Professional Documents
Culture Documents
45
Unit objectives
By the end of this unit, you will be able to:
Explain “all-in rates”;
Compute “all-in rates” for labour and plant;
Explain unit rates;
46
Estimators need a clear and coherent strategy
for building up their estimate.
Estimators should be able to read and
understand drawings and technical
documents, and clearly understand the
provisions of construction contracts.
47
Step 1
Establishment of ‘all-in rates’ includes:
A rate per hour for the employment of
labour;
Operating rate per hour (per day, per week
etc) for plant; and
The cost per unit of material delivered and
unloaded at the site.
48
Step 2
Use standards from the contractor’s data
bank or other sources.
These standards are net unit rates which are
set against the items in the bills of quantity.
Alternatively, rates received from sub-
contractors may be used.
49
Step 3
This stage involves the incorporation of rates
from specialist trade contractors, including
those offering ‘labour-only’ services into
producing either the whole or part of a rate.
50
Assumptions
1. State all basic facts on which build-up is
based. E.g.:
i. Cost of all resources
ii. Units that resources are costed in
2. what is included in these costs.
3. Output/production rates on which you have
based your calculations;
Wastage rates for different materials; and
Number of uses for formwork items.
51
If a gang of two bricklayers and one labourer
is chosen,
this gang can be used for most brickwork
items.
Rate is calculated once – and re-used when
required
52
The gang rate for 2 + 1 brickwork gang:
2 bricklayers@ GH¢6.00 GH¢12.00/hr
1 labourer @ GH¢4.50 GH¢ 4.50/hr
Total GH¢ 16.50/hr
Divided by 2 GH¢ 8.25/hr
So – for each hour that a bricklayer works, half a
labourer hour is allocated (to supply him with
materials, clear up etc).
The all-in-daily rate of any operative may be
defined as the total cost to the employer for
employing an operative’s services for “one
operative labour day’s” output.
In this case, the employer is the contractor.
54
Built up from the following:
The basic daily wage of the operator involved.
Statutory additions such as employer’s contribution
to national provident fund, workmen’s compensation
insurance, rent and leave allowances.
Trade union requirements of tools allowances for
tradesman using their own tools, uniform or
protective clothes and trade supervision.
Social expenses like canteen subsidy, sick pay, death
benefits, medical expenses and transport allowances.
Unforeseen expenses such as bad weather days,
idleness and overtime requirements for necessary
work required to keep delivery schedules.
55
A typical computation of the all-in-daily rate starts with the
calculation of the effective number of working days per year.
For a typical year, number of days per year 365
less
no. of days for weekends in a year, 2 x 52 weekends 104
National holidays in a year 13
Annual leave 18
Bad weather days 7
155
Hence effective working days/year 210
56
MULTIPLYING FACTOR (Mf)
Description Labourer Carpenter Painter Mason Steel Bender
A. Basic daily wage as consolidated to cover wage + 1.00 1.00 1.00 1.00 1.00
rent ,leave allowance, canteen subsidy transport
B. MF/month at 27 days pay 27.00 27.00 27.00 27.00 27.00
C. MF/year (B x 12) 324.00 324.00 324.00 324.00 324.00
D. MF/working day at 210 days/year = C/210 1.543 1.543 1.543 1.543 1.543
E. Statutory additions: MF 0.150 0.150 0.150 0.150 0.150
i. social security 0.125 }
57
The all-in daily rate for an item is the cost to
the employer (the contractor) of employing
the services of the item of plant for one plant
day’s output. This thus represents all the
costs which the employer pays as a result of
using the plant for one plant day’s work.
58
The main components of the all-in-daily rate
for plant are as follows:
i. The daily hiring rate (this normally includes
the operator’s wage) ;
ii. Delivery and installation (where necessary),
maintenance and removal expenses;
iii. Running expenses for fuel, oil and other
consumables;
iv. Administrative charges for co-ordination of
services relating to the plant.
59
Description Achieved Average Repair and Running and Overhead
(1) (2) economic utilization renewals 5 consumables cost % of
life years days/years of annual % of annual annual
(3) (4) depreciation depreciation depreciation
(5) (6) (7)
60
The process of building up unit rates for an
activity involves the extraction of the
resources content in terms of materials,
labour and plant for each bill item.
This is followed by a computation of the
respective costs of each of them.
61
Three distinct stages e as follows:
Stage 1
The establishment of ‘all-in rates’ for the key
items that make need to be considered. This
includes:
A rate per hour for the employment of
labour;
An operating rate per hour (or per day, per
week etc) for an item of plant; and
A cost per unit of material delivered and
unloaded at the site.
