You are on page 1of 78

AEON 

MALL HADONG SHOPPING CENTER
DESIGN DRAWING GUIDELINES

ISSUED ON 28/June/2019
TABLE OF CONTENTS

A. DESIGN CONCEPT

B. DRAWING
1. MASTER PLAN
2. 1ST, 2ND, 3RD  and 4TH OVERALL LAYOUT PLANS
3. ELEVATIONS

C. TENANT CATEGORIES
1. PHOTOS
2. LIGHTING & SIGNAGE ACTIVITY
3. SCOPE OF WORK
4. REGULATIONS

D. TENANT DESIGN RESTRICTIONS
1. LOADING RESTRICTIONS
2. INSTRUCTION OF ELECTRICAL DISTRIBUTION BOARD
3. INSTRUCTION OF VENTILATION FOR HOT POT & BBQ TENANT

E. DETAIL DRAWINGS
1. EXPANSION JOINT DETAILS

Page 2
A. DESIGN CONCEPT

Page 3
Page 4
A. DESIGN CONCEPT (Introduction)
・Introduction
■About Hanoi

・Population Increase, Economic Development, City Development  (same as HCMC)


・Capital of Politics & Education
・Hanoian→Traditional, Conservative, Formal, Spending money on appearance

■About Ha Dong

・This is a remarkable area with a bustling population in Hanoi; Wide highways are being constructed, the BRT is opening up which connects central Hanoi and Ha Dong district, 
and future preparations for a city wide high‐speed rail system (2018) are in place.
・With high rise apartments and villa housing development projects currently underway, this is an area where we can expect to see further growth in the population 
・Textile town specializing in silk
Page 5
A. DESIGN CONCEPT (Ground Design Concept)

・Ground Design Concept
Knitting Future,
Weaving Future
Inspire Future

Knitting
“the Ha Dong’s
Future”
〜Knitting Ha Dong’s future〜
SC was born in Hanoi at the center of Vietnam's remarkable development,
Growing up with the towns and local residents,
I’ve always wanted to make something for everyone

Town × SC, SC × People, People × Beautiful product, People × Delicious food,


People × People, People × Time, People × Nature, Past × Future, Light × Dark…
Page 6
A. DESIGN CONCEPT (Design Concept)

・Design Concept

Inspire Knitting
Changing from cocoon to thread, changing from thread to cloth, changing 
through the fusion of light, wind,
Changes that are born by enveloping something,
Incorporating "various changes" into the design
Page 7
A. DESIGN CONCEPT (Exterior Design : Image Perspective)
・Exterior Design : Image perspective
• The concept and design was inspired by the image of SC wrapped in clothing
→The size of the hole in the panel and density creates the illusion of moving cloth. In addi on, the glass part ac vely 
disseminates the bustle inside the SC,  and incorporates the interior and exterior.
・ The image of a “wrinkle” line forms by using a large canopy at the entrance.
・Produce a bustle of commerce with the atmosphere that exudes from glass, billboards, color usage of louvers, etc. view
Page 8
A. DESIGN CONCEPT (Exterior Design : Image Perspective – Night time)
・Exterior Design : Image perspective(night time)
・As a city landmark, through the glowing lights, we want to revitalize Ha Dong. 
Page 9
A. DESIGN CONCEPT (Interior Design : Sub Anchor Court)

view
Page 10
A. DESIGN CONCEPT (Interior Design : Center Court)

view
Page 11
A. DESIGN CONCEPT (Interior Design : Anchor Court)

view
Page 12
A. DESIGN CONCEPT (Interior Design : Main Mall – 1FL)
Page 13
A. DESIGN CONCEPT (Interior Design : Food Zone Concept 1)
Page 14
A. DESIGN CONCEPT (Interior Design : Food Zone Concept 2)
Page 15
A. DESIGN CONCEPT (Interior Design : Restaurant Mall)
Page 16
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 1FL)
Dark Zone Blight Zone

Bright Zone
・white , beige

Dark Zone
・dark gray
, dark Brown
Page 17
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 1FL Dark Zone)

view
Page 18
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 1FL Bright Zone)

view
Page 19
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 2FL)
Spacious Alley Excite Alley

