TABLE OF CONTENTS

A. DESIGN CONCEPT

B. DRAWINGS
MASTER PLAN
1ST, 2ND, 3RD AND 4TH OVERALL LAYOUT PLANS
ELEVATIONS

C. TENANT CATEGORIES
PHOTOS
REGULATIONS
SCOPE OF WORKS

D. TENANT DESIGN RESTRICTIONS


LOADING RESTRICTIONS
MEP SCOPE OF WORKS
LOCATION OF TENDONS FOR DRILLING WORKS

E. DETAIL DRAWINGS
EXPANSION JOINT DETAILS
WATERPROOFING DETAILS
A. DESIGN CONCEPT
SUMMARY
DESIGN THEME
MALL
WAVE COURT (Central Court)
RIPPLE COURT (Sub Court AEON SIDE)
SPARKRING COURT (Sub Court CINEMA SIDE)
B. DRAWINGS

Site Plan
st nd rd th
Overall Layout Plans (1 , 2 , 3 & 4 Floor)
Elevations
ELEVATION-01
ELEVATION-02
C. TENANT CATEGORIES

PHOTOS
SCOPE OF WORKS
REGULATIONS
FFL Tenant have to submit Illuminate distribution calculation for
lighting and lighting list with light color, power for approval
from AM
Gian hàng ph i n p b ng tính toán c ng chi u sáng c a
èn và b ng danh sách èn có công su t, màu s c ánh sáng
Aeon Mall phê duy t
AEON MALL Viet Nam Ha Noi Long Bien Shopping Center
TYPE 1-D : F&B OUTDOOR C-WORK 1F Please always be sure to confirm the individual regulation.

F&B Outdoor:1F

C-WORK AREA-A T147-1 T147-2

As a general rule, the shop facade should be full open.


Only Translucent material will be permitted such as Glass,
Vinyl sticker, acrylic.
All C-WORKs and their designers are expected to have their The C-WORKs are allowed to have their entrance signage and
original and unique brand image and design. front signage.
Since the new concept of Outmall is Green Tunnel,
In addition, the the signage on the gate should be designed.
please consider arranging plants as much as possible. billboard in front of the common corridor is recommended.
GLASS BOX COVER AND FINISH BY C-WORK Inside LED lighting type and channel signage is recommended.
Kitchen is not allowed in Glass box
As a main sign, plain sign such as just paint or
Making the overhanging wall by the C-WORKs is recommended,
it should be the lightweight dry-type cladding panel, and so on. sheet may be not be approved.

and setting up the lighting is recommended.


Planting and planting box Keeping a corridor is recommended , As a general rule, the shop facade and seat area Base lightings of common area shall be provided by A-WORK.
should be full open.
Door open inside glass box
during operation time
All decoration must be installed on the inside of glass wall. When a C-WORK sets up lighting, the discussion with
Anything on outside of glass wall is not allowed. the A-WORK is necessary.
Glass wall and sash should not be damaged or replaced.

Please keep the security measures of each shop by all means at


each C-WORKs
CANOPY In glass box, kitchen is not allowed, only furniture, plants,
BY A-WORK decoration is allowed.
Presenting the lively scene is recommended.
Keeping a corridor in front of the shop is recommended, and it Please note that TC might request to have adjustment or
the aspects of overall harmony, aesthetics and operational view.
In addition, about the entrance corrider from the common corridor,
Plants
By A-WORK On the existing Glass box panel, any decoration is not allowed.
Inside of glass box, blind is allowed, but please use it from 2pm to 6pm.
Anything on outside of glass wall is not allowed.
Billboard BY C-WORK Glass wall and sash should not be damaged or replaced.
(If required) Gate BY A-WORK
Sign By C-WORK
Green Roof COMMON CORRIDOR Entrance floor
By A-WORK By A-WORK

Recessed Lighting
CANOPY Paint BY A-WORK
BY A-WORK BY A-WORK Glass eaves
Eaves BY A-WORK
BY A-WORK

Paint w/White color


by A-WORK Paint w/White color by A-WORK
LED Signage GLASS BOX
BY C-WORK BY A-WORK
Plants at Column H:5,000 By A-WORK
CANOPY
BY A-WORK Plants on roof By A-WORK
Space for machine and plant box C-WORK CEILING 4200mm

Hanging Sign(inside)
By C-WORK
COMMON OUT SIDE As a general rule, the shop facade should be full open.
If it is necessary to build a wall,
separating 800 from glass,
Gate By A-WORK Should be Skeleton ceiling
setting up the lighting near glass is recommended.
Sign By C-WORK

Billboard Gate By A-WORK Set up the lighting near glass C-WORK AREA
BY C-WORK Sign By C-WORK Glass and Sash by Awork
(If required)
On the existing Glass panel
Roll screen by tenant If required) --Only Translucent material will be permitted
Handrail
BY A-WORK allowed only from 2pm to 6pm such as Glass,Vinyl sticker, acrylic

FFL BY C-WORK FFL BY C-WORK

Entrance floor Plants BY C-WORK


Putting the graphic on glass directly are not allowed.
& Handrail If required
Any partition around Glass is not allowed.
By A-WORK
AEON MALL Viet Nam Ha Noi Long Bien Shopping Center
TYPE 1-D : F&B OUTDOOR C-WORK 1F Please always be sure to confirm the individual regulation.

