Professional Documents
Culture Documents
Ed 1/Rev.1
ASPHALT MIXTURE
Preparing, transporting and Page 1 of 10
spreading of asphalt mixture
1 0 1
2 0 2
3 0 3
4 0 4
5 0 5
6 0 6
m1
m2
0
m3
m4
m1
m2
1
m3
m4
Code F-SP - 03
METHOD STATEMENT MS-M-22
Ed 1/Rev.1
ASPHALT MIXTURE
Preparing, transporting and Page 2 of 10
spreading of asphalt mixture
Summary
1. Scope
2. Reference
3. Materials and equipment
4. General information
5. Production proces
5.1. Check the cleanliness for asphalt mixing plant.
5.2. Preparation of asphalt mixture in asphalt mixing plant.
5.3. Tolerances of dosage.
6. Transport
7. Trafic
8. Site preparation
9. Laying and supplying
10. Application of prime coat and tack coat
11. Installation of the finisher and work procedure.
12. Compaction.
13. Compaction technology
14. Joints, Shaping and Edge Cleaning
15. Tolerances on finished work
16. Acceptance of executed layer
17. Weather conditions
18. Responsibilities
19. Resources
20. Reports and records
Code F-SP - 03
METHOD STATEMENT MS-M-22
Ed 1/Rev.1
ASPHALT MIXTURE
Preparing, transporting and Page 3 of 10
spreading of asphalt mixture
1. Scope
This method statement defines the work procedure for preparing, transporting and spreading of asphalt
mixture (binder course and wearing course )
2. Reference
SM STB 1033-2008
GOST 8267-93 - Aggregates Technical requirements,
SNIP 3.06.03-85 - Highways. Construction norms and rules
SM GOST 22245 – 90 Viscous Road Petroleum Bitumen. Specifications
SM GOST 8736 – 93 Sand for construction. Technical Conditions.
SM GOST 16557- 78 Filler for asphaltic-concrete mixtures. Technical requirements
Technical specification – chapter 305 Asphalt concrete for pavements
Traffic management plan
ASPHALT MIXTURE
Preparing, transporting and Page 4 of 10
spreading of asphalt mixture
4. General information
All aggregates, crushed stones 4/8, 8/16, 16/31, crushed sand 0/4, bitumen BND 60/90, filler material,
prime coat/tack coat -bituminous emulsion type EBK1, fiber, are delivered from approved sources only
and inspected by Engineer. A stockpile is done at the asphalt mix plant yard in Cîșlița-Prut necessary to
cover production for at least one day or planned production amount. The stockpiles will be inspected by
Engineer and approved through the system of “MAR”.
Type of asphalt mixture which we will make in our asphalt plant will be in accordance with the
Technical Specification and the project, like :
- Binder SKVPG -I
- Binder SKBG II 2,3
- Wearing course ȘMCC-I 2,2
Trials sections. The contractor will carry out trials sections on a minimum 200m length to determine for
JMF (job mix formula) the optimum method of use and sequence of operation for laying and number of
passes for rollers and check the adequacy of the equipment used. The works will be in compliance with
Technical Specifications chapter 305.
5. PRODUCTION PROCESS
5.1. Check the cleanliness for asphalt mixing plant.
The plant will be inspected each day before commencement of production. The inspection consist of:
- Checking the cold bins for aggregate
- Checking the operation of each electrical engine
- Checking the operation of each electrical pump for water or hydro oil.
- Checking of the software of the computer
All aggregates for execution of asphalt mixture comply to the norms and standards (see requirements
and methods in and TS 305)
ASPHALT MIXTURE
Preparing, transporting and Page 5 of 10
spreading of asphalt mixture
damage or contaminate the aggregates either by overheating or by the deposition of soot, oil or other
residues.
Test and calibrate asphalt mix plant. All aggregates proportions shall be according to JMF of binder
course layer and wearing course layer. Fill cold bins with aggregates, crushed stones 4/8, 8/16, 16/31,
sand 0-4 mm, and transport them for drying and hot screening. The material in the pug mill is added in
the following way: first is added course aggregate then fine and filer and the last is bitumen. The mixer
creates a thorough coating of all ingredients. The mixing time is between 40 – 45 seconds. As soon as
mixing is ready, the material is discharged in the moving bucket. It transport the material over the
trucks, where the gate is open and material flow down in the box. The final product meets the
requirements of JMF (305.13 Supplying and Laying).
The bitumen will be uniformly heated to permit a continuous introduction of bitumen from the storage
tank into the mixer. The temperature of bitumen will be less than 175°C. Bitumen heating shall be
indirect, that means using oil-filled heating coils or other approved systems.
6. Transport
Mixed asphalt material will be transported from the mixing plant to the laying site in tipping trucks
specially reserved and designated for this purpose.
Trucks shall be metal bodies, insulated and equipped with insulated tarpaulin covers.
Covers shall be deployed at all times when the truck is being used for the transport of
asphalt.
Temperature of asphalt leaving the plant shall be 140-160 ° C.
7. Traffic.
The works will be made in base of the approved Traffic management plan. All arrangements to divert
traffic to only one side of the road, work area will be free of any unauthorized vehicles (use fences,
barricades, signs, traffic light or personnel). Where a diversion road exists work is performed on full
width.
8. Site preparation.
All the surfaces, on which the asphalt is to be laid down, have to be cleaned by mechanical brush and
blow up by compressed air ( TS 305.06 The preparation of the Supporting Surface).
ASPHALT MIXTURE
Preparing, transporting and Page 6 of 10
spreading of asphalt mixture
The supplying and laying of the asphalt mixture will be done according to SNiP 3.06.03-85.
