clinker production achieved since commissioning of the plant are given below in Table
4.1:
17326 4.1
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The potential capacity of the plant and adequacy in terms of equipment sizing & storages for
producing 6,000 tpd clinker (1.98 mio tpa) is discussed in the subsequent paras.
The main equipment specifications installed for clinker production along with existing storages
have been furnished in Chapter 3.
Capacity assessment of the clinkerisation section has been done based on the following
operating parameter as given in Table 4.2:
Sn Description Values
Limestone 95 %
Silica Sand 1.50 %
3 Raw mix
Pond Ash 2.50 %
Flue Dust 1.00 %
Fuel (Net CV kcal/kg of fuel) Mix Fuel NCV 5,788 kcal/kg
4 (Based on 30% Pet coke, 40% imported coal and 30%
Indian coal)
Kiln : 35 %
6 Fuel Firing
PC : 65 %
Limestone : 3.0 %
Silica Sand : 6.0 %
7 Feed Moisture
Pond Ash : 20.0 %
Flue Dust : 10.0 %
17326 4.2
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Capacity assessment of the pyro process section and its preceding and succeeding system has
been done based on the following operating parameter as received from JKLC;
The norms for operating hours for main machinery considered for assessment is furnished
below in Table 4.3.
Operating
Sn Department
Hrs/Day Days/week Days/year
1 Limestone Crusher 12 6 300
2 Coal Crusher 12 7 330
3 Raw Mill 21 7 330
4 Pyro processing 24 7 330
5 Coal Mill 21 7 330
Table 4.3: Operating Hours
The storage days considered for assessment of storages is furnished below in Table 4.4.
Sn Details Days
1. Limestone 3-5
2. Correctives 7-14 (depending upon lead time)
3. Raw meal 1-1.5
4. Clinker 7-14
5. Fuel 7-14 (depending upon lead time)
Table 4.4: Storage Days
The assessment criterion (norms) considered for determining the kiln & cooler potential capacity
are given below in Table 4.5.
17326 4.3
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Kiln
Specific volumetric loading of kiln
- Sustained operation tpd/m3 7.0
- Peak tpd/m3 7.5
Kiln filling % 12 -16
Specific thermal loading Gcal/h/m2 5.5
Cooler
Specific cooler load tpd/m2 <45
Cooler specific cooling air Nm3/kg clk 1.8 – 2.0
These norms have been formulated based on operating experience both in India & abroad and
depend upon the geographical location of the plant.
The assessment criterion (norms) considered for determining the adequacy of preheater, pre-
calciner and tertiary air duct for 6,000 tpd clinker are given below in Table 4.6.
PH
Gas velocities in riser ducts (for efficient m/s < 18
operation)
Optimum Cyclone Loading tpd/m2
- Top stage 110
- Lower stages 90-100
PC
Gas residence time sec >5
TAD
Tertiary Air Take off Velocity m/s 5-6
TAD gas velocity m/s > 25
17326 4.4
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The specifications of installed kiln and cooler system are given below in Table 4.7:
The capacity of the clinkerisation plant is mainly driven by its pyro-processing section (pre-
heater, kiln & cooler). Hence, assessment has been accordingly done for determining the
adequacy of pyro-processing section as per the HOLTEC norms and based on the
specifications of the installed Kiln and Cooler.
The assessment of kiln and cooler for 6,000 tpd production capacity at design kiln rpm (5.0 rpm)
and proposed kiln rpm (5.5 rpm) is given below in Table 4.8.
17326 4.5
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Specific volumetric
tpd/m 3 7.0-7.5 5.5 7.3 7.3 Manageable
loading
Last two
existing fans
may be
Specific Cooling Air Nm3/ kg
1.9-2.0 1.76 1.76 1.76 replaced
required clinker
with higher
capacity
fans
Table 4.8: Kiln & Cooler Assessment
HOLTEC Assessment:
Kiln
At the clinker production level of 6,000 tpd, expected kiln operating load works out to be
402 kW, leaving 100% margin over installed capacity 805 kW. Generally, a design margin
of 75 - 100% is considered in the rating of installed motor over required operating power.
The purpose is to take care of high torque needed during start - up and abnormal situations
like ring formation, ball formation, fall of coating, etc. This margin will be about 100 % if the
existing drive of rating 805 kW is continued to be used for a production level of 6,000 tpd
clinker. Hence, the kiln main motor rating is adequate.
Degree of filling preferably 12-16% is suggested. The degree of filling at the current kiln
design RPM of 5, works out to 15.6%, which is closer to the limit. Hence, kiln rpm is
proposed to be increased upto 5.5 by changing gear reduction ratio through
modifications in gear box internals for flexibility in operation.
Specific thermal loading works out to 5.1 Gcal/hr/m2, which is within the acceptable value of
5.5 Gcal/hr/m2
Specific volumetric loading works out 7.3 tpd/m3, which is within the peak recommended
loading and is manageable.
