Professional Documents
Culture Documents
004/RUI.GSC.RSS/11/
DOCUMENT NO. REV. A
2021
Page 1 of 35
DOCUMENT TITLE:
QA /QC PLAN
ORIGINATOR PROJECT
REV DATE PURPOSE CHECKER CONTRACTOR COMPANY DATE
MANAGER
004/RUI.GSC.RSS/1
DOCUMENT NO. REV. A
1/2021
Page 2 of 35
RECORD OF REVISIONS
THE REVISIONS LISTED BELOW HAVE BEEN INCORPORATED IN THIS COPY OF THE DOCUMENT
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 3 of 35
Contents
RECORD OF REVISION
Content
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 4 of 35
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 5 of 35
1.0 INTRODUCTION
Medco E&P Indonesia a oil and gas company, hereby invites potential contractors to
participate in the Tender for the Pekerjaan Jasa Penyediaan, Pengorasian dan Perawatan
3.0 DEFINITIONS
The following words shall have the meaning indicated when used herein :
The party that carries out all or part of the detailed design,
PURCHASER engineering, procurement, construction, installation &
commissioning
Is defined as the selected Party to supply the equipment &
service detailed in this specification. This is the entity having
VENDOR
unit responsibility as defined in the industry code and
standards.
MIGAS Indonesian Government Board responsible for issuing
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 6 of 35
The QA program for every project is to give confidence to and client that contract;
specification and such quality requirements are achieved. The QA program is designed to
of contracts.
The QA program covers all project activities affecting quality together with relevant
documentation.
The activities that are covered by the QA program are carried out within a system where
communications lines are clearly defined. Furthermore such activities are documented
All personnel are responsible for the quality of the work that they carry out. For each
program.
The Quality Assurance Organization verifies the implementation of the QA program and
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 7 of 35
The scope of Quality Assurance activities for construction project is mainly to:
Ensure that procedures and instructions are issued for the performance of all required
work.
Demonstrate by documented records that the work has been carried out and
The Client’s Representatives have the right to verify all aspects of the QA System
established for the project. They shall have free access to documentation and facilities
The training needs an provision for the training of all personnel, performing quality-
affecting activities, are identified by the Management and are part of the Quality Assurance
program.
In particular personnel performing special tasks shall be quality on title basis of appropriate
education and in compliance with the applicable standards and regulations. Records of
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 8 of 35
LEVEL 1
The is the Divisional Quality Assurance Manual which describes the Quality Policy, the
Quality Assurances program, the hand office and project organization, the Quality
LEVEL 2
Scope of this plan is to identify all quality-related activities of the specific project. Such plan
shall describe the project organization; the sequence of planned activities, the list of
The project QA plan is to be prepared by the appointed project QA/QC Specialist and
LEVEL 3:
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 9 of 35
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 10 of 35
The following definitions are provided to assure a uniform understanding of selected term
Approval
Audit
Calibration
Comparison of two instruments, one of which gas a know standard of accuracy (or
having a relationship with a standard) with the purpose of knowing the accuracy of
Cross check
In a function of the quality control system carried out as an internal audit in the
operation specifications.
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 11 of 35
Design
input, and which lead to and include the issuance of the design output documents.
Documentation
Hold Point
Step of manufacturing sequence beyond the work cannot proceed without preventive
Item
Non-Conformity
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 12 of 35
Procedure
operations.
Qualification (Personnel)
Quality Assurance
that an item or a facility will perform satisfactorily in service and the actions are
Quality Control
Those actions, which proved a means to control and measure the characteristic of an
Repair
The process restore non-conforming characteristic to condition such that the capacity
of an item to function reliably and safety is unimpaired, and conforms to the original
requirement.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 13 of 35
Rework
Specification
Standard
Supplier
Test
Verification
The act of review, inspection, test, check, audit or otherwise determine and
requirements.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 14 of 35
The Division Quality Assurance Manager is responsible for the preparation, maintenance
The Quality Assurance Manual is divided in deferent sections, each of them separately
revisable.
The index of the section with the latest revision applied is contained in the Quality
Assurance Manual. Each section shall carry a front page listing the following:
Section No.
