On the progress of the project "Construction of Obigarm - Nurobod Road" Section


Tagikamar - Nurobod from km 30+217 to km 75+600
(Section - 2) on 02.08.2022
The length of the "Obigarm-Nurobod Road Construction Project" Tagikamar-
Nurobod section from km 30+217 to km 75+600 (section - 2) is 95.51 km. It
includes 4 sections of road with a total length of 44.10 km, construction of a
temporary road with a length of 3.81 km, construction of the road tunnel
"Tagikamar" with a length of 2.6 km, rural roads with a total length of 45 km, 7
bridges and 1 temporary bridge, 86 reinforced concrete culverts and retaining
walls of 250 pieces. The following work is currently in progress at the site:

Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
Preparation of working drawings
Main road (cross-sections
of the road on all sections
1 km 44,10 29,587 - 67,09
without taking into account
geological surveys)
Temporary road (cross
sections of the road without
2 km 3,81 3,81 - 100
taking into account
geological surveys)
Detailed topographic
3 surveys for rural access
roads km 45,00 45,0 - 100
4 Bridges pcs 8 8 - 100
Pipes, total pcs
80 57 -
Including:

5 Section No.4 pcs 20 16 - 71,25


Section No.5 pcs 20 16 -
Section No.6 pcs 26 19 -
Section No.7 pcs 12 4 -
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
pcs
Temporary road 2 2 -
Gabion retaining walls, pcs
total 170 129 -
Including:
6 Section No.4 pcs 58 40 - 75,88
Section No.5 pcs 56 40
Section No.6 pcs 48 32 -
Section No.7 pcs 8 3 -
Temporary road pcs 14 -
Gabion retaining walls, pcs
total 54 21 -
Including:
7 Section No.4 pcs 11 8 - 38,88
Section No.5 pcs 17 2 -
Section No.6 pcs 20 10 -
Section No.7 pcs 6 1 -
Rubble concrete retaining
pcs
walls, total 6 6 - 100
8 Including:
Section No.4 pcs 2 2 -
Section No.5 pcs 1 1 -
Section No.6 pcs 3 3 -
Earth Works
9 Clearing and grubbing км 47,91 12,015 - 25,07
10 Tree cuttings шт 5954 2 016 - 33,85
Non rock earth works
11 м3 3 026 556,0 1 674 430 1 300 55,32
(excavation)
12 Rock excavation м3 1 729 787 256 902 500 14,85
13 Embankment м3 2 544 801 82 650 300 3,24
Removal of existing
14 м3 642 119 - 18,53
concrete structures
Bridge No.8
Dismantling of reinforced
15 concrete pavement of -
м3 30,24 37,27 123,24
carriageway
Dismantling of a 31.5 m
16 long metal span with -
т 133,22 88,8 66,66
transportation to DEU
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on

Dismantling of precast
17 м3 171 114,97 - 67,23
concrete slabs

Bridge No.9
Drilling of boreholes for
18 П.м 1 156 120,5 3 10,42
bored piles d-1200 mm
Installation of bored piles
19 with a diameter of 1200 Шт/
68/1156 4/68 - 5,88/5,88
П.м
mm. Concrete class B25
Preparation of reinforcing
20 П.м 1 156 128 5 11,07
cage for piles
Bridge
No.10
Dismantling of precast
21 reinforced concrete slabs м3 40,82 40,82 - 100
2.99 m long
Dismantling of metal
22 barrier with transportation т 4,3 3,9 - 91
to DEU.
Dismantling of reinforced
23 concrete pavement of the м3 62,4 62,4 - 100
roadway
Manual digging of a well
24 П.м 360 360 - 100
pile
Installation of bored piles
25 with a diameter of 1200 Шт/
20/360 20/360 - 100/100
П.м
mm. Concrete class B25
Bridge No.11
Dismantling the existing
26 шт 1 1 - 100
bridge
Drilling of boreholes for
27 П.м 360 426 - 118,33
bored piles d-1200 mm
Installation of bored piles
28 with a diameter of 1200 Шт/
24/360 24/426 - 100/118,33
П.м
mm. Concrete class B25
Bridge No.12
Common excavation for
29 М3 2 388,44 - 51,27
structures 4658
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
Drilling of boreholes for
30 П.м 336 336 - 100
bored piles d-1200 mm
Drilling of boreholes for Шт/
31 24/336 24/336 - 100/100
bored piles d-1200 mm П.м
Bridge No.13
Drilling of boreholes for
32 П.м 336 396 - 117,85
bored piles d-1200 mm
Installation of bored piles
33 with a diameter of 1200 Шт/
24/336 24\396 - 100\117,85
П.м
mm. Concrete class B25
Bridge No.14
Drilling of boreholes for 105,42
34 П.м 516 544
bored piles d-1200 mm
Installation of bored piles
35 with a diameter of 1200 Шт/
46/516 44/540 95,65/104,65
П.м
mm. Concrete class B25