62
Use standard rates from the contractor’s data
bank or other sources.
These standards rates may be net unit rates
which are set against the items in the bills of
quantity.
Alternatively, rates received from sub-
contractors are used.
63
Incorporation of rates from specialist trade
contractors, including those offering ‘labour-
only’ services in producing either the whole
or part of a rate.
(The calculation and addition of project
overheads is a separate and subsequent
operation).
64
Unit rates for measured items in the bills of
quantity (excluding preliminaries) consist of
any or all of the following basic elements:
Labour;
Plant;
Materials;
Sub-contractors;
Overheads (site and head office); and
Profit
65
In determining the total material input in a bill of
quantities, the net material content and
associated wastes in respect of that material
should both be considered.
With regard to material waste, this may be
classified into two - These are AVOIDABLE and
UNAVOIDABLE wastes.
The classification of waste into these two
categories is based upon the causes of the waste
and the potential to minimize its occurrence.
66
Avoidable waste Unavoidable waste
Pilfering Cutting waste
Carelessness Damage in transit
Poor quality work demolished to Stock pile or residual waste
be made good Utilization waste
Wrong utilization or preparation
Mistakes in ordering, both in
quality and quantity
Improper storage
Ineffective supervision
67
Item Method used for Excavating in Gravel Soil Output
A 250HP-D8 Bulldozer in oversite excavation 150m deep 500m. sq / plant day
B 250HP-D8 in reduced level excavation 80cubic metres / plant day
C Manual excavation to reduce levels 3 cubic metres / man day
D Load and wheel excavated material 100m away 5 cubic metres / man day
E Load excavated material only- 10 cubic metres/ man day
F Filling excavated material around foundation 5 cubic metres / man day
Spread, level and compact excavated material in layers not
G 5 cubic metres / man day
exceeding150mm thick
H Spread and level hardcore in layers not exceeding 150mm thick 4 cubic metres / man day
6 cubic metres/plant day
I Compressor breaking through rock or concrete
per drill
J Compacting hardcore with mechanical compactor and operator 8 cubic metres / plant day
K Spreading and leveling only 10 cubic metres / man day
Multipliers for different excavation types
1 2 3 4 5 6
Surface not
A exceeding 1.000 - - -
B 30mm deep 0.85 0.75 0.06 0.05
C Basement 0.83 0.70 0.30 0.40
D Trenches 0.75 0.60 0.40 0.30
Pits
Multiplying
` Type of soil Bulkage factor
factor
1 2 3 4
Gravel
A Compact soil 1.00 20.00
B (laterite) 1.00 22.00
C Soft rock 0.70 35.00
D Hard rock 0.30 50.00
E Loose soil and 0.60 33.33
sand
Item Description Depth
1 2 3 4
0.6 cubic
Fixing timber pooling 0.8 cubic metres/ gang metres / gang
A boards, day day
B walling and struts 1.5 cubic metres/ gang 1.00 cubic
Stripping day metres / gang
day
Unloading and stacking 4.00 cubic metres / man day or 150 pieces
C
of timber of 50x150x360mm
Lecture 3
72
Estimating Process – 10 stages
What all-in rates are
Data / outputs etc.
All-in rate calculation – plant / labour
Worked example for labour
MULTIPLYING FACTOR (Mf)
Description Labourer Carpenter Painter Mason Steel Bender
A. Basic daily wage as consolidated to cover wage + 1.00 1.00 1.00 1.00 1.00
rent ,leave allowance,canteen subsidy transport 27.00
B. MF/month at 27 days pay 27.00 324.00 27.00 27.00 27.00
C. MF/year (B x 12) 324.00 324.00 324.00 324.00
D. MF/working day at 210 days/year = C/210 1.543 1.543 1.543 1.543 1.543
E. Statutory additions: MF 0.150 0.150 0.150 0.150 0.150
i. social security 0.125 }
74
Items need not be priced in the order they appear
in bills
A better understanding of activities can be
gained by pricing one trade at a time.
Computers also allow resources to be entered
either through a resource build-up screen for
each item or with the aid of a ‘spreadsheet’ type
comparison system where like trade items can be
viewed in a single table.
If it is known that quotations for materials will be
delayed, the estimator can price labour and plant
first, and return to part-priced items later when
quotations are available.
75
Recommended that prime cost and
provisional sums should form a separate
section at the end of the measured work part
of the document which is being priced.
Estimators must carefully check all the bill
pages, including preliminaries, to ensure that
the written-in sums are incorporated in the
final tender amount.
76
Nominated suppliers
The cost of materials from nominated
suppliers should be identified in the tender
documents as prime cost sums.
A separate item is also given for the
contractor to add his profit.
