Operation Dept.

PSE SHIFT HANDOVER LOGBOOK

Doc No. KLIC-OPE-LGB02-01


Date: 17-Jan-24 Record time 08:00-16:00
Shift: 3 Name: Mr Thonglone SIYALATH

XPXN-PSE Status MW MVar XPXN-PSE Status MW MVar


Line 1 Energize De-Energize -78.25 31.45 Line 2 Energize De-Energize -78.54 31.45

PSE-UB3 Status MW MVar PSE-UB3 Status MW MVar


Line 1 Energize De-Energize 81.45 -31.54 Line 2 Energize De-Energize 81.42 -31.24

SHUNT REACTOR 1 Energize De-Energize 0.00 SHUNT REACTOR 2 Energize De-Energize 0.00

CB 80212A DS 80215A CB 80232A DS 80235A

Close Open Close Open Close Open Close Open

CB 80112 CB 80122 CB 80132 CB 80312


Close Open Close Open Close Open Close Open
CB 80212 CB 80222 CB 80232 FUSE 601
Close Open Close Open Close Open Close Open

Service Voltage (kV) Current (A)


KW1A TR 21.25 0.9 12.27

Record Time Note


I. Transmission Line Status
08:00-16:00 Transmission line 230KV No.1 during Pakse substation to Xepian switchyard
08:00-16:00 Transmission line 230KV No.2 during Pakse substation to Xepian switchyard
Normal Conditions
08:00-16:00 Transmission line 230KV No.1 during Pakse substation to Ubon3 Substation
08:00-16:00 Transmission line 230KV No.2 during Pakse substation to Ubon3 Substation
II. Daily Activities
8:00 Receiving and Sending information to power house (call)
10:00 DCMS, Equipment Room inspection
13:00 DCMS, Equipment Room and Switch Yard inspecction
14:00 230kV Main Bus 1 230kV Main Bus 2
𝑈𝑎𝑏 = 240.0 kV 𝑈𝑎𝑏 = 239.0 kV
𝑈𝑏𝑐 = 239.0 kV 𝑈𝑏𝑐 = 240.0 kV
𝑈𝑐𝑎 = 238.0 kV 𝑈𝑐𝑎 = 238.0 kV
F = 50.0 Hz F = 50.0 Hz
III. Switching Order Activities
None

IV. Fault and Alarm Event Log

1. Analog Input 4-20 mA shows incorrectly data such as 230 kV TLS and High of Service Transformer // (Active power and Reactive power )
2. SICAM SCC event list of UPS inverter pannel No.2 is not showing data //02.12.2022
3. Air conditioner of control room does not work

V. Special Activities
None

VI. Work Permit Activivties


None
VII. Issue Trouble Memo
No Issue
15:55 VIII. Handover Activities
1. Observation Scada, Protection systems, Voltage Transmission line 1&2
2. Follow to record daily record and check list

Management Notification
Incomming Shift Signature: ……………………………… Out Going Shift Signature: ………………………………….
(Vanxai) (Thonglone)
Pakse Sub Operation Supervisor Signature: …………………………………………..
(Vongkham)