17326 4.6
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Cooler
The specific cooler loading works out as 50 tpd/m2, which is higher than acceptable industry
norms (< 45 tpd/m2). Higher thermal load leads to high wear and tear of the cooler internals
and high clinker cooler discharge temperature.
Installed cooling air at 6,000 tpd production works out as 1.76 Nm3/kg clinker, which is
lower than the recommended 1.9-2.0 Nm3/kg clinker.
There is aspect of WHR as well, as JKLC has installed 8 MW WHR based power plant. The
higher cooler loading will lead to higher cooler vent temperature, which will get trapped in
the WHR system once WHR is running and the higher heat loss will be recovered in terms
of power through WHR.
Considering current operation with WHR, cooler operation at 6,000 tpd clinker production
appears manageable at cooler loading of 50 tpd/ m2. However, the cooler operation needs
to be reviewed on regular basis in this scenario.
However, for most efficient operation and minimum wear & tear specific cooler loading
needs to be reduced from 50 tpd/m2 to < 45 tpd/m2, by addition of one module in
consultation with OEM. For extension of module following modifications are expected:
Extended module foundation shall start from DPC tunnel bottom
Roller crusher drive need to be relocated towards water spray tank
Water spray system needs to be relocated.
ESP discharge arrangement need to be relocated
DPC vent filter & its fan need to be relocated
For the above actions, approximately 4-5 weeks downtime may be required.
Last two fans may be replaced with higher capacity fans to increase the cooler installed
air to around 1.9-2.0 Nm3/kg clinker.
4.3.3 Assessment of PH, PC, Kiln Feed & Clinker Pan Conveyor
The details of assessment of PH, PC, kiln feed and DPC capacity have been given in Table 4.9.
17326 4.7
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
From the above assessment of cyclone loading, PH Cyclones sizes are adequate for
operation at 6,000 tpd.
The gas velocity in Riser, Down-comer duct, TAD and the gas residence time in PC have
been estimated at 6,000 tpd and found within the permissible limit.
The pan conveyor capacity has lesser margin of 32% over the required capacity which is
lower than the specified norm and is considered manageable at 6,000 tpd.
The kiln feed bucket elevator capacity has no margin and needs upgradation/ replacement.
The Kiln feed bucket elevator rated capacity is 302 and operating at 390 tph at a speed of
1.86 m/s. The elevator speed is already at its maximum, any up gradation by increasing the
speed further does not appears to be feasible. Since margin in kiln feed system is already
exploited the same needs to be upgraded/ replaced by a new kiln feed bucket elevator
of 510 tph capacity.
The assessment has been done based on 715 kcal/kg clinker of sp. heat consumption, fuel
NCV of 5,788 kcal/kg fuel, fuel firing rate in kiln as 35% for 6,000 tpd clinker production. The
details of assessment are given in Table 4.10.
17326 4.8
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
Both the kiln & PC burners are suitable to meet the requirement of 6,000 tpd clinkerisation
plant.
The PH fan assessment has been carried out based upon the PH exit gas volume of 1.48
Nm3/kg clinker. The details of assessment are given below in Table No 4.11.
HOLTEC Assessment:
The PH fan is adequate with WHR operation. However, in case of WHR stop condition the
fan volumetric capacity marginally exceeds the design capacity. The PH fan may be
upgraded by tipping of the blades in consultation with OEM to have an additional volumetric
margin for sustained operation.
4.3.6 Assessment of Cooler ESP & ESP Fan
The cooler ESP and ESP fan assessment has been carried out based upon the cooler exit gas
volume of 1.0 Nm3/kg clinker. The details of assessment are given below in Table 4.12.
17326 4.9
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Table 4.12: Cooler Bag House & Bag House Fan Assessment
HOLTEC Assessment:
Cooler ESP and ESP Fan volumetric capacity are adequate to meet the requirement of
6,000 tpd clinker with WHR operation. However, the ESP fan pressure is marginally
exceeds the design. Since, there is sufficient margin available in the volumetric capacity of
the ESP fan, this would compensate the shortfall in the pressure margin. In view of this the
operation at 6,000 tpd is manageable. However, it is suggested to get the ESP fan
upgraded in consultation with OEM to have adequate margin in the pressure for sustained
operation.
4.3.7 Assessment of Kiln/ Raw Mill Bag House & Bag House Fan
The detail of assessment of Bag House and Bag House Fan is given below in Table no 4.13.
17326 4.10
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
Raw Mill/ Kiln Bag House and Bag House Fan are adequate to meet the requirement of
6,000 tpd clinker with WHR in operation. However, in case of WHR stop condition the fan is
just adequate. The BH fan may be upgraded by tipping of the blades in consultation with
OEM to have an additional margin for sustained operation.
.
