Professional Documents
Culture Documents
A-1
Annexure-II
A-2
Annexure-III
Water Requirement of the Project
No. of Water Total Water
Land Use No. of Units Persons/ requirement per Requirement in
unit person in l * KLD
Block A to D 567 5 135 382.7
Amenities 1 115 45 5.2
Swimming pool 1 5.0
Visitors 2 15 17.0
TOTAL 409.9
*Water requirement as per NBC
Approximately 124.2 Kl/day water will be saved by adopting recycling of treated water
in the toilet flush. The effective water consumption is reduced by 124.2 Kl/day and the
requirement will be in the order of 285.7 Kl/day.
The water used in the order of 409.9 KL/day would generate 327.9 KL/day of
wastewater, which has to be treated for reuse and or disposal.
A-3
Sewage treatment plant based on Moving bed bio reactor system (MBBR) - 400 KLD
The moving bed biofilm process combines the technologies of activated sludge
processes and biofilm processes. The moving bed biofilm process is frequently used
when space is an issue. High-rate biofilm systems such as the Kaldnes Moving Bed
Reactor (KMB) or the NATRIX technology are highly efficient in removing the soluble
organic and nitrogen load.
When a pure KMB process is employed, a typical overall treatment design consists of
pre-treatment (screening) followed by one or more MBBR tanks, where the degradation
processes of soluble matter take place. The final stage of the treatment is normally the
particle separation.
A-4
= 1.2 X 0.052 =0.062m2
Assuming the inclination of screen of 60° to horizontal. Gross area of screen needed
would be 1.0X0.45 Mt. for ease of maintenance.
Equalization tank:
The flow from the bar screen chamber is let into the equalization tank of minimum 8
hours capacity. This tank is provided to even out the flow variation, and to provide a
continuous feed into the secondary biological treatment units.
MBBR Tank:
The biological aeration system is designed as an extended aeration system with sludge
recycle. Aeration is by means of fine pore membrane diffusers.
Design Flow = 400 m3/day.
Proposed to provide 12hr of holding capacity = 200m3.
Hence required volume of the tank = 100m3 x 2nos.
The tank size would be (10 x 3.5 x 3.0m SWD) X 2NOS. (effective volume)
Air Blowers
Sewage inflow = 400/20 = 20 cum.
Total BOD5 load = 250 mg/l.
BOD load in tank in Kg = (250x20) / 1000 = 5.00 kg/hr
For 1 kg of BOD removed 1.2kg of oxygen is required
Density of air = 1.17
% of oxygen in air = 21% = 0.21
Alpha factor = 0.65
Beta factor = 0.90
Oxygen transfer efficiency = 0.12
There for Air required = 5.00 x 1.2 / (1.17 x 0.21 x 0.65 x 0.9 x 0.12)
A-5
= 6 / 0.017
= 352.94 m3/hr.
Aeration time = 20hr
Therefore air required in cum/ hr. = 352.94 cum/ hr. = 207.73cfm.
Consider 35% excess considering the air required in the equalization tank
Total air required = 280.43 cfm
Hence provide 2 blower of 150cfm
One as standby with an operating pressure of 0.5KSC.
Transfer rate of oxygen in 1m.
Long membrane diffusers = 10 cum/ hr.
There for total number of membranes required = 280.43/10
= 28.04 nos. Say= 28 nos.
Secondary clarifier with sludge scraping mechanism:
The over flow from the aeration tank will be taken into the secondary clarifier for the
separation of biological flog.
A-6
proposed. The clear water from the settling tank shall be fed to the clarified water tank,
from where it will be pumped to the filters.
Design flow =400KLD
Provide min of 16 hours holding capacity.
Hence required volume of the tank = 266 m3
Provide a tank of 265KL. Capacity
The sizes of the tank will be 10X8.8X3.0 m
Ultraviolet Disinfection:
UV applied to low turbidity water is a highly effective means of disinfection. UV is not
harmful to aquatic organisms in the receiving water. UV light kills viruses, Vegetative-
and spore-forming bacteria, algae and yeasts. No chemicals are added to the
wastewater to change the pH, conductivity, odor or taste to create possible toxic
compounds. UV treatment has a few moving parts to adjust or wear out
Sludge Disposal:
The biomass in the aeration tank stabilizes BOD in wastewater by consuming the
organic matter in the wastewater. The metabolic activity results in growth of the
biomass population in the aeration tank. Consequently, in order to contain the level of
MLSS in the aeration tank to the design level of 4000mg/l, it will be necessary to bleed
off or waste the excess activated sludge. For this purpose, a sludge-holding tank of 20
cum with air supply and one no. filter press is proposed.
Filter Press:
A-7
The filter press is used to separate excess moisture in the sludge by application of
hydraulic pressure. The thickened sludge is used as manure.
Civil works
S. No. Name of the Unit Size in m
1. Bar Screen Chamber 1.0 m x 0.45 m
2. Equalization Tank 10 X 4.5 X3.0 m
3. MBBR Tank 10 x 3.5 x 3.0m - 2 nos.
4. Clarifier tank 2 X 2 X 1.6 m
5. Clarified water tank 10 X 4.5 X 3.0 m
6. Pressure Sand Filter 1500 mm dia and 2295 mm height.
7. Activated Carbon Filter 1500 mm dia and 2295 mm height.
8. Chlorinator 200 lts capacity
9. Mechanical Filter Press 40m3/day plant
Disposal of Treated Waste Water: It is proposed to reuse the treated wastewater for
green belt development and for toilet flushing. Excess treated water shall be utilized
for development of greenery in the surrounding areas.
A-8
Sewage Treatment Flow Diagram
A-9
Annexure-IV
A - 10
Annexure-V
A - 11
ANNEXURE-VI
Material Consumption for Total Units
Total
Total Total Total
BUA per Total Total Total Reinfor
Ready Mix Aggr Bricks
Units unit in Cement Sand Water cement
Concrete egate (Nos) x
(m2) (bags) (m3) (m 3
) Steel
(m3) (m3) 1000
(MT)
Total BUA 102977 42220 95768 40161 4428 24920 11945 2368
Total 102977 42220 95768 40161 4428 24920 11945 2368
A - 12
ANNEXURE-VII
Electricity Consumption Statement
Total Total
Connected Connected Total Max
No. of Load Load Demand
S.No Description Units Load in KW (KW) (kVA) (KVA)
1 Block A to D 567 4 2268.0 2835.0 2835.0
2 Street Lights 60 0.04 2.4 3.0 2.4
3 Amenities 156.1 195.1 156.1
4 STP 1 85 85.0 106.3 106.3
5 Lifts 9 15 135.0 168.8 168.8
TOTAL 2646.5 3308.1 3268.5
Maximum demand in kw at 0.6 diversity factor 1587.9
Consumption of power for 8 hours per day 12703.1
Maximum demand in kw at 0.2 diversity factor 529.3
Consumption of power for 16 hours per day 8468.7
Total consumption of power per day 21171.8 KW
Total consumption of power per year 77.3 Lakh Units
A - 13
Energy saving by using Solar Street Lights
Power Total power
No. of
S.No Description allocated in required in
Units
watts / unit (KW)
1 Street lights 20 40 0.8
TOTAL 0.8
Maximum demand in kw at 0.6 diversity factor 0.5
Consumption of power for 8 hours per day 4
Maximum demand in kw at full load 0.8
Consumption of power for 4 hours per day 3
Total consumption of power per day 7.0 KW
Total consumption of power per year 0.03 Lakh Units
saving with Solar Heater and Street Lighting 5.65 Lakh Units
A - 14
ANNEXURE-VIII
A - 15