Bright Zone
・white , light gray
Dark Zone
・Black
, dark gray
Page 20
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 2FL)
Page 21
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 2FL Spacious Alley)

view
Page 22
A. DESIGN CONCEPT (Interior Design : Restaurant Mall 2FL Excite Alley)

view
Page 23
A. DESIGN CONCEPT (Interior Design : Food Entrance ‐ Sketch “Green Terrace”)
Page 24
A. DESIGN CONCEPT (Interior Design : Food Entrance ‐ Sketch “Green Terrace”)
Page 25
A. DESIGN CONCEPT (Interior Design : Food Entrance ‐ Sketch “Green Terrace”)
Page 26
A. DESIGN CONCEPT (Interior Design : Food‐court Zoning 1)
Page 27
A. DESIGN CONCEPT (Interior Design : Food‐court Zoning 2)
Page 28
A. DESIGN CONCEPT (Interior Design : Food‐court Image)
Page 29
A. DESIGN CONCEPT (Interior Design : Food‐court Entrance)

Key plan
Page 30
A. DESIGN CONCEPT (Interior Design : Food‐court)

Key plan
Page 31
A. DESIGN CONCEPT (Digital Signage Concept)
Our SC  Design Theme is <Interior Digital‐Signage Shift>
We make <Digital‐SC> in this shopping center at Ha Dong.

Interior Digital-Signage Shift


This is not only in Outdoor but also in Indoor.
We will Plan  to Install  many Digital‐Signage  in common space.
Please  Design and  Install <Digital‐Signage> inside shop area  for cooperation of Digital‐Signage activity.
The plan of planting will  help to making <Attractive>  in your store.

Digital‐Signage Tower + Digital‐Signage on Bulkhead Digital‐Signage Banner

Court : image perspective MAll : image perspective

Digital‐Signage Elevator Digital‐Signage on Bulkhead

Entrance : image perspective Outside Plaza : image perspective
Page 32

B. DRAWINGS
1. MASTER PLAN
2. Basement, 1st, 2nd, 3rd  and 4th  OVERALL LAYOUT PLANS
3. ELEVATIONS
Page 33
B‐1. MASTER PLAN
Page 34
B‐2. Basement Floor OVERALL LAYOUT PLANS
Page 35
B‐2. 1st  Floor OVERALL LAYOUT PLANS
Page 36
B‐2. 2nd Floor OVERALL LAYOUT PLANS
Page 37
B‐2. 3rd Floor OVERALL LAYOUT PLANS
Page 38
B‐2. 4th Floor OVERALL LAYOUT PLANS
Page 39
B‐3. ELEVATIONS (Night view)
Page 40

C. TENANT CATEGORIES
1. PHOTOS
2. LIGHTING & SIGNAGE ACTIVITY
3. SCOPE OF WORK
4. REGULATIONS
Page 41
C‐1. PHOTOS 01 (Tenant Image – 1F, 2F and 3F GN Shop)
Page 42
C‐1. PHOTOS 02 (Tenant Image – 1F, 2F and 3F F&B Shop)
Page 43
C‐1. PHOTOS 03 (Tenant Image – 1F, 2F and 3F Kiosk Shop 01)
Page 44
C‐1. PHOTOS 04 (Tenant Image – 1F, 2F and 3F Kiosk Shop 02)
Page 45
C‐1. PHOTOS 05 (External Glass Wall Facade)
Page 46
C‐1. PHOTOS 06 (Other)
Page 47
C‐2. LIGHTING & SIGNAGE ACTIVITY (Lighting Activity 01)
Page 48
C‐2. LIGHTING & SIGNAGE ACTIVITY (Lighting Activity 02)
Page 49
C‐2. LIGHTING & SIGNAGE ACTIVITY (Digital Signage Activity)
01. Digital Signage combine with Façade Design 02. Digital Signage for VP

03. Combination

05. Digital Atraction

04. Menu Board
Page 50
C‐2. LIGHTING & SIGNAGE ACTIVITY (Corporate Signage Activity)
Page 51
C‐3. SCOPE OF WORK

Work in the Tenant Area
Scope of work for finishing work and M&E work of Tenant Area will be divided as follows,

Classification Property of Contents

A work Landlord Building work, MEP work and other works which includes main construction work and paid by landlord

C work Tenant The works are performed by tenant’s nominated contractor as tenant request and expense

Additional work Tenant Works are performed by the main contractor as tenant’s request and expense

*Above classifications are applied to Anchor Tenant, Sub Anchor Tenant and General Tenant. The other areas such as Central Court, Mall Zone, Food Court Seat, AEON Hall, 
Customer toilet, Staff Toilet, AEON MALL office, Meeting Room, Electrical Room, Machine Room, Pump Room or other Common Area.
Page 52
C‐3. SCOPE OF WORK

C‐2‐01. SCOPE OF WORK FOR SUB ANCHOR AND SPECIALTY TENANT
SUB ANCHOR TENANT AND SPECIALTY STORE
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the 
FLOOR All construction Work after "A" Work Tenants' finishing are to be similar with floor finished levels of shopping center.
common areas/ corridor FFL.
CONCRETE 
Demising wall 
Bare concrete finish. All construction Work after "A" Work
WALLS
BRICK WALLS Concrete Block Wall Surface All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
DRAYWALL
LGS with GB (t12) Surface only All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
ARCHITECTURAL

PARTITIONS
CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work
All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Soffit of slab
etc..) 'EXIST SIGN' must be installed if needed.