4.3.8 Assessment of Coal Mill Bag House & Bag House Fan
The detail of assessment of Bag House and Bag House Fan is given below in Table no. 4.14.
Table 4.14: Coal Mill Bag House & Bag House Fan Assessment
HOLTEC Assessment:
Coal mill Bag House and Bag House Fan are adequate to meet the requirement of 6,000
tpd clinker. Since the margin available in BH fan is limited, the coal mill Bag House Fan
may be upgraded by tipping of the blades in consultation with OEM to have an additional
margin for sustained operation.
The crusher requirement for a 6,000 tpd clinkerisation plant is worked out as below based on
the operating practices and working raw mix parameter:
= Clinker capacity per day x Clinkerisation factor x (Limestone % in raw mix/100) x (1/(1-%
loss/100)) x Kiln operating days per week/crusher working hrs per week
17326 4.11
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Crushing operation is adequate for a 6,000 tpd clinker plant based on 12 hours operation per
day.
The assessment detail of limestone crusher is given below in Table no 4.15:
Requirement at
Parameter Units Design Remarks
6,000 tpd
865 based on 12
hrs per day
Limestone Crusher tph 950 Adequate
operation in two
shift
Table 4.15: Limestone Crusher Assessment
Limestone Stacker
The plant has a 1,000 tph stacker installed which has ~5% margin over the crusher capacity of,
and hence adequate for 6,000 tpd clinker plant.
Limestone Reclaimer
The plant has a 600 tph reclaimer installed. The requirement of a reclaimer based on 95%
usage of limestone, works out to 415 tph. The installed reclaimer has thus a margin of about
~45% and hence adequate for 6,000 tpd clinker plant.
HOLTEC Assessment:
Equipment installed for limestone crushing, stacking & reclaiming is of Indian/ European
origin and the capacity of crusher is adequate for a 6,000 tpd clinker plant based on 12 hrs
per day operation. Stacker and reclaimer have sufficient margin and hence adequate.
Environment control measures in this section is by means of installation of adequate
numbers of bag filters at transfer points, dust suppression by water spray and covered
storage.
The raw mill requirement for a 6,000 tpd clinkerisation plant is worked out as below:
= (Clinker Capacity per day x clinkerisation factor / mill run hrs per day)
17326 4.12
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
= 6,000 x 1.53 / 21
= 437 tph
The assessment detail of raw mill to operate the clinkerisation plant at 6,000 tpd is given below
in Table no 4.16:
Requirement at 6,000
Parameter Units Operating Remarks
tpd
437 @ 16% residue
475 @ 16%
Raw Mill tph on 90 µ based on 21 Adequate
residue on 90 µ
hrs per day operation
Table 4.16: Raw Mill Assessment
The raw meal residue is subject to adjustment depending upon the burnability of raw meal and
the current residue level being maintained in the plant operation is 15-16% on 90 µ. Hence, the
design mill output becomes 475 tph at 16% residue on 90 µ which is adequate to meet the
requirement of 6,000 tpd clinker plant and no constraint is foreseen.
HOLTEC Assessment:
Raw grinding technology selected is from a reputed supplier, efficient from maintenance
and power consumption considerations.
Raw Mill with guaranteed figure of 400 tph @ 12% R on 90 µ installed in the plant is
operated at an output of 475 tph @ 16% R on 90 µ and is adequate for a 6,000 tpd clinker
plant.
Material transport system deployed is mechanical system- energy efficient.
Environment control is through Bag Filter, suitable for maximum permissible dust emission
of 30 mg/ Nm3.
For sustained operation, mill optimization is proposed
Plant is using mix fuel namely Pet coke and Coal. The fuel mix is pre-dominantly having Pet
coke of 30% followed by 70% Coal. Hence, the mill for fuel grinding has been evaluated based
on Mix fuel usage for capacity assessment purposes.
17326 4.13
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
= Clinker capacity in tpd x (Sp heat cons / NCV of fuel) x ((100- % moisture in dry fuel)/(100-
%moisture in fine fuel)) / Mill run hours per day
The assessment detail of coal mill to operate the clinkerisation plant at 6,000 tpd is given below
in Table no 4.17:
Requirement at
Parameter Units Operating Remarks
6,000 tpd
45 @3.5% R on
90 µ (20% pet 35 based on 21 hrs
Coal Mill tph Adequate
coke and 80% per day operation
coal)
HOLTEC Assessment:
Coal grinding technology selected is state of art and sourced through a reputed supplier
and offers a best solution with respect to maintenance and power consumption
considerations.
Coal Mill installed in the plant is adequate to meet the plant requirement at 6,000 tpd
clinker.
Environment control is through Bag house suitable for maximum permissible dust
emission of 30 mg/ Nm3.
