This document summarizes the power system energization log from 8:00 to 16:00 on January 8th. It records the energization of two transmission lines, PSE-XPXN Line 1 and Line 2, providing their status, voltage and power readings. It also lists the switching operations taken at the Pakse and XPXN substations to energize the lines, including opening and closing various circuit breakers and disconnect switches. Several equipment checks were performed during the shift and no issues were found.
This document summarizes the power system energization log from 8:00 to 16:00 on January 8th. It records the energization of two transmission lines, PSE-XPXN Line 1 and Line 2, providing their status, voltage and power readings. It also lists the switching operations taken at the Pakse and XPXN substations to energize the lines, including opening and closing various circuit breakers and disconnect switches. Several equipment checks were performed during the shift and no issues were found.
This document summarizes the power system energization log from 8:00 to 16:00 on January 8th. It records the energization of two transmission lines, PSE-XPXN Line 1 and Line 2, providing their status, voltage and power readings. It also lists the switching operations taken at the Pakse and XPXN substations to energize the lines, including opening and closing various circuit breakers and disconnect switches. Several equipment checks were performed during the shift and no issues were found.
Date: 08-Jan-20 Record time 08:00 - 16:00 Shift: 1 Name: Mr. Sengsouvanh PSE-XPXN Status MW MVar PSE-XPXN Status MW MVar Line 1 Energize De-Energize -83.3 33.19 Line 2 Energize De-Energize -82.24 32.52
PSE-UB3 Status MW MVar PSE-UB3 Status MW MVar
Line 1 Energize De-Energize 82.4 -32.29 Line 2 Energize De-Energize 82.22 -34.7 MWh MVarh MWh MVarh Main Main Metering PSE-XPXN 0 3308.27 PSE-UB3 7503.97 0 Line1 Line 1 MWh MVarh Line 1 kWh MVarh Backup Backup 0 3308.72 7501.18 0 MWh MVarh MWh MVarh Main Main Metering PSE-XPXN 34.09 5448.75 PSE-UB3 11104.97 0 Line2 Line 2 MWh MVarh Line 2 MWh MVarh Backup Backup 33.96 5450.76 11104.38 0 CB 80112 CB 80122 CB 80132 CB 80312 Close Open Close Open Close Open Close Open CB 80212 CB 80222 CB 80232 FUSE 603 Close Open Close Open Close Open Close Open
Service Voltage (kV) Current (A)
KW1A TR 21.65 0.6 Event log Record Time: Note: 08:29-16:00 Pakse Substation Energization Line No.1 08:00-16:00 Pakse Substation Energization Line No.2 08:00 Receiving and Sending information to power house (call) 08:16-08:17 Pakse Substation: Open Loop Transmission Line XPXN-PSE Line 1 and Prepare for Energization Transmission Line XPXN-PSE Line 1 (Switching Command by XPXN) Turn OFF Auto. Re-Closer UB3-PSE Line 1, Open CB 80122, CB 80112, Close DS 80111 08:18-08:21 XPXN Switchyard: Energize Transmission Line XPXN-PSE Line 1 and Charge Line to PAKSE Substation (Switching Command by XPXN) Close DS 8014, DS 8016, CB 8012 08:22 Pakse Substation: Loop Transmission Line XPXN-PSE Line 1 With Bus 1 ( Switching Command by XPXN) Close CB 80112 Check: - UB3-PSE Line 1 Voltage = 0 kV - UB3-PSE Line 2 Voltage = 236.4 kV - XPXN-PSE Line 1 Voltage = 236.3 kV - XPXN-PSE Line 2 Voltage = 236.2 kV 08:24-08:25 Pakse Substation: Open Loop Bay 1with Transmission Line UB3-PSE Line 1 ( Switching Command by EGAT NCC) Open CB 80132, Close DS 80121 08:25-08:30 UBON 3 Substation: Switching for Energization Transmission Line UB3-PSE Line 1 ( Switching Command by EGAT NCC) Close CB 80512, Turn ON Auto. Re-Closer Switch of UB3-PSE Line 1 08:28-08:29 Pakse Substation: Loop Bay 1 with Transmission Line XPXN-PSE Line 1 and UB3-PSE Line 1 ( Switching Command by EGAT NCC) Close CB 80132, CB 80122, Turn ON Auto. Re-Closer Switch of UB3-PSE Line 1 10:00 DCMS, Equipment Room Check (No problem) 13:00 DCMS, Equipment Room Check (No problem) 15:00 DCMS, Equipment Room Check (No problem)