F&B Outdoor:1F

T148 T149
As a general rule, the shop facade should be full open.
C-WORK AREA-A Only Translucent material will be permitted such as Glass,
Vinyl sticker, acrylic.
All C-WORKs and their designers are expected to have their The C-WORKs are allowed to have their entrance signage and
original and unique brand image and design. front signage.
Since the new concept of Outmall is Green Tunnel,
In addition, the the signage on the gate should be designed.
please consider arranging plants as much as possible. billboard in front of the common corridor is recommended.
GLASS BOX
COVER AND FINISH
Kitchen is not allowed in Glass box
BY C-WORK
Inside LED lighting type and channel signage is recommended.
As a main sign, plain sign such as just paint or
Making the overhanging wall by the C-WORKs is recommended,
it should be the lightweight dry-type cladding panel, and so on. sheet may be not be approved.

and setting up the lighting is recommended.


Planting and planting box Keeping a corridor is recommended ,
As a general rule, the shop facade and seat area Base lightings of common area shall be provided by A-WORK.
should be full open.
CANOPY
BY A-WORK All decoration must be installed on the inside of glass wall. When a C-WORK sets up lighting, the discussion with
Anything on outside of glass wall is not allowed. the A-WORK is necessary.
Glass wall and sash should not be damaged or replaced.

Please keep the security measures of each shop by all means at


CANOPY each C-WORKs
BY A-WORK
In glass box, kitchen is not allowed, only furniture, plants,
decoration is allowed.
Presenting the lively scene is recommended.
Keeping a corridor in front of the shop is recommended, and it Please note that TC might request to have adjustment or

Plants
the aspects of overall harmony, aesthetics and operational view.
By A-WORK In addition, about the entrance corrider from the common corridor,

On the existing Glass box panel, any decoration is not allowed.


Billboard BY C-WORK Inside of glass box, blind is allowed, but please use it from 2pm to 6pm.
(If required) Gate BY A-WORK Anything on outside of glass wall is not allowed.
Green Roof Sign By C-WORK
Glass wall and sash should not be damaged or replaced.
By A-WORK Entrance floor
By A-WORK Recessed Lighting
COMMON CORRIDOR BY A-WORK
Glass eaves
Eaves BY A-WORK
BY A-WORK

CANOPY
Paint
BY A-WORK
BY A-WORK

Paint w/White color


by A-WORK

Paint w/White color by A-WORK


LED Signage Green Roof
BY C-WORK By A-WORK CANOPY
GLASS BOX BY A-WORK Plants at Column H:5,000 By A-WORK
BY A-WORK Plants on roof By A-WORK
Space for machine and plant box C-WORK CEILING 4200mm

Hanging Sign(inside)
As a general rule,
By C-WORK
COMMON OUT SIDE the shop facade should be full open.
If it is necessary to build a wall,
separating 800 from glass,
Gate By A-WORK Should be Skeleton ceiling setting up the lighting near glass
Sign By C-WORK is recommended.
Set up the lighting near glass C-WORK AREA
Gate By A-WORK Glass and Sash by A-work
Sign By C-WORK On the existing Glass panel
Roll screen by tenant If required) -Only Translucent material will
allowed only from 2pm to 6pm be permitted such as Glass,
Vinyl sticker, acrylic
FFL BY C-WORK FFL BY C-WORK

Billboard BY C-WORK Entrance floor Plants BY C-WORK


Putting the graphic on glass directly are not allowed.
(If required) & Handrail If required
Any partition around Glass is not allowed.
By A-WORK
AEON MALL Vietnam Hanoi Long Bien Shopping Center

Plants (H-1200~1500 from FL)


BY A-WORK

Canopy by A-WORK

Handrail
MAIN CORRIDOR by A-WORK

T156
BRIDGE BY C-WORK

T157-2 T156 T156 T156


ACCESS Swing door needed.

There will be access w-1750mm from park. FLOOR FINISH BY C-WORK Entire Outmall signage by A- Work
Please consider it when you design it. ( There is already deck finish, Tenant can change it, if they want to.
There will be park by A-WORK But the material should be wood texture)
HANDRAIL BY C-WORK
(There is already handrail, Tenant can change it, if they want to.)

MAIN CORRIDOR OUTMALL SIGNAGE


Please always be sure to confirm the individual regulation.

Plant with Plant box on the roof


BY A-WORK

HANDRAIL BY C-WORK
HANDRAIL BY C-WORK
Height should be more than 1100mm,
Height should be more than 1100mm,
(There is already handrail, Tenant can change it, if they want to.)
(There is already handrail, Tenant can change it, if they want to.)