For sustained operation, mill optimization is proposed
The provision of storages varies from plant to plant, depending upon the following:
Lead distance of raw material source from plant
Ownership of raw material source i.e. self or “bought out”
Transportation route
Cost of resource
Operator’s comfort
Inventory cost for storages
The storage capacity of the plant has been assessed for a 6,000 tpd clinker plant based on the
operating raw mix. The detail of the assessment is given below in Table no 4.18:
17326 4.14
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Storages
Design Required Capacity
Material Type Remarks
Capacity at 6,000 tpd
Covered
Limestone 2 x 25,000 t 24,696 t Adequate for 2.7 days
Stock Yard
Silica Sand 2,534 t
Covered
Flue Dust 10,000 t 1,764 t Adequate for 17 days
Stock Yard
Covered
Coal 2 x 5,000 t 5,053 t Adequate for 7 days
Stock Yard
Table 4.18: Assessment of Storages
HOLTEC Assessment:
Limestone storage is adequate for 2.7 days against industry practice of 3-5 days.
However, the material is captive and no constraint is foreseen in timely availability of
material. Thus limestone storage available in the plant is manageable for operation of
plant at 6,000 tpd clinker.
The storages envisaged for Silica Sand, Flue Dust & Pond Ash are locally available and
are adequate for smooth running of the plant at 6,000 tpd clinker.
Raw Meal storage available is sufficient for 1.6 days against industry practice of 1-1.5
days of kiln running and is adequate.
Coal & clinker storages facility is sufficient for about 7 days operation against industry
practice of 7-14 days. Storage available in the plant is adequate from operation point of
view and are within industry norms.
Environment control measures in this section is by means of installation of adequate
numbers of bag filters at transfer points, dust suppression by water spray and covered
storages.
The annual requirement of raw materials and fuel for clinkerisation section of 1.98 mio tpa
capacity (6,000 tpd) is proposed to be met as given below in Table 4.19:
17326 4.15
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Volumes
Sn Material Source category
(mio tons on annual basis)
Raw materials:
1 Limestone (Local) Captive Leased Mine 3.03
2 Silica Sand Outsource 0.05
3 Flue Dust Outsource 0.03
The annual requirement is estimated based on percentage usage of material in raw mix,
moisture content in respective material, handling loss of 2% and clinker conversion factor of
1.53. For assessment of fuel requirement, 30% pet coke, 40% imported coal and 30% Indian
coal with NCV of 5,788 kcal/ kg of mix fuel has been considered.
The additional number of truck load by virtue of increase in clinker capacity to 6,000 tpd is given
below vis-à-vis 4,500 tpd plant.
HOLTEC Assessment:
Limestone constitutes about 95% of raw material requirement and its transportation to
plant is through truck. However, quantity/ frequency of dumpers for transport of
limestone to crusher and subsequently to plant shall be suitably increased. JKLC is in
17326 4.16
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
the process of constructing a pipe conveyor which after the completion would eliminate
the need for trucks.
Similarly, JKLC shall develop railway siding in future eliminating the need for truck for
transport of fuel. Considering 3,500 t carrying capacity rake, there would be requirement
of 1 wagon in every 4 days for a 6,000 tpd plant and 1 wagon in every 6 days for a 4,500
tpd plant. Thus, additional 19 wagon load shall be required on annual basis in transport
of coal.
For transport of other raw materials such as silica sand, pond ash, flue dust would
require additional 4 truckloads on daily basis (1,320 truck load on annual basis)
The Capex towards efficiency improvement/ optimization measures as deliberated above and
proposed by JKLC for the smooth & sustained operation of the plant at 6,000 tpd clinker are
summarized below in Table 4.20.
Investment
Section Description (Lakh Rs)
17326 4.17
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Investment
Section Description (Lakh Rs)
The plant Layout at JKLC has adequately considered Infrastructure, approach road, internal
roads, plant & non plant buildings according to the production needs, along with desired green
area.
The overall layout is compact and functional from arrangement point of view.
The layout has adequate space for putting additional production lines, WHR and captive power
plant.
4.7.1 Laboratory
To ensure consistent product quality and for the trouble free and cost effective operation,
modern quality control facilities have been provided at JKLC.
The laboratory is equipped with X-ray lab facility for raw materials, clinker & cement and with
basic chemical analysis facility for raw materials, clinker & cement testing for quality control.
The plant laboratory has the basic facilities for physical testing of raw materials, fuel, clinker and
cement. For physical analysis the laboratory has the facilities for sample grinding and testing of
complete physical properties of cement & clinker like sieve analysis, soundness, CCS, moisture
content, lime reactivity, drying shrinkage etc.
The list of laboratory equipment available at Durg Cement Plant Is given below;
17326 4.18
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
To produce good quality cement, it is imperative that sampling & testing of various raw
materials, fuels, in-process materials and the final product is carried out regularly at the required
intervals for taking corrective action timely.
To ensure consistent product quality and to permit the trouble free and cost effective operation,
the quality control plan for sampling & testing of various raw materials, in-process materials and
the final product is given in Table below.
