Medupi Units 6 Shutdown Daily Update.

MHPSA Manager Bradley Laubscher


Date: 23 March 2018
Genrec Senior Supervisor: Elias Matshobeng
Genrec Manager: Reitumetse Mafereka
Man Power Qty: Qty: Qty: Qty:
Genrec Supervisor 2 Welders: 6 Boiler Makers: 8 Skyriders:
Genrec Foreman 2 Grinders: M. Controller 1 Rigger: 2
Genrec Safety 1 QC: Safety Rep. 1 Rigger Ass:
Unit : 6
Genrec WI MHPSA Scaffolding %
Level Grid location Work Scope Remark
No. Nirc No. No Complete
1) Site weld existing gusset to brace. 2) Removal of bolts.
3) Site weld pack to brace. 4) Erect & place new gusset
plate. 5) Bolt up bolts. 6) Site weld both sides of gusset to
10366 48m 1008 78.1/S/48m beam webs. 50% Sequence no. 1, 2,3 & 4 - complete
1) Site weld existing gusset to brace. 2) Removal of bolts.
3) Site weld pack to brace. 4) Erect & place new gusset
plate. 5) Bolt up bolts. 6) Site weld both sides of gusset to
10366 48m 1005 75.1/S/48m beam webs. 30% Sequence no. 1 & 2 - complete
1) Cutting existing gusset & stiffeners. 2) Installation &
10393 43m 1004 79.2/S/43m welding of new gusset plate. 90% MPI and torqueing of bolts outstanding
Fitting & welding the new bracket on the beam , drilling 4
10361 52m 1006 82/MN/52m holes and installing splice plate 90% MPI done , torqueing of bolts outstanding

10363 48m 1009 80.1/W/48m Installing & welding 2 new gusset plates 90% MPI done , torqueing of bolts outstanding
1) Fitting & welding of new plates. 2) Installing the splice
10365 69m 1012 75.1/U/69m plates. 90% MPI done , torqueing of bolts outstanding
1) Fitting & welding of new plates. 2) Installing the splice
10365 69m 1011 75.1/W/69m plates. 90% MPI done , torqueing of bolts outstanding
1) Drilling of 8 new holes on the beams. 2) Welding the
packer plate to gusset plate. 3)Bolt up 2 beams and drilling
10406 59m 1007 82/T/59m of 4 holes using gusset plate as a template. 85% MPI and torqueing of bolts outstanding
1) Fitting & welding of new plates. 2) Installing the splice
10365 69m 1012 78.1/U/69m plates. 80% Welding in progress
1) Fitting & welding of new plates. 2) Installing the splice
10365 69m 1010 78.1/W/69m plates 80% MPI and torqueing of bolts outstanding

10391 43m 1013 80.1/X/43m Fitting and welding 2 off gusset plates 60% Welding in progress

10391 43m 1018 79.2/X/43m Fitting and welding 2 off gusset plates 50% Welding in progress

10391 43m 1014 74.1/U/43m Fitting and welding 2 off gusset plates 50% Welding in progress

10391 43m 1017 73.1/X/43m Fitting and welding 2 off gusset plates 10%

10391 43m 73.1/X/43m Fitting and welding 2 off gusset plates 0% Scaffolding in progress

Responsible Supervisor: B/M Welder Gas Monitor Semi Skill Rigger Assistants QC Total Man Power

8 6 1 1 2 0 0 18
Total 18

Job Level Grid location Road Blocks/Time delays Comments

Page 1 of 1