Preparation of reinforcing
36 П.м 516 565 5 109,49
cage for piles

Concrete of class B25 for


37 pile heads of abutments and М3 448,6 382,8 - 85,33
intermediate piers.
Structure of the pier body
38 М3 933,34 250,15 - 26,80
Concrete class B25
Retaining walls
Common excavation for
39 М3 648 882 107 420 - 16,55
retaining walls
Construction of gabion
40 М3 433 726 5 517,5 40 1,27
retaining walls
41 Construction of reinforced
concrete retaining walls
М3 126 488,2 5 727,61 58 4,52

Drainage works
42 Excavation of common М3 78 386 4 751,89 - 6,06
ground for pipes, capping
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
and monolithic ditches

Construction of culverts
43 М3\шт 8 389,30\86 694,73\9 - 8,28\10,46

Tunnel
Type-1
44 Tunnel tunneling
(arched part L-114,1 lm)
(vault walls L-74,5 lm)
м3 10 487,70 11 000,85 - 104,89
45 Installation of an I-beam
#30 arch frame on the east тон 184,4 124,831 - 67,69
portal
Concreting B 25 arch frame
46 on the eastern portal м3 50 - -
47 Surface cover of shotcrete
layer around the perimeter
of the tunnel 50 mm vault
and walls (produced at the m2 2710 3 036,97 - 112,06
same time as item 47)

Coating of shotcrete layer


around the perimeter of the
48 tunnel with a thickness of
270 - 300mm vault and -
m2 3 315,25 2921,02 88,10
walls, by applying
subsequent layers of 50
mm.
49
Steel mesh for shotcrete
reinforcement.
Тон 18,92 8,189 - 43,28

Type-I-А
50 Tunnel excavation (crown м3 2 941 35
part L-34,3 m)
51 . Installation of an I-beam Тон 14,282 0,137
#30 arch frame on the east
portal
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
52 Steel mesh for shotcrete Тон 3,074 0,018
reinforcement
53 Covering of shotcrete layer m2 1 097,4 6,4
around the perimeter of the
tunnel with 190 mm thick
vault and walls, by
applying subsequent layers
of 50 mm.
Type-II
54 Tunnel excavation by
drilling and blasting
method м2 208 257 13 509,53 393 6,48
(arched part L-159,9 lm)
(walls vault L-49,50 lm)
55 Covering of shotcrete layer
around the perimeter of the
tunnel with 50 mm thick м2 54 860 3 758 71 6,85
vault and walls, concrete
B15
Steel mesh 5Br-1 step
100x100 for shotcrete тон 236,93 10,095 0,199 4,26
56
reinforcement

57 Anchor bolts of rebar d 25 тон 196,93 12,201 6,19

58 Welding of a d 25 rebar тон 112,5 7,643 0,067


Concreting of the collapsed
area (at Km 32+946.00 to
59 м3 276
Km 32+938.00) (concrete
B20)
Covering the shotcrete
layer of the collapsed area
60 М3 254
(on Km 32+943.40 to Km
32+921.40)
Tunnel
Type-III
Tunnel excavation by 12,90
drilling and blasting
61 М3 49 770 6 421 -
method
(summary part L-51.0 m)
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
Covering of shotcrete layer
around the perimeter of the
tunnel with 50 mm thick
vault and walls, concrete
13,24
B15
62 м2 10 598 1 404 -

Steel mesh 5Br-1 step 8,33


63 100x100 for shotcrete тон 45.71 3,812 -
reinforcement
64 Anchor bolts of rebar d 25 тон 22.61 4,59 - 20,30
65 Wedling of a d 25 rebar тон 10.50 2,777 - 26,44
Production of materials from crushed stone and sand
Material production at the
66 м3 450 000 21 600 - 4,80
stone crushing plant

Completed work 03.08.2022 by sections:

Location Responsible
№№ Machinery and person by
Work description Section
п/п From km To km Equipment Employer and
Engineer
1 2 3 4 5 6 7
Western portal:
Drilling and installation of a
Excavator-1
1 leading anchor from d-114mm 4 30+500
Drilling rig-1
pipe tunnel header entry (7 pcs/
156 l.m.) Ibragimov M.
Dump truck - 4 90 912 20 20
Eastern portal: Water carrier - 1
Walls lower ledge left side Shotcrete machine - 1
installation of reinforcement Excavator-2
2 4 33+000
mesh and casting of concrete Loader-2
Km 32+772.50 to Km
32+764.20
3 Preparation of stones for gabion 6 Vakhsh River Floodplain
retaining wall Excavator-2
Loader-2

Excavator - 11
Gasoline tanker - 1
№№ Location Machinery and Responsible
Work description Section person by
п/п From km To km Equipment
1 2 3 4 5 6 Employer
7 and
Watering of roads and
4 residential areas along the work 6 52+000 59+000
sites to suppress dust
5 Embankment 6 52+500 52+862