While talking about the methods and procedures for quality control, the following aspects have
been taken into account:
17326 4.19
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Facilities and equipment envisaged for quality control of the raw materials and final products for
the existing plant are as follows:
Sampling/ Test
Stage of Testing Method and
Sn Material Type of Tests
Inspection Frequency Acceptance
Criterion
1.0 Raw Materials
Chemical As per applicable
Bi Hourly
analysis by standard, SOP
1.1 Limestone Pile stacking during
XRF & and reference
operation
moisture defined by JKLC
Chemical
Additives / As when analysis by Day average
1.2 -Do-
Correctives received XRF & composition
moisture
Air slide to Chemical
bucket analysis by
1.3 Raw Meal Hourly -Do-
elevator/Auto XRF &
sampler moisture
Air slide to Chemical
Kiln Feed &
bucket analysis by
1.4 Homogenization Bi Hourly -Do-
elevator/Auto XRF &
silo
sampler moisture
As when
1.5 Standard Sand Size analysis Each Lot -Do-
received
2.0 Pyro Processing
Proximate Day average
2.1 Fuel Pile stacking -Do-
analysis & CV composition
Air slide to Residue on
Fine Blended fine fuel 212 and 90
2.2 Twice in shift -Do-
Fuel bin/Auto micron, IM,
sampler VM, Ash
Degree of
2.3 Calcination 5th cyclone Per shift -Do-
calcination
Liter weight, Hourly/ Bi
Deep bucket
2.4 Clinker Chemical Hourly/ Day -Do-
conveyor
analysis by average
17326 4.20
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Sampling/ Test
Stage of Testing Method and
Sn Material Type of Tests
Inspection Frequency Acceptance
Criterion
XRF, Free
lime,
Mechanical
test
Clinker Chemical & Consignment
2.5 Clinker Sale dispatch mechanical average -Do-
point parameter composite
3.0 Others
Physical
As when As when
3.1 Lab Glass ware inspection/clas -Do-
received received
s
Physical
As when As when
3.2 Lab Chemicals inspection/Gra -Do-
received received
de
Dimension,
Packing As when valve opening,
3.3 Each Lot -Do-
Material (Bags) received Mass &
Strength
HOLTEC Assessment:
Quality control systems and equipment installed are modern, established, as per the current
industry norms and are adequate for managing quality control system for 6,000 tpd plant
Laboratory is well equipped for carrying out complete Chemical and Physical analysis
JKLC has also installed cross belt analyzer before the limestone stacker belt for on-line real
time process control & raw material management
4.8.1 Introduction
This section deliberates upon the prevailing site and infrastructural conditions and structural
adequacy in general of civil and structural facilities at site.
The various salient parameters attributing to the assessment of the main design considerations
being:
The basic plant civil design criteria adopted/ considered for the buildings/ structures at Durg
Cement Plant is as given below:
17326 4.21
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Buildings Description
Mechanical Buildings
The plant structures have been designed considering a combination of reinforced cement
concrete (RCC) as well as structural steel elements with suitable block wall/CGI sheet roofing
and/or cladding and other building materials as required based upon design criteria and type of
structure.
The status of civil structure on the basis of visual observation is as given the Table below:
CIVIL STRUCTURES
Building Condition Rehabilitation required
Crusher Good No
Raw Mill Good No
Preheater Good No
Kiln & Cooler Good No
17326 4.22
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
CIVIL STRUCTURES
Building Condition Rehabilitation required
Cement Mills Good No
CCR Good No
Approach roads Good No
Internal roads Good No
HOLTEC Assessment:
Overall condition of civil structures is good and no major rehabilitation is foreseen in the
immediate future.
Assessment of plant utilities and infrastructure are given below in Table 4.21.
WHR (gross) 8 MW OK OK
17326 4.23
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Rail Infrastructure
Bhilai – Nandini rail link is close to the project site near Ahiwara at a distance of about 2
km.
Charoda Rly. Siding is located at a distance of about 30 km from plant site and is
presently utilized for bringing imported coal/ pet coke for plant operation.
JKLC does not have their own railway siding. Provision of railway siding and allied utilities
shall help reduce the logistics cost, improve the net realization, augment market reach
Road Infrastructure
Cement plant is well connected with road network.
17326 4.24
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
A complete firefighting system is available in Durg Unit, which comprises of the following:
• A suitable high-pressure system of fire hydrants consisting suitable number of fire
hydrants
• A complete separate firefighting water piping network for feeding the hydrants
• Heavy-duty ABC powder type fire extinguishers hanged at particularly important electrical
equipment areas
• Portable CO2 extinguishers provided throughout the plant
• Automatic fire extinguishing system utilizing water considered for the empty bags store in
the packing plant. A 7,000 liter capacity fire tender is available 24x7.