PC sums may also be written-in to an item
description (such as a rate for the supply of
facing bricks) for the estimator to incorporate
the cost in his rate build-up.
77
A nomination arises in construction contracts
where the selection of a sub-contractor is to
be made by the client or his representative.
When this happens, a prime cost sum is
inserted in the tender documents to cover the
nominated sub-contractor’s charge.
78
Items to be included in the bills of quantity for each
nominated sub-contractor are as follows:
The nature and construction of the work;
A statement of how and where the work is to be
fixed;
Quantities which indicate the scope of the work;
Any employers’ limitations affecting the method of
the works;
A prime cost sum;
General attendance item;
An item for main contractor’s profit, to be shown as a
percentage; and
Details of special attendance required by the sub-
contractor.
79
Defined as, ‘the labour, plant, materials or
other facilities provided by the main
contractor for the benefit of the sub-
contractor and for which the sub-contractor
normally bears no cost’.
Built into main contractor’s tender and
consequently become a charge against the
client.
In assessing sums to be allowed for general
attendance, the estimator must investigate
the facilities which will already be provided
for the main contractor’s use and determine
any cost which may arise by the nominated
sub-contractor’s use of any such facilities. 80
use of temporary roads, pavings and paths;
use of standing scaffolding;
use of standing power operated hoisting
plant;
use of mess rooms, sanitary accommodation
and welfare facilities;
providing temporary lighting and water
supplies;
providing space for sub-contractor’s own
office accommodation and storage of plant
and materials;
clearing away rubbish. 81
Other specific attendances which do not fall
under the category of ‘general attendance’
must be specially measured in the bill of
quantity as ‘special attendance’. Items to be
measured include:
82
special scaffold to be added to contractor’s standing
scaffolding;
the provision of temporary access roads and
hardstandings in connection with structural
steelwork, pre-cast concrete components, piling ,
heavy items of plant and the like;
unloading, distributing, hoisting and placing in
position of items required as part of “special
attendance”, giving in the case of significant items
the weight, location and size;
the provision of covered storage and accommodation
including power supply to these;
power supply giving the maximum load; and
any other attendance not including ‘general
attendance’ or listed above.
83
Sum provided for work or for costs which cannot
be entirely foreseen, defined or detailed at the
time the tendering documents are issued.
Included in BOQ for items of work which cannot
be fully described or measured in accordance
with the rules of the method of measurement at
time of tender.
Three types of provisional sum under the rules of
SMM7:
i. Provisional sums for defined works;
ii. Provisional sums for undefined works; and
iii. Provisional sums for works by statutory
authorities 84
With the exception of provisional
services provided by statutory
authorities, provisional sums are
deemed to include an allowance for
main contractor’s head office
overhead or profit.
Provisional sums should allow for
overheads and profit
85
Normally occur where variations cannot be
valued by measuring using the rates or
comparable rates, nor by negotiation before
an instruction is issued.
Dayworks charges are usually calculated
using the definitions for prime cost and
overheads.
Total Dayworks charges include the
following costs: Labour; materials and
goods; plant; incidental costs, overheads
and profit
86
The Code of Estimating Practice defines
overheads as ‘the cost of administering a
project and providing general plant, site
staff, facilities, site-based services and other
items not included in all-in rates’.
The contractor’s opportunity to price for
these items is in the preliminaries section of
the bill, the section containing the basic
background and contractual conditions of the
contract.
87
Fixed Charge: as the cost of work which is to
be considered as independent of duration
Time Related Charge as the cost of work
which is to be considered as dependant on
duration.
Items in bills of quantity for Employer’s
requirements and Contractor’s general
overheads cost items are given for both
categories.
88
A schedule which shows all the associated
project overhead items, the durations for
which they will be required and estimates of
how much they will cost
NB:
Contractors and firms, carrying out small
repetitive works, may apply a fixed
percentage for overheads (about 10 – 15%)
instead of using a schedule.
89
Direct overheads –
Those which relate to a particular project
including management and supervisors, site
accommodation, temporary services and plant.
They can be calculated on a weekly or monthly
basis and converted to a total cost for the whole
project by relating these costs to the project
duration.
The total cost is either included as a lump sum or
a percentage addition to the unit rates.
It is also usual to include a figure for profit and
attendance on sub-contractors in the
preliminaries.
90
Indirect overheads –
General costs relating to the contractor’s
business such as office rent, rates of pay for
general staff such as secretaries, pay-roll
staff, senior management and professional
support staff (who will have to be paid
regardless of the amount of work that the
contractor is winning) and the company’s
finance costs.
Usually calculated for forthcoming years on
the basis of previous years’ costs, with every
project contributing towards them.
