Professional Documents
Culture Documents
Contract: EZ01-CW04-CON-16
Deliverable
Project Stage: Issued for Approval
Schedule Ref.
Signature
1. GENERAL .............................................................................................................. 5
1.2. GENERAL INFORMATION .................................................................................... 5
1.3. BACKGROUND AND LOCATION .......................................................................... 5
1.4. INTRODUCTION .................................................................................................... 6
1.5. SCOPE ................................................................................................................... 7
1.6. DEVELOPMENT OBJECTIVES ............................................................................. 7
2. Architectural ........................................................................................................10
2.2. Introduction............................................................................................................10
2.2.1. General brief project identity ........................................................................................ 10
2.2.2. Project background ....................................................................................................... 10
2.3. Brief Description of plots in Ras Bufontas .............................................................11
2.4. THE PROJECT REQUIREMENTS ........................................................................12
2.5. BUILDING AREA PROGRAM REPORT ...............................................................24
2.6. DESIGN CONCEPT ..............................................................................................27
2.7. Design features: ....................................................................................................34
2.8. FIRE & LIFE SAFETY STRATEGY: ......................................................................34
2.9. ARCHITECTURAL: STANDARDS AND CODES ..................................................35
2.10. ...................................................................................................................................38
2.11. FENCE DESIGN....................................................................................................38
2.12. EMPLOYERS DESIGN BRIEF VALIDATION ........................................................39
3. ELECTRICAL ........................................................................................................43
3.1. REGULATIONS, CODES AND STANDARDS ......................................................43
3.2. INTRODUCTION ...................................................................................................44
3.3. SCOPE OF ELECTRICAL WORKS ......................................................................45
3.4. DESIGN CRITERIA – POWER SUPPLY SYSTEM ...............................................47
3.4.1. Substation ...................................................................................................................... 47
3.4.2. Design Conditions ......................................................................................................... 48
3.4.3. Electrical System Specifications .................................................................................. 48
3.4.4. Characteristics............................................................................................................... 53
3.5. DESIGN CRITERIA - LIGHTING INSTALLATION.................................................56
3.5.1. Internal Lighting ............................................................................................................ 56
3.5.2. Emergency Lighting ...................................................................................................... 58
3.5.3. Outdoor Lighting ........................................................................................................... 58
3.5.4. Lighting Management System ...................................................................................... 59
3.6. DESIGN CRITERIA: SMALL POWER INSTALLATION ........................................59
3.7. DESIGN CRITERIA - EARTHING AND LIGHTNING PROTECTION ....................61
1
3.7.1. Earthing System ............................................................................................................ 61
3.7.2. Lightning Protection...................................................................................................... 62
3.8. DESIGN CRITERIA - FIRE DETECTION AND ALARM SYSTEM ........................62
3.9. DESIGN CRITERIA - IP CCTV SURVEILLANCE .................................................64
3.10. DESIGN CRITERIA – ACCESS CONTROL SYSTEM ..........................................66
3.11. DESIGN CRITERIA – ICT SYSTEM......................................................................68
3.11.1. Design Considerations.................................................................................................. 70
3.12. BMS SYSTEM .......................................................................................................71
3.13. VALUE ENGINEERING .........................................................................................72
3.14. ELECTRICAL LOAD CALCULATIONS .................................................................73
3.15. CALCULATIONS ...................................................................................................77
3.15.1. Lighting Calculations .................................................................................................... 77
3.15.2. Electrical Power calculations ....................................................................................... 78
3.16. EMPLOYERS DESIGN BRIEF VALIDATION ........................................................79
5. ROADS .................................................................................................................91
5.2. Road Design Basis & Criteria ................................................................................91
5.2.1. Design Criteria Manuals ................................................................................................ 91
5.2.2. Design S ......................................................................................................................... 91
5.2.4. Traffic Study .................................................................................................................. 96
5.3. Traffic Study Report...............................................................................................97
5.3.1. Abstract .......................................................................................................................... 97
5.3.4. Traffic Study ................................................................................................................ 101
5.4. Site Grading Report .............................................................................................110
5.4.1. Abstract ........................................................................................................................ 110
5.4.3. Evaluation of ................................................................................................................ 110
5.4.5. Proposal of Grading .................................................................................................... 113
6. STRUCTURAL ....................................................................................................117
6.2. INTRODUCTION .................................................................................................117
6.3. DESIGN CRITERIA .............................................................................................119
6.4. MATERIALS ........................................................................................................122
6.4.1. Structural steel ............................................................................................................ 122
6.4.2. Structural Concrete ..................................................................................................... 122
6.5. LOADINGS ..........................................................................................................123
6.5.1. Load combinations ...................................................................................................... 127
2
6.5.2. Wind Loads Assessment ............................................................................................ 129
6.6. ANALYSIS AND DESIGN SOFTWARE ..............................................................132
6.7. FOUNDATION DESIGN SOFTWARE .................................................................133
6.8. ANALYSIS OF SUPER-STRUCTURES/STEEL GEOMETRIC DATA.................133
6.9. FIRE RATING AND DESIGN LIFE ......................................................................136
6.10. CODES AND STANDARDS ................................................................................136
6.11. EMPLOYER’S DESIGN VALIDATION FOR CONCEPT STAGE ........................137
7. MECHANICAL ....................................................................................................138
7.2. PLUMBING AND DRAINAGE DESIGN BASIS ...................................................138
7.2.2. Plumbing Scope .......................................................................................................... 138
7.3. Concept Design Initial Plumbing Calculations .....................................................145
7.3.1. Main Potable Water Storage Calculation for PA-WH-07............................................ 145
7.3.3. Main Potable ................................................................................................................ 147
7.4. Drainage System Design .....................................................................................150
7.5. FIRE FIGHTING DESIGN BASIS ........................................................................154
7.5.1. General ......................................................................................................................... 154
7.5.2. Proposed Fire Protection System .............................................................................. 155
7.6. Concept Design Initial Fire Fighting Calculations ................................................162
7.6.1. Fire Water Storage Calculation ................................................................................... 162
7.6.2. Fire Pump Calculation ................................................................................................. 163
7.7. HVAC DESIGN BASIS ........................................................................................165
7.7.1. Environmental Design Conditions ............................................................................. 165
7.7.2. Building Fabric Thermal Properties ........................................................................... 167
7.7.4. Heat Gain from Internal Lighting ................................................................................ 168
7.7.5. Heat Gain from Equipment / Appliances .................................................................... 169
7.7.6. Ventilation Design Criteria .......................................................................................... 170
7.7.7. Infiltration ..................................................................................................................... 172
7.7.9. Noise Levels ................................................................................................................ 173
7.7.10. Air distribution system................................................................................................ 173
7.7.11. Air conditioning system .............................................................................................. 174
7.8. Concept Design Initial HVAC Calculations for PA-WH-07 ...................................176
7.8.1. Cooling load Calculations ........................................................................................... 176
7.8.2. Air Handling Units Calculations ................................................................................. 180
7.8.3. Smoke Extract Fans Calculations .............................................................................. 183
7.9. Concept Design Initial HVAC Calculations for PA-WH-04 ...................................186
7.9.1. Cooling load Calculations ........................................................................................... 186
7.9.2. Air Handling Units Calculations ................................................................................. 192
7.10. EMPLOYER’S DESIGN BRIEF VALIDATION FOR LIGHT INDUSTRIAL &
LOGISTICS UNITS FOR CONCEPT STAGE ..................................................................202
3
8.2. PROJECT PROGRAM WORK FLOW CHART ...................................................205
8.3. GSAS – DESIGN AND BUILD CERTIFICATION FLOW CHART ........................206
8.4. BUILDING PERMIT PROCESS...........................................................................207
4
1. GENERAL
1.2. GENERAL INFORMATION
The overall design for the LIGHT INDUSTRIAL, LOGISTICS AND MIXED USE
OFFICE is designed and build by “Qatar Building Engineering Company” under the
Tender number –GTC- 08-2015 & EZ00-CW02-TND-16 at Qatar Economic Zone 1 in
Ras Abu Fontas. The project also involves the following organizations:
MANATEQ as Developer.
QBEC have been awarded with this design & build project and have invited ACE to
review their Architectural design and prepare the Structural and MEP Engineering
along with obtaining Municipal DC-1, DC-2 and Utilities and Statutory approvals
(Kahramaa, Ashghal, Qatar Civil Defense and Ooredoo) related to Municipal Building
Permit and GSAS- 1 star rating certification.
5
Figure 1: The Three Special Economic Zones.
Ras Bufontas Special Economic Zone is located on the south-eastern side of Doha,
and within Doha Municipality and is located adjacent to and south of the Hamad
International Airport. The total development area is approximately 4.1 Km², distributed
in 2 Parcels of land (Parcel A and Parcel B), with the initial development taking place
in Parcel A which has an approximate area of 2.45Km².
Master Planning of Ras Bufontas Special Economic Zone has been completed and
currently construction works are progressing in site, particularly in Parcel A.
The employer intends to develop Light Industrial/ Logistics Units (LIU’s) in Parcel A.
1.4. INTRODUCTION
The purpose of this report is to develop, identify and agree on the design parameters.
This report has been developed based on the following documents received from
QBEC.
Tie in points and road levels received from DORSCH via QBEC.
6
1.5. SCOPE
The Employers Requirements in this tender includes “Provision of Plant and Design-
Build Services” for the implementation of a Pilot Development comprising Light
Industrial Units & Logistics (LIU’s) in Ras Bufontas and Special Economic Zones as
outlined in this Tender Document and summarized as follows:
-
1.6.
Sq.m DEVELOPMENT OBJECTIVES
The LIUs by the owner will:
Provide functional and efficient industrial parcels of land to the market that can
be adapted to accommodate various light industrial land activities and logistical
activities envisaged for Ras Bufontas Master Plan, over the life of the project;
Support various light industrial, assembly, warehousing and logistics activities that
support and form synergies with the wider Qatar economy;
Maintain an efficient and effective transport network that supports the logistical
and light industrial nature of the Master Plan development, by ensuring
roadways, access, servicing, car parking and traffic movements are
unobstructed;
7
Promote clean industries and industrial business practices that avoid
generating any adverse impacts or hazards on people, property and the
environment; and
The Light Industrial Units (LIU’s) are pilot offerings in the market by the employer to
enable investors have an early access to ready-built “shell and core” facility that are
intended to serve both functions below:
1. Industrial function (light manufacturing, assembly and supply chain in line with
master plan development etc) and
Both plots PA-WH-04 & PA-WH-07 are individual developments and are to be
developed per Design/Development Brief.
8
Figure 3: Location of the Plots at Parcel A, Ras Bufontas, Enlarged.
9
2. Architectural
2.2. Introduction
Manateq has been entrusted with the responsibility to develop the 3 Special
Economic Zones, listed below:
1. General:
The overall design for the LIGHT INDUSTRIAL is designed and builds by “Qatar
Building Engineering Company.
- MANATEQ as Developer.
Construction Management
10
- ACE as Design Consultant.
This design & build project and have Employed ACE as the contractor sub
Consultant.
Scope:
• Provide functional and efficient industrial parcels of land to the market that can be
adapted to accommodate various light industrial land activities and logistical
activities envisaged for Ras Bufontas Master Plan, over the life of the project.
Support various light industrial, assembly, warehousing and logistics activities that
support and form synergies with the wider Qatar economy;
Maintain an efficient and effective transport network that supports the logistical
and light industrial nature of the Master Plan development, by ensuring
roadways, access, servicing, car parking and traffic movements are
unobstructed;
Promote clean industries and industrial business practices that avoid generating
any adverse impacts or hazards on people, property and the environment; and
The Light Industrial Units (LIU’s) are pilot offerings in the market by the employer to
enable investors have an early Access to ready-built
11
“Shell and core” facility that are Intended
to serve both functions
Below:
(PLOT- PA-WH-07)
12
And the MANATEQ GUIDELINES & PLOT CONTROL SHEET
13
PLOT- PA-WH-07)
14
PLOT- PA-WH-04
15
PLOT- PA-WH-04
16
SITE DEVELOPMENT
Fig. 1 – Shows the location of light industrial unit building on the site.
17
Kindly find enlarged plan in attachment (2) Part‐A
Fig. 2 – Shows the location of light industrial unit building on the site.
18
SITE ACSESS
PLOT- PA-WH-07
Entrance 1
Entrance 2
Figure -3 – The site has been provided with 2 separate entrances serving
vehicular purposes which are as follows:
19
Entrance 1 is located at the north western side of the plot,
The car enters to the parking for main office for light industrial unit.
The truck enters to the loading and unloading area for light industrial unit.
PLOT- PA-WH-04
Entrance 1
Entrance 3
Entrance 2
20
VEHICULAR / PEDESTRIAN ACCESS
Figure ‐4 – The site has been provided with 3 separate entrances serving
vehicular purposes which are as follows:
The car enters to the parking for main office for light industrial unit.
The car enters to the parking for main office for light industrial unit.
The truck enter to the loading and unloading area for light industrial unit
PARKING
PLOT (PA-WH-07)
This required parking number according to client requirement in plot sheet was
(Est. Car Parking Spaces) 30 in number,
32 have been provided in the ground floor at site, while all parking are shaded.
21
- The car parking entries are from entrance 1, completely isolated from the
trailer entry which further benefits efficient functioning of the building and also
helps in avoiding accidents.
Shaded Parking
PLOT (PA-WH-04)
This required parking slots according to client requirement in plot sheet was
(Est. Car Parking Spaces) 32 in number.
22
- The car parking entries are from entrance 1 and entrance 2, completely
isolated from the trailer entry which further benefits efficient functioning of the
building and also helps in avoiding accidents.
Shaded parking
Shaded parking
23
2.5. BUILDING AREA PROGRAM REPORT
PLOT (PA-WH-07)
24
PLOT (PA-WH-04)
25
PLOT (PA-WH-04 AND PA-WH-07)
BUILDING Wall:
MATERIALS
1. Twin skin PIR Insulated Architectural Cladding with
insulation to give U value of 0.35 W/m2K for the storage area.
Roof:
Glazing:
Floor:
Elevation treatments:
26
exterior texture Paints, Steel pergolas and shading elements
- Administration area
The schedule of this area in each LIU accommodates the reception area,
pantry and toiles in the ground floor and offices in the mezzanine floor and
gives the opportunity to the tenants to manage his own space conveniently.
Contemporary architectural Style has been incorporated into the design and
façade treatments of the building.
2. The offices façade of the building is treated with glass window openings &
aluminum panels along the elevation to match the gateway project.
3. Administration entrance and exit is separated from the truck entrance. Those
two entrances/exits along the plot will serve as emergency access and exits.
5. Office area has been provided for the administration area with a small
meeting room, manager’s room, pantry, toilets.
SUBSTATION BUILDING
27
-Elevation treatments Stone, GRC (Glass Reinforced concrete).
PLOT-PAWH-07
28
Female Toilet
Male Toilet
Janitor
Pantry
Stairs
Reception
Entrance
PLOT-PAWH-04
29
LIU (ADMIN. AREA)
30
MEZZANINE floor offices area
31
COLUMN LAYOUT
PLOT PA-WH-07
32
PLOT PA-WH-04
33
2.7. Design features:
PLOT PA-WH-04
PLOT PA-WH-07
2. The northern side of the building is treated with glass window openings &
aluminum panels along the elevation to matching with gateway project.
3. Main access to the building for admin‐ the entry to the building is separated
from Truck entrance, these two entry/exits along with plot will serve as Fire
exits in case of an emergency.
4. Administration area has a reception and waiting area point where tenants
can manage and control the LIU unit.
5. Office plan area has been provided for the tenant area with a small meeting
area, manager’s room, pantry, toilets.
6. Contemporary architectural style has been incorporated into the design and
elevation selection of the building.
7. The main access to the building is from the northern façade, the same
entry/exit has been Oriented parallel to the road for security enquires.
11. Building materials include Clay blocks and Hollow concrete blocks with
structural Elements of concrete Elevation treatments (BLOCK, SANDWICH
PANEL, ALUMINUM CLADING, GLAZED, Textured paints, and shading
elements)
34
According to NFPA 5000, the fire hard standing, assembly point and route of
civil defense Vehicle is given in Attachments mentioned below:
2. Ground Floor:
3. Mezzanine Floor:
Based on NFPA 101, NFPA 5000 and QCDD requirements 2015, Code
analysis, occupancy and egress calculations, building construction
requirements and MEP provisions are presented.