Table 4.21 : Plant Utilities & Infrastructure
HOLTEC Assessment:
17326 4.25
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The power to plant loads is distributed via Load Centers, located close to the electrical loads in
the different process departments.
6.6 kV is envisaged to feed the plant HT loads. The single bus switchboards in the load centers
are fed from the Main Substation.
The power at 6.6 kV is stepped down to 415 V at these load centers through 6.6/ 0.433 kV
distribution transformers and connected to LT switchboards to cater to LT loads of the plant.
Radial system of plant power distribution has been considered as it is economical, safer and
allows expansion if needed.
The main Electrical and Control items considered are as given below:
HOLTEC Assessment:
The power connection is adequate to meet the power requirement of the plant
The Electrical, Controls and Instrumentation are from reputed supplier
Distributed control system comprising of programmable controllers and operator stations with
peripherals considered for remote operation of plant from a central control room.
Necessary field sensors installed to monitor process variables like pressure, temperature, flow,
level, speed etc. The sensors are linked to Plant Control System through field transmitters/
transducers to display the parameters on Operation Station and exercise the desired controls.
HOLTEC Assessment:
The Controls and Instrumentation system installed in the cement plant are adequate to meet
the production needs of the plant.
JKLC has 240 staff on regular basis and 653 on contract basis to look after the operation and
maintenance of the plant.
17326 4.26
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
The staff strength is adequate for satisfactory operation of the plant.
Type of equipment installed in the plant to clean the dust laden gas before discharge to the
atmosphere and designed outlet dust concentration is given below in Table 4.22.
Equipment
Section/ Area Unit Designed Efficiency
Installed
Raw Material
mg/ Nm3 < 30 mg/ Nm3 99.99 %
Grinding Bag House
Kiln mg/ Nm3 < 30 mg/ Nm3 99.99 %
Coal Grinding Bag Filter mg/ Nm3 < 30 mg/ Nm3 99.99 %
Cement Grinding Bag Filter mg/ Nm3 < 30 mg/ Nm3 99.99 %
Bagging and
Bag Filter mg/ Nm3 < 30 mg/ Nm3 99.95 %
Loading
Transfer Points Bag Filter mg/ Nm3 < 30 mg/ Nm3 99.95 %
Ministry of Environment and Forest (MOEF) has amended the Environment (Protection) Rules,
1986 vide Gazette Notification dated 10th May 2016 called as Environment (Protection) Third
Amendment Rules, 2016. Relevant portion of the Amendment Rules is given in Table 4.23
below:
17326 4.27
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The emission level of the Kiln/ raw mill bag house stack, Cooler ESP, Coal mill stack, Slag mill
stack, LS Crusher stack for last 3 years is given in Table no. 4.24 below:
3
Particulate Matter (mg/Nm )
RABH 8.3 26.8 23.3 20.3 27.2 24.0 22.3 24.5 23.6
Cooler ESP 9.4 29.6 26.5 22.5 29.3 25.9 24.8 27.8 26.5
Coal Mill Stack 8.3 28.4 24.7 21.2 28.3 24.4 23.2 25.6 24.5
Slag Mill Stack 9.4 28.1 24.3 20.5 28.4 25.4 19.0 26.5 24.5
L/S Crusher
13.8 29.7 26.8 21.6 29.0 25.5 23.4 27.5 25.3
Stack
Source: JKLC
Table 4.24: Emission Level
The maximum reading for NOX emission in the plant is recorded as 949 mg/Nm3 and 436.73
mg/Nm3 on average basis. Maximum recorded NOX emission is high than the permissible limit.
JKLC is taking step to install SNCR system to control the same within the permissible limit.
Average SOX level recorded in the plant is 18.61 mg/Nm3which is within the permissible limits.
Green Initiatives
17326 4.28
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
Plant practices continuous monitoring of dust and gas emission from the main process
stacks
Dust emissions from main stacks were found within the limits.
The cooler ESP sometimes indicates emission level close to the limit. It is suggested to
take appropriate measures to keep the emission level always well within specified limit and
taking care of the additional volume handling capacity after the proposed capacity
enhancement. Similar steps shall be taken to improve the emission level from bag houses
by improving the quality of bags and gas handling capacity.
A standard procedure and practice for regular internal monitoring and recording of all dust
and gaseous emission levels are in place
Nuisance bag filters have been installed at all material transfer points to control the fugitive
dust
NOX emission data reported shows occasionally higher emission than specified. To
maintain the NOX level within the specified limit, JKLC shall install SNCR system to control
NOX to less than 600 mg/Nm3
For control of SOx in the CPP area, FGD system is envisaged to control SOX less than 100
mg/Nm3. SOx emission level in the Cement Plant is within permissible limit.
