Professional Documents
Culture Documents
LAND KEY
CONTRACTOR'S VERIFICATION STAMP
3 1 COMMENTS INDICATED
CODE 4
REVISE & RESUBMIT. WORK MAY NOT
PROCEED
PROCEED
CW-30
51250
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
OPEN TO SKY
2500 1250 ACCORDANCE WITH THE REQUIREMENTS OF THIS CONTRACT.
LOWER ROOF LEVEL
ACP-ALUMINIUM COMPOSITE PANEL
(DETAILED DRAWING SHALL BE
SUBMITTED SEPARATELY )
2250
----------------------------- --------------- ------------------
AD PORTS GROUP APPROVAL CODE DATE
200
250 x 200 x 10mm BASE PLATE P.SHAFT CW-02c
250 x 200 x 10mm BASE PLATE
GI BRACKET-250 x 200 x 10mm thk
UR-04
F F
UR-03
F.F.L.+VARIES
RW S.S.L+47.70
CW-02b
S.E.
S.M.
F.F.L.+VARIES
ELEVATION GEAD
S.S.L+47.70 MEP
G S.M.
UP STAND AS PER THE Client
G
S.M.
TFAD
UR-02
ST-02 DETAIL FOR THE DUCT
200mm CONCRETE UP
S.M. PENETRATION THRU SLAB OPEN TO ABOVE OPEN TO ABOVE OPEN TO ABOVE
UR-05 STAND FROM S.S.L
DN S.M.
F.H.C
UR-01
OF-SE01 DETAIL FOR THE DUCT
P.SHAFT
(FIRE RW F.F.L.+46.00
PENETRATION THRU SLAB
FIGHTING LANDING DN
LIFT)
UP STAND AS PER THE ST-01
DETAIL FOR THE DUCT
MEP T.O.P + 49.15 PENETRATION THRU SLAB UR-01
F.F.L.+46.00
Contract No. & Project Title
P.SHAFT
WITH PAINT FINISH WITH PAINT FINISH WITH PAINT FINISH WITH PAINT FINISH
F.CWP
P.
P.SHAFT SHAFT LANDING 73 x 140 x 4mm VERTICAL COLUMN 73 x 140 x 4mm VERTICAL COLUMN T.O.P + 49.15 73 x 140 x 4mm VERTICAL COLUMN 73 x 140 x 4mm VERTICAL COLUMN
WITH PAINT FINISH
MEP 73 x 140 x 4mm HORIZONTAL BEAM
2201-246
H H
STAIRCASE SHOP.DWG. CW-02a CONSTRUCTION OF KIZAD HQ OFFICES
WILL BE SUBMITTED
SEPARATELY Abu Dhabi, KIZAD AREA B, Plot:C1
10900
A1920
OPEN TO SKY
Sub Contractor
CW-27
F.F.L.+VARIES 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
CW-29
S.S.L+43.93
42500
J J
T.O.P.+44.18 LOWER ROOF LEVEL
T.O.P.+44.20 Contractor
T.O.P.+44.88 DECORATIVE TENSION RODE (AL-C2) ACP-ALUMINIUM COMPOSITE PANEL T.O.P.+44.88 DECORATIVE TENSION RODE T.O.P.+44.88
(AS PER APPROVED MATERIAL) (DETAILED DRAWING SHALL BE (AS PER APPROVED MATERIAL)
SUBMITTED SEPARATELY )
Consultant
K 3 K
ELEVATION
Drawing Title
L L
SCAFFOLDING DESIGN
Sheet Scale Paper Size
05 OF 08 As Shown A1
Drawing Status
DESIGN DRAWING
QR CODE
M Drawing No. Revision M
UNCONTROLLED IF PRINTED 2201-246-VA-6800-01204 C01
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16