The detailed design & engineering shall be carried out in accordance with the latest
Standards and Specifications listed below shall be used in the first instance, design
codes and standards shall only be considered from the following.
Publishing organizations:
35
QCS Qatar Construction Specification
EN European Norms
36
IBC International Building Code
UL Underwriters Laboratory
37
2.10.
2.11. FENCE DESIGN
38
2.12. EMPLOYERS DESIGN BRIEF VALIDATION
1 The Light Industrial Unit Building (s) should be designed as flexible yes
modular units as much as possible.
2 The modular units are to provide up to 10% of the space as internal offices. yes
3 Modular units should have a clear office entry and separate entry for the industrial yes
functions.
4 Walls should be separating Modular units and shall be constructed as a separating yes
wall to full height
5 Modular Units should have a dedicated loading yard with ramp access for forklifts yes
and the building frontage to the public roadway.
6 Service yard and parking area should be provided for each of the modular yes
unit.
Each plot should be provided with a fence, the side facing the roads to be of
7 decorative vertical steel bars yes
Each plot to be provided with minimum 1 no. entrance & exit for trucks & 1 no.
8 entrance & exit for employees’ cars. yes
Provide sufficient shaded car parking for staff and visitors as per
9 regulations and Master Plan guidance document. yes
10 Provide two fully functioning toilets (with provision for access to especially yes
abled/disabled’) for each Logistics building (one male and one female) together with
associated MEP & builder’s works.
39
Provision of complete HVAC system for temperature control requirements in the
12 range of 18°C to 24°C is not required. yes
15% of units should be capable of having enhanced power provision for cold
13 storage. yes
14
complete firefighting system with all associated MEP and Builders work as yes
per QCDD regulations includes a sprinkler system, Clean Agents Systems,
fire extinguishers, storage tank or fire-mains, fire hose reel & cabinets and
hydrants in the service yard as required by the QCDD.
Mandatory Recommended
1. Light Industrial Unit Site plan Reflect to design a shape as much YES
Building designed as layout , ground as possible to leased as individual
flexible modular units. floor plan units or sub-divided and can be
combined as larger units
depending on potential investor
needs.
2. modular units are to Ground floor, Recommended to be 15% or YES
provide up to 10% of mezzanine more to give more facilities in
the space as internal floor ground floor area and more
offices space in mezzanine floor for
offices
40
3. Modular units have a Ground floor Separated entrances for each LIU YES
clear office entry and connected with the parking.
separate entry for the
industrial functions.
6. ramp access for Site plan Ramp for forklift should be YES
forklifts layout , ground beside the truck yard to make a
floor plan loading and unloading process
easy
7. Service yard and Site plan Service yard and parking area YES
parking area layout , ground provided for each of the modular
floor plan unit to give the investor more
flexibility to have his own special
work
8. fence around the plot Site plan Location of Fence is not around YES
layout the plot, as per client
requirement to match with
projects surrounding
9. entrance and exit for Site plan entrance and exit for intent cars YES
intent cars layout should be added to plot and
integrated with surrounding
streets and design and
requirement
10. entrance and exit for Site plan entrance and exit for truck YES
truck layout should be added to plot and
integrated with surrounding
streets and design and
requirement
11. Lockable steel Gates Site plan Gates should be with barriers to YES
layout give more security to the plot as
per requirement
12. security kiosk Site plan Security kiosk should be beside YES
layout the entrance to control the
vehicle and pedestrian access
13. shaded car parking Site plan Car parking should be as per YES
layout regulations and Master Plan
guidance document.
41
block the sun light
14. Separation of car, Site plan Entrance and exit for cars and YES
pedestrian & truck layout trucks should be separate to
traffic avoid traffic problem and to give
the loading and unloading
process more effectiveness
16. cold storage ground floor Cold storage should be 15% of YES
plan area for warehouses
17. Walls of LIU’s plans ,section Walls of unit shall be 2.80 m YES
and elevation blockwork and then metal sheet
to the top to avoid any crashes
happen to metal panels
18. Roof cladding Site plan Twin skin PIR Insulated YES
layout Architectural Cladding with
insulation to give U Value of 0.25
W/m2K.
19. Rainwater Goods Site plan The gutter had been provided on YES
layout the top of each liu to dispose the
rain water from the roof to the
storm water network
20. Roller Shutter Door ground floor The loading and unloading YES
plan process needs roll shutter door
with 4*4.5 m as per the
requirement
21. industrial worker door ground floor industrial worker door(s) shall be YES
plan in the warehouses from truck
yard to access and as per QCDD
REQUIREMENT for life safety
23. Substation/ Plant Site plan Substation, Plant Rooms and Fire YES
Rooms/ Fire Main layout Main as per client requirement
42
3. ELECTRICAL
The electrical work will be designed and specified in conformity with the
following:
43
r. EN61000-3-3(Flicker Requirement– EMC)
Equipment and materials specifications will comply with the relevant standards
of IEC, BS, DIN and/or UL, when not in contradiction with local standards, and
codes.
In addition, Electrical design (in points not described by the local Authorities)
will be based on international standards, guidelines and best engineering
practices.
3.2. INTRODUCTION
44
To facilitate robust, cost effective installations with due regard to operational
reliability, flexibility for future changes and longevity of equipment and
associated components;
To achieve energy efficiency (in compliance with QCS requirements & score)
within the dynamic system elements to result in optimum operating and
maintenance costs.
The scope of electrical work will include the systems components described
below, which will be applicable to the entire project. The electric demand
calculations will be based on occupancy type provisions stated on architectural
drawings in compliance with the KAHRAMAA Regulation. The allocated power
supply will be observed to the utmost possibility.
45
Lighting switches
Socket and power outlets
Isolating switches
Industrial outlets
Cooker control units
d) Lightning Protection System
Air terminals
Copper tape
Earthing rods
Earthing pits
e) Fire Alarm and Detection System
RJ45 outlets
Wi-Fi Access Points
UTP 4pair cables
Patch Panels
19 inch Racks
g) IP CCTV Surveillance
46
IP fixed cameras
IP Dome Cameras
NVR storage
Ethernet Switches
UTP/FO cables
h) Access Control System
IP fixed cameras
IP Dome Cameras
NVR storage
Ethernet Switches
UTP/FO cables
3.4.1. Substation
The source of electrical power supply will be from an indoor type substation
located within the plot. The substation will be equipped with MV RMU, Oil type
transformer and Low Voltage switchgear designed as per Kahramaa
requirements.
The size and layout of the Substation Building shall be as pre Kahramaa
requirements:
Low voltage cables will be routed from the Substation Main LV panel to the
Sub main distribution boards located in the buildings electrical rooms.
47
3.4.2. Design Conditions
I. Power Supply system
d) Frequency 50 Hz
48
The MV switchgear shall be 11kV, 3-ph, 50Hz as per KAHRAMA standards
and regulations, provided by approved vendor.
II. Transformers
The Transformers shall be 11/0.415 kV, 50Hz, Dry Type as per KAHRAMA
standards and regulations, provided by approved vendor.
Emergency power shall be provided for fire safety equipment, fire alarm
system, exit and emergency lights and security systems.
EDG shall be 3-phase, 4-wire, 50 Hz with grounded neutral, 1500 rpm, air
cooled, complete with fuel tank, exhaust system, daily fuel tank, fuel pumping
systems, lubricating pump, battery charging alternator, DC exciter, control
panel and Circuit breaker. The EDG shall be installed indoors. The standby
emergency generator shall be a Type 10, Class 24, Level 1, standby power
generator in accordance with NFPA 110.
The generator must be capable of handling the maximum load with 25 per cent
spare at 0.8 lagging power factor at the rated RPM including all accessories.
The engine and starting equipment shall be designed to ensure the engine-
generator is up to speed, on line, and capable of accepting the full generator
load within a period of ten (10) seconds after the initiation of the starting signal,
by automatic devices hereinafter specified, upon loss of normal AC supply to
the system.
49
All emergency / standby lighting\
The UPS shall provide continuous, regulated AC power under normal and
abnormal conditions, including loss of the utility AC power, to ELV systems:
CCTV, Access Control and Telecom system.
The system shall operate in conjunction with the building electrical system and
the generator to provide high quality power for critical equipment loads such as
computer servers and related equipment, power outlets feeding main
controllers of BMS, security system, Fire alarm system etc. The UPS shall be
completely solid-state except for maintenance bypass switches which may be
mechanical.
All UPS shall have interface cards to have the following and shall be complete
with system software:
Required input and output dry contacts for reporting alarm and status.
All UPS systems shall be based on latest IGBT technology with PWM.
50
maintenance bypass switch, Cooling fan, inlet dust filter etc. and shall have a
radio frequency interference suppression filter at the input and output.
Input:
Frequency : 50 Hz ±10%.
Output:
Tolerance : +/- 1%
The UPS system shall provide redundancy for a period of 60 minutes under
full load.
One UPS unit shall be provided for CCTV system and one UPS unit shall be
provided for other IT systems.
The CCTV UPS system shall be located inside CCTV Room for the complete
plot and the IT UPS shall be located in the Electrical room of each LIU. Extra
room space should be foreseen inside these rooms in case of external battery
cubicles to be utilized. The space shall be constructed according to QDDC
requirements.
51
IV. LV Panel Boards
LV Main Switchboards
The LV Main switchboard will be the substation Main LV Panel complying with
following minimum specifications:
Factory assembled by approved manufacturer
Form 4B-type 6, 415V/230V – 3-ph, 50Hz
3-Phases, Neutral and Earth bus bars
Earth Fault rating: 44kA for 3 seconds
Max height 2200mm - according to (KAHRAMMA)
Min. 25% spare capacity on design load
CTs for fiscal metering purposes as per KAHRAMMA requirements
CTs and VT for protection purposes
Restricted Earth Fault protection relay
30VDC battery and charger system for tripping function
Metering
Main Meter Spare Provision shall be made in cubicle main switchboards for
the installation of the Qatar General Electricity & Water Corporation
“KAHRAMAA” metering equipment located in separate cubicle above or below
the main switch.
CTs shall be located on the main bus bars immediately after the main
incoming switch where the complete installation is to be metered at source.
Removable links 250 mm long shall be provided in the main bus-bar of each
phase to enable easy maintenance and replacement of current transformers.
The metering CTs are to be installed in a cubicle main switchboard; they shall
be supplied and fitted by the panel manufacturer to comply with Qatar General
Electricity & Water Corporation KAHRAMAA requirements.
52
Each Kilowatt Hour (kWH) Meter installed by Kahramaa shall be mounted on
the plywood base board having minimum dimensions of 300mm x 300 mm x
12 mm thick. This plywood mounting board shall be supplied and installed by
the panel manufacturer.
All small wiring for controls, voltmeter suppliers, etc. that originate from the
main and sub-main bus bars shall be connected to the bus-bars by means of
bus-bar mounted H.R.C. cartridge fuses suitable rated for their intended use.
The maximum size of fuse used shall not exceed 20 Ampere.
Intermediate kWH meters for each LIU shall be installed after the Circuit
Breaker of each LIU MDB and shall be located on the Main LV Room.
As part of the BP procedure the contractor shall provide for future AMI
equipment according to Kahramaa directives ‘’CS-CSI-P1/C4 Advanced
Metering Infrastructure Code (AMI)’’.
Unit Capacitors: The capacitor units shall be dry, self-healing type with
individually discharged resistors shall be protected against internal faults, over
pressure, etc. and shall fully comply with and tested to the requirements of the
International Electro-technical Commission Publication No IEC 60831, Part-1
and Part-2.
3.4.4. Characteristics
53
discharge of the capacitor to less than 50 V in one minute after a
switch off and capacitors should not restart until a minimum 3 minutes
after the restoration of the supply.
Characteristics:
Fault level calculation shall be submitted for the electrical distribution system.
If the fault level calculations are higher than what has been indicated on doc.
“Employers Requirements for LIUs, Part B, Section II of IV, 2.01 Ain Table
2: Non-Essential Distribution Systems Panel’s Requirement”, they shall
be followed otherwise the fault level in the above table shall be as a minimum.
54
MCC boards
The MCC boards shall be Form 3b construction and shall be provided to feed
motor loads. Panels shall be sized with min. 25% spare capacity on design
load.
Distribution Boards
25% fully equipped outgoing spare ways will be provided for all local
distribution boards.
The Outdoor Feeder Pillars shall be provided to feed outdoor lighting loads.
Panel shall be Form 2b, IP 56. Fault level shall be 10kA if fed from SMDB or
25KA for 3 sec if fed from main LV panel. Min.10% spare capacity on design
load 2.0 mm
Current Capacity
Voltage Drop
Installation method
55
Cable sizes will be limited to a maximum size of 300mm 2 with no more than 3
cables per phase. The load will be split if it deemed that larger sizes of cables
or greater quantity of cables/phase are required.
Duct sizes will be a minimum of 150mm and 25% spare ducts will be provided.
Internal final circuit for lighting and small power will be PVC insulated non
armoured cables rated 300/500V according to BS 6004:2012, installed inside
trucking or conduits.
Building/Area Average
illuminance
56
Offices 500 Lux
LED lights will be generally considered in all areas. All other decorative lighting
will be electronic ballasts and long life energy saving lamps. No incandescent
lamps allowed.
All luminaires shall be rated as a minimum to IP44 and lighting circuits will be a
residual current device with a 100mA trip setting.
57
Toilets/ Pantry LED Recessed (60x60cm) or LED Down light
(IP54)
All light fittings shall have ENEC approval. Global Sustainability Assessment
System, GSAS Design guidelines to be followed
The system will be designed in accordance with NFPA101, Section 21, and
Part 12 of QCS.
All emergency lighting circuits shall be fed from EDG backed up Distribution
Boards.
Exit signs will be provided at all exit locations. Illuminated EXIT signs will be of
the LED type complete with all necessary legends.
4-pin plug-in type ceiling roses will be provided for all self-contained
emergency type luminaires
The outdoor lighting will be provided to achieve adequate lighting level for
security, safety & decoration purposes. Luminaries in outdoor wet areas
installation will be selected for ingress protection IP 54 in protected areas, IP
65 in exposed areas.
58
Timer and solar switch (Photocell) will control the external lighting to reduce
overall lighting power density, facade and landscape exterior lighting as per
ASHRAE standards.
The LED type lights shall have min 35000 Hr Life Time. The Lighting feeder
pillars shall be 4mm thick. Outdoor Lighting poles shall be 10m Height with
500mm arm long, with cut-out box (MCB + Earthing Lug).
All outdoor lighting shall be fed from EDG backed up Distribution Boards. The
outdoor emergency lighting system shall include fittings with battery pack for
3h redundancy. The outdoor emergency circuits will be monitored through the
central emergency lighting monitoring system mentioned on par. 7.5.2.
The control of public area and staircase lighting will be achieved with timer
switches and occupancy detectors.
Lighting system provided with motion sensor & daylight sensor to save power.
The small power installation will be designed to suit occupancy and equipment
layout and it will be in accordance with QCS.
Power supply for permanently connected fixed equipment will be via suitably
rated isolator or fuse connection units and fed from local distribution boards.
Flexible cable outlet will be provided where required.
Power supplies for all items of IT, telecoms and ELV equipment will be
provided as required.
All electrical accessories will be flush mounted, ring circuits will be used for
final socket outlet circuits.
Final ring socket outlets will be wired in 4mm2 cables in trucking/conduits and
shall be protected by 32A/30MA RCBO’s at the local distribution boards.
59
Office areas will be provided with two numbers twin 13A switch socket outlet
per computer workstation. Areas without computer workstations will be
provided with sufficient number of twin 13A twin switch socket outlets.
Wiring accessories will be installed flush mounted in all offices and public
areas and will be whit PVC. Plant rooms, utility rooms and similar areas will be
provided with surface installations utilizing Metal clad type accessories. Wiring
accessories will be IP65 rated in all external and wet locations.
In offices, stairs, and toilet areas the cover plates polycarbonate type. The
switches shall confirm to BS EN 60669-1. The minimum rating of switches
shall be 10A.