JKLC is taking all necessary measures to control pollution with respect to water, air, solid
waste and also in the development in and around the factory premises
JKLC practices rain water harvesting (52 rain water harvesting units), ground water level
monitoring, green belt development inside the plant and nearby villages
17326 4.29
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
The environmental impacts that are likely to arise due to the proposed capacity enhancement
during the operations phase are summarized below:
8 Vehicular Movement Increase in vehicular traffic for other raw material and clinker
movement
9 Solid Waste Not applicable
10 Aesthetics Not applicable
11 Site of Cultural, Not applicable, no such structure in the vicinity.
Historical & Scenic
Importance
12 Socio-Economic No impact
condition
Mitigation measures including prevention and control for each environmental component have
been delineated in the sub-sections that follows.
17326 4.30
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
17326 4.31
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Concrete road is provided for the road transportation from crusher to plant site.
17326 4.32
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
The proposed enhancement in plant capacity to 6,000 tpd clinker shall cause minimal
environmental degradation, as the plant has been designed as an environmentally efficient
Cement Plant with adequate measures. Further, there is no new equipment/ construction is
envisaged and the capacity enhancement shall be based on exploiting the inherent plant
potential by process optimization/ minor upgradation means.
Adequately designed bag filters/ bag houses are installed in the Cement Plant with outlet
dust emission <30 mg/Nm3.
Since there is no pyritic sulfur reported in the raw meal, only the fuel sulfur will account for
SOx produced. Hence, the SOx, so produced shall be absorbed completely by the clinker
itself.
Plant has taken adequate primary measures to keep NOx at the minimum level. These
measures include installation of low NOX calciner, Low NOx burner. The plant is
considering use of AF for which necessary feeding system shall be installed. In addition,
JKLC shall install SNCR system to control NOx further. It is expected that SNCR shall be
commissioned by July 2018.
Proper metallic access road/ internal road exist in the plant.
17326 4.33
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Stack emissions and fugitive emissions is being controlled by use of bag filters & regular
water spray, etc.
Plant has STP of 70 KLD.
JKLC has taken necessary measures to control pollution with respect to water, air, solid
waste.
The clinker production figures for 2015-16, 2016-17 and 2017-18 are as given in the Table
below:
Year 2017-18
3 : 1.49
Design Specific heat consumption for the cement plant is < 715 kcal/ kg clinker.
The operating specific heat consumption of the plant is varying from 710-715 kcal/kg clinker with
5 stage operations which is expected to reduce further by 4-5 kcal/ kg clinker with enhancement
in capacity to 6,000 tpd clinker.
17326 4.34
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
With 4 stage operations, benefit to environment will be higher due to high waste heat based
generation of power corresponding to higher exit temperature from preheater gases which will
be used in WHR Boiler more efficiently. At 6,000 tpd clinker production with 4 stage operation,
generation of power will be even higher with higher and more efficient heat recovery process
thereby reducing GHG emission to atmosphere to a larger extent. However, the specific heat
consumption at 4 stage operation will be more and expected to be around 725-730 kcal/ kg
clinker.
At the current operating parameter of specific power consumption, there is a net reduction of
4.71 kWh/t clinker over the design specific power consumption.
The max power demand @ 4,500 tpd clinker, SPC of 58.2 kWh/t ~ 13.6 MW
The max power demand @ 6,000 tpd clinker, SPC of 53.5 kWh/t ~ 16.7 MW
The max power demand @ 6,000 tpd clinker is estimated as 16.7 MW based on current
operating SPC of 53.49 kWh/t.
Thus, an overall increase in power demand is expected as 3.1 MW, but due to waste heat
recovery based power plant in operation, grid connectivity addition will not be required.
Further process optimization (modification in raw mill cyclone to reduce pressure drop,
installation of VFD in RABH fan, etc) with respect to capex infusion is expected to generate
savings of about 0.5 kWh/t clinker.
17326 4.35
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
HOLTEC Assessment:
• The clinker production has increased over the years.
• The specific heat consumption is around 715 kcal/ kg clinker which is comparable with the
best operating plants of same vintage and technology.
• The specific power consumption has reduced over the years in all sections except for coal
grinding due to partial pet coke grinding. The design value of specific power consumption is
with coal. The specific power consumption is comparable with the best operating plants of
same vintage and technology.
• Further reduction of about 4-5 kcal/kg clinker in specific heat consumption and 0.5 kWh/t
clinker in specific power consumption is expected with process optimization/
debottlenecking at production level of 6,000 tpd.
Planned Maintenance
Routine and preventive maintenance
Scheduled overhauls involving shutdowns
Corrective maintenance
Other scheduled overhaul, repair, building
Emergency / breakdown maintenance
Adequate arrangement are provided for maintenance of bucket elevators, mills, cooler
building (clinker crusher, burner platform, refractory), cement mill drives, separators,
compressor houses, preheater building, packing plant and major drives.
HOLTEC Assessment:
Plant is practicing preventive & corrective maintenance measures and has installed
necessary arrangement to carry out the same
17326 4.36
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Each plant department quipped with audible start-up alert systems and local manual and
automatic emergency stop devices to prevent danger to people or damages to equipment.
