TEHNI^KI PRESMETKI

TECHNICAL CALCULATION
PRESMETKA NA PAD NA NAPON
CALCULATION OF VOLTAGE SAG

DELNICA km 2 + 560 do km 2+950


SECTION

PO - 1 izvod - 1 faza - R
PO - 1 extract - 1 phase - R

0,55kW

-102m - - 102 m- - 102 m -

25 m
0,55 kW 0,55 kW 0,55 kW

2
KLU^KA "KNE@INO"
INTERCHANGE "KNEZINO"

PO - 1 izvod - 2 faza - S
PO - 1 extract - 2 phase - S
2x0,116 0,116

-38m- 20m -76m- -76m-

15 m

0,166kW 0,166 kW 0,166 kW 0,166 kW

PO - 1 izvod - 3 faza - T
PO - 1 extract - 3 phase - T

0,166 kW

- 76 m - - 76 m - - 76m - - 76 m -

65m

0,166 kW 0,166 kW 0,166 kW 0,166 kW 0,166 kW

3
Presmetka na vkupnata instalirana i ednovremena snaga za potrebite za
osvetluvawe na severnata obikolnica delnica: Ki~evo - Podvis klu~ka
-"Kne`ino"
Calculation of total installed and simultaneous power for needed for
illumination of north round, section Kicevo-Podvis, intercharge "Knezino"

Elektri~noto optovaruvawe od poedini razvodni ormari na koi e priklu~eno el. osvetlenie


iznesuva:
Electrical loading in some distribution boards, on which is connected el. lighting, is:

Mestopolo`ba Instalirana/
Potro{uva~ / Feeder Locality ednovremena snaga
(ormar) / (board) (stacionirana na avtopat) Installed/
(placed on motorway) simultaneous power

RO – 1 km 2 + 660 9,5 / 9,5 kW

 Pi / P e = 9,5/ 9,5 kW