Enable-On- Both Breakers from EDGs for particular Unit should be in open position or Test Position.
Auto Shutdown- GT Flame "off".
CRIT CMD
1
SLC-2 GT Enclosure Ventilation – ON
SLC Hot Water Station – ON
0 SLC Deload – OFF W=0 Sec.
1 SLC Demin Water Pump 1/2 – ON M=5 Sec.
1 SLC CT Raw Water Pump – ON
1 SLC CT Service Water Pump - ON
1 SLC-2 GT Enclosure Ventilation – ON
0 SLC Hot Water Station – ON
2
1 Demin Water Supply is in Operation
1 Service Water Supply is in Operation
1 Raw Water Supply is in Operation No Command
W=0 Sec.
M=1800 Sec.
3
1 SGC CCW- " is in Start Up Step SGC CCW -Auto Operation Command
W=0 Sec.
M=5 Sec.
1 CW System is in operation
1 Condenser Status is in Operation 6 No Command
W=0 Sec.
M=1800 Sec.
7
W=0 Sec.
M=5 Sec.
8
W=0 Sec.
M=0 Sec.
9
W=0 Sec.
M=5 Sec.
10
W=0 Sec.
M=0 Sec.
0/1
A). Aux Steam Supply is in operation 14 No Command
B). Start up Without Aux. Steam. W=0 Sec.
M=2400 Sec.
14 No Command
W=0 Sec.
M=2400 Sec.
Case-2:-
HRSG Status in operation (GT NG ESV close-command not persisting and GT Speed is > 3 Hz.)
& LP Drum Pressure > 2.5 Bar and LP Main Steam Flow > 5.0 Kg/Sec.
Case-3:-
HRSG Status in operation (GT NG ESV close-command not persisting and GT Speed is > 3 Hz.)
& LP Drum Pressure > 2.5 Bar and LP FW Flow > 6.2 Kg/Sec since last 1 miniute.
15
W=0 Sec.
M=5 Sec.
16
W=0 Sec.
M=0 Sec.
17
W=0 Sec.
M=5 Sec.
18
W=0 Sec.
M=0 Sec.
19
W=0 Sec.
M=5 Sec.
20
W=0 Sec.
M=0 Sec.
0/1
SGC Bypass Deaerator- is in Start Up Step 27
Start up Without Aux. Steam- Selected W=0 Sec.
M=5 Sec.
Start up Without Aux. Steam- Selected
0/1
B/P Deaerator Status is in operation.
CPH Cold By D/S Temp. > 132 C. & Main Cond. To D/A DT
28 No Command
W=0 Sec.
> 4K.
M=3600 Sec.
There is only one difference between a and b that LP Bypass Pressure Control in Auto mode.
31
W=0 Sec.
M=5 Sec.
32
W=0 Sec.
M=0 Sec.
There is only one difference between a and b that IP Bypass Pressure Control in Auto mode. Pressure controller will be switched on by SGC ST when cond. Pr. <0.3 bar.
41
W=0 Sec.
M=5 Sec.
Branch
Unit S/up Preselection -RF GT OP.
Unit S/up Preselection -CC OP. 42 No Command
W=1800 Sec.
M=1805 Sec.
42 No Command
W=1800 Sec.
M=1805 Sec.
If Waiting time is expired and still HRSG Fill is selected than it will jump to last step.
SEL Start up Without Aux. Steam. Out put command allows SGC ST Aux. to start
1 SGC GT Ready For SR. Evacuation System. In step-3
1 Unit Start up preselection CC OP.
0 Condenser Pr. <0.5 Bar. 48
1 Condenser Level < 1050 mm. W=0 Sec.
Seal Steam is not tripped or Startup Without Aux. Steam is M=5 Sec.
1 selected.
0 All the above or Generator On Load.
49
W=0 Sec.
M=5 Sec.
53
W=0 Sec.
M=5 Sec.
Means Seal Steam Temp is >275 (In general) for 5 minute and Seal Steam Control valve has not closed since last 5 minutes.