The materials will be spread, leveled and tamped by an approved self-propelled paving
machine. The asphalt mixture will be supplied continuously to the paver and laid without
delay. The rate of delivery of material to the paver will be regulated to enable the
paver to operate continuously.
The speed of the paver and the maner of working its method of operation shall be adjusted to ensure an
uniform flow of material across the full laying width, avoiding dragging or tearing and without
segregation of material.
In confined areas where irregularities or unavoidable obstacles make the use of
mechanical laying impracticable, the mixture may be spread by hand. Hand spreading
shall be done by staff experienced in the work and the standard of finish of the
completed hand spread asphalt shall not be noticeably inferior to the machine laid areas.
The asphalt will be laid in courses of less than 40 mm thickness unless specifically called for in the
design. Asphalt wearing course shall not be laid in thicknesses greater than 60 mm and asphalt binder
course shall not be laid in thicknesses of more than 80 mm without first obtaining the specific approval
of the Engineer.
When required by the construction drawings, geocomposite,, type 1, must be placed between binder and
wearing cours, The width of geocomposite is about 50 cm and must be placed half over the existing
road and half on the widening.
ASPHALT MIXTURE
Preparing, transporting and Page 7 of 10
spreading of asphalt mixture
The unloading of the trucks and speed of the finisher will be so adjusted to avoid the stoppage of the
finisher.
Only in exceptional cases, the manual laying is permitted (narrow spaces). In this case, the unloading of
mixture is to be done in successive piles. The mixture will be transported with frontal loader, and spread
with shovel (not by throwing). Levelling will be made with rake and the transverse profile achievement
is realised with pattern, which will be moved in the road length supported by the height moulds
adequate height, for verification before compaction. The thickness of layer has to be 20 - 25 % higher
than the requested compacted thickness.
12. Compaction.
Laying and compaction is performed according to the requirements of TS Chapter 305 and SNIP
3.06.03-85. Basically, compaction will start immediately after the spreading;
The temperatures of asphalt mixture have to fulfill the following table requirements:
Bitumen The mixture temperature (C) Temperature during compaction (C)
The compaction is very important because this operation influences directly the layer durability. When
the compaction is performed at 130 - 140°C, good compaction results are obtained. The compaction is
indispensable in the laying mixture to obtain the optimum physical - mechanical characteristics values
and of deformability (apparent specific weight, voids percentage, compression strength, high
temperature stabilizing, deformation and elasticity modulus) and a good road surface, assuring the
quality and durability for the road system.
Basically the compaction has to be performed in straight, longitudinal passes, the changing of rollers
direction must be done on compacted mixture where the roller leaves no traces. Rolling should be
accomplished by diagonal rolls <15 ° from axial direction. The compaction begins with the longitudinal
joint area (on adjacent strips) and then from the edge to the axis and in the climbing sense of the
longitudinal slope. In all cases, the compaction have to be fast executed to obtain the required
compaction in the shortest time.. The temperature of the asphalt mixture will be frequently checked to
obtain a good leveling and compaction.
Compaction of wearing course will commence immediately and will be performed by using exclusively
non-vibrating steel drum rollers to meet density requirements as specified. Pneumatic tyred rollers shall
not be used for wearing course.
ASPHALT MIXTURE
Preparing, transporting and Page 8 of 10
spreading of asphalt mixture
On the sections with cross fall, laying begins with the lowest lane (from the edge or shoulder) and then
the following lane till the axis. The roller will execute long passes. First pass will be done with low
speed 2 – 4 Km/h and following passing with higher speed 4 – 6 Km/h.
Direction changes will be progressive effectuated without shocks, to avoid the waving. Stopping in the
road lengths will be staggered between them.
Eventual unevenness, which appears in front of the roller on the asphalt surface, will be corrected
moving transversely with a small roller.
In some cases, it is necessary to start rolling with a rubber roller. The tires of the rollers should be
covered with a thin layer of organic oil to prevent sticking of the mixture.
After first compaction the second compaction will be done by steel vibrating rollers. It will eliminate
longitudinal marks of the rubber roller tires. At low temperature, under 20° C and windy conditions, the
tires will be covered by tarpaulin
When the steel roller should go first, the wheels will be wet with water. Finally if the final rolling will
be done with rubber roller, on the beginning when tires are warm, it will be wet with water.
The number of passes of the roller will be determined by trail sectors, for each type of asphalt mixture.
The criteria for compaction are given in TS 305.14.
Code F-SP - 03
METHOD STATEMENT MS-M-22
Ed 1/Rev.1
ASPHALT MIXTURE
Preparing, transporting and Page 9 of 10
spreading of asphalt mixture
18. Responsibilities
The Site Manager is responsible for exact application of the execution documentation (Drawings),
Technical Specifications, Standards and this execution procedure.
The Quality Manager is responsible for exact application of the Drawings, Technical Specifications
provisions, rule and regulations in force, application of this technical execution procedures not correct
preparation of quality records.
The Chief of the working place coordinates the works and provides humans resources, materials
necessary for works execution.
The person in charge for labor protection are responsible for training on compliance with labor
protection regulations and PSI.
The Traffic Manager is responsible of the planning and the execution temporary signs and roads and
the management of traffic problems.
The Head of the laboratory is responsible for performing the examinations and tests required by
specifications before and during the work execution and prepare proper records.
The Head of surveyor is responsible for the setting out and the execution of the survey.
19. Resources
ASPHALT MIXTURE
Preparing, transporting and Page 10 of
spreading of asphalt mixture 10
Code F-SP - 03