Install hanging wall at front of shop. 
SHOP FRONT All construction Work after "A" Work Ceiling heights comply with AEON MALL requirement.
Common area side with painting/ interior side without painting
SIGNAGE NIL All works such as wiring, graphics, light fixtures, etc.
SECURITY
NIL All works.
SHUTTER
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the necessary 
form
ELECTRICAL

All construction work after "A" work
TEL / DATA Conduit/cable at each tenant lot.
(including subscription procedure for single telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only All works, if necessary.
Main air duct from AHU till demising wall + volume damper stop. Or 
AIR‐CONDITIONING volume damper + flanger stop in case of duct line passing through tenant  All construction Work after "A" Work
premises
VENTILATION
Ducting till demising wall All construction Work after "A" Work Limited to cases where the tenant is required.
(EXHAUST & FRESH AIR)
MECHANICAL

SMOKE SPILL
All work required by regulations. All construction Work after "A" Work
SYSTEM
Limited to cases where the tenant is required.
Till valve points in tenant premises. (if necessary)
WATER SUPPLY All construction Work after "A" Work. ( If necessary) Water meter shall be installed lower than 1.5m for reading if water supply is 
Water meter shall be handed over to tenant for installation.
necessary.
DRAINAGE/ One‐thirds of tenants shall be provided drainage point forfuture
Waste discharge pipe at tap of point at slab. ( FFL+100) (if necessary) All construction Work after "A" Work. ( If necessary)
WASTE PIPE preparation.
GAS SUPPLY NIL NIL

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.

EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

All work required by regulations All construction Work after "A" Work
EXIT SIGN authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
NIL All works.
LIGHTING authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. All construction Work after "A" Work
ALARM EQUIPMENT authorities
EMERGENCY Sub anchor tenant : installing sub receiver for office Sub anchor tenant: wiring from speaker and sub receiver Tenant needs to get approval for its specification by AEON MALL & related 
ALERT SYSTEM Specialty store : NIL Specialty store : NIL authorities
WET CHEMICAL NIL NIL

NIL : Not Included
FFD : Fire Fighting Department
Page 53
C‐3. SCOPE OF WORK

C‐2‐02. SCOPE OF WORK FOR CINEMA TENANT
CINEMA
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the common areas/ 
FLOOR All construction Work after "A" Work Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL.
Demising wall  CONCRETE 
Bare concrete finish. All construction Work after "A" Work
WALLS
BRICK WALLS Concrete Block Wall Surface All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
DRAYWALL
LGS with GB (t12) Surface only All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
PARTITIONS
ARCHITECTURAL

CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work


All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Soffit of slab
etc..) 'EXIST SIGN' must be installed if needed

Install hanging wall at front of shop. 
SHOP FRONT All construction Work after "A" Work Ceiling heights comply with AEON MALL requirement.
Common area side with painting/ interior side without painting
SIGNAGE (INDOOR) NIL All works such as wiring, graphics, light fixtures, etc.
SIGNAGE (EXTERIOR WALL) Base for signage including installation work All works such as  wirings, letter signs, light fixtures, etc.
SECURITY SHUTTER NIL All works.
MEZZANINE NIL Steel structure, bare concrete finished at 4FL +6,500 & 9,500
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the 
necessary form
ELECTRICAL

All construction work after "A" work
TEL / DATA Conduit/cable at each tenant lot.
(including subscription procedure for single telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only All works, if necessary.
Chilled water pipe (910kW or 79 m3/hr ‐ delta T: 10 degC) with BTU meter 
AIR‐CONDITIONING All construction Work after "A" Work
till demising wall above ceiling 
VENTILATION
Extenal wall louver & ducting till demising wall All construction Work after "A" Work
(EXHAUST & FRESH AIR)
MECHANICAL

SMOKE SPILL
All work require by regulations. All construction Work after "A" Work
SYSTEM
Till valve points in tenant premises. Water meter shall be installed lower than 1.5m for reading if water supply is 
WATER SUPPLY All construction Work after "A" Work. ( If necessary)
Water meter shall be handed over to tenant for installation. necessary.