All supporting structures, maintenance platforms, stairs for equipment are reported to have
been designed with the safe access to the equipment for the purpose of inspection and
maintenance. Platforms have been adequately dimensioned to provide lay-down areas for
spare parts and consumables.
17326 4.37
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Holtec Assessment:
Safety systems and procedures are well laid in JKLC plant with regular briefing to staff and
contractors on precautions to be taken before start of the day.
17326 4.38
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
4.18 SUMMARY
Based on the above analysis, adequacy of various equipment for production at 6,000 tpd
clinker (1.98 mio tpa) is summarised below:
Design
Required Capacity
Capacity Adequate /
Description Unit (1.98 mio tpa or
(1.5 mio tpa or Shortfall
6,000 tpd))
4500 tpd)
400 tph @ 12 % R
on 90 µ,
437tph @16%R on
Raw Mill tph OR Adequate
90 µ
460 tph@16 %R
on 90 µ
25 tph @ 3% R on
90 µ for petcoke 35 tph @3.5% R on
Coal Mill tph OR 90 µ (20% pet coke Adequate
50 tph @ 12% R on and 80% coal)
90 µ for coal
Needs
Kiln Feed tph 390 405
upgradation
17326 4.39
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
Design
Required Capacity
Capacity Adequate /
Description Unit (1.98 mio tpa or
(1.5 mio tpa or Shortfall
6,000 tpd))
4500 tpd)
proposed for
sustained
operation.
11,14,731 @2150C,
-70 mm WG at
11,25,870 @2800C, WHR stop condition
Kiln/ Raw Mill Bag -100 mm
m3/hr Adequate
House WG(pressure drop) 8,69,421 @1440C,
-50 mm WG at
WHR operation
5,58,693 @3000C,
-55 mm WG at
WHR stop condition
6,99,720 @4000C,
Cooler ESP m3/hr Adequate
-204 mm WG
4,07,597 @1200C,
-180 mm WG at
WHR operating
Adequacy with respect to Land, water, power requirement, specific heat & power consumption,
emission vis-à-vis design is summarized below:
After Proposed
Design
Sn. Parameter Unit Enhancement Remarks
(1.5 MTPA)
(1.98 MTPA)
1 Land Area Hectare 130 130 No change
17326 4.40
Technical Feasibility Report for Augmentation of Clinker
Capacity of Durg Cement Plant (DCP), Chhattisgarh
After Proposed
Design
Sn. Parameter Unit Enhancement Remarks
(1.5 MTPA)
(1.98 MTPA)
Expected saving of
~4-5 kcal/kg clinker
Specific Fuel kcal/kg
5 <715 ~710 with the proposed
Consumption clinker
optimization
measures
There shall be
slight increase in
dust emission due
to higher
production level.
JKLC to ensure
6 Particulate Matter mg/Nm3 <30 <30
particulate
emission to less
than 30 mg/Nm3 by
enhancing the bag
house volume/ ESP
field.
JKLC shall implement SNCR system to control NOx in the cement plant. SOX is within
permissible limit.
CONCLUSION:
Based on the above assessment, it can be concluded that the clinker line has the potential to
produce 6,000 tpd, which may be achieved by de-bottlenecking/ optimization of process
parameters and minor up-gradation in the equipment. The expenses for de-bottlenecking/
optimization and improvement measures envisaged to produce 6,000 tpd clinker is estimated as
Rs 1,550 Lakh.
With increase in production to 6,000 tpd, plant key performance parameters namely Specific
heat consumption is expected to reduce about 4-5 kcal/ kg clinker and Specific power
consumption is expected to reduce about 0.5 kWh/t clinker. Saving in fuel and power shall also
help in reduction of CO2 emission.
At 6,000 tpd clinker production, there shall be enhanced power generation through Waste Heat
Recovery System installed in the Cement Plant. Hence, the project activity will displace
equivalent amount of electricity generation in fossil fuel based thermal power plant, thereby
reducing GHG emission to atmosphere.
Based on assessment of clinkerisation section, total annual clinker capacity of Durg Cement
Plant of JKLC of 1.98 mio tpa clinker (6,000 tpd) is feasible with proposed de-bottlenecking/
optimization measures. JKLC, hence, may reckon the plant clinker capacity as 1.98 mio tpa.
17326 4.41
HOLTEC CONSULTING PRIVATE LIMITED
‘Holtec Centre’
A Block, Sushant Lok,
Gurgaon - 122 001, Haryana, India
Phones : +91-0124-4047900, 2392940, 2385095*
Fax : +91-0124-2385114, 2385116
(from Delhi prefix ‘95124’)
Email : info@holtecnet.com
Registered Office
01-0103 Imperial Tower, C-Block Community Centre, Naraina, New Delhi-110028
Phone : 25771002 Fax : ++91-11 25771001