N°__
PROCEDIMIENTO DE
TRABAJO – HALLAZGOS
S/E CUMBRE ARQUEOLÓGICOS Y DE
OSAMENTAS
AUTOR DOCUMENTO SUBCONTRATISTA
REVISADO
P-SGI-OPE-270-0030
APROBADO
AUTOR DOCUMENTO ALSTOM
REVISADO
TEN-6-CO-PRW-0067
APROBADO
DOCUMENTO CLIENTE
SIGATE
TEN-6-CO-PRW-0067
REVISADO TEN
ALSTOM GRID
Salar Ascotán 1288, Parque Industrial ENEA, Pudahuel, Santiago – CHILE
Page 1 of 1
Code:TEN-6-CO-PRW-0067_CS
Revision : B Date : 03-02-2016
TECHNICAL COMMENT SHEET
Owner Status table
Owner : TEN A - REJECTED
Owner Engineer : SIGATE Project reference: B-ACCEPTED WITH MAJOR COMMENTS
Contractor: ALSTOM Document number : TEN-6-CO-PRW-0067 Rev. B Project: Sistema de Transmisiones 500 kV C-ACCEPTED WITH MINOR COMMENTS
F- ACCEPTED WITHOUT COMMENTS
PROCEDIMIENTO HALLASGOS ARQUEOLÓGICOS Y DE
Document Title:
OSAMENTAS S/E CUMBRE
Status: Owner status I - FOR INFORMATION
A B C F I R
For drawings, a scanned copy of the drawing showing the numbered
(1) Note: comments is usually helpful R- REVIEWED AT SITE