Waste discharge pipe at tap of point at slab. ( FFL+100)
DRAINAGE/ WASTE PIPE All construction Work after "A" Work. ( If necessary) Limited to cases where the tenant is required.
(foods beverage tenant in cinema)
GAS SUPPLY NIL NIL

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point. Stop valve for fire hose reel. All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.

Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

EMERGENCY EXIT SIGN All work require by regulations. All construction Work after "A" Work


authorities
Tenant needs to get approval for its specification by AEON MALL & related 
EMERGENCY LIGHTING NIL All works.
authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. All construction Work after "A" Work
ALARM EQUIPMENT authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
Install input/output module from MFAP to tenant premises Wiring from speaker and sub receiver
ALERT SYSTEM authorities
WET CHEMICAL NIL NIL
ESCALATOR NIL Install escalators M15 & M16 (by Nominated Contractor) Escalator manufacturer shall be appointed by AEON MALL

NIL : Not Included
FFD : Fire Fighting Department
Page 54
C‐3. SCOPE OF WORK

C‐2‐03. SCOPE OF WORK FOR AMUSEMENT TENANT
AMUSEMENT
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the common areas/ 
FLOOR All construction Work after "A" Work Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL.
Demising wall  CONCRETE 
Bare concrete finish. All construction Work after "A" Work
WALLS
BRICK WALLS Concrete Block Wall Surface All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
DRAYWALL
LGS with GB (t12) Surface only All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
ARCHITECTURAL

PARTITIONS
CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work
All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Soffit of slab
etc..) 'EXIST SIGN' must be installed if needed

Install hanging wall at front of shop. 
SHOP FRONT All construction Work after "A" Work Ceiling heights comply with AEON MALL requirement.
Common area side with painting/ interior side without painting
SIGNAGE NIL All works such as wiring, graphics, light fixtures, etc.
SECURITY
NIL All works.
SHUTTER
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the 
ELECTRICAL

necessary form

All construction work after "A" work (including subscription procedure for single 
TEL / DATA Conduit/cable at each tenant lot.
telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only All works, if necessary.
Main air duct from AHU till demising wall + volume damper stop. Or 
AIR‐CONDITIONING volume damper + flange stop in case of duct line passing through tenant  All construction Work after "A" Work
premises.
VENTILATION
Main exhaust ducts and fresh air return ducts till demising wall with VD All construction Work after "A" Work Only in the case that restaurant in tenant area will need
(EXHAUST & FRESH AIR)
MECHANICAL

SMOKE SPILL
All work require by regulations. All construction Work after "A" Work
SYSTEM
Limited to cases where the tenant is required.
Till valve points in tenant premises.(if necessary)
WATER SUPPLY All construction Work after "A" Work. ( If necessary) Water meter shall be installed lower than 1.5m for reading if water supply is 
Water meter shall be handed over to tenant for installation.
necessary.
DRAINAGE/ Waste discharge pipe at tap of point at slab. ( FFL+100)
All construction Work after "A" Work. ( If necessary) Limited to cases where the tenant is required
WASTE PIPE (foods beverage tenant in cinema)
GAS SUPPLY NIL NIL

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.

EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

All work require by regulations. All construction Work after "A" Work
EXIT SIGN authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
NIL All works.
LIGHTING authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. All construction Work after "A" Work
ALARM EQUIPMENT authorities
EMERGENCY
NIL NIL Because the sound of emergency broadcasting is heard in Tenant
ALERT SYSTEM
WET CHEMICAL NIL NIL

NIL : Not Included
FFD : Fire Fighting Department
Page 55
C‐3. SCOPE OF WORK

C‐2‐04. SCOPE OF WORK FOR SERVICE TENANT
CLINIC, BEAUTY SALON & SPA, HAIR SALON, ENRICHMENT CLASSROOM, PET SHOP
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the common areas/ 
FLOOR All construction Work after "A" Work Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL.
CONCRETE 
Demising wall 
Bare concrete finish. All construction Work after "A" Work
WALLS
BRICK WALLS Concrete Block Wall Surface All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.
DRAYWALL
ARCHITECTURAL

LGS with GB (t12) Surface only All construction Work after "A" Work Full height walls will only be applied to fire‐resisting wall.