Mounting Height
1. Lighting fittings:
Lighting Switches: 1250 mm
Wall mounted light fitting (above:2400mm AFFL The doors) for
external
Flood lights for external lighting:8000mmAFFL
2. Socket Outlets:
General:450mm
High Level:1250mm (Inside Warehouse, Pantry and Kitchen)
Spur Control Unit:1250mm
3. 20 A or 30 A D.P Switches:
4. Flex Outlets:
Exhaust Fans: On center line above the Exhaust fan
Others: Related to each particular Item or equipment
Photo Cell: Feeder Pillar enclosure
Condensing unit’s isolators: 800mm – Steel frame mounted
Control Panel for Air Conditioning :1400mm
60
3.7. DESIGN CRITERIA - EARTHING AND LIGHTNING PROTECTION
The Earthing system will be in full compliance with Kahramaa & BS74309
Standards. Separate neutral and protective conductors will be provided
throughout the LV electrical Distribution system. Main equipotential earth bar
of copper will be mounted in the low voltage switchboard room. MV
switchgear frame and the LV switchgear frame will be connected to the main
earth bus bar by using bare conductor. Transformer neutral and generator
neutrals will be earthed separately.
The LV switchgear neutral will be connected to the main earth bar by means of
a bare copper conductor suitable sized in accordance Regulations. The main
earth bar will have two separate earth paths via test links and insulated copper
cables connected with the earth electrode.
The main earth source will be designed in accordance with site conditions and
to meet the requirements of the Regulations. The Earthing system will be
achieved with earth electrodes interconnected with underground bare copper
conductor in a loop.
The earth source must have an overall resistance value not exceeding 1 ohm
measured during the dry summer season
All Earthing stakes (rods) will be installed to a minimum of 2 meters below the
summer water table in accordance with KAHRAMAA regulations and Section
21, Part 22 of the QCS.
61
EARTH for Light Current Systems
Lightning protection shall be with 18mm copper bond Earth rod, inspection pit
with concrete protection cover, 95mm² Inter connection cable for earth
pits,25x3mm Copper tape, 2000mm multiple point Air termination rod with
base, clamp for rod to cables/tapes as indicated in the design drawings.
Earth electrode pits and hence earth electrode rods, installed as close as
practical to the positions shown on the drawings.
Each connection to the earth electrode made in a purpose made pit with a
removable concrete inspection cover.
Standalone Analogue addressable fire alarm control panel, fire alarm repeater
panel/LCD annunciator, photo electric smoke detectors, heat detectors, duct
mounted detectors, line isolators, various addressable interfacing modules,
manual break glass call units, fire alarm bells/sounders, bells with strobe light,
power supplies & in built battery backup for 48 hours, etc.
62
HVAC system
All equipment proposed and planned for use must have proper listing and/or
approval from the nationally recognized agencies listed below:
1) UL Underwriters Laboratories
2) FM Factory Mutual
6) The cables used for fire alarm system shall meet the following
standards:
All the equipment shall operate reliably under the environmental conditions
mentioned on 7.4.2
The Main Fire Alarm Control Panel (MFACP) shall be located at the security
control room, with secondary FA panels to be located at the ELV room of each
LIU.
Optical type addressable smoke detectors will be provided throughout the LIU
and offices areas. Break glasses will be provided at all floor exits with
maximum 30m spacing. Heat detectors will be provided in pantry & kitchen.
Infrared flame detectors will be provided in generator room. Ceiling voids over
63
800mm height will be equipment with additional void detectors. Sounders and
light flashers will be provided at exits and designated areas.
Mounting Height:
Each warehouse/LIU
Plot entrances and exit gates
Plot truck circulation area
Plot perimeter wall
The CCTV system Control Room monitors will be located in security Room at
gate. The Equipment room will be located at CCTV Room and will provide 24h
access to MOI personnel. Access control of entrances and critical rooms will
be considered.
All cameras high performance based on motion detector alarm System will
contain a program capable of simultaneous recording, playback, storage,
copying and remote access without any adverse effect on any of the functions.
Management software will provide camera number, location, Date & time of
recording generated by system server, forced masking (password protected) in
recorded video and alarm management. Images recording and storage
system's performance will be checked daily.
64
Cameras used in the system will cover the required field of view and its details
day and night.
System will have sufficient storage system for all camera recordings for a
period of 120 days, in MPEG-4 or H.264 format or better quality compression
techniques. The recording frame rate and resolution will be programmable
from the user level. It will give the ability to customize also quality of the video
output based on the viewing needs and storing capacity.
Cameras used in the system for outdoor and indoor specific areas will have
Auto-iris, Auto- ICR, Auto-exposure, Backlight compensation, Wide Dynamic
Range, Contrast Enhancement, Digital Noise Reduction, Digital Image
Stabilization, Privacy masking, Motion detection, Digital/Optical zoom, Multiple
Gain Control, White Balance, Intelligent Video Analytics, and Audio.
Sufficient High quality infrared camera will be used in full dark areas.
A single CCTV operator will monitor no more than nine (9) camera displays at
any one time in a standard 32" wall screen. At any given circumstances, the
number of cameras per display screen will depend primarily as the size of the
screen. A separate viewing displays or area may also be required for
reviewing recorded video.
A single CCTV operator will monitor no more than nine (9) camera displays at
any one time in a standard 23" Desktop screen.
65
CCTV system will be an integral part of the whole IP based network
Infrastructure system.
The network infrastructure will be able to carry a high quality, high resolution,
real time video in a converged voice/video and data network.
The system will also support NTP (network time protocol) to synchronize the
system time of the video to a reference time for time stamping.
System will have full function control unit Joystick control unit and touch
screen feature if its available) including keyboard and mouse facility to use
with.
The system will ensure that the image and video being produced is
tamperproof and cannot be altered. The recording shall have an audit trail
feature.
The system will also allow for backup of specific data on any drives like
CD/DVD/Blue Ray Recorders or any other device in a format which can be
replayed through a standard PC based software. Log of any such activity
should be maintained by the system which can be audited at a later date.
The recorded video will be exported in its native file format (i.e. without
converting between formats) to maintain image quality and no additional
compression should be applied during the export process.
The system will have a UPS backup power to run the whole system for NOT
less than one (1) hour in case of power failure
The system will have a hot standby system with automatic changeover in case
of any fatal failure in the active system.
The CCTV system infrastructure shall be an individual ICT network with the
same characteristics as described in par.7.11.
The Access Control System shall be installed for ultimate reliability and
maximum operating efficiency using only the highest quality, fully field proven
products.
66
The system shall be at the time of installation, listed by Underwriters
Laboratories listed for UL 294 Access Control Systems, and UL 1076
Proprietary Burglar Alarm Systems or approved equal.
System shall be interfaced with the fire alarm system of the building in order to
operate the door locks automatically in case of fire as per Company approved
cause and effect logic and fire philosophy.
System shall be interfaced with the CCTV system for real time viewing of
CCTV camera outputs to be used for ID verification.
The contact less smart cards of the system shall have an art work imprinted on
it based on the design provided by the end user and approved by the owner.
System shall support full backward compatibility such that future expansion
and up gradation is possible without replacing any of the existing components
and making major changes to the existing system.
The system shall be modular in nature, and shall permit expansion of both
capacity and functionality through the addition of control panels, card readers,
and sensors.
67
The system shall incorporate the necessary hardware, software, and firmware
to collect, transmit, and process alarm, tamper and trouble conditions, access
requests, and advisories in accordance with the security procedures of the
facility. The system shall control the flow of authorized personnel traffic
through the secured areas of the facility.
The user interface at the host computer (server) and at the operator
workstation terminal computers shall be a mouse driven graphical user
interface (GUI) allowing the user to open and work on multiple windows
simultaneously.
Communications between the controller(s) and the host server shall be via
Ethernet TCIP at 10/100Mbps. There shall be an alternate communications
path to the host via a secondary IP address such that in the unlikely even the
primary IP address/network is down an alternate communications path may be
established. Communication between controllers shall be by RS 485/RS-422
as per manufacturer’s standard.
The Access Control system shall be installed at the following rooms in the
complex:
Generator Room
Main LV Room
CCTV Room
IT Room
The system shall be autonomous for each LIU. The site Access Control
system server shall be installed in the IT Room and the system WS inside the
security room(s) at the entrance of the plot.
68
CCTV
Access Control
a) RJ45 outlets
b) Horizontal Wiring
c) Intermediate Distribution Frame (IDF)
d) Riser Cable Wiring
e) Main Distribution Frame (MDF)
f) Mounting Boards and Cabinets
g) Outdoor Cabling
The incoming telecom supply point from TSP (Ooredoo) for the complex shall
be the IT room. The Room shall be designed according to following Ooredoo
Design Guidelines:
The following standards shall be applicable for the system design and
installation:
69
3.11.1. Design Considerations
For each LIU a complete and individual structure cabling and ICT network
shall be provided
In each LIU individual ICT Ethernet Switches shall be provided for Data
Services
For each LIU individual incoming telecom lines shall be provided from the
Telecom Service Provider (TSP) according to the tenant’s requirements. The
provision of the lines shall be responsibility of the TSP. The plot developer
shall provide only telecom ducts and manholes according to Ooredoo
requirements for cabling routing form IT Room to the ELV room of each LIU
At each LIU ELV room space for TSP Distribution Frame shall be allowed
Wi-Fi access points shall be provided for office & warehouse areas
UTP cables, Patch Panels and RJ-45 outlets shall be cat7 category equipment
Backbone Fibre Optical cables will be 50/125 multi-mode optical fibres (MMF),
or four 10 micron single mode optical fibres (SMF), 1270 to 1355 nanometre
light wavelength with SC connectors 100Base –FX.
Ethernet switches will receive the incoming services from wide area network
infrastructure (TSP Router/ Telecom Line, etc.) and distribute to the other
switches or to users serving the CCTV and Telephone TCP/IP networks.
70
The switch shall be equivalent to ‘’Cisco Switch - WS-C2960X-24PS-L,
Catalyst 2960-X 24 GigE PoE 370W, 4 x 1G SFP, LAN Base, Smart net
8x5xNBD Catalyst 2960-X 24 or approved equal according to specialist vendor
design for CCTV and IT services
Offices : 450mm
Warehouse : 1250mm
71
The above should be reevaluated during schematic and detailed design.
For provisional reasons the installation of spare raceways and conduits from
the ELV room of each LIU and the installation of underground ducts from each
ELV Room to the facility IT Room shall be utilized.
1. Lighting. LED vs. Fluorescent or Son-T light fittings. The adoption of LED
fixtures throughout the facilities provides high quality of illumination and
extended life cycle of fitting with minimum power demand. The expanded
usage of LED technic for the past years has led to cost levels which are similar
with conventional lights.
2. Transformer. Dry Type vs. Oil Type. Dry type transformers require reduced
maintenance compared with oil-type, and limited space allocation. Because
dry type transformers have larger load utilization factors compare with oil type,
the same demand load can be served with a smaller size transformer.
72
3.14. ELECTRICAL LOAD CALCULATIONS
Based on the above described criteria the detailed design electrical load calculations for LIU WH-04 are shown on the
following table:
PA-WH-04
Load Type Lighting (W) Centralized Pow er Air UPS PUMPS Lighting (W) Pow er Sockets Water Heater (W) Cooker (W) Air Conditioning PUMPS (W)
Em ergency Sockets (W) Conditioning (W) Device (W) (W) (1.0) (W) (W) (1.0)
TCL (W) MDL (W)
Connected Load/ Maximum CL MDL (0.6) CL MDL (0.6) CL MDL (0.6) CL MDL (0.9) (1.0) CL MDL (0.6) CL MDL (0.6) CL MDL (0.3) CL MDL (0.4) CL MDL (0.9)
Demand Load TCL (W) MDL (W)
WARE HOUSES NA 0 36,800 22,080 40,000 36,000 NA 264,140 219,144 49,440 29,664 67,200 40,320 NA 0 NA 0 318,000 286,200 1,332,546 1,049,032
Adm inistrative 20,261 12,157 NA 0 56,000 50,400 48,000 22,586 13,552 107,700 64,620 56,000 16,800 48,000 19,200 399,480 359,532
4,800 2,880 NA
MECHANICAL 250 150 1,500 900 NA 0 9,900
Based on the above described criteria the detailed design electrical load calculations for LIU WH-07 are shown on the
following table:
PA-WH-07
Load Type Lighting (W) Centralized Pow er Air UPS Device (W) (1.0) PUMPS (W) (1.0) Lighting (W) Pow er Sockets Water Heater (W) Cooker (W) Air Conditioning PUMPS (W) (1.0)
Emergency Sockets (W) Conditioning (W) (W) (W)
Connected Load/ Maximum Demand CL MDL (0.6) CL MDL (0.6) CL MDL (0.6) CL MDL (0.9) CL MDL (0.6) CL MDL (0.6) CL MDL (0.3) CL MDL (0.4) CL MDL (0.9)
Load TCL (W) MDL (W) TCL (W) MDL (W)
WARE HOUSES NA 0 18,400 11,040 42,000 37,800 NA 171,654 143,722 78,720 47,232 35,200 21,120 NA 0 NA 0 371,000 333,900 1,034,139 833,329
Administrative 10,267 6,160 NA 0 28,000 25,200 24,000 14,445 8,667 64,400 38,640 28,000 8,400 24,000 9,600 246,720 222,048
2,400 1,440 NA
MECHANICAL 250 150 1,500 900 NA 0 9,200
73
The UPS loads for WP-04 are shown on the following table:
ICT/CCTV
Total
Functional Area Power Total Demand
DF Connected
/ Building Area Demand Power (W)
Power (W)
(W)
Security
1,000 1 1,000 1,000
Room
CCTV/IT
15,000 1 15,000 15,000
Room
The UPS loads for WP-07 are shown on the following table:
ICT/CCTV
Total
Functional Area Power Total Demand
DF Connected
/ Building Area Demand Power (W)
Power (W)
(W)
Security
1,000 1 1,000 1,000
Room
CCTV/IT
15,000 1 15,000 15,000
Room
74
Total 56,000 56,000
Transformer selection
a. Plot WP-04
b. Plot WP-07
a. Plot WP-04
75
b. Plot WP-07
a. Plot WP-04
b. Plot WP-07
UPS Selection
a. Plot WP-04
A. ICT
76
4. Total LIUs for WH-04:16
5. UPS size per LIU according to standard market products: 8 kVA
B. CCTV
b. Plot WP-07
C. ICT
D. CCTV
3.15. CALCULATIONS
The detailed design lighting calculations are shown on the below documents:
77
EZ01-CW04-QBEC-ELE-DWG-000017 DAYLIGHT & LIGHTING CALCULATIONS FOR PA-WH-04
The detailed design electrical power system calculations are shown on the
below documents:
78
3.16. EMPLOYERS DESIGN BRIEF VALIDATION
79
power and switchgear shall be sufficiently sized to facilitate
the electrical power demands stipulated in the Plot Control
Sheets for the different sizes of LIU Buildings. The
Contractor shall coordinate connection to the 11KV supply
at the Utility Connection Point directly with KAHRAMAA /
Principal Contractor.
In both above cases (c) & (d), Smart metering shall be
A-16 COMPLY
provided as per KAHRAMAA Standards and Specifications.
415V non-essential distribution systems with, including
metering as per KAHRAMAA requirements, and power
factor correction of 95% to be provided as per the table:
A-17 ‘’Table 2: Non-Essential Distribution Systems Panel’s COMPLY
Requirement’’
of document 2.01A - Employers Requirements for LIUs.
Part B, Section II of IV
Contractor shall provide full lighting to the Industrial floor
area, designed and installed per Lighting Standard of
Chartered Institution of Building Services Engineer (CIBSE)
A-18 COMPLY
requirements. Emergency Lighting to be provided for all
areas, including the Industrial Floor space/ areas in
accordance with QCDD, QCS and Code requirements.
Fault level calculation shall be submitted for the electrical
distribution system. If the fault level calculations are higher
A-19 than what has been indicated in table above shall be COMPLY
followed otherwise the fault level in the above table shall
be as a minimum
General Space Lighting to be provided for the Industrial
A-20 Floor space/ area and also to the loading zone internally COMPLY
and externally.
Emergency Lighting and Exit Signage to be provided as per
A-21 QCD 2014 requirements and BS 5266 for space not covered COMPLY
by QCDD/NFPA
Fire Detection and Alarms to be provided as per
QCDD/NFPA requirements and to be integrated with
A-22 COMPLY
sprinklers and other third party mechanical/ELV/Electrical
systems as required.
A-23 Lightning Protection to be provided as per BS EN 62305 COMPLY
Cables and wires to be low smoke and fume type
A-24 COMPLY
(LSF/LSOH), or fire rated where required by QCDD.