North side ( Outmall side) elevation

Plant with Plant box on the roof Plant with Plant box on the roof
BY A-WORK BY A-WORK

Glass door by C-WORK.

West side elevation( Park side) elevation East side elevation elevation
Please always be sure to confirm the individual regulation.

Plant with Plant box on the roof


BY A-WORK

HANDRAIL BY C-WORK HANDRAIL BY C-WORK


Height should be more than 1100mm, Height should be more than 1100mm,
(There is already handrail, Tenant can change it, if they want to.) (There is already handrail, Tenant can change it, if they want to.)

South side ( Parking side) elevation

Pendant lightings or hanging plants


BY C-WORKS
All tenants and their designers are expected to have their original The tenants are allowed to have their entrance signage, front signage
and unique brand image and design. and billboard signage.
Since the new concept of Outmall is Green Tunnel, please consider In addition, making the gate signage or billboard in front of the common
arranging plants as much as possible. corridor(park side) is recommended.
Inside LED lighting type and channel signage is recommended, and
billboard signage should be lighting up for night landscape
As a general rule, the shop facade and outdoor deck should be Plain sign such as just paint or sheet may be not be approved.
full open.
If it is necessary to build a wall inside the building, separating
Base lightings of common area shall be provided BY A-WORK.

Putting the graphic on the glass directly are not allowed.


When a tenant sets up lighting, the discussion with the landlord is
For Paint of building facade, please choose a low color chroma. necessary.
High chroma color will not be accepted.
OUTDOOR DECK Please keep the security measures of each shop by all means at
P BY C-WORKS each tenants
IF NECESSARY There are already deck floor finish, and handrail by A-WORK.
But If Tenant wants to have their own design, please proceed
Please note that TC might request to have adjustment or
with your own design. Deck should be wood finish,
Handrail should not be solid material H-over 1,100mm. the aspects of overall harmony, aesthetics and operational view.
See-though handrail is recommended.

Please consider pendent lightings, hanging plants under folding


roof structure.
Presenting the lively scene is recommended.

FLOOR FINISH BY C-WORK


( There is already deck finish, Tenant can change it, if they want to.
But the material should be wood texture)
AEON MALL Vietnam Hanoi Long Bien Shopping Center
TYPE 1-D : F&B OUTDOOR C-WORK 1F Please always be sure to confirm the individual regulation.

For this special location, all work should be done by Inside LED lighting type and channel character signage is
Glass Handrail
C-WORKs and their designers are expected to have recommended.
By C-WORK
their original and unique brand image and design.
Since the new concept of Outmall is Green Tunnel, For the size of the signage, see the drawings.
please consider arranging plants as much as possible. Well coordinated shop signage in size ,color, material, lighting, is
Floor BY C-WORK highly recommended.
Plain sign such as just paint or sheet may not be approved.
Please always be sure to confirm the seat assumption area .

Bridge INCL.Handrail
As a general rule, the seat assumption area should be
Base lightings shall be provided BY A-WORK under canopy.
By C-WORK
The plants can be over 1350mm.
Height control area is recommended to use see-througe When C-WORK sets up lighting, the discussion with the landlord is
necessary.
create open image as much as possible.
Existed C-WORK Area Any large wall may not be approved.
Height control area Deck should be wood finish, Please note that TC might request to have adjustment or
Handrail should not be solid material H-over 1,100mm.
See-though handrail is recommended. the aspects of overall harmony, aesthetics and operational view.

Please consider pendent lightings, hanging plants under canopy.


Presenting the lively scene is recommended.

Seat assumption area

The location of having to keep see-through

Pendant lightings or hanging plants


BY C-WORKS
Using structure under canopy.

Full OPEN
Signage by C-WORK
without parasol, lighting such as pole type
(C-WORK should provide drawing approved by TC)
Bridge incl.Handrail
By C-WORK P BY C-WORKS
IF NECESSARY

Handrail BY C-WORKS
The height should be more 1100
Floor BY C-WORK
Existed C-WORK Area

Seat area height control area-2500mm Seat area


LOUVER (vertical)
Building paint Reference Image

NOT ACCEPTED

ACCEPTED NOT
ACCEPTED ACCEPTED
Signage reference image

Ceiling - Skeleton ceiling reference image


Tenant have to submit Illuminate distribution calculation for
lighting and lighting list with light color, power for approval
from AM
Gian hàng ph i n p b ng tính toán c ng chi u sáng c a
èn và b ng danh sách èn có công su t, màu s c ánh sáng
Aeon Mall phê duy t
27

27'

P
22

O P
18 19 20

20
D. TENANT DESIGN RESTRICTIONS

Loading Restrictions
MEP Scope of Works
Location of Tendons for Drilling Works
NOTE:

About Summary of Structural Design, it was decided at the


beginning of this project. Though the loading plan is different
from the latest plan, Tenants to follow the loading as shown.
E. DETAIL DRAWINGS

Expansion Joint Details


Waterproofing Details