SEL S/Up Without Aux. Steam -OFF Command. This output command will switch "off" the SLC Start up
55 without Aux. Steam.
58 Last Step
W=0 Sec.
M=0 Sec.
1
2
3
4
5
6
7
8
9
10
11
12
Raw Water System is in operation or it is blocked by suitable means to avoid furious start.
Demin Water Distribtion System is in operation.
Service Water System is in operation or it is blocked by suitable means to avoid furious start.
CCW System is in operation.
CW Condenser is in operation.
CW Pump System is in operation.
Service Cooling Water System is in operation
If non of the Unit is in operation Aux. Steam Common header is drained and MOV are operating ok.
If any other Unit is in operation line up Aux. Steam to the Unit which is to be started.
Lube. Oil System is in operation.
Stack Demper is open.
Take trail of Hot Water Station each boiler for five minutes.
Unit Cordinator- Shutdwon Program
CRIT CMD
Normaly Continuation Criterion Step Command Output
SLC HRSG Drain Pumps-"On" Command
61 SLC Clean Drain Pumps-"On" Command
1 SLC HRSG Drain Pumps-"On" Feedback W=0 Sec.
1 SLC Clean Drain Pumps-"On" Feedback M=5 Sec.
65
W=0 Sec.
M=5 Sec.
66
W=0 Sec.
M=0 Sec.
69
W=0 Sec.
M=5 Sec.
70
W=0 Sec.
M=0 Sec.
73
W=0 Sec.
M=5 Sec.
74
W=0 Sec.
M=0 Sec.
77
W=0 Sec.
M=5 Sec.
Preselect Unit S/D-Unit "Off" Selected than it will continue for further shutdown program.
Preselect Unit S/D-Unit "Restart" Selected than it will jump to last step of shutdown.
91
W=0 Sec.
M=5 Sec.
92
W=0 Sec.
M=0 Sec.
95
W=0 Sec.
95
W=0 Sec.
M=5 Sec.
98
W=0 Sec.
M=5 Sec.
Sr. No. GT RFO Condition
1 No DP Fault in Compressor
2 Turbine speed < IGN speed
3 No fault in BFE/BMA/BUC/BUD/BUB present
4 SFC should not blocked
5 Excitation should not blocked
6 Turbine oil Temp > 25
7 No Acc inspection Bit present
8 No GT Fail safe function Reset Required
9 No Trip in BAT present
10 No Trip in BBT present
11 NG press d/strm of Pilot CV<Max
12 No Generator Trip present
13 Gen Start At low speed no rls should not be present.
14 Level of liquid switch at EE< Max
15 Level of liquid switch at TE< Max
16 Press H2 Gen > 4.7
17 IPD vent Fan in Operation
18 Purity H2 Analyzer 1 > 95.5
19 Purity H2 Analyzer 2 > 95.5
20 No fault in Seal oil supply should be present
21 No Speed measurment Dead should be present
22 No load measurment DBL fault should be present
23 No pressure Comp Outlet DBL fault should be present
24 No fault in IGV position measurment
25 No Acc monitoring Trip fault should be present.
26 No prem CV Not Closed fault should be present
27 No pilot CV Not Closed fault should be present
28 GT Control Simulation Should be OFF
29 No pilot gas position control Not Closed fault should be present
30 No Gas pressure (NG MBP) DBL fault should be present
31 No position Measurement NG Prem CV DBL fault should be present
32 No position Measurement NG PG CV DBL fault should be present
33 No DP measurement PM CV DBL fault should be present
34 No DP measurement PG CV DBL fault should be present
35 All NG valves (MBP) closed
36 GT Enclosure Ventilation In OP
37 Cooling Turning Start Release
38 Release from HRSG
39 Release from Unit Control
40 HCO State Monitoring SR Rel
41 Temp Ambient Air > -35 Deg C
42 Rotor Temp > Min
HP Bypass aut.
clutch disturbance
interval turning gear