Conduits and cable trunking to be galvanized steel. PVC
A-25 COMPLY
Extra heavy duty conduits only to be used where embedded
80
in concrete with suitable cover
Complete earthing system for Electrical and clean earthing
A-26 for ICT/ELV shall be designed and installed as per the COMPLY
relevant BS/EIA/TIA/ KAHRAMAA standards
All Electrical calculation not limited to Fault, short circuit &
cable calculations as per BS 7671, Lighting (Normal &
Emergency), Power factor correction, Voltage drop,
A-27 COMPLY
protection coordination, Lightning protection etc. and any
other calculations requested by the Engineer shall be
submitted for review and approval / NOC.
Load calculations for both total connected and maximum
A-28 COMPLY
demand shall be performed
Emergency lighting to be provided as per QCDD
A-29 COMPLY
requirements.
Fire Detection and Alarm System per NFPA Code and QCDD
A-30 COMPLY
requirements.
Provide appropriate ducting for all telecom networks from
tie-in points at Plot Boundary to outlet panels located
A-31 internally in each of the individual light industrial units and COMPLY
Logistics Buildings. Works to include all necessary manholes
and chambers.
Main Warehouse
The warehouse lighting (open area and in aisle) shall be
designed to provide a minimum 300 lux, measured 1m
above the floor slab, measured on the horizontal plane. The
uniformity ratio of 0.8 should also be achieved. The high
level fluorescent luminaire should be the Verteco fitting
A-32 manufactured by Dexeco Ltd, T5 mercury tubes, or similar COMPLY
equal approved by client, to include integral sensor options
for both presence detection and daylight control (open area
or in aisle version). The fittings should fully dimmable,
designed to be used up to 8m and fully programmable from
ground level. Work areas (as determined by the EMPLOYER)
to be provides with 400 lux as minimum.
B. MIXED USE OFFICE/ WAREHOUSE FACILITIES
Power/ telephone & data outlets minimum requirements at
Administrative Space
1. the estimated number of employees is 200, for each
B-01 COMPLY
employee the CONTRACTOR
to provide 1 floor box complete with all connections,
sockets/ outlets etc. contains
81
the following electrical/ IT/ utilities requirements:
A. 2 no 240v power outlets for small power,
B. 1 no 240v power dedicated computer outlet,
C. 1 no telephone terminal, CAT 7,
D. 1 no data terminal. CAT 7.
2. Additional floor boxes equal to 20% of the employees’
number to be provided for
common areas, meeting rooms etc.,
3. Wi-Fi, to cover all the Administrative Space.
The floor boxes to receive a finish of the same type of the
space it is located in.
Power/ telephone & data outlets minimum requirements at
the Warehouse
B-02 1. Minimum 75 no twin socket power points. COMPLY
2. Minimum 60 no data points, CAT 7.
3. Wi-Fi to cover all the warehouse area.
Provide new electrical main incoming service Substation
connected to main 11 kV network to feed the new building
B-03 including provision of new MV panel, transformer(s) and COMPLY
main switchboard of suitable size for the building load and
as per Kahramaa regulations
Provide main switch panel complete with “Automatic
B-04 Transfer Switch” (ATS) to receive an auxiliary power supply COMPLY
from the emergency diesel generator
Provide all necessary metering equipment at main panel
B-05 and secondary sub–metering equipment at all principal sub COMPLY
distribution panels
Provide Emergency Diesel Generator system sized to
B-06 accommodate for the building maximum demand in case of COMPLY
main power supply failure
All electrical cabling to be distributed properly supported in
B-07 cable trays. Distribution panels shall have sufficient capacity COMPLY
for the designed circuit installation plus 25% spare.
Provide suitable quantity and type of power outlets
B-08 COMPLY
internally
Provide suitable quantity and type of power outlets
B-09 COMPLY
externally.
Provide outlets throughout the warehouse allowing for the
following:
B-10 COMPLY
1. 1 no single phase 240v outlet per 200sqm floor area in
warehouse.
82
2. 2 no single phase 240v outlets at each vehicle loading
door.
3. 1 no 60 amperes three phase isolator for compactor.
4. 3 phase 100 ampere dedicated switch panel in Battery
charge room and supply for connection to charging
equipment. (Charging equipment supplied by others).
5. 5 no single phase 240v outlets in battery room/ area for
workshop tools.
6. 3 phase 60 ampere 415V isolators on mezzanine floor
allowing 1 per 500 sq.m floor area.
IT HUB ROOM
Provide clean electrical supply to 15 no power outlets and
B-11 COMPLY
battery powered emergency lighting in event of mains
lighting failure
Main Administration Offices
Provide outlets throughout the office areas allowing for the
following: COMPLY.
• Integrated 3-compartment PVC trunking to office Design based
workstations with 3no 240v power outlets for small power in LED
and 1 no dedicated computer circuit fitted at max spacing lighting
B-12
3.0m. Trunking to be fitted to a minimum of two walls in fittings with
each office. the same or
• Single power outlets in corridors, social rooms for better
cleaning purposes according to normative. performance
• 4 no power outlets in Kitchenettes.
• 3 phase 60 ampere 415v isolator in Canteen.
Main Administration Offices COMPLY.
The required lighting intensity is 500 lux. Offices, meeting Design based
room areas to be provided with fluorescent T5 tube in LED
lighting, Category 2 luminaries set flush and integrated into lighting
B-13
suspended ceiling systems. Luminaries to be suitable for fittings with
VDU applications, automatically switched by PIR presence the same or
detectors. better
performance
Ancillary Rooms
The required lighting intensity is 100 lux Provide low energy
B-14 COMPLY
lighting automatically switched by PIR presence detectors
to WC’s, Locker Rooms, and other amenity areas.
Battery Charging Room/ Area Requirements for Forklifts
B-15 Provide battery charging room/ area complete with the COMPLY
following equipment:
83
1. 3 Phase 100 ampere dedicated switch panel and supply
for connection to charging equipment (Charging equipment
supplied by the EMPLOYER).
2. Provide drencher facility for emergency eyewash as
Health & Safety measures.
3. Provide adequate ventilation to limit build-up of
hydrogen gas within an enclosed area.
4. Provide Wash Basin with Hot and Cold water supply.
5. Provide perimeter wall protection at low level to prevent
damage from truck forks.
6. Provide an abrasion and acid resistant coating to floor.
Fire Detection System
1. Provide a fully, addressable and integrated Fire Alarm/
Fire Detection System throughout the building complete
with zone control panel. The system shall generally
comprise:
• Heat/ smoke detectors to offices, storage, corridors and
B-16 social rooms. COMPLY
• High level optical beam detectors to warehouse storage
areas.
2. Provide a secondary repeater panel in the site’s Security
Gatehouse.
3. The main panel is to include “Pump Run Alarm”
interfaced to the fire pumps in the sprinkler pump house.
Telephone System
1. Provide appropriate ducting and cabling for all telecom
networks from tie-in points at Plot Boundary to outlet
panels located internally.
B-17 COMPLY
2. Provide appropriate structural cabling including
termination, patching, flux test PAPX- telephone system to
be IP based. Works to include all necessary manholes and
chambers.
IT System
Provide appropriate raceways and cabling for the IT system
B-18 COMPLY
incl. Termination, Patching, Flux-Test. Data cables shall be
CAT7 IT equipment shall be installed by EMPLOYER.
Intruder Alarms
1. Provide a zoned infrared Intruder alarm installation to
ground floor offices with openable windows.
B-19 COMPLY
2. Provide zoned intruder alarm to warehouse building,
comprising surface mounted magnetic contactors to all
external vehicle and personnel entrance and escape doors.
84
Swipe Access
Provide a raceways and cabling for swipe card access
control system within the office areas. Include for the
B-20 COMPLY
control of a maximum of 30 doors. Equipment like
biometric readers, magnet locks, card readers, will be
provided by EMPLOYER.
CCTV / MOI Requirements:
Contractor shall provide complete raceways, power and
control cabling for internal and external CCTV & security IP
system, including a centralize security room internally.
Equipment like camera, server, storage and applications are
B-21 by EMPLOYER. COMPLY
Minimum number of CCTV data points (IP system):
Internal: 100 CCTV data points (majority in warehouse
area),
External: 30 CCTV data points, on fences, boundary walls,
gates, etc.
UPS Requirements:
Contractor shall provide complete UPS system, size 70 KVA,
B-22 COMPLY
complete with battery & distribution panels, wiring. Battery
capacity shall be sized for minimum of 15 minutes.
85
4. EXTERNAL DRAINGE
4.2. EXTERNAL DRAINAGE SYSTEM
Gradient for drainage pipes shall strictly comply with ASHGHAL requirements
& provisions of QCS.
First manhole at the head of the line will be vented. This manhole shall be
vented to the roof of the building.
All the external foul and waste water drainage pipe work shall be U-PVC to BS
EN1401-1.
The minimum size of building external drainage gravity pipe line shall be
160mm diameter.
The hydraulic design of the sewers has been undertaken using the Colebrook-
White equation as given below:
Ks 2.51
V 2 (2 gDi) log( )
3.7 D D (2 gDi)
Q AxV
Where:
D - bore of pipeline;
86
g - gravitational acceleration;
Q - discharge;
V - velocity of flow;
i - hydraulic gradient
- Kinematic viscosity;
x - Multiplication factor.
The proposed storm drainage system for building’s flat roof run-offs shall be
discharged in roof outlets or drain, and for the sloped roof run-offs shall be
discharged in roof rain water gutter and collected through storm water
downpipes to the nearest storm water manhole proposed.
Surface water collected from the area drains and channel drains, at side or
provided in the Potable & Irrigation Pump room, etc shall be collected through
a separate piping network which will be discharged directly into the proposed
surface water manhole distribution system in the site.
The storm water at car parking area shall be proposed with car park drains.
Car park drains shall be heavy duty cast iron with sediment bucket. Surface
water shall be collected through a separate piping network and discharged into
the grease & oil interceptor before discharging it to the proposed surface water
manhole distribution system in the site.
All the internal and External surface water drainage pipe work shall be U-PVC
to BS EN1401-1.
87
4.4. Storm Water Design
The storm water shall be directed through piping system network, catch pits
and series of manholes and shall be discharged to the Existing Main network.
The proposed surface water network design will be based on the following
design criteria and methodology, according to Ashghal Drainage Design
Manual for Storm Water:
Runoff coefficient C:
Intensity I
Storm intensity figures will be in accordance with the Storm Profiles adopted
by Public Works Authority, Drainage Affairs as shown in the following table:
88
56. 67. 78. 94. 108. 125.
5
1 8 2 4 9 7
10. 12.
3hrs 7.6 9.2 14.8 17
6 8
89
All stormwater gravity drainage pipes will be designed to have a self-cleansing
velocity of not less than 0.75 m/s at full-bore free discharge.
Depth of Pipes
The minimum cover to surface water pipes will be 600 mm in non-traffic areas
and 1200 mm in traffic areas. Where less cover is unavoidable, it will be
necessary to provide protection to the pipes from both normal and construction
traffic.
Manholes
90
5. ROADS
5.2. Road Design Basis & Criteria
This section presents the proposed design basis/criteria and standards that
shall be followed for the roads design within plots. The criteria govern the
minimum parameters that should or may be used in developing the horizontal,
vertical and pavement design.
The criteria are dependent upon a number of factors including the following:
Size of the largest and heaviest vehicle that will commonly use the
facility.
The level of safety, functionality and comfort desired for the facility
under design.
The roads design shall be prepared in accordance with, but not limited to, the
following Design Manuals and Technical Notes:
The structural design of heavy duty pavements for ports and other
industries, edition 4, 2008
The road network within the proposed plot will be of one way roads with
separate gate Entrances and Exits for Trucks and Cars.
For the car parking aisle and Truck yards only vehicle manoeuvrability
is considered.
91
a. Internal Roads
Internal roads are designed as Wider Single Lane one or two way movements
as required for the truck maneuvering.
- Horizontal Alignment
Design Speed
N/A
Median Width
N/A
The proposed Road Cross Sections was developed to ensure capacity and
safety within the designated facility service plot limits and to ensure
accessibility to new facilities structures finished ground level.
Vertical Alignment
92
o Minimum Longitudinal Slope 0.30%
b. External Footpaths
The external footpaths around the plots as per the master plan
layout guidelines will be provided including tiles, concrete
pavers, hardscaping & softscaping, cross over points, traffic
bumper, protective bollards, and signage as per
Ashghal/Municipality requirements and as per Master Plan
Guidelines
c. Pavement structure
The pavement design will be as per QHDM, with the following design criteria:
93
o Axle Load: 13.5 tonnes gross axle weight
The pavement design will be based on the Existing & Fill Soil Parameters,
Traffic loading Assessments and Drainage conditions.
The Proposed pavement structure for the landing strip and access roadways
for Trucks will be concrete roadway.
- Sub Grade
The proposed pavement structure for the car parking Aisle and access
roadways for cars will be Asphalt roadway.
- Sub Grade
The proposed pavement structure for the car park areas will be precast paving
block.
94
- Granular Sub Base Course (200mm thick)
- Sub Grade
Front-In 620mm
Rear-In 900mm
e. Cul-De-Sac
95
Min. Pavement Width
6.0m
f. Junctions
General
o At grade T-Junctions
o 90 degree bends
Design Vehicle:
The expected vehicles likely to require access to the designated site such as
Warehouses, Light industrial units on a daily basis are:
o Passenger cars
So to cater for the various vehicles to use the road network, turning radii
proposed for the road layouts and proposed landing strip will be verified. And
design vehicles will be chosen to carry out the swept path analysis for service
vehicles (WB-12), passenger cars, and emergency vehicles. Swept path
drawings of these vehicles will be provided accordingly. Please refer section
4.2 for detailed traffic study report.
A separate report for traffic study is provided in section 4.2 to cover the
parking requirements, swept path analysis and Impact on external road traffic
etc.
96
5.2.5. Roads Traffic Sign and markings
5.3.1. Abstract
This traffic study was made for Plot Number 07, RAS BUFONTAS, Qatar. The
plot is intended to be a multi-purposes stores. The plot is divided into 8 stores.
Each store requires at least a space for one truck, and 3 private cars parking
bays for the administration. The internal roads should accommodate fire trucks
in case of emergency conditions. The study showed that the proposed design
can satisfy the function of the plot.
5.3.2. Introduction
In this report, a traffic study of plot 07 is introduced. The traffic study is divided
into two major parts. The first one is considering the internal circulation and all
internal traffic statistics, and the second part is considering the impact of the
traffic using the site on the adjacent roads.
Three types of traffic units might use the plot. Trucks, passenger cars, and fire
trucks. The dimensions of each unit were considered according to the
AASHTO green book. As follows.
Trucks
97
The trucks which expected to use the plot are of model WB-12 and according
to the AASHTO green book having the following dimensions:
The turning radii of the different turns are governed by the following AASHTO
template
Firefighting Trucks
98
The trucks which expected to use the plot are of model pumper fire truck which
have the maximum dimensions of a fire truck and according to the AASHTO
green book having the following data were obtained:
The turning radii of its different turns are governed by the following AASHTO
template.
99
Figure 4: Dimensions of the expected firefighting truck to AASHTO
Private Cars
The private cars which expected to use the plot are of model SUV and
according to the AASHTO green book having the following dimensions:
The turning radii of the different turns are governed by the following AASHTO
template.
100
Figure 6: Template of turning radii of passenger cars
This part of study is considering the internal condition of traffic for heavy
trucks, passenger cars, and the fire trucks. The study shows the counts of
vehicles that might be accommodated in this plan, and the adequacy of the
available space for handling, maneuvering of goods.
The master plan of the plot 07 is divided into two major zones. The first zone
serves the commercial vehicles. The second zone serves the passenger cars.
Each of the two zones’ movement is in one direction.
101
Figure 7: The distribution of traffic zones according to function
When we put an eye on the private cars parking zone; to see the main
direction of movement, the entrance and exit; it might be illustrated by the
following sketch:
Figure 8: Travel Direction, Entrance, and Exits for Zone of Passenger Cars
Parking
For the trucks parking and maneuvering zone; the main direction of
movement, the entrance and exit might be illustrated using the following
sketch:
102
Figure 9: Travel Direction, Entrance, and Exits for Zone of Heavy Vehicles
The traffic counts might be showed in the following chart which summarizes
the capacity of the available areas if used for parking purposes. The traffic
counts show that the available space can cover the traffic which is expected to
use the plot.
According to the previous table, the minimum number of required spaces for
trucks should be equal to the number of stores which is 8. The actual available
number for trucks parking and maneuvering is 10 which is greater than the
minimum by about 25%.