PARTITIONS
CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work
All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Soffit of slab
etc..) 'EXIST SIGN' must be installed if needed
Install hanging wall at front of shop. Common area side with painting/ 
SHOP FRONT All construction Work after "A" Work Ceiling heights comply with AEON MALL requirement.
interior side without painting
SIGNAGE NIL All works such as wiring, graphics, light fixtures, etc.
SECURITY
NIL All works.
SHUTTER
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the 
necessary form
ELECTRICAL

All construction work after "A" work
TEL / DATA Conduit/cable at each tenant lot.
(including subscription procedure for single telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only All works, if necessary.
Main air duct from AHU till demising wall + volume damper stop. Or 
AIR‐CONDITIONING volume damper + flanger stop in case of duct line passing through tenant  All construction Work after "A" Work
premises
VENTILATION
Ducting till demising wall All construction Work after "A" Work
MECHANICAL

(EXHAUST & FRESH AIR)
SMOKE SPILL
All work required by regulations. All construction Work after "A" Work
SYSTEM
Till valve points in tenant premises. Water meter shall be installed lower than 1.5m for reading if water supply is 
WATER SUPPLY All construction Work after "A" Work
Water meter shall be handed over to tenant for installation. necessary.
DRAINAGE/
Waste discharge pipe at tap of point at slab. ( FFL+100) (if necessary) All construction Work after "A" Work Hair/ Beauty saloon tenants MUST install straner/ hair trap at discharge outlets.
WASTE PIPE
GAS SUPPLY NIL NIL

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.

EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

All work required by regulations All construction Work after "A" Work
EXIT SIGN authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
NIL All works.
LIGHTING authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. All construction Work after "A" Work
ALARM EQUIPMENT authorities
EMERGENCY
NIL NIL Bacasue the sound of emergency broadcasting is heard in tenant.
ALERT SYSTEM
WET CHEMICAL NIL NIL
NIL : Not Included
FFD : Fire Fighting Department
Page 56
C‐3. SCOPE OF WORK

C‐2‐05. SCOPE OF WORK FOR FOOD & BEVERAGE TENANT
FOOD & BEVERAGE
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the common areas/  All construction Work after "A" Work
FLOOR Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL. Including water proofing and protection mortal in kitchen area
CONCRETE 
Bare concrete finish. All construction Work after "A" Work
Demising wall 
WALLS
All construction Work after "A" Work
BRICK WALLS Concrete Block Wall Surface Full height walls will only be applied to fire‐resisting wall.
including water proofing up to the height of the standard
All construction Work after "A" Work
ARCHITECTURAL

DRAYWALL
LGS with GB (t12) Surface only Including concrete block stacked for water proof compartmentalization at kitchen  Full height walls will only be applied to fire‐resisting wall.
PARTITIONS
area
CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work
Soffit of slab.
All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Terrace (indoor seating area) shall be same condition as building common 
etc..) 'EXIST SIGN' must be installed if needed
area.
Install hanging wall at front of shop. Common area side with painting/ 
SHOP FRONT All works. Ceiling heights comply with AEON MALL requirement.
interior side without painting
SIGNAGE NIL All works such as wiring, graphics, light fixtures, etc.
SECURITY
NIL All works.
SHUTTER
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER.
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the 
ELECTRICAL

necessary form
All construction work after "A" work
TEL / DATA Conduit/cable at each tenant lot.
(including subscription procedure for single telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only. All works, if necessary.
Only chilled water pipe with BTU meter till demising wall above ceiling, 
FCU by Tenants.
AIR‐CONDITIONING All construction Work after "A" Work
Terrace (indoor seating area) shall be provided main air duct from AHU till 
diffuser.
Duct for outdoor air for kitchen dedicated (KOA) shall be closed in the ceiling. 
VENTILATION
Main exhaust ducts and fresh air return ducts till demising wall with VD. All construction Work after "A" Work Outlet vent in the kitchen shall be connected without fail, and execute final 
(EXHAUST & FRESH AIR)
performance test with AEON MALL and "C" work contractor together.
SMOKE SPILL
MECHANICAL

All work required by regulations. All construction Work after "A" Work
SYSTEM
EQIUPMENT FOR FREEZER CASES waste discharge pipe at tap of point at slab. ( FFL+100) All construction Work after "A" Work Drainage of freezer equipment must be conntected to grease trap.
Till valve points in tenant premises. Water meter shall be installed lower than 1.5m for reading if water supply is 
WATER SUPPLY All Construction Work after "A" Work (if necessary)
Water meter shall be handed over to tenant for installation. necessary.
DRAINAGE/ Authority approval grease interceptor/ trap MUST BE provided by Tenants.
Waste discharge pipe at tap off point at slab. (FFL+100) All Construction Work after "A" Work (if necessary)
WASTE PIPE Removable strainers also MUST BE provided at all discharge outlets