Date of revision
No. of page
approval).
The original of the Quality Assurance Manual is filed within the Divisional Quality Assurance
The Divisional Quality Assurance Manual is subject to the Divisional Management approval
The Client shall approve the Quality Assurance for each specified project if required.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 15 of 35
Each copy of the Divisional Quality Assurance Manual is numbered and distributed as a
A distribution register shall be kept update by the Quality Assurance Department of the
Any revision or changes made to the Quality Assurance Manual sections for any reason
shall be notified to the assignees of each controlled copy. The obsolete sections shall be
Controlled copies of the Division Quality Assurance Manual are also distributed to client for
information or review as applicable and kept updated for the duration of the project.
5.0 PLANNING
5.0.1. GENERAL
At the bidding stage, the Commercial Department shall evaluate the tender documents and
therefore prepare a master plan for the contract development. At the contract award the
project activities shall be planning in details on the basis of contract requirements and
internal resources. An overall project plan shall be issued to Client before commencement
The project plan shall list the sequence of activities involved in the project development
such as :
Engineering preparation
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 16 of 35
Material management
Equipment calibration
Execution of operations
The QA/QC Coordinator shall interface with the Project Control and the Project Manager to
ensure that time and resources are foreseen for all quality- related activities.
All projects documentation both outgoing and incoming shall be maintained under control
documents shall be duly numbered, checked, recorded, filed and distributed. Every
outgoing document shall be given a title explaining the content and a unique number. A
code reference to the specific project shall be identified before starting any project work.
Every technical document shall carry a number identified by the numbering system
established for the project technical documents. All the documentation produced is logged
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 17 of 35
Contracts = Subcontracts
Above register may be incorporated in an overall Project Register listing all projects
Title
Number
Approval status
Transmittal reference
The registers will be updated as soon as new issues and/or revisions are produced. All
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 18 of 35
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 19 of 35
7.0 PROCUREMENT
According to the above, the Project Engineering Department shall produce the material
requisition with all the necessary data for procurement. At this stage, the Quality
Assurance Organization shall ensure that: applicable quality requirements are included,
taking particular care of inspection and certification requirements. The Procurement Officer
is responsible for issuing the inquiries. The inquiries shall be issued only to qualified
suppliers. The qualification shall be assessed by the procurement unit with the support of
supplying same standard items. The Procurement Unit is responsible for updating the list of
subcontracted.
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 20 of 35
documentations.
The Project Quality Assurance Manager shall review the requisition for completeness and
The different areas involved in bid evaluating and other issuing shall follow the step here
below to describe:
Inspection and testing requirements at Vendor works and relevant certification. The QA/QC
Coordinator shall review the Quality Control plans produced by Vendors, marking up the
intended inspection points. Such review shall be performed in connection with specialist
engineers for the different involved disciplines. Once completed and approved the Quality
Control plans will become the reference. Documents for performance of inspection at
Vendor works.
The assigned inspector is responsible to examine the specifications with all relevant
technical data and carry out the following activities according to the Quality Control plan:
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 21 of 35
At completion of all required inspection, the inspector shall fill and sign an inspection note,
issue it to the Vendor and to the Procurement Unit, who shall transmit release notes to the
Such certification will be part of the final documentation produced by Vendors before
material delivery.
The Certifying Authority shall inspect and certify all items on the basis of contractual rules
and regulations and shall be supplied by Purchase Order and relevant specifications.
Tools, gauges, instruments, and other inspection, measuring, and test equipment and
devices which are needed to perform activities affecting quality must first be of the proper
The equipment must then be calibrated to assure that it produce accurate measurements.
The equipment should be physically identified by unique serial (or other) numbers,
calibrated ill accordance with appropriate procedures, and adjusted to accuracy sufficient
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 22 of 35
for its intend use. Calibrations should be performing with reference standards, which are
Since the accuracy of equipment may change during use, equipment should be re-
calibrated at scheduled intervals. The calibration interval for each item should be based on
the type of equipment required accuracy, and its frequency of use. Special calibrations
A calibration label should be placed on the equipment to permit the user to determine if
the equipment is within its calibration interval. The label should bear the calibration data,
the last data the equipment can be used. The serial number of the equipment, and the
The manufacturer may perform the calibrations or use the services of an independent
laboratory. The equipment supplier can usually perform the initial calibration of equipment
requested.