For Passenger cars, there no universally known rates for calculating the
number of parking units required for such type of structures. Some American
103
specifications says that it should be not less than 1 parking bay for each 100
square meters of the administrative buildings.
The people having disabilities are taken into the account. One parking bay with
ramps leading to the platform was planned to be there to serve 3.13% of the
parking users.
Maneuvering Speeds
The speed used for validating maneuvering for different vehicles were
assumed to be 5 km/hr when moving forward, and 2.5 km/hr when it moves
back during the maneuvering.
As it might be noted from the next figure, there are 8 trucks serving the stores,
also there are 2 parking bays might be used as a maneuvering bays for
changing the direction of movement of any truck, or in case of saturated traffic
capacity of stores; it might be used as holding bays.
104
Here are some samples for the trucks maneuverings. All maneuverings were
tested using simulation softwares. The chosen maneuverings are
representative for all the rest of maneuverings and give an idea about how
adequate is the available space for the trucks’ maneuverings.
The truck comes from the position number 1 to enter the gate of the plot until
reaching position number 2, then stops and begin to move backwards until
reaching the platform at position 3. After the end of the truck’s mission it
begins to move forward and getting out the plot from the plot exit gate and
then join the traffic of the main external road at position 4.
As a sample for these trucks, truck number 3 was chosen to introduce the
maneuvering procedures.
105
Figure 12: Maneuvering of truck number 3 as sample of trucks (2 to 6)
The truck comes from the position number 1 to enter the gate of the plot until
reaching position number 2, then stops and begin to move backwards and
turning perpendicularly until reaching the platform at position 3. After the end
of the truck’s mission it begins to move forward and getting out the plot from
the plot exit gate and then join the traffic of the main external road at position
4.
The truck comes from the position number 1 to enter the gate of the plot until
reaching position number 2, then stops and begin to move backwards and
turning perpendicularly until reaching the platform at position 3. The truck after
that moves from position number 3 to position number 4. The truck then
moves backwards from location 4 to location 5 at with the truck mission
(loading| unloading) starts. After the end of the truck’s mission it begins to
move forward and getting out the plot from the plot exit gate and then join the
traffic of the main external road at position 6.
106
Figure 14: Maneuvering of truck number 8
The truck comes from the position number 1 to enter the gate of the plot until
reaching position number 2, then stops and begin to move backwards and
turning perpendicularly until reaching the platform at position 3. The truck after
that moves from position number 3 to position number 4. The truck then
moves backwards from location 4 to location 5 at with the truck mission
(loading| unloading) starts. After the end of the truck’s mission it begins to
move
forward and getting out the plot from the plot exit gate and then join the traffic
of the main external road at position 6.
107
The passenger car comes from the position number 1 to enter the gate of the
plot until reaching position number 2, then stops and begin to move backwards
and turning perpendicularly until reaching the parking bay at position 3. After
the end of the passenger car’s mission it begins to move forward and getting
out the plot from the plot exit gate and then join the traffic of the main external
road at position 4.
The maneuvering study shows that all the used curves have sufficient
curvature to satisfy safe turnings in the movement directions for the traffic units
that use the curve. The curbs also were checked to be away enough from the
swept path of the different vehicles.
Although the external traffic study is out of scope of this project. The internal
traffic study showed that the spaces available for the traffic which is intended
to use the plot is sufficient for accommodating such traffic. Accordingly, we
expect no or limited impact of the internal traffic on the external traffic;
108
especially because no waiting of any traffic units, and no maneuvering actions
will be made outside the plot gates.
Conclusion
109
5.4. Site Grading Report
5.4.1. Abstract
This study was made for Plot Number 07, Abo-Fentas, Qatar. The plot is
intended to be a multi-purposes stores. The plot is divided into 8 stores. The
existing roads that located on the external perimeter of the plot showed
relatively great levels variations. The report recommends making some fill
work in order to make an effective and serviceable solution.
5.4.2. Introduction
In this report, a study of the exiting levels of plot 07 is introduced. The grading
study of plot 07 is divided into two major sections. The first section introduces
an analysis of the existing situation of the plot levels. In the second section, a
leveling proposal will be introduced.
Site Overview
The site shows tangible variation of the existing levels the variation shall be
evaluated by 0.9m. The following figure shows the variation of the levels.
110
Figure 17: The existing levels of plot 07
18%
16%
15%
14%
11%
9%
7%
6%
5%
4.7 - 4.8
4.8 - 4.9
4.9 - 5.0
5.0 - 5.1
5.1 - 5.2
5.2 - 5.3
5.3 - 5.4
5.4 - 5.5
5.5 - 5.6
Figure 18: Area of Each Level as a Percentage of the total plot area
111
The previous statistical analysis gives an idea about the exiting levels of the
plot. We might detect that more than 60% of the area of the plot have levels
exceeding 5.1m up to 5.6
Property Value
The levels of the external roads at gates is illustrated in the following figure. It
is worth to be said that the levels of the internal roads must meet this levels at
the gate.
112
5 4
. .
3 8
5 7
m m
5 5
. .
5 1
Figure 19: Levels of external roads at plot gates
0 5
m m
5.4.5. Proposal of Grading
The road levels are chosen to satisfy the following criteria as possible:
The slopes of the interior roads should drain the storm water and the
rain fall and other water out of the plot.
The interior road levels of the plot should be designed for prohibition of
any water to enter the plot.
The interior road levels should meet the levels of the surrounding
roads network especially at gates.
113
Proposed Roads Grading Profiles
The following plan & profiles shows the proposed levels that satisfies the grading criteria introduced in 1.1.5.1
114
Grading of Passenger Cars’ Road
115
Conclusion
The proposed design of the road levels is reliable and satisfies the serviceability of the plot. The
site requires some kind of fill earth work in some places.
116
6. STRUCTURAL
6.2. INTRODUCTION
The document covers the schematic and detail design procedure for the Light Industrial and
Logistics Unit WH-PA-04 and WH-PA-07 at Ras Bufontas Economic Zone (QEZ-1) according to
QCS 2014, local standards and as per Tender number EZ00-CW02-TND-16 Part B, Section III,
Minimum Requirements for Civil & Structural design.
117
RC
structure Right part of WH-PA-07
118
RC structure Middle part of WH-PA-07
The light industrial and logistic unit at Ras Bufontas economic zone comprises storage areas as
well as administration areas.
The main materials selected for the structure are structural steel and reinforced concrete,
materials readily available, economic and in wide application in local construction.
Specifically, the super structure covering the storage areas is studied as a steel structure, as
the appropriate lightweight economical solution for achieving the large spans (up to 21m), and
free space required for functionality, while the administration areas are studied as a reinforced
concrete (RC) structure for ease of construction, load carrying capability and appropriate to the
119
fire safety demands of the spaces. The building design working life is considered 50 years
according to QCS specification Section-01: Part-01.
For the storage areas, the gravity loads acting on the steel structure are transferred through the
framing action of the Ordinary Moment Resisting Frame (OMRF) to the foundations. Lateral
load resisting systems in the direction perpendicular to the plane of the main framing system
are utilized to provide stability of the structure to support lateral Wind the Seismic loads (see
figures 1.1-1.3). The loads imposed by the stored items are transferred directly to the R.C. slab
on grade at the storage area. The administration areas structural systems area composed of a
traditional column, beam and slab RC structure. The following figure shows the layout of
building WH-PA-04.
WH-PA-04
120
The following figure shows the layout of building WH-PA-07.
WH-PA -07
The acting loads are determined according to BS EN 1991 Eurocode 1: Actions on Structures
and Qatar Construction Specifications QCS2014. The load actions and load combinations are
discussed in Section 6.5.1. The design procedure of steel components is carried out according
to EUROCODE 3 BS EN-1993. The design procedure of RC components is carried out
according to EUROCODE 2 BS EN 1992.
For the sub-structure, the foundation system for the steel structures is a combination of isolated
and combined pedestal footing according to the reactions computed from the super-structure
analysis. Foundations for structural RC columns in the RC building are designed as a
combination of isolated and combined. Flooring is a slab on grade, isolated from the pedestal,
ground beam and any base equipment.
The foundation is designed for the worst combination of dead, live, temperature and
wind/seismic loads. The foundation for the different structures is designed according to BS
8004:1986 Code of practice for Foundations, however they do not confirm to the Project
Specifications. Foundation is designed with a factor of safety of 2 against ultimate bearing
capacity failure of the sub-soil. A factor of safety of 2 against overturning, 1.5 against sliding
and 1.4 for buoyancy is considered in foundation stability analysis.
Permanent settlement of foundations shall not exceed 25mm and the differential settlement of
individual foundations shall not exceed 10mm. According to the Geotechnical report the
121
allowable net soil bearing capacity is 250KPa for depth of foundation 1.5m from ground level for
both the building WH-PA-04 and WH-PA-04.
6.4. MATERIALS
According to QCS2014 specification the steel grade for steel plates is according to BS EN
10025 such that, all structural steel members are of grade S355 (fy= 355N/mm2, fu=
490N/mm2).
Welding materials: confirm to AWS code and AWS filler metal specifications.
Structural concrete shall comply shall fulfill the requirements for both strength and durability
aspects, as per project specifications and geotechnical and geophysical reports. The corrosion
effects of the environment shall be taken into consideration in designing the cement/concrete
design for the project, as well as the necessary concrete protection required. Concrete cover
will be in accordance to QCS 2014 requirements. Concrete blinding will not be considered as
cover.
Cement for reinforced structures above ground level shall be Ordinary Portland Cement (OPC),
and for underground structures Sulphate Resisting Cement (SRC) in compliance with the BS
EN 197-1:2000/ BS EN 196 or equivalent standards.
According to the geotechnical report for the project the exposure class is X2 and the sulfate
exposure class extracted from tested soil/rock samples is S2.
122
Therefore the used concrete grades are:
Walls, beams,
SUPERSTRUCTURE C50 (OPC)
columns
Reinforcement steel is of high yield strength deformed bars with a characteristic strength of
500N/mm² conforming to BS4449
6.5. LOADINGS
The acting loads are determined according to BS EN 1991 Eurocode 1: Actions on Structures.
Table 1.1 shows the values of densities, dead and live loads action on the structures.
Table 6.1: Material densities, dead and live loads acting on the structures
Densities Value
123
100mm thick solid Block wall + Rendering = 3.12 kN/m²
Screed = as actual
Screed = as actual
124
Collateral at other areas = 0.15 kN/m2
Wind Load
Wind Load as per QCS 2014 provisions is given as fundamental basic wind
velocity of 27 m/s.
125
Seismic Load
The seismic design for all building structure is based upon local seismic
accelerations recommended as per BS EN 1998-1:2004. Local seismic spectral
accelerations based upon uniform hazard response spectra with peak ground
acceleration of 0.045g for 475-year return period
Earth/Water/Surcharge pressures
=100kN (Concentrated
Load)
Temperature Load
126
Notional Loads
The unfavorable effects of possible deviations in the geometry of the structure and the position
of loads are taken into consideration under “Geometric Imperfection”. This load is taken into
consideration only in ultimate limit states.
φ= φ_0×α_h×α_m
Load combinations for structural design excluding seismic design are based on the EN 1990.
Table 6.2 shows the load partial factors for ultimate limit state.
Table 6.2: Load factors and partial load factors according to EN1990
Dead Gk 1.35 1
Load
Lateral Hk 1.5 0
Earth/W
127
ater
pressure
Seismic E - - -
Such that, Ψo is a factor for combination value of a variable action and Ψ 2 is Factor for quasi-
permanent value of a variable action. Following is a list of the ultimate and service limit state
combinations used in the analysis and design of the different structural components of the Light
Industrial and Logistics Units at Ras Bufontas Economic Zone (QEZ-1):
128
6.5.2. Wind Loads Assessment
The wind loads are assessed, as minimum, as per Wind Load as per QCS 2014 results may be
obtained by calculating wind loads according to ASCE 7-05 method 2 (analytical method) such
that the basic wind speed is 38m/s and the exposure category C. Following is a summary of the
wind load application to the light structural unit of PA-WH-07 and WH-PA-04. The velocity
pressure can be calculated by the following equation
And Kz velocity pressure exposure coefficient, its value is determined according to the exposure
category (C) and the structure height from the following table:
The maximum velocity pressure at the highest point in the structure is 820 N/m 2.The design
wind pressure is calculated from the following equation:
129
Such that Gf is the gust wind factor and is taken as 0.85 and Cp is the external wind pressure
coefficient. The wind pressure distribution for mono-slope type roof structure is as follows:
The wind pressure coefficients are considered according to the wind direction and roof slope
(θ=9˚) from the following table:
130
Wind load design cases are considered according to ASCE 7-05 load case 1 and load case 3
shown in the following figure:
131
6.6. ANALYSIS AND DESIGN SOFTWARE
CSI SAP 2000 is used for the analysis and design of the steel structure. CSI ETABS and CSI
SAFE software is used for the analysis and design of RC structures. Furthermore, PROKON is
used for the design of foundations.
132
6.7. FOUNDATION DESIGN SOFTWARE
The sub-structure reactions are imported from the analysis files of the steel as well as the RC
structures. The foundation for the different structures is designed according to BS EN 1992
requirements. The PROKON software is used for the design of the foundation.
The depth of soil above footing was considered 0.75m. Weight of top soil layer (0.5m) was
neglected. The foundation analysis and design for all the sub-structures is executed
accordingly. It is worth mentioning that the serviceability limit states such as stability and
overturning are the governing load cases for most of the footings dimensions.
The foundations have been designed for allowable stresses confirming to BS 8004: 1986 Code
of Practice for Foundations. An increase of 25% was permitted in the allowable bearing capacity
for transient loads such as Wind and earthquake load combinations. This allowable increase of
25% for transient load combinations complies with BS 8004: 1986 Code of Practice for
Foundations- Cl 2.3.2.4.3 Wind loading and also with BD 74/00 Foundations Cl 2.3.2.4.3 Wind
loading.
The analysis of the super structure is divided into two models; a SAP2000 V18 model for the
steel structure and an ETABS/SAFE model for the RC structure. For all steel structures the roof
covering system consists of purlins and double layer steel sheet roof.
The structural system of the steel structure consists of a main frame of saw tooth type spaced
at 7.35m and of span 21m. The main structural system is illustrated in Figures 6.1 and 6.2. The
main structure also supports lateral loads such as wind and seismic loads acting in its plane.
Figure 6.3 shows a plan for the main structural system. The out-of-plane lateral loads are
supported the bracing structural system shown in Figures 1 and 2. The steel components
design is carried out according to the BS EN 1993 specifications and the load combinations
mentioned in Section 6.4. Figure 6.4 shows the design interaction results from the SAP2000
model and all interactions are below 1.
133
Figure 6.1: 3D SAP2000 model for the WH-PA-04 plot Part 1
134
Figure 6.4: 3D SAP2000 model for the WH-PA-07 plot Part 1
135
6.9. FIRE RATING AND DESIGN LIFE
The use of fireproofing system (factory applied intumescent coating etc) for all structural steel
(including connections) as required for compliance with statutory & regulatory requirements,
and QCDD requirements. The building designed working life is considered 50 years according
to QCS specification Section-01: Part-01.
Standard Title
Eurocode 0
BS EN 1994-1-1: 2004 Part 1-1: General rules and rules for buildings
BS EN 1996-1-1: 2005
136
masonry structures
BS EN 1998-1: 2004 Part 1: General rules, seismic actions and rules for buildings
ASCE 7-05: Minimum Design Loads for Buildings and Other Structures
BS EN 1998-1: 2004 Part 1: General rules, seismic actions and rules for buildings
Level ground floor structural concrete slab capable of taking a minimum design load
3 of 50kN/m2 UDL & T ton concentrated load, for Logistics Buildings – Forklift traffic yes
All Structure Steel (and connections) shall be protected against fire and corrosion
4 with Intumecent paint; for design life of the building. The Intumecent paint must be yes
factory applied
5 All connections, steel to steel, steel to concrete shall be designed and detailed by the yes
contractor in coordination with all disciplines
137
7. MECHANICAL
7.2. PLUMBING AND DRAINAGE DESIGN BASIS
7.2.1. Introduction
This chapter shall outline the design basis memorandum of mechanical services on Plumbing
and Drainage system for the Light Industrial, Logistics Facilities at Ras Bufont Economic Zones,
plots PA-WH-04 and PA-WH-07.
The objective of this document is to provide design philosophies for adequate and efficient
mechanical building services for the facility’s plumbing and drainage system considering safety,
maintainability, reliability and controllability as per site conditions.