STRICTLY NO alteration to gas piping before gas meter unless approval is obtained 
from AEON MALL.
Till isolation valve c/w Gas meter and Control panel.  All construction Work after "A" Work. C/w preparation and installation of Gas 
GAS SUPPLY ATI and ATO MUST BE obtained before gas supply is turned on.
Pipe work till FFL+1500mm. dectector.
Gas detector shall be installed lower than 0.3m, and Gas meter shall be installed 
lower than 1.5m for reading

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

All work required by regulations All construction Work after "A" Work
EXIT SIGN authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
NIL All works.
LIGHTING authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. Relocation and expansion work after "A" work
ALARM EQUIPMENT authorities
EMERGENCY
NIL NIL Bacasue the sound of emergency broadcasting is heard in tenant.
ALERT SYSTEM
WET CHEMICAL NIL NIL
NIL : Not Included
FFD : Fire Fighting Department
Page 57
C‐3. SCOPE OF WORK

C‐2‐06. SCOPE OF WORK FOR FOOD COURT TENANT
FOOD COURT
DESCRIPTION A WORKS C WORKS REMARKS
Bare concrete finished with ‐ 50mm drop from the common areas/  All construction Work after "A" Work
FLOOR Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL. Including water proofing and protection mortal in kitchen area
CONCRETE 
Bare concrete finish. All construction Work after "A" Work
Demising wall 
WALLS
All construction Work after "A" Work
BRICK WALLS Concrete Block Wall Surface Full height walls will only be applied to fire‐resisting wall.
including water proofing up to the height of the standard
ARCHITECTURAL

All construction Work after "A" Work
DRAYWALL
LGS with GB (t12) Surface only Including concrete block stacked for water proof compartmentalization at kitchen  Full height walls will only be applied to fire‐resisting wall.
PARTITIONS
area
CONCRETE COLUMNS Bare concrete finish. All construction Work after "A" Work
All construction Work after "A" Work (Suspended ceiling, painting, access cover  Ceiling heights comply with AEON MALL requirement.
CEILING Soffit of slab
etc..) 'EXIST SIGN' must be installed if needed
Install hanging wall at front of shop. Common area side with painting/ 
SHOP FRONT All works. Ceiling heights comply with AEON MALL requirement.
interior side without painting
SIGNAGE NIL All works such as wiring, graphics, light fixtures, etc.
SECURITY
NIL All works.
SHUTTER
EXPANSION JOINTS All works, if necessary NIL
If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC All works including relocation of and connection from TPN isolator, DB, lighting  by tenant for maintenance
Install Isolator in tenant premises and centralized electricity meter in ER
POWER SUPPLY fixtures/fitting, etc. All electrical works MUST BE carried by approved wiremen for submit the 
ELECTRICAL

necessary form
All construction work after "A" work
TEL / DATA Conduit/cable at each tenant lot.
(including subscription procedure for single telephone)
PA SYSTEM NIL All works, if necessary.
SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only. All works, if necessary.
Only chilled water pipe with BTU meter till demising wall above ceiling, 
AIR‐CONDITIONING All construction Work after "A" Work
FCU by Tenants.
Duct for outdoor air for kitchen dedicated (KOA) shall be closed in the ceiling. 
VENTILATION
Main exhaust ducts and fresh air return ducts till demising wall with VD All construction Work after "A" Work Outlet vent in the kitchen shall be connected without fail, and execute final 
(EXHAUST & FRESH AIR)
performance test with AEON MALL and "C" work contractor together.
SMOKE SPILL
All work required by regulations. All construction Work after "A" Work
SYSTEM
MECHANICAL

EQIUPMENT FOR FREEZER CASES waste discharge pipe at tap of point at slab. ( FFL+100) All construction Work after "A" Work Drainage of freezer equipment must be conntected to grease trap.


