Daily Report 03.08.2022
Daily Report 03.08.2022
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
Preparation of working drawings
Main road (cross-sections
of the road on all sections
1 km 44,10 29,587 - 67,09
without taking into account
geological surveys)
Temporary road (cross
sections of the road without
2 km 3,81 3,81 - 100
taking into account
geological surveys)
Detailed topographic
3 surveys for rural access
roads km 45,00 45,0 - 100
4 Bridges pcs 8 8 - 100
Pipes, total pcs
80 57 -
Including:
Dismantling of precast
17 м3 171 114,97 - 67,23
concrete slabs
Bridge No.9
Drilling of boreholes for
18 П.м 1 156 120,5 3 10,42
bored piles d-1200 mm
Installation of bored piles
19 with a diameter of 1200 Шт/
68/1156 4/68 - 5,88/5,88
П.м
mm. Concrete class B25
Preparation of reinforcing
20 П.м 1 156 128 5 11,07
cage for piles
Bridge
No.10
Dismantling of precast
21 reinforced concrete slabs м3 40,82 40,82 - 100
2.99 m long
Dismantling of metal
22 barrier with transportation т 4,3 3,9 - 91
to DEU.
Dismantling of reinforced
23 concrete pavement of the м3 62,4 62,4 - 100
roadway
Manual digging of a well
24 П.м 360 360 - 100
pile
Installation of bored piles
25 with a diameter of 1200 Шт/
20/360 20/360 - 100/100
П.м
mm. Concrete class B25
Bridge No.11
Dismantling the existing
26 шт 1 1 - 100
bridge
Drilling of boreholes for
27 П.м 360 426 - 118,33
bored piles d-1200 mm
Installation of bored piles
28 with a diameter of 1200 Шт/
24/360 24/426 - 100/118,33
П.м
mm. Concrete class B25
Bridge No.12
Common excavation for
29 М3 2 388,44 - 51,27
structures 4658
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
Drilling of boreholes for
30 П.м 336 336 - 100
bored piles d-1200 mm
Drilling of boreholes for Шт/
31 24/336 24/336 - 100/100
bored piles d-1200 mm П.м
Bridge No.13
Drilling of boreholes for
32 П.м 336 396 - 117,85
bored piles d-1200 mm
Installation of bored piles
33 with a diameter of 1200 Шт/
24/336 24\396 - 100\117,85
П.м
mm. Concrete class B25
Bridge No.14
Drilling of boreholes for 105,42
34 П.м 516 544
bored piles d-1200 mm
Installation of bored piles
35 with a diameter of 1200 Шт/
46/516 44/540 95,65/104,65
П.м
mm. Concrete class B25
Preparation of reinforcing
36 П.м 516 565 5 109,49
cage for piles
Drainage works
42 Excavation of common М3 78 386 4 751,89 - 6,06
ground for pipes, capping
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
and monolithic ditches
Construction of culverts
43 М3\шт 8 389,30\86 694,73\9 - 8,28\10,46
Tunnel
Type-1
44 Tunnel tunneling
(arched part L-114,1 lm)
(vault walls L-74,5 lm)
м3 10 487,70 11 000,85 - 104,89
45 Installation of an I-beam
#30 arch frame on the east тон 184,4 124,831 - 67,69
portal
Concreting B 25 arch frame
46 on the eastern portal м3 50 - -
47 Surface cover of shotcrete
layer around the perimeter
of the tunnel 50 mm vault
and walls (produced at the m2 2710 3 036,97 - 112,06
same time as item 47)
Type-I-А
50 Tunnel excavation (crown м3 2 941 35
part L-34,3 m)
51 . Installation of an I-beam Тон 14,282 0,137
#30 arch frame on the east
portal
Executed
from the
Execution commencem
Unit ent of
№ of Quantity construction
Work description
п/п measu under From the
remen contract commenc
t. ement of Per day (%)
constructi
on
52 Steel mesh for shotcrete Тон 3,074 0,018
reinforcement
53 Covering of shotcrete layer m2 1 097,4 6,4
around the perimeter of the
tunnel with 190 mm thick
vault and walls, by
applying subsequent layers
of 50 mm.
Type-II
54 Tunnel excavation by
drilling and blasting
method м2 208 257 13 509,53 393 6,48
(arched part L-159,9 lm)
(walls vault L-49,50 lm)
55 Covering of shotcrete layer
around the perimeter of the
tunnel with 50 mm thick м2 54 860 3 758 71 6,85
vault and walls, concrete
B15
Steel mesh 5Br-1 step
100x100 for shotcrete тон 236,93 10,095 0,199 4,26
56
reinforcement
Location Responsible
№№ Machinery and person by
Work description Section
п/п From km To km Equipment Employer and
Engineer
1 2 3 4 5 6 7
Western portal:
Drilling and installation of a
Excavator-1
1 leading anchor from d-114mm 4 30+500
Drilling rig-1
pipe tunnel header entry (7 pcs/
156 l.m.) Ibragimov M.
Dump truck - 4 90 912 20 20
Eastern portal: Water carrier - 1
Walls lower ledge left side Shotcrete machine - 1
installation of reinforcement Excavator-2
2 4 33+000
mesh and casting of concrete Loader-2
Km 32+772.50 to Km
32+764.20
3 Preparation of stones for gabion 6 Vakhsh River Floodplain
retaining wall Excavator-2
Loader-2
Excavator - 11
Gasoline tanker - 1
№№ Location Machinery and Responsible
Work description Section person by
п/п From km To km Equipment
1 2 3 4 5 6 Employer
7 and
Watering of roads and
4 residential areas along the work 6 52+000 59+000
sites to suppress dust
5 Embankment 6 52+500 52+862
Dismantling of reinforced
10 concrete retaining wall 6 55+406 55+418
formwork
11 Backfilling 6 55+740
Excavator-21
Hydrohammer-3
Loader -12
Dump truck -23
Petrol tanker - 1
Bulldozer - 3
Manipulator-2
Motor grader - 2
Roller - 2
Total number of equipment and machinery: 150 pcs Water carrier - 4
Truck Crane-2
Rig-2
Mixer-7
Shotcrete machine-1
Drilling Rig-1
Total (active): - 86
Mobilization of personnel: a total of -402 people, including -54 (PRC), 348 local personnel (262- workers, 86 hs-
drivers, and operators).
Weather conditions: +31 ⁰С (sunny)
Installation of arch and rebar mesh of lower ledge left side Km 32+772.50 to Km 32+764.20 East portal
Installation of the arch and wall reinforcement mesh lower ledge left side Km 32+772,50 to Km 32+764,20
Preparation of the site for works on the pier No. R-1 of the bridge No. 14
Concreting of the lower tier of pier A2 (concrete B25) bridge No. 14