The scope of design basis as referred herein shall be the potable water distribution within the
Light Industrial, Logistics Facilities at Ras Bufontas Economic Zones. This includes the tie-in to
the existing potable water network at the plots boundaries, Kahramaa water meter cabinet
provision & connection, underground RCC potable water tank, booster pumps and its controls,
underground piping and its appurtenances, and internal water distribution system.
The scope of design basis as referred herein shall be of the internal and external sewer
drainage piping connected to the existing Foul water drainage network available near the site
and to review the surface drainage design.
The following reference documents, codes and standards shall be used when developing the
Mechanical Building Services Design, Systems and Specifications:
4) CIBSE Guidelines
138
6) Qatar Drainage Affairs Regulation (ASHGAL)
10) Qatar Sewerage and Drainage Design Manual – Issued by ASHGAL – December 2006
edition)
Proposed Light Industrial, Logistics Facilities at Ras Bufont Economic Zones domestic water
needs shall be served by constructing a new potable water distribution system within the site
boundaries. The potable water supply shall be from the tie-in point with the public infrastructure
at the plot limit. The system shall consist of below ground water storage tank, booster pumps
and underground and aboveground piping network.
The new potable water distribution system shall be designed with a total reserve storage
volume capacity for two (2) days. This capacity will be stored in the main underground water
tank of the plot.
The underground storage tank shall be filled-up through a water supply pipe tapped to the
existing potable water network. Domestic water for the proposed Light Industrial Units shall be
taken from this tank, via buster and will be supplied to all the fixture units of each tenant.
The potable water network will supply also water to the firefighting tank. Additionally the potable
water network will supply temporarily the irrigation tank till TSE water is available.
Sub-water meters will be provided for each tenant and for the supply of the firefighting tank and
irrigation tank.
139
External Plumbing System
1. Building service valve chamber shall be provided with an isolation valve, check valve and
pressure gauge, to connect from the tie-in point with the public infrastructure network at
the plot limit to the proposed water meter cabinet.
2. Water meter with digital display for easy reading of potable water consumption shall be
provided on the potable water supply line to the proposed building. Water Strainer is
provided in the water piping network before the metering unit to eliminate any foreign
material entering the metering unit or causing a blockage in the main pipeline.
3. The Main water tank will be located within 10m of the main water meter.
4. Water piping network shall be provided with isolating valves such that its mains, loops
and lateral pipe branches can be isolated to provide continuity of water supply if a
maintenance or break in pipe will occur.
5. Size of the pipe main for the building shall be based upon the time taken to fill the
potable water requirement for the building in less than 6 hrs which will correspond to a
recommended pipe size which is not to exceed water velocity of 3 m/s as per UPC
paragraph A.6.1.
6. Underground potable water piping from the tie-in to the underground main potable water
RCC tank shall be of MDPE pipe. All additional underground pipe work for potable water
in the plot area shall be also of MDPE.
7. All above ground pipe work shall be PPR pipe DIN-8077-8078 or equivalent and shall be
manufactured by ISO certified company. PPR fittings shall be manufactured with DIN-
16962 or equivalent
1. Plumbing system internal of building shall consist of hot and cold water supply piping.
2. Water supply pipe sizes will be determined based on Fixture Unit calculation method as
described in International Plumbing Code. Typical design values are:
140
Fixture type Water fixture
unit1
Lavatory 0.7
Bidet 2.0
3. Pipe sizing shall be based upon the total water fixture unit’s equivalent flow. Maximum
water velocity in the selected pipe should not exceed 3.0 m/s (as per UPC paragraph
A.6.1).
4. Actual fixtures water flow will be in compliance with QCS requirements (related to the
GSAS /sustainability).
5. Building sanitary fixtures and equipment service water pipe connection requirements
shall be identified and located in the plan of which pipe size and its required valve and
fittings shall be provided accordingly.
6. All sanitary fixtures such as wash basins, water closets, and pantry sinks shall be
provided a minimum of 2 bar water pressure at its inlet piping connection.
141
7. The mixed warehouse plumbing fixtures shall be selected so that it will ensure the
minimum water flow requirement. This shall include low flow fixtures for urinals, water
closets etc. and sensor operated fixtures for wash basins.
8. Each group of sanitary fixtures such as those located in one toilet or kitchen shall be
provided with an isolation valve. This is to facilitate maintenance for a particular set of
fixtures without affecting the functional operation of the adjacent toilets.
9. Water hammer arrestors shall be provided at all end piping end points of a group of
fixtures to mitigate water hammering which creates noise and subsequently stress on the
water piping itself.
10. All water piping shall be concealed to walls, cavity wall, above dropped ceiling. Access
ceiling or wall panel shall be provided for isolating valves, pressure regulating valves and
other control valves in a concealed location.
11. Service water connections shall be provided with Hose bib-tap arrangement in the
warehouse, storage areas to cater the need of any specific water requirement for the
cleaning, maintenance for equipment’s to be used in these areas.
12. Service water connection with Hose bib-tap arrangement shall also be provided in car
parking area for general cleaning.
13. All aboveground hot and cold water supply piping shall be PPR pipe DIN-8077-8078 or
equivalent and shall be manufactured by ISO certified company.
14. All synthetic and plastic materials used in above ground installation or within the ceiling
plenum shall comply with the 25/ 50 Flame spread/ Smoke development index rating as
tested by American Society for Testing and Materials (ASTM) ASTM-E84.
Hot water supply shall be generated by storage type electric water heater. Individual Horizontal
pressure type electric water heaters concealed in the ceiling is proposed for Toilet, Kitchen &
Pantry area usage. Hot water storage estimate will be based on guidelines in American Society
of Plumbing Engineers Data Book and ASHRAE Applications Handbook Chapter 50 Table 10.
142
Demand factor (industrial area): 0.4
The hot water storage capacity and electrical power input will be based on the nearest
commercially available size of water heaters.
Pumping System
1. Water booster pumps shall be sized and selected based on the anticipated maximum
water flow of the piping network and the pressure requirements of the remotest sanitary
fixtures or equipment it served. The booster pumps (1duty and 1standby) shall be
located beside the main storage tank in the potable water pump room.
2. Pressure head requirement for the booster pumps shall be calculated based upon the
pressure requirements of the remotest sanitary fixture which is set at 2 bars or the
pressure requirement of the equipment if there is such, plus the elevation and friction
head of the piping from the pump to the remotest fixture. Maximum flow requirement is to
be determined based upon the total water demand units (as per BS EN 806) of the
sanitary fixtures water flow equivalent plus the flow requirements of the equipment if
there is such.
3. Safety instrumentation devices to protect the water booster pump motor shall also be
provided such as low water tank level switch and the dry run switch which sense no-flow
in the suction pipe. When one of this safety devices activate, the pump will automatically
stop and an alarm shall be activated.
4. Water booster pumps to be used in the piping network shall be of one duty and one
standby configuration. The standby pump will be also connected to the emergency
generator for backup power supply.
5. The Booster Pump shall be of vertical multistage centrifugal pumps. The pumps shall be
speed controlled such that it maintains a constant pressure through continuous
adjustment of the speed of the pumps.
143
6. The Booster Pump set shall be factory installed and tested complete with its associated
controls.
Potable water storage requirements will be calculated in accordance with Kahramaa regulations
for Commercial Office buildings based on the following factors:
1. Potable water storage estimate will be based on occupant density OR on fixture demand,
as per CIBSE, whichever is greater.
Fixture Liters/24h
WC 1802
Basin 902
Sink 90-1802
Urinal 1102
3. Water consumption for the industrial area of the unit will depend upon the type of usage.
For the concept design stage it is assumed a daily consumption of 5m3 /day
144
4. Total potable water stored should provide as per Kahramaa two (2) days reservoir.
5. Tank total volume capacity shall be calculated based on the above factors. The main
potable water storage tank shall be an underground RCC tank.
6. The tank will be divided in 2 equal compartments and will be complete with inlet, outlet,
drain, overflow connections, vent, manhole etc.
The calculation of the daily potable water for each tenant of PA-WH-07 will be based on
occupancy density OR daily fixture demand as per CIBSE Guideline G Tables 2.3 and 2.4 as
mentioned in paragraph 7.2.5.
Occupancy density
Assuming 20 occupants per Light industrial unit the daily consumption will be: 80 lt/p. x 20 p. =
1600 lt/day.
Assuming additional water consumption of 15% of the fixture demand the daily requirement will
be:
No. of Total
Fixture Demand
Fixtures (per demand
description (liters/24)
tenant) (liters/day)
Water Closet 4 180 720
Wash Basin 6 90 540
Pantry Sink 1 180 180
TOTAL 1440
Assuming additional water consumption of 15% of the fixture demand the daily requirement will
be:
1440 lt x 1.15 = 1656 lt/day. < 1840 so calculation will proceed with occupancy density.
Assuming a daily consumption of 5m3/day for the industrial area the total daily requirement will
be:
145
1840 + 5000 = 6840 lt / day
The total daily consumption of the Light Industrial Unit for PA-WH-07 will be:
Considering 2 days water storage capacity as the required volume for the main potable water
tank the considered capacity will be: 2 x 54720 = 109440 lt (~109 m 3) net potable water volume.
Tank size: 6.0m x 6.0m x 4.0m (LxWxH) RCC underground tank (divided in 2 equal
compartments).
The flow rate for the booster pump will be based on the Water Fixture Unit calculation method
of IPC as described in paragraph 7.2.5
No. of Fixtures
Fixture Fixture Units (FU) No. of tenants Total FUs
per tenant
Water Closet 2 4 8 64
Lavatory 0.7 6 8 33.6
Kitchen Sink 1.4 1 8 11.2
Hose Bib 2.25 2 8 36
TOTAL 144.8
From Hunter’s Curve and table E103.3(3) of IPC: for 145 FUs the flow rate demand is 53.6 gpm
= 3.4 lt/sec.
146
From the above the booster pumps will have the following characteristics:
Flow
Equipment Installation Area Head
No. Description rate Input Power Remarks
type. Location served [mWG]
[l/s]
Vertical Multi-stage
Main centrifugal pump
Potable The 4.0kW with VFD
Booster 1 Duty + 1
1 water whole 4.5 50
Pump Stand By 415V/50Hz/3Ph Stand by pump will
Pump LIU
room be connected to the
generator.
The calculation of the daily potable water for each tenant of PA-WH-04 will be based on
occupancy density OR daily fixture demand as per CIBSE Guideline G Tables 2.3 and 2.4 as
mentioned in paragraph 7.2.5.
Occupancy density
Assuming 20 occupants per Light industrial unit the daily consumption will be: 80 lt/p. x 20 p. =
1600 lt/day.
Assuming additional water consumption of 15% of the fixture demand the daily requirement will
be:
No. of Total
Fixture Demand
Fixtures (per demand
description (liters/24)
tenant) (liters/day)
Water Closet 4 180 720
Wash Basin 6 90 540
Pantry Sink 1 180 180
TOTAL 1440
Assuming additional water consumption of 15% of the fixture demand the daily requirement will
be:
1440 lt x 1.15 = 1656 lt/day. < 1840 so calculation will proceed with occupancy density.
147
Assuming a daily consumption of 5m3/day for the industrial area the total daily requirement will
be:
The total daily consumption of the Light Industrial Unit for PA-WH-04 will be:
Considering 2 days water storage capacity as the required volume for the main potable water
tank the considered capacity will be: 2 x 109440 = 218880 lt (219.0 m 3) net potable water
volume.
Tank size: 8.0m x 8.0m x 4.0m (LxWxH) RCC underground tank (divided in 2 equal
compartments).
The flow rate for the booster pump will be based on the Water Fixture Unit calculation method
of IPC as described in paragraph 7.2.5
No. of Fixtures
Fixture Fixture Units (FU) No. of tenants Total FUs
per tenant
Water Closet 2 4 16 128
Lavatory 0.7 6 16 67.2
Kitchen Sink 1.4 1 16 22.4
Hose Bib 2.25 2 16 72
TOTAL 289.6
From Hunter’s Curve and table E103.3(3) of IPC: for 290 FUs the flow rate demand is 83 gpm =
5.2 lt/sec.
148
Approximate pipe length for most remote fixture: 250 m
Equivalent length allowance for fittings and valves in network
125 50%:
m
Maximum pressure loss through the network 4%: 15 mWG
Geodetic height : 10 m
Total pressure drop in network: 25 mWG
Pressure allowance 20%: 5.00 mWG
Residual pressure at fixture: 20 mWG
Total required pump pressure: 50 mWG
From the above the booster pumps will have the following characteristics:
Flow
Equipment Installation Area Head
No. Description rate Input Power Remarks
type. Location served [mWG]
[l/s]
Vertical Multi-stage
Main centrifugal pump
Potable The 4.0kW with VFD
Booster 1 Duty + 1
1 water whole 5.5 50
Pump Stand By 415V/50Hz/3Ph Stand by Pump will
Pump LIU
room be connected to the
generator
149
7.4. Drainage System Design
1) The collection of foul and waste drainage from the sanitary areas of the office space and
the floor drainage of the production area of the Light Industrial Units.
2) Site drainage piping network consisting of concrete manholes and underground uPVC
pipes.
3) Storm water collection from the Light Industrial Units’ roofs which will be managed
through on-site attenuation and percolation through soak ways.
Tie-in point of the public infrastructure foul water network is available to tap-in at plot boundary.
1. Sewer effluents from water closets, urinals & bidets will be referred herein as “Black
Water” and building waste water emanating from, wash basins, showers, kitchen &
pantry sinks, floor gulley’s will be referred to as “Grey Water” shall be collected through a
separate piping network which will be discharged directly into the proposed sewage and
waste manhole distribution system.
2. The Drainage system for the Light Industrial Units will have a separate piping riser stack
for waste (grey) and soil (black/sewer) water. The condensate drain water will combined
with the waste water pipe stack.
3. Drainage at ground floor level shall be separated from the first floor levels. The proposed
drainage system design shall follow SYSTEM IV – Secondary Ventilated Discharge
Stack (Separate Stack System) in accordance with BS EN 12056-2:2000.Drainage from
all kitchens sinks known as waste or grey-water will be routed as a separate system to
external gulley trap(s) or oil interceptor and thereafter into common inspection
chamber(s).
4. The drainage from the building services is discharged to the Sewage and Waste
manhole distribution system of the site and from there to the existing public infrastructure
foul water drainage network at the plot’s boundary.
5. Main sanitary waste system should be sized with 10% to 15% extra capacity at peak flow
conditions.
150
7.4.2. Internal Drainage System
1. Drainage piping shall be sized as per the recommended guidelines of BSEN 12056-
2:2002. Sizing is based on using System IV Table with secondary ventilated stack
system. Discharge Units shall be determined for each fixtures connected to a pipe stack
and the total square root sum shall be multiplied by its frequency factor which will result
to the expected flow units that the pipe stack can handle. Typical values are given in the
table below, according to BS12056-2, section 6.2.2 Table 2:
Water Closet 2
Wash Basin 03
Urinal 0.3
Shower 0.5
Floor Gully 1
2. The size of the drainage and vent pipe stack for the corresponding expected flow is
determined from Table 12 of BS12056-2, section 6.5.2. Typical values of Table 12 are
given bellow:
151
Stack
System I, II, III, IV
and Secondary
stack Vent
Qmax (l/s)
vent
Square Swept
DN DN
entries entries
60 50 0.7 0.9
70 50 0.0 2.6
90 50 3.5 4.6
3. The main sanitary waste system should be sized with 10% to 15% extra capacity at peak
flow conditions.
152
4. Drainage pipes inside the building shall be sloped from 1.5% up to 2% of maximum
slope. Gradient for drainage pipes shall strictly comply with ASHGHAL requirements &
provisions of QCS.
5. Vent pipe shall be provided to all water closets & waste drainage piping. Vent pipe shall
be connected to a vent stack as applicable and be terminated on roof vent cowl.
6. Drainage piping change of direction shall be provided with floor clean out or rodding eye
as applicable.
7. Floor drain shall be provided near each Hose bib Tap location.
8. Drain channels will be provided along the floor of the industrial area of each unit for the
purposes of discharging contents of floor cleaning and to collect possible machine
drainage.
9. uPVC to BS EN1401-1 pipe material shall be used for foul water and waste water
drainage and ventilation piping.
10. Provision for oil / fuel separator will be made for the drainage of the floor of the industrial
usage area of each tenant..
11. All synthetic and plastic materials used in above ground installation or within the ceiling
plenum shall comply with the 25/ 50 Flame spread/ Smoke development index rating as
tested by American Society for Testing and Materials (ASTM) ASTM-E84.