Till valve points in tenant premises. Water meter shall be installed lower than 1.5m for reading if water supply is 
WATER SUPPLY All Construction Work after "A" Work (if necessary)
Water meter shall be handed over to tenant for installation. necessary.
DRAINAGE/ Authority approval grease interceptor/ trap MUST BE provided by Tenants.
Waste discharge pipe at tap off point at slab. (FFL+100) All Construction Work after "A" Work (if necessary)
WASTE PIPE Removable strainers also MUST BE provided at all discharge outlets

STRICTLY NO alteration to gas piping before gas meter unless approval is obtained 
from AEON MALL.
Till isolation valve c/w Gas meter and Control panel.  All construction Work after "A" Work. C/w preparation and installation of Gas 
GAS SUPPLY ATI and ATO MUST BE obtained before gas supply is turned on.
Pipe work till FFL+1500mm. dectector.
Gas detector shall be installed lower than 0.3m, and Gas meter shall be installed 
lower than 1.5m for reading

In the event of ceiling installation, and if additional or adjustment of sprinkler 
SPRINKLER Heads up fire sprinkler with tapping point All construction Work after "A" Work
heads and piping was needed, such work shall be " C" work.
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
FIRE/ LIFE SAFTY

All work required by regulations All construction Work after "A" Work
EXIT SIGN authorities
EMERGENCY Tenant needs to get approval for its specification by AEON MALL & related 
NIL All works.
LIGHTING authorities
AUTOMATIC FIRE Tenant needs to get approval for its specification by AEON MALL & related 
All work required by regulations. Relocation and expansion work after "A" work
ALARM EQUIPMENT authorities
EMERGENCY
NIL NIL Bacasue the sound of emergency broadcasting is heard in tenant.
ALERT SYSTEM
WET CHEMICAL NIL NIL

NIL : Not Included
FFD : Fire Fighting Department
Page 58
C‐3. SCOPE OF WORK

C‐2‐07. SCOPE OF WORK FOR KOISK TENANT
KIOSK
DESCRIPTIONS A work C work REMARKS

Bare concrete finished with ‐ 50mm drop from the common areas/  All construction Work after "A" Work


FLOOR Tenants' finishing are to be similar with floor finished levels of shopping center.
corridor FFL. Including water proofing and protection mortal in kitchen area

CONCRETE 
Demising wall

Same condition as building common area NIL
WALLS
BRICK WALLS Same condition as building common area NIL
ARCHITECTURAL

DRAYWALL
Same condition as building common area Only open partition is allowed
PARTITIONS
CONCRETE COLUMNS Same condition as building common area NIL

Ceiling heights comply with AEON MALL requirement.
CEILING Same condition as building common area NIL
'EXIT SIGN' must be installed if needed.

SHOP FRONT NIL All works Ceiling heights comply with AEON MALL requirement.


SIGNAGE NIL All works such as wirings, graphics, light fixtures, etc.
SECURITY
NIL NIL Security shutter is not allowed
SHUTTER
EXPANSION JOINTS All works, if necessary. NIL

If TPN isolator is remained above the ceiling level, access panel MUST BE provided 
ELECTRIC Install Isolator at slab in tenant premises and and centralized electricity  All works including relocation of and connection from TPN isolator, DB, lighting  by Tenants for maintenance.
POWER SUPPLY meter in ER fixtures/fittings, etc. All electrical works must be carried by approved wiremen for submit the
necessary form.
ELECTRICAL

All Construction Work after "A" Work
TEL/ DATA Conduit/cable at each tenant lot.
(Including subscription procedure for single telephone)

PA SYSTEM NIL NIL


SECURITY SYSTEM NIL All works, if necessary.
CCTV SYSTEM Install CCTV at Cash register in tenant premises only All works, if necessary

AIR CONDITIONING Same condition as building common area NIL


VENTILATION
Same condition as building common area NIL
(EXHAUST & FRESH AIR)
SMOKE SPILL SYSTEM All work required by regulations. NIL
MECHANICAL

Till valve points at slab only. Water meter shall be installed lower than 1.5m for reading if
WATER SUPPLY All Construction Work after "A" Work (if necessary)
Water meter shall be handed over to tenant for installation.(if necessary) water supply is necessary.

