Operation Dept.

PSE SHIFT HANDOVER LOGBOOK


Doc No. KLIC-OPE-LGB02-01
Date: 01-Nov-20 Record time 00:00-8:00
Shift: 3 Name: Mr vanxai Sylaphet
XPXN-PSE Status MW MVar XPXN-PSE Status MW MVar
Line 1 Energize De-Energize -29.43 34.56 Line 2 Energize De-Energize -29.65 34.09

PSE-UB3 Status MW MVar PSE-UB3 Status MW MVar


Line 1 Energize De-Energize 29.59 -34.21 Line 2 Energize De-Energize 29.61 -34.80
CB 80112 CB 80122 CB 80132 CB 80312
Close Open Close Open Close Open Close Open
CB 80212 CB 80222 CB 80232 FUSE 603
Close Open Close Open Close Open Close Open

Service Voltage (kV) Current (A)


KW1A TR 21.85 0.8

Record Time Note


I. Transmission Line Status
00:00-8:00 Pakse Substation Energization Line1 XPXN-PSE
00:00-8:00 Pakse Substation Energization Line2 XPXN-PSE
00:00-8:00 Pakse Substation Energization Line 1 PSE-UB3
00:00-8:00 Pakse Substation Energization Line 2 PSE-UB3
II. Daily Activities
0:30 Receiving and Sending information to power house (call)
6:00 DCMS, Equipment Room Check (No problem)
6:30 DCMS, Equipment Room and Switch Yard Check (No problem)
7:45 230kV Main Bus 1 230kV Main Bus 2
𝑈𝑎𝑏 = 245.6 kV 𝑈𝑎𝑏 = 245.5 kV
𝑈𝑏𝑐 = 346.6 kV 𝑈𝑏𝑐 = 246.7 kV
𝑈𝑐𝑎 = 244.4 kV 𝑈𝑐𝑎 = 244.4 kV
F = 50.00 Hz F = 50.00 Hz
III. Switching Order Activities
No have
IV. Fault and Alarm Event Log
No have
V. Special Activities
No have
VI. Work Permit Activivties
No have
VII. Issue Trouble Memo
No have
VIII. Handover Activities
Observe Transmission line No. 1&2

Management Notification

Incomming Shift Signature: ……………………………… Out Going Shift Signature: ………………………………….

Pakse Sub Operation Supervisor Signature: ………………………………