6 Excavation (non-rocky soil) 6 53+010 53+060

Reinforcement of the foundation


7 6 53+095 53+282
r/c retaining wall

8 Excavation (non-rocky soil) 6 53+500 53+650

9 Excavation (non-rocky soil) 6 54+100 54+300

Dismantling of reinforced
10 concrete retaining wall 6 55+406 55+418
formwork

11 Backfilling 6 55+740

12 Slope works 6 55+760 55+860

13 Soil transportation 6 56+100 56+200 Lorry - 13


Loader-4
Sprinkling water on the main Manipulator-2
14 6 По всему участку Bulldozer - 3
road and residential areas
Water carrier - 1
Preparation of places for pouring
Roller - 1
beams, preparation of
57+000 Motor grader - 1
15 frameworks for pile foundations 6
село Тегерми Truck Crane-1
of bridges in the reinforcement
Mixer-3
plant Camp 3
Hydrohammer - 3
Sprinkling the water of the
16 6 Tagermi village
residential area
17 Preparing the static pile test 6 Мост №12

Reinforcement of r/c retaining


18 57+444 57+468
walls

19 Embankment 6 57+613 57+780

Reinforcement of r/c retaining


20 6 57+870 58+000
walls
Chuponov
Concreting of reinforced Khayriddin
21 6 57+942 57+954
concrete retaining walls 904 33 27 47

22 Gabion retaining walls 6 59+850 60+036

23 Gabion retaining walls 6 60+309 60+405

Concreting the foundation of


24 62+229
culverts

25 Excavation (non-rocky soil) 6 62+500


Kurbonzoda
Shohrukh
26 Excavation (non-rocky soil) 6 64+360 501 40 40 41
№№ Location Machinery and Responsible
Work description Section person by
п/п From km To km Equipment
1 2 3 4 5 6 Employer
7 and
27 Reinforcing the head of the
6 64+599 Sobirov
culvert
Sprinkling water on the main Water carrier-1 Sairiddin
28 road and residential areas 7 On the whole route 98 501 84 22

Sprinkling water on the main Temporar


29 Temporary road
road and residential areas y road
Temporar
30 Rock excavation y road 0+560 0+740
Temporar
31 Gabion retaining walls 0+927,37 1+080
y road
Temporar Loader - 1
32 Embankment 1+120 1+220 Excavator - 4
y road
Temporar Dump truck - 4
33 Works on dumping area 1+500 Water carrier - 1
y road
Drilling of boreholes for bored Temporar Roller-1
Grader-1 Kuziev Furkat
piles pier No. A-1, concreting y road
Crane-1 88 899 54 24
34 the lower tier of pier A2 Bridge No.14
(concrete B25) and Mixer-4
reinforcement of pier P-2
Loader - 2
Dismantling a rock crushing
35 Road M-41 Km 112 Excavator - 1
plant
Dump truck - 1
36 Asphalt plant Installation works Road M-41 Km 110
Loader - 1
37 Concrete works Road M-41 Km 110
Dump truck - 1

Machinery and Equipment

Excavator-21
Hydrohammer-3
Loader -12
Dump truck -23
Petrol tanker - 1
Bulldozer - 3
Manipulator-2
Motor grader - 2
Roller - 2
Total number of equipment and machinery: 150 pcs Water carrier - 4
Truck Crane-2
Rig-2
Mixer-7
Shotcrete machine-1
Drilling Rig-1
Total (active): - 86
Mobilization of personnel: a total of -402 people, including -54 (PRC), 348 local personnel (262- workers, 86 hs-
drivers, and operators).
Weather conditions: +31 ⁰С (sunny)

Attachment 1: Site Photos


Western Portal: Drilling and installing a leading anchor from a pipe d-114mm tunnel header entry

Installation of arch and rebar mesh of lower ledge left side Km 32+772.50 to Km 32+764.20 East portal
Installation of the arch and wall reinforcement mesh lower ledge left side Km 32+772,50 to Km 32+764,20

Concrete spraying of walls lower ledge left side Km 32+772,50 to Km 32+764,20


Excavation (non-rock work) Km 53+050

Formwork installation of reinforced concrete retaining wall Km 55+406 to Km 55+618


Preparation of frameworks for pile foundations of bridges in the reinforcement plant Camp 3

Preparation of places for pouring beams, Camp 3


Reinforcement of the body r\c retaining wall on Km 57+300 to Km 57+400

Embankment at km 57+613 to km 57+780


Reinforcement of r/c retaining wall Km 57+870 to Km 58+000

Concrete of reinforced concrete retaining wall Km 57+942 to Km 57+954


Installation of gabion retaining walls on Km 59+850 to Km 60+036

Installation of gabion retaining walls on Km 60+306 to Km 60+405


Concreting the foundation of the culvert Km 62+229

Excavation (non-rock work) Km 62+500


Excavation (rock works) Km 0+896 (temporary road)

Determination of embankment compaction coefficient Km 1+220 to Km1+320 (temporary road)


Gabion retaining walls Km 0+960 (temporary road)

Construction of embankment Km 1+220 to Km 1+320 (temporary road)


Embankment of Km 1+320 to Km 1+420 (temporary road)

Excavation (non-rock work) Km 1+600 (temporary road)


Drilling of boreholes for bored piles Bridge #14

Preparation of the site for works on the pier No. R-1 of the bridge No. 14
Concreting of the lower tier of pier A2 (concrete B25) bridge No. 14

Concreting of the lower tier of pier A2 (concrete B25) bridge No. 14


Determining the strength of concrete