153
7.5. FIRE FIGHTING DESIGN BASIS
7.5.1. General
Introduction
This chapter shall outline the Design Philosophy of Fire Fighting system for the Light Industrial
and Logistics facilities at Ras Bufontas Economic Zones plot PA-WH-04 and PA-WH-07. The
objective of this document is to provide Design Philosophies to ensure an efficient and reliable
performance for the facilities.
Fire Fighting system in accordance with NFPA Codes and the Qatar Civil Defense Department
fire safety requirements.
The following are Codes and Standards which shall be used in the development of Firefighting
design for this project:
d. NFPA 14 – Standard for the Installation of Standpipe, Private Hydrant and Hose Systems
e. NFPA 20 – Standard for the installation of Stationary Pumps for Fire Protection
g. NFPA 24 - Standard for the Installation of private fire mains and their appurtenance.
h. NFPA 25 - Standard for inspection, testing and maintenance of Water based fire
protection system.
154
m. Qatar Construction Specifications 2014.
General Summary
a. The proposed firefighting system for the Light Industrial Units shall be designed in
accordance with the mandatory requirements for safety and loss prevention as
prescribed by NFPA Codes and the Qatar Civil Defense Department fire safety
requirements. It is the objective of this document to ensure that safe design is achieved
and to minimize the risk of injury to personnel, loss or damage to property and structures
and pollution to the environment.
b. The proposed building shall be protected with automatic sprinkler system for the office
and the industrial area of each unit, hose reel system provided in compliance with NFPA
13 & NFPA 14 for each floor, and dry stand pipe for the office area of each unit.
Adequate portable fire extinguishers of various types and fire blankets shall be installed
at appropriate locations.
c. The unit of each tenant will be covered through by individual zone control valves (one for
the office area and one for the industrial area).
d. Fire Water for the sprinkler system and hose system shall be served from firefighting
water network.
e. Calculations summary shall be prepared for the proposed building showing the required
demand residual pressure and fire water flow of the feed main pipe inside the building
assuming a fire event has occurred on one area of the building. This feed main pipe will
supply the water source for an automatic sprinkler system design of the building and the
fire hose system.
f. Identifying the correct demand water flow and pressure at the feed main pipe will ensure
an efficient and reliable performance of the firefighting piping layout considering the most
hydraulically demanding area of the building by specifying the minimum end head
condition of the most repot and most demanding sprinklers and Fire Hose outlets in use
as the basis of the flow to determine the required demand.
g. Hydraulic piping analysis shall be prepared using ELITE software Systems, Inc. using
Hazen-Williams Formula in accordance with NFPA 13. Software output shall show
required flow demand and pressure at the source as well as velocity and pressure drop
at each piping nodes.
155
h. The Main Telecom/IT room, Substation Building MV & LV room, CCTV room and the
electrical rooms shall be protected by FM 200. The cylinders required for protecting
these rooms shall be located outside the room been protected.
i. The FM 200 system shall be sized to provide the required 7% concentration of agent in
the space protected. A piping arrangement and nozzle shall convey the agent from the
cylinders to the hazard and discharge the agent completely within10 seconds. The piping
and nozzles shall be engineered for the specific flow rates required and calculations shall
be supplied with the system layout drawings for approval.
j. A prefabricated low expansion foam system with open foam sprinklers will be installed for
the coverage of the generator room as per NFPA 11.
Design Criteria
e. The following are Design Criteria for each system for the various space occupancy in the
building shall be used in the development of firefighting design for this project
(1) Class II standpipe and hose systems will be designed in accordance with NFPA14. Fire
hazard classifications for this building will be based on the life safety design and
indicatively will be as below:
156
(2) Water demand requirements for the Hose reels:
(1) The use of automatic sprinkler system will be in compliance with QCDD requirements as
below:
Office area
o Automatic sprinkler coverage : Office area (ground and mezzanine) of the LIU
157
o Number of Sprinklers : 12 sprinklers (in 3 lines of 4 sprinklers each)
v) Commodities to be stored.
(1) In case the tenant intends to use part of their allocated Units for storage or warehouse
these must maintain the Ordinary Hazard 2 classification in order to be supported by the
firefighting system. Below are restriction that need to be followed for possible storage or
warehouse areas:
(2) The above are classified (as per NFPA 13) as “type I-IV”. Similar arrangements with the
same classification are possible.
158
(3) Maximum storage (racks) height 3.0m, hazard Ordinary Hazard 2 (as per NFPA 13,
table 13.2.1).
System Description
Fire protection system for the proposed mixed warehouse shall be as per below tables:
Dry
Building Wet Hose Fire
Si.No. Stand FM 2002 Foam 3 Remarks
Name Sprinkler Reel Ext.
Pipe 1
2. FM200 for LV/MV rooms, IT room, CCTV room and electrical rooms > 5.1m 2
159
Table-2 External fire protection:
Fire Truck
S.N.O Building Name Hard Remarks
Standing
1. Fire water for the above mentioned firefighting systems shall be taken from dedicated
Fire water tank through Firefighting pumps (electrical, diesel and jockey) as per QCDD
and NFPA requirements will provide water to the above network.
2. Fire water stored will be potable water received from Kahramaa through separate sub-
water meter. The fire water tank will be constructed of reinforced concrete and will be
located underground. Adequate quantity of water to meet NFPA and QCDD codes will be
stored in a segregated and compartmentalized tank (two equal compartments), to act as
fire reserve.
3. Wet system shall consists of feed main, cross main, branch piping, supervised gate
valves, water flow switches, alarm check valve, drain pipes, pendent and sidewall
standard response sprinklers, breeching inlets, gauges, fire hose connection and fire
hose reels and landing valves. Inspector test valves shall be provided at each end of
hydraulically demanding area to test the alarm check valve serving the building. Alarm
Check Valve activation shall initiate an alarm action.
5. Class II wet standpipe system as per QCDD requirements and NFPA 14, shall be
provided for the light industrial units. Class II is system that provides 1½ in. (40 mm)
hose stations to supply water for use by trained personnel. The Class II wet system shall
be located at the Fire exit stairways at the main floor landing or wall adjacent to the exit
openings. Class II with DN25 wet fire hose reel system connection shall also be provided
in every floor to supply water for use by trained personnel and building occupants. The
proposed “Class II Fire Hose Reel cabinet” shall be covered with following content:
DN25 x 30m fire hose in upper compartment including PRV if required for office are,
160
6 Kg DCP and 5kg CO2 fire extinguisher in lower compartment.
and
DN40 x 30m fire hose in upper compartment including PRV if required for industrial
area
6. Portable extinguishers shall be provided to comply with NFPA 10 and as per the Qatar
Civil Defense Department fire safety requirements.
Electrical Room & Utilities Room: Dry Powder Portable Fire Extinguisher & CO2 Fire
Extinguisher.
Pantry: Type K Portable Fire Extinguisher (wet chemical) and Fire Blanket.
Substation:
a. MV Room - Dry Powder Portable Fire Extinguisher & CO2 Fire Extinguisher.
b. LV Room - Dry Powder Portable Fire Extinguisher & CO2 Fire Extinguisher.
Warehouse Area: Dry Powder Portable Fire Extinguisher & CO2 Fire Extinguisher.
Admin Area, Office Area etc.: Dry Powder Portable Fire Extinguisher & CO2 Fire
Extinguisher.
7. All pipes above ground shall be seamless galvanized steel, schedule 40 to ASTM A53.
All external pipes below ground shall be HDPE (underground more than 1 m depth).
The FM 200 system shall be sized to provide the required 7% concentration of agent
in the space protected. A piping arrangement and nozzle shall convey the agent from
161
the cylinders to the hazard and discharge the agent completely within10 seconds.
The piping and nozzles shall be engineered for the specific flow rates required and
calculations shall be supplied with the system layout drawings.
The system design shall incorporate the capability of fully testing all electrical
detection, discharge control, abort, power shutdown, air-conditioning shutoff, fire
damper, and door closer circuits without discharge of the agent and without
disconnecting the agent supply from the system.
Installed systems shall be complete with all control wiring for detectors, alarms, door
releases, fire damper releases, abort stations, manual pull stations, air conditioning
and computer equipment shutdown devices, voltage trips and circuit breakers. All
wiring, including control circuitry, shall consist of insulation copper conductors
installed in metal conduit.
FM -200 cylinders are stored outside the protected space as per QCDD regulation.
Cylinders that need to be installed outdoors will be located in air conditioned weather
enclosures
9. The generator room will be protected by low expansion foam system in accordance with
NFPA 11.
The required water volume for the Firefighting Water Tank will be calculated based on the
Design Criteria in paragraph 7.5.2 after examining various possible scenarios of operation and
selecting the most demanding. For both plots, PA-WH-04 and PA-WH-07 the scenarios are the
same.
Scenario 1:
Activation of sprinklers in the industrial area of a unit (ESFR sprinklers) and simultaneous use of
2 Hose reels.
As per the design criteria 12 ESFR sprinklers with K=12 @ 50psi will be activated for 60
minutes.
The flow from each sprinkler is determined from its K-factor from the formula Q = K √P where:
Q = flow in gpm
162
K = K factor in gpm/(psi)1/2
The total estimated flow from the sprinklers will be 12 x 1.25 x 84.85 = 1273 gpm, where the
1.25 is a correction factor to take into account the variation of the sprinkler water density since
the network can’t be 100% symmetrical.
As per QCDD requirements the total flow from the Hose reels will be 100 gpm.
Total required flow: 1273 + 100 = 1373 gpm. As per NFPA 20 standardization a pump with 1500
gpm @ 10 bar will be selected.
For 60 minutes operation the total required water volume is 60 x 1500 = 90000 gal = 340 m 3.
This total volume will be divided into two equal fire water tanks.
For the final capacity calculation analytic Hydraulic calculations will be provided.
Scenario 2:
Activation of sprinklers in the office area of a unit and simultaneous use of 2 Hose reels.
The total required flow from the sprinklers will be 1500 x 0.20 x 1.3 = 390 gpm, where 1500 is
the covered area in ft2, 0.20 is the density in gpm/ft2 and 1.3 is a correction factor to take into
account the variation of the sprinkler water density since the network can’t be 100%
symmetrical.
As per QCDD requirements the total flow from the Hose reels will be 100 gpm.
As per the above calculations a fire fighting pump of 1500 gpm @ 10 bar will be selected. The
firefighting pump set will have the following characteristics:
163
Pump Flow Pump Pressure Power
Pump ref Area Served
lt/min gpm bar psi kW HP
164
7.7. HVAC DESIGN BASIS
For the Light Industrial Units the provision of ACs is not a scope item. However, the contractor
should provide each unit with sufficient power to facilitate fully Air Conditioning of the Light
Industrial Units by the future tenant, without the need for upgrade to substation or electrical
infrastructure.
Contractor shall provide complete ventilation system for the Light Industrial Units as required by
QCS 2014.
Following parameters are assumed as the Basis of Design to arrive at the power requirement
for plot PA-WH-07 and PA-WH-07.
The outdoor climatic data for the design of indoor comfort air conditioning will be based on
QCS-2014, unless otherwise established by the authority having jurisdiction such as Doha
Municipality, especially in respect of circulars on Qatar conditions:
Topography:
Elevation : 10 meters.
165
All plant, equipment and systems will be of a type suitable for continuous operation without
mechanical/electrical failures in hot weather ambient (shade) air temperature of 50°C DB, 85%
RH and cold weather ambient air temperature of 7.50°C DB, 100% RH, altitude 20m above sea
level.
In general, environmental design conditions for indoor spaces will conform to values stipulated
in ASHRAE Handbook of Fundamentals as tabulated here under.
Summ Relative
Area Winter1
er humidity2
166
Summ Relative
Area Winter1
er humidity2
Notes:
1. Direct heating process will not be provided during winter. Heating achieved will be an
indirect consequence of internal heat gains from occupancy, lighting and equipment.
2. Summer Relative Humidity mentioned in the table is the value used for design of the
systems. Resultant humidity in the space is an indirect consequence of the temperature
control resulting from the air conditioning process.
3. Not applicable.
Thermal characteristics of the building fabric - only in building envelopes where temperature
control system (a/c) is applicable - shall comply with QCS-2014 Standards for energy efficiency
(Section 15, part 2). Thermal properties of building fabric materials proposed as inputs to heat
gain calculations are as tabulated below.
Roof 0.44
Wall above grade and exposed to 0.57
Floor
sun on grade 0.57
Window glass (area <40% of wall) 2.1 0.40
Window glass (area >60% of wall) 1.9 0.25
167
Activity Heat gain (W/person1)
Notes:
1. Occupant density will be calculated on the basis of office ID furniture layout. In case of
open spaces the requirements of ASHRAE 62.1 will be used.
2. Based on 24OC room dry bulb temperature ASHRAE Fundamentals Chapter 18 Table 1.
Lighting loads will be calculated based on actual lighting design to achieve uniform lux and
lumens for each type of room spaces along with ballast factor considerations.
During preliminary design stage, heat dissipation from lighting luminaires will be assumed as
tabled below. Energy distribution for recessed luminaires will be allowed as per
recommendations provided in CIBSE Guide A.
168
Sr. Room/Area Adopted load
No. (W/m²)
4 Reception 7.5
6 Stores 10
7 HV/LV room 10
8 Mechanical/ Electrical-plant 10
Rooms
10 Warehouse 7.5
Heat dissipation from electric appliances in offices such as computer VDUs, CPUs, Printers,
etc. will be considered in cooling load estimates as tabled below:
169
1 Offices - Private 25
3 Meeting rooms 25
4 Reception/Lobbies 15
2. If no information is available 40kW sensible and 10kW latent per tenant to be assumed
Outside air flows required for ventilation shall be calculated in accordance with Ventilation Rate
Procedure described in ASHRAE 62.1. In this procedure, the design ventilation rate is
determined based on standards of minimum ventilation requirements. These requirements are
expressed as “outdoor airflow rate per occupant and per unit floor area”.
170
ASHRAE 62.1 – 2007 parameters
Space
l/s.m2
Pantry - NA e - - 10
Warehouse - - - 0.3
l/s.m2
171
Notes:
a. Default values of occupancy density (m2/person) and combined outdoor air rate
(l/s/person) will be used together for the design wherein the definitive occupancy density
is undefined in the architectural layouts.
e. Not applicable.
The Ventilation required for the Industrial area of each unit is related to the production process.
This will be dependent from each tenant and the information is not available at this stage. For
the concept design stage the assumption of 5000 m 3/h for each unit is made.
All fresh air intakes shall pass through sand trap louvers with pre-filters to remove particulate
matter before being allowed to enter the Air Handling Units or Ventilation system.
Smoke Ventilation shall comply with NFPA 92 and relevant QCDD standards.
Warehouse, workshop, production areas and any other area that smoke control is required will
be equipped additionally with smoke extract fans providing 10 ACH of exhaust rate.
Final smoke ventilation requirements are subject to change based on the Type of storage
materials, arrangement and condition of production and storage areas.
7.7.7. Infiltration
To prevent ingress of outside ambient air, the building will be pressurized by supplying
minimum 10% treated outside air in excess of the building exhaust air. Also, the overall
differential air pressure between inside and outside will be maintained in the range of +4Pa to
+5 Pa. This is sufficient to prevent infiltration and is proven to avoid over-pressurization that
could result in whistling noise through doors, windows and building cracks.
Internal to the building positive or negative pressure zones are not required from the laboratory
procedures.
172
7.7.8. Heat Load Estimation Method
Proposed Software: CARRIER HAP (Hourly Analysis Program) Version 4.50 or higher.
Design supply air temperature: 12.8oC or 10oC differential temperature from the room
design one
Private Offices: NC 30
Public Offices: NC 35
Lobbies/Reception: NC 35
Toilets/Pantries: NC 40
Workshop: NC 50
Warehouse: NC 55
173
Air velocity in branch ducts : 8 m/s (Maximum);
Although the provision of A/C systems is not a requirement, air conditioning systems are
proposed in order for the contractor to supply the necessary provisions (power, space etc) for
future installation.
For the industrial area the possible options are between a chilled water based system and a DX
system. Since each tenant must be autonomous due to the number and size of each sub-unit
the use of multiple water bases systems with separate chillers and cooling towers is not
suitable. The DX systems that are considered are a Packaged Rooftop system or the use of an
AHU with DX coils and separate DX condenser. Rooftop packaged units are favored due to is
more compact design and the restricted available installation space.