Since the reference standards used to calibrate the measuring and test equipment may
The Project Q.A. Organisation is responsible to maintain a log of calibration with all
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 23 of 35
9.0.1. GENERAL
The construction activities shall be duly planned and organized before work starts.
Technological process to be adopted shall be neither evaluated nor only under production
Resources, facilities and materials shall be provided on time in order to avoid delays or
reworking.
The production personnel shall be qualified and trained for the operations they will carry
out.
Responsibility for the quality of the work is on those managing, supervising, planning the
work and on the personnel performing it, however, in process inspection during installation
and construction of items provides assurance that the required quality is being obtained ill
accordance with approved procedures. It also assures that deficient items or systems are
found and removed from further processing early in the construction of the project.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 24 of 35
Inspection of the work in progress should be performed to verify that items are being
installed, assembled, and constructed in compliance with the contract, and the latest
The production activities shall be covered by adequate instruction, i.e. drawings, work
procedures, specifications.
The Site Manager at project shall timely issue above instruction to the work sites and
forward any subsequent revision ensuring that production personnel are provided with
The QA/QC Coordinator shall verify recording, filing and distribution of procedures and
The special processes shall be covered by detailed procedures and quality by tests before
work starts.
Not only the processes but also the assigned operator shall be quality by performance tests
The Project QA Manager shall ensure that qualification trials are carried out in compliance
shall maintain a log of all qualifications for both processes and operations.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 25 of 35
After contract award a list of planned qualification shall be finalized by the Project
SCOPE: This section describes methods and requirements for Quality Control. The purpose
Final inspections verify that the completed systems and items are in conformance with
specified requirements. These inspections also verity the operational readiness of systems
and items. Examples of things checked during final inspection are as follows :
Workmanship is satisfactory;
Safety features are being used and comply with applicable codes and
Regulations
or parameter to be measured or the work operations being performed. The basic criteria
for the selection of inspection techniques and processes are the requirement of the
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 26 of 35
indirect control by monitoring of the processing methods, equipment, and personnel can
10.0.1. GENERAL
The Quality Assurance programme ensures that objective evidence of the quality of the
For this purpose a system of records shall documents the internal control on tile project
activities. Records shall be easily retrievable and traceable to the activities, which they
Therefore, they will be properly filed, preserved and provided with identification, date,
Each project function is responsible to produce and maintain records of his work. At the
beginning of the work an indexing system shall be establish for all records to be produced
on the project. Subsequently then the records shall be identified, according to the pre-
established index.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 27 of 35
evidence that the inspected items or system are acceptable. Checklists, which list each
minimum, they should identify the data of the inspection, the inspector, and reference
appropriate drawings and specifications, and note the type of observation, the results, the
acceptability of the results, and the action taken in connection with any deficiencies noted.
The inspection results for the various construction processes should be monitored to keep
a running track of those processes, which are producing deficiencies. This monitoring is
often called trend analysis. These trend analyses may be performed by complex methods
(e.g. statistical evaluation) or simple methods (e.g. plotting the percentage of rejects on
weekly basis). Whatever the method selected, it is important to perform these trend
analyses, since they provide a much more objective and systematic appraisal than that
achieved by simply relying upon the memory of the inspection or construction personnel.
When the analysis reveals that there are numerous problems, the first is to determine the
cause of the problem. When this is known, step should be taken to correct the cause. It is
not sufficient to simply increase inspection, since this will only separate the good from the
bad. Increased inspection will increase costs because the money spent on work, which was
rejected, cannot be retrieved and the increase volume of inspection work cost more
money. The greater amount of rework also affects the schedule, since less acceptable work
is completed.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 28 of 35
The project records shall be collected in the final data book, which documents the
complete history of the work, performed. The detailed list of the record to be included shall
be finalized after contract award under the responsibility of the Project Q.A. Organisation.
procedures
concessions.