91
Extending bills of quantity
The extension of the bill rates to
totals, collections and summaries
must be carried out in a manner that
eliminates clerical errors and also
allows the establishment of various
sub-totals relating to elements of the
work or trades as necessary.
92
The estimator must prepare summaries of the
resources which make up an estimate so that
management can assess the source of labour,
plant, materials, services, possible discounts
available and price level as well as undertake
price comparisons among suppliers.
The final summary brings together all the
parts of an estimate, with costs apportioned
between labour, plant, materials, sub-
contractors, site overheads, PC and
provisional sums.
93
In times of relatively low and predictable
inflation, contractors are expected to submit
tender prices which remain fixed for the
anticipated duration of the work.
The method of calculation of fluctuations in
costs is set out in the appendix to the
conditions of contract.
Fluctuations in cost can be ‘full’, ‘limited’ or
none at all.
Fluctuations in cost may give rise to both
increases and decreases in the final cost
94
These are costs normally associated with
overheads, which will be calculated as a
proportion of the total value of work.
Some bills of quantity provide items for these
costs on the final summary page. They are:
Contractor’s insurances;
Performance bond;
Water for the works; and
Professional fees for design.
95
The final review of an estimate and its conversion
to a tender is the responsibility of management.
This is a separate commercial function based
upon the cost estimate and it’s supporting
reports and documents.
The need for a formal approach to finalising
tenders should be regarded as fundamental to
competent tendering.
An evaluation of alternatives, scope to improve
profitability and risks which may be encountered
will be considered at each stage of the estimating
process and converted into costs at the final
review meeting.
96
The desire to win the contract
The amount of contract finance required;
The contractor’s knowledge of the client and
consultants;
The local market conditions; an evaluation of
their previous biding performance;
Intelligence information on the client’s
budget and target; and
Risk (technical and contractual).
97
The effects of any changes to rates etc on bill
should be noted
For example, a change to the basic labour
rate will affect all bill items concerning
labour.
This will affect all net rates that have been
compiled by the estimator.
With computer-aided estimating system, such
changes can be easily accommodated at the
end of the tender period
98
The estimator must ensure that the procedure set
out in the tender documents for the submission
of the tender is followed meticulously.
The form of tender and any other declarations
must be completed as required and signed by an
authorised person from the contractor’s
organisation.
A letter should be attached to the forms to list
the documents, and confirm the amendments
received during the tender period.
Any other remarks about the technical content or
price may be reviewed as a qualification to a
tender and so should be avoided.
The role of the estimating department at this
stage include:
Responding to further requests by client
team,
Attending tender opening
Adjustment of errors
Negotiation and award –if no tender meets
client’s budget
Evaluating the tender efficiency.
Advise management on future bidding
strategy
When a tender has been successful, the
documents must be checked thoroughly to
ensure they reflect the exact content of the
documents used to prepare the tender.
Contract documents should be checked to
establish that:
❖ the drawings are those which were circulated
with the tender documents
❖ the dates, penalties and particulars given in the
appendix to the condition of contract are those
stated in the tender document; and
❖ the submission bills have been copied correctly.
When the result of a tender is known, the
tender performance form should be
completed where possible with a comparison
made between the estimator’s organisation
and the one with the lowest (or the accepted)
tender.
Tender results can be reported at regular
management meetings so that all those who
contributed to the estimate can assess their
performance.
Suppliers and sub-contractors who submitted
quotations should be notified of the results
as promptly as possible.
Estimators must monitor their performance with
an analysis of results recorded over a period of
consistent estimating.
If data are available from a large number of
tenders, it is possible to evaluate tender
performance in relation to; types of work (new
build or refurbishment), clients (public, private),
procurement routes (traditional, design and
construct, trade packages), and estimating
resources for further tendering.
Large contractors should analyse performance
over time to ensure they win a proportionate
number of contracts in comparison to
submissions (at least 1 in 6).
The contractor will keep track of submitted
tenders, number of tendering contractors, lowest
tenders submitted, their estimated cost of the
project, their tender sum and the maximum
profit potential for the winning contractor.
From this information, they can calculate the
approximate % profit used by their competitors
and adjust theirs in the future to be more
competitive.
Example
Building Procurement Inc. has tendered for 6
projects in June. Table 3.1 shows the break down
of the tenders of in comparison with competitors.
Table 3.1
Project No. Tenders Rank %Over lowest bid % Over mean bid
1 3 1 0 -2.3
2 6 5 11.0 4.9
3 6 1 0 -3.1
4 5 2 5.0 -3.8
5 7 1 0 -7.7
6 14 5 15.0 1.0