For the office areas the possible options are again between a chilled water based system and a
DX system. Since each tenant must be autonomous due to the number and size of each sub-
unit the use of multiple water bases systems with separate chillers and cooling towers is again
not suitable. The DX systems that are considered are a split type a/c units and VRF type a/c
174
systems. The VRF systems are favored due to its increased efficiency and the offer of a
centralized control system.
Industrial areas: packaged direct expansion unit (rooftop) for each tenant.
Air conditioned individual areas: split unit or Variable refrigerant flow unit depending on
the building (indoor unit will be wall mounted or 4way cassette or ducted low or high
pressure) for each tenant.
The a/c units will use R410a refrigerant or equivalent environmentally friendly.
The Package rooftop unit for the industrial are of the ILUs location shall be shown tentatively in
the Architectural drawings with the provision of wall openings for Supply / Return air ducts to
enter the industrial area.
The Outdoor unit location for the office VRF units shall be shown tentatively in the Architectural
drawings with the provision of roof cutouts to run the Refrigerant pipes, control cables, etc., to
interconnect with the Indoor & Outdoor units serving the Office area.
Additionally, the design shall specifically address and demonstrate that all mechanical
equipment, accessories and devices that would be considered as part of the routine
maintenance operation shall be located in a way that they are easily and safely accessible.
Maintenance and equipment access path shall maintain a head room clearance not less than
2100mm clear and be free from any low level or floor level installation that obstruct or interferes
with Trolley access to all mechanical equipment.
All fresh air supply systems shall be dust free and utilized to provide necessary ventilation air
requirements in addition to keeping the building positively pressurized relative to outdoor. The
fresh air system shall be a forced system and design to suit local ambient conditions an
optimize maintenance requirements (use of inertial filter or other approved similar system /
device).
All synthetic and plastic materials used in above ground installation or within the ceiling plenum
shall comply with the 25/ 50 Flame spread/ Smoke development index rating as tested by
American Society for Testing and Materials (ASTM) ASTM-E84.
175
7.8. Concept Design Initial HVAC Calculations for PA-WH-07
As per the design criteria in paragraph 7.6 initial cooling load calculations are made to
determine the required electrical load of the air conditioning equipment. Software calculations
are made with Carriers HAP 4.50 and can be found at Appendix – A of this document.
The cooling loads for the office and industrial area of each tenant for the concept design are
summarized as follows:
176
Cooling load summary
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 1 office area 170 612 38598 1155 39753 38717 6138 44855 38717 44855
LIU 1 industrial area 1390 5004 80217 17115 97332 87381 53219 140600 87381 140600
LIU 2 office area 170 612 23718 1155 24873 24580 6161 30741 24580 30741
LIU 2 industrial area 1390 5004 66032 17115 83147 75346 53874 129220 75346 129220
LIU 3 office area 170 612 27659 1155 28814 28247 6134 34381 28247 34381
LIU 3 industrial area 1390 5004 72482 17115 89597 79987 53657 133644 79987 133644
LIU 4 office area 170 612 27659 1155 28814 28247 6134 34381 28247 34381
177
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 4 industrial area 1390 5004 87893 17115 105008 96924 54031 150955 96924 150955
LIU 5 office area 170 612 27659 1155 28814 28247 6134 34381 28247 34381
LIU 5 industrial area 1390 5004 68655 17115 85770 76206 53458 129664 76206 129664
LIU 6 office area 170 612 27659 1155 28814 28247 6134 34381 28247 34381
LIU 6 industrial area 1390 5004 93269 17115 110384 99869 51994 151863 99869 151863
LIU 7 office area 170 612 25067 1155 26222 25795 6156 31951 25795 31951
LIU 7 industrial area 1390 5004 66032 17115 83147 75346 53874 129220 75346 129220
LIU 8 office area 170 612 36274 1155 37429 36874 6203 43077 36874 43077
178
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 8 industrial area 1390 5004 85876 17115 102991 93491 54094 147585 93491 147585
179
7.8.2. Air Handling Units Calculations
As per the above calculated cooling loads the requirements for the air conditioning units for
each tenant will be as follows:
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
180
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
181
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
182
7.8.3. Smoke Extract Fans Calculations
The industrial areas will be equipped with smoke extract fans. The fans will provide for each
are 10 ACH.
183
7.8.4. Fresh air and Ventilation Fans Calculations
As per the design criteria in chapter 6 the fresh air requirements for the office and industrial
area of each tenant are as follows:
LIU 1 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 2 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 3 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 4 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
184
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
LIU 5 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 6 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 7 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 8 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
185
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
As per the design criteria in paragraph 7.6 initial cooling load calculations are made to
determine the required electrical load of the air conditioning equipment. Software
calculations are made with Carriers HAP 4.50 and can be found at Appendix – A of this
document.
The cooling loads for the office and industrial area of each tenant for the concept design are
summarized as follows:
186
Cooling load summary
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 1 office area 170 612 22189 1155 23344 23142 6216 29358 23142 29358
LIU 1 industrial area 1390 5004 55572 12390 67962 64692 49534 114226 64692 114226
LIU 2 office area 170 612 16382 1155 17537 17324 6095 23419 17324 23419
LIU 2 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 3 office area 170 612 16412 1155 17567 17356 6096 23452 17356 23452
LIU 3 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 4 office area 170 612 16382 1155 17537 17324 6095 23419 17324 23419
187
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 4 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 5 office area 170 612 16412 1155 17567 17356 6096 23452 17356 23452
LIU 5 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 6 office area 170 612 16382 1155 17537 17324 6095 23419 17324 23419
LIU 6 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 7 office area 170 612 16412 1155 17567 17356 6096 23452 17356 23452
LIU 7 industrial area 1390 5004 58575 17115 75690 68086 53046 121132 68086 121132
LIU 8 office area 170 612 24171 1155 25326 24606 6067 30673 24606 30673
188
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 8 industrial area 1390 5004 64697 17115 81812 73555 53170 126725 73555 126725
LIU 9 office area 170 612 25324 1155 26479 26071 5729 31800 26071 31800
LIU 9 industrial area 1390 5004 60412 12390 72802 68866 50700 119566 68866 119566
LIU 10 office area 170 612 15814 1155 16969 16954 5721 22675 16954 22675
LIU 10 industrial area 1390 5004 58763 17115 75878 67203 53507 120710 67203 120710
LIU 11 office area 170 612 15605 1155 16760 16500 593 17093 16500 17093
LIU 11 industrial area 1390 5004 58763 17115 75878 67203 53507 120710 67203 120710
LIU 12 office area 170 612 15814 1155 16969 16954 5721 22675 16954 22675
189
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 12 industrial area 1390 5004 58763 17115 75878 67203 53507 120710 67203 120710
LIU 13 office area 170 612 15605 1155 16760 16500 5973 22473 16500 22473
LIU 13 industrial area 1390 5004 58763 17115 75878 67203 53507 120710 67203 120710
LIU 14 office area 170 612 15814 1155 16969 16954 5721 22675 16954 22675
LIU 14 industrial area 1390 5004 57863 17115 74978 67203 53507 120710 67203 120710
LIU 15 office area 170 612 15605 1155 16760 16500 5973 22473 16500 22473
LIU 15 industrial area 1390 5004 58763 17115 75878 67203 53507 120710 67203 120710
LIU 16 office area 170 612 27803 1155 28958 28842 5297 34139 28842 34139
190
Cooling loads Ventilation Excluded at 23oC/27oC Cooling loads Ventilation Included at 23oC/27oC Indoor A/C required
Ventilation
Indoors, 46oC Outdoors Indoors, 46oC Outdoors Cooling Capacity [W]
Area
Sensible Total
lt/sec m3/h Sensible [W] Latent [W] TOTAL [W] Sensible [W] Latent [W] TOTAL [W]
[W] [W]
LIU 16 industrial area 1390 5004 63120 17115 80235 72158 54444 126602 72158 126602
191
7.9.2. Air Handling Units Calculations
As per the above calculated cooling loads the requirements for the air conditioning units for
each tenant will be as follows:
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
LIU 1 VRF
office area 29.4 system 35.2 15.0/415/3/50
LIU 1 Packaged
industrial Rooftop
area 114.2 137.1 55.0/415/3/50
LIU 2 VRF
office area 23.4 system 28.1 15.0/415/3/50
LIU 2 Packaged
industrial Rooftop
area 121.1 145.4 60.0/415/3/50
LIU 3 VRF
office area 23.5 system 28.1 15.0/415/3/50
LIU 3 Packaged
industrial Rooftop
area 121.1 145.4 60.0/415/3/50
LIU 4 VRF
office area 23.4 system 28.1 15.0/415/3/50
192
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
area Rooftop
LIU 5 VRF
office area 23.5 system 28.1 15.0/415/3/50
LIU 5 Packaged
industrial Rooftop
area 121.1 145.4 60.0/415/3/50
LIU 6 VRF
office area 23.4 system 28.1 15.0/415/3/50
LIU 6 Packaged
industrial Rooftop
area 121.1 145.4 60.0/415/3/50
LIU 7 VRF
office area 23.5 system 28.1 15.0/415/3/50
LIU 7 Packaged
industrial Rooftop
area 121.1 145.4 60.0/415/3/50
LIU 8 VRF
office area 30.7 system 36.8 15.0/415/3/50
LIU 8 Packaged
industrial Rooftop
area 126.7 152.1 65.0/415/3/50
193
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
LIU 9 VRF
office area 31.8 system 38.2 20.0/415/3/50
LIU 9 Packaged
industrial Rooftop
area 119.6 143.5 60.0/415/3/50
LIU 10 VRF
office area 22.7 system 27.2 15.0/415/3/50
LIU 10 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
LIU 11 VRF
office area 17.1 system 20.5 10.0/415/3/50
LIU 11 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
LIU 12 VRF
office area 22.7 system 27.2 15.0/415/3/50
LIU 12 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
194
Total AC Unit
Cooling
Load Cooling
Required at Capacity at
Area
23oC/27oC 23oC/27oC Electrical
Served
Indoors, Type Indoors, load
46oC 46oC [kw//V/p/Hz]
Outdoors Outdoors
[kW] [kW]
LIU 13 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
LIU 14 VRF
office area 22.7 system 27.2 15.0/415/3/50
LIU 14 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
LIU 15 VRF
office area 22.5 system 27.0 15.0/415/3/50
LIU 15 Packaged
industrial Rooftop
area 120.7 144.9 60.0/415/3/50
LIU 16 VRF
office area 34.1 system 41.0 20.0/415/3/50
LIU 16 Packaged
industrial Rooftop
area 126.6 151.9 65.0/415/3/50
195
7.9.3. Smoke Extract Fans Calculations
The industrial areas will be equipped with smoke extract fans. The fans will provide for each
are 10 ACH.
LIU
12.4 10 2.2/415/3/50
10 216 2678 26784 2 13392
LIU
12.4 10 2.2/415/3/50
11 216 2678 26784 2 13392
LIU
12.4 10 2.2/415/3/50
12 216 2678 26784 2 13392
196
Total Proposed fans
Required
Room Average Room required
Room ACH in
Area Height Volume Fan Flow Electrical
Name Fire
[m2] [m] [m3] capacity Quantity [m3/h] load
Mode
[m3/h] [kw//V/p/Hz]
LIU
12.4 10 2.2/415/3/50
13 216 2678 26784 2 13392
LIU
12.4 10 2.2/415/3/50
14 216 2678 26784 2 13392
LIU
12.4 10 2.2/415/3/50
15 216 2678 26784 2 13392
LIU
12.4 10 2.5/415/3/50
16 301 3732 37324 2 18662
As per the design criteria in chapter 6 the fresh air requirements for the office and industrial
area of each tenant are as follows:
LIU 1 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 2 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
197
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
LIU 3 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 4 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 5 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 6 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
198
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
LIU 7 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 8 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 9 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 10 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 10
5000m3/h - 5000 1 1.5/415/3/50
Industrial 5000
LIU 11 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
199
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
LIU 11
5000m3/h - 5000 1 1.5/415/3/50
Industrial 5000
LIU 12 office
8.5 l/s.p 20 612 1 0.5/230/1/50
Area 650
LIU 12
5000m3/h - 5000 1 5000 1.5/415/3/50
Industrial
LIU 13 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 13
5000m3/h - 5000 1 5000 1.5/415/3/50
Industrial
LIU 14 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 14
5000m3/h - 5000 1 5000 1.5/415/3/50
Industrial
LIU 15 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
200
No of Total Proposed fans
Ventilation people required Fan
Ventilated Area
Requirement (est.) or capacity Flow Electrical load
units [m3/h] Quantity
[m3/h] [kw//V/p/Hz]
LIU 15
5000m3/h - 5000 1 5000 1.5/415/3/50
Industrial
LIU 16 office
8.5 l/s.p 20 612 1 650 0.5/230/1/50
Area
LIU 16
5000m3/h - 5000 1 5000 1.5/415/3/50
Industrial
201
7.10. EMPLOYER’S DESIGN BRIEF VALIDATION FOR LIGHT INDUSTRIAL &
LOGISTICS UNITS FOR CONCEPT STAGE
2 Associated MEP & builders works for a Kitchenette in the office yes
location should be provided.
Substation/ Plant Rooms/ Fire Main and the like, including all
5 yes
associated builders work.
yes
Complete ventilation system for the Light Industrial Unis as [as per QCS
6
required by QCS 2014 2014, QCDD and
ASHRAE
standards]
yes
Standards to be used in the design, […] of the plumbing
system(s) shall be QCS 2014. If QCS 2014 does not [additional coded
7 used as per
adequately cover the plumbing requirements, British Standards
or International Plumbing Code (IPC) shall apply. paragraph 7.1.4
of this document]
202
The two-day storage potable water tank, required by the local
8 Authorities (KAHRAMAA), shall be sized based on daily yes
maximum consumption.
yes
Drainage lines shall be sized to ensure that adequate
14 cleansing velocities are achieved with the minimum flow or at [building services
least once per day. drainage sized as
per BS EN
12056:2000]
203
Provision of Heating and AC systems are not a requirement.
15 Howerver, a design is required to determine the power yes
requirements
All fresh air supply systems shall be dust free and utilized to
provide necessary ventilation air requirements in addition to yes
keeping the building positively pressurized relative to outdoor.
18 The fresh air system shall be a forced system and design to [not part of
suit local ambient conditions an optimize maintenance current Concept
requirements (use of inertial filter or other approved similar Design stage]
system / device).
204
8. STAGES OF SUBMISSION:
8.2. PROJECT PROGRAM WORK FLOW CHART
205
8.3. GSAS – DESIGN AND BUILD CERTIFICATION FLOW CHART
206
8.4. BUILDING PERMIT PROCESS
207
9. EMPLOYERS DESIGN BRIEF VALIDATION
208
9.2. PA-WH-07 – R E Q U I R E M E N T C O M P AR I S O N
TOTAL COVERED AREA 7819.9 Sq.m TOTAL COVERED AREA 6840.50 Sq.m
EST. CAR PARKING SPACES 0.377 /100 30 Nos NO. CAR PARKING 32 Nos
TOTAL GFA 7819.9 Sq.m TOTAL BUILT UP AREA (G+M) 8131.24 Sq.m
209
210
9.3. EMPLOYER’S DESIGN BRIEF VALIDATION FOR CONCEPT STAGE
s.no Remarks
The Light Industrial Unit Building (s) should be designed as
1 yes
flexible modular units as much as possible.
3 Modular units should have a clear office entry and separate yes
entry for the industrial functions.
6 Service yard and parking area should be provided for each of yes
the modular unit.
7 Each plot should be provided with a fence, the side facing the yes
roads to be of decorative vertical steel bars
8 Each plot to be provided with minimum 1 no. entrance & exit yes
for trucks & 1 no. entrance & exit for employees’ cars.
211
complete firefighting system with all associated MEP and
Builders work as per QCDD regulations includes a sprinkler
14 system, Clean Agents Systems, fire extinguishers, storage yes
tank or fire-mains, fire hose reel & cabinets and hydrants in the
service yard as required by the QCDD.
212
10. APPENDIX A – SOFTWARE COOLING LOAD CALCULATIONS
HAP-4.5 Software calculations for cooling loads from Chapter 7.7 and 7.8 for
detailed design stage electrical load estimation.
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
10.2.2. Cooling Load Output Data
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
10.2. Detailed Design Initial HVAC Calculations for PA-WH-07
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
10.2.2. Cooling Load Output Data
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578