At the end of the works the final data book shall be collected, reviewed and issued to Client
under responsibility of the Q.A. Organisation and final approval of the Project Manager.
The aim of a corrective action is to rectify non-conformances and prevent their recurrence.
The QA/QC Coordinator (or the Project Q.A. Manager) is responsible for initiating all
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 29 of 35
corrective action.
action.
Material defects
Lack of documentation
Failure on a process
The head of production function concerned with the audited/inspected activity shall
propose and agree the corrective action together with the Project Q.A. Manager.
Should no agreement be reached between the Project QA/QC Coordinator and the head tile
projection function concerned, the Project QA/QC Coordinator shall report the findings to
The corrective action request shall be explained in a report where the responsibility under
The Q.A. Organization has the responsibility to verify the effectiveness of corrective
actions.
The QA/QC Coordinator uses corrective action report to check the performance of the
quality.
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 30 of 35
12.0 AUDIT
In order to satisfy the requirements of the Quality Policy, a periodical evaluation and
For this purpose, an internal Quality Audit program is establish and implemented as
follows: The Divisional Quality Assurance Manager has the responsibility to verify that the
Quality Assurance provision set out in this Manual and effective and improvement the
The Project Quality Assurance Manager shall develop and implement for each project a
The results of such auditing activities are distributed by the Divisional Quality Assurance
Manager to the Head of Technological Innovation and Quality Assurance for his evaluation.
Depending on the findings reported by the auditing activities, corrective actions and
suggestion are proposed by the Head of Quality Assurance to the Resources and Systems
The Resources and Systems Direction shall then analyze both feedback information, and
return to the Head Quality Assurance of the Division with any corrective action or
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 31 of 35
The QA/QC Coordinator of the Division shall be responsible for the implementation of tile
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 32 of 35
The Q.A. Manager in co-operation with the Project QA/QC Coordinator should perform
audits to verify compliance with the Project Q.A. program and to measure the effectiveness
of tile program during all phases of the design process, procurement and construction
Planning the audit by means of a planning document which defines the organization
Providing audit personnel who are familiar with the types of activities to audited and
Preparing the audit report that summarizes the audit results and details and non-
conformances observed;
Submitting the audit report to management responsible for they are audited for
The audits should be regularly scheduled on the basis of the status and importance of work
intervals during peak periods, and near the completion of work. Regularly scheduled audits
should be supplemented by additional audits when any of the following conditions occur:
QA/QC PLAN
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 33 of 35
It is suspected that the quality of the item is in jeopardy due to deficiencies in the
Significant changes are made to the quality management program such extensive
Audit is performed in accordance with checklists used by the auditor to enter all pertinent
areas in an orderly sequence and with a minimum of wasted time and effort. Without a
checklist, the auditor enter an area with only the requirements, and/or working procedures
sport and pick out the specific items that can be check at that point. It is all too easy to
leave the area only to find, often when it is entirely too late to remedy the oversight, that
one or more significant point have been overlooked. The audit checklist provides a useful
means of determining, at any time, what was actually done during the audit and what the
auditor found.
To avoid conflicts of interest, audits are performed by personnel who do not have direct
responsibility in the areas being audited. Personnel performing audits should be competent
and have sufficient authority and organizational freedom to make the audit process
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 34 of 35
personnel having responsibility for the activity audited. An audit report includes the
following:
program.
The report should be distributed to management of both the audited and auditing
Manager of the audited activity should review and investigate all audit non- conformances
stated in the audit report determine and schedule appropriate corrective action, along with
the action, to prevent recurrence (including, where necessary, changes to the quality
004/RUI.G
DOCUMENT NO. REV. A
SC.RSS/11/2
021
Page 35 of 35
documenting the results of their review and investigation. The response should be made
within 30 days of the issuance of the report and should clearly state the corrective action
taken or planned and indicate prior to the issuance of the response, a scheduled date for
The audited activity should provide a follow-up report stating the corrective action taken
and the date the corrective was completed. They should also take appropriate action to
The audit team leader for the following reasons should take follow-up action:
To obtain a written response to the audit report, when a response is required and it
To assure that the corrective action and means of preventing recurrence are