DRAINAGE/ Authority approval grease interceptor/ trap MUST BE provided by Tenants.
Waste discharge pipe at tap off point at slab. (FFL+100)(if necessary) All Construction Work after "A" Work (if necessary)
WASTE PIPE Removable strainers also MUST BE provided at all discharge outlets

GAS SUPPLY NIL NIL


SPRINKLER  Same condition as building common area NIL
FIRE/LIFE SAFETY

EMERGENCY EXIT SIGN NIL NIL


EMERGENCY LIGHTING NIL NIL
AUTOMATIC FIRE
All work required by regulations. NIL
ALARM EQUIPMENT
EMERGENCY ALERT SYSTEM NIL NIL
WET CHEMICAL NIL NIL

NIL : Not Included
FFD : Fire Fighting Department
Page 59

D. TENANT DESIGN RESTRICTIONS
1.  LOADING RESTRICTIONS
2.  INSTRUCTION OF ELECTRICAL DISTRIBUTION BOARD
3.  INSTRUCTION OF VENTILATION FOR HOT POT & BBQ TENANT
Page 60
D‐1. LOADING RESTRICTIONS
D‐1‐01. LOADING RESTRICTION 1FL
Page 61
D‐1. LOADING RESTRICTIONS
D‐1‐02. LOADING RESTRICTION 2FL
Page 62
D‐1. LOADING RESTRICTIONS
D‐1‐03. LOADING RESTRICTION 3FL
Page 63
D‐1. LOADING RESTRICTIONS
D‐1‐04. LOADING RESTRICTION 4FL
Page 64
D‐1. LOADING RESTRICTIONS
D‐1‐05. LOADING RESTRICTION 4FL MEZZANINE 01
Page 65
D‐1. LOADING RESTRICTIONS
D‐1‐06. LOADING RESTRICTION 4FL MEZZANINE 02
Page 66
D‐2. INSTRUCTION OF ELECTRICAL DISTRIBUTION BOARD

D‐2‐01. INSTRUCTION 01
Page 67
D‐2. INSTRUCTION OF ELECTRICAL DISTRIBUTION BOARD

D‐2‐02. INSTRUCTION 02
Page 68
D‐2. INSTRUCTION OF ELECTRICAL DISTRIBUTION BOARD

D‐2‐03. INSTRUCTION 03
Page 69
D‐3. INSTRUCTION OF VENTILATION FOR HOT POT & BBQ

D‐3‐01. INSTRUCTION 01

1. Kitchen Exhaust duct (KEA) & Kitchen Fresh Air duct (KOA):

 All kitchen exhaust duct under table/ on floor should be use Galvanized steel duct thickness 1.2 mm or fireproof material (see Table 1)/ Tất cả ống hút
khói bếp lắp dưới bàn/trên sàn phải dùng ống thép mạ kẽm có chiều dày tối thiểu 1.2mm hoặc dùng vật liệu chống cháy (xem bảng 1).

 For kitchen Exhaust duct (included Flexible duct) under chair use material same as duct under table but need install heat insulation outside duct by
Rockwool thickness 50mm or other material same quality/ cho ống hút khí thải bếp (kể cả ống gió mềm) đặt dưới ghế ngồi dùng vật liệu như ống đặt
dưới bàn, nhưng cần phải bọc cách nhiệt bên ngoài ống gió bằng Rockwool dày 50mm hoặc vật liệu khác chất lượng tương tự.

 For kitchen Exhaust duct above ceiling use Galvanized steel duct thickness 1.2mm (included main kitchen exhaust duct & duct connect to Damper), and
install oil collection point on main kitchen exhaust duct/ cho ống hút khói bếp trên trần phải dung ống thép tráng kẽm dày 1.2mm (bao gồm ống hút khói
bếp chính & ống nối tới miệng gió), và phải lắp điểm thu dầu trên đường ống hút khói bêp chính.

 Install check point at exhaust duct under table/under chair/on floor for checking, oil collect & cleaning weekly (see Table 1)/ phải mở lỗ thăm tại ống hút
khói bếp dưới bàn/dưới ghế/trên sàn cho mục đính kiểm tra, thu dầu và vệ sinh định kỳ hang tuần (xem bảng 1).

 Should be install KOA duct (double duct system) for area install KEA duct/ phải lắp ống gió cấp khí tươi nhà bếp cho khu vực lắp ống hút khói bếp.

 After finished install need to take picture for evident & Witness by Tenant Coordinator/ sau khi đã hoàn thành lắp đặt cần phải chụp hình để minh chứng
và được chứng giám bởi đơn vị điều phối khách thuê.
Page 70
D‐3. INSTRUCTION OF VENTILATION FOR HOT POT & BBQ

D‐3‐02. INSTRUCTION 02

2. STOVES ROOM / PHÒNG BẾP LÒ ( LÒ THAN):


 Need to install sprinkler head 141oC & Rase Heat detector 93oC /phải lắp đặt đầu chữa cháy 141oC và đầu báo nhiệt loại gia tăng 93oC.
 Kitchen exhaust duct should be insulation by Rockwool thickness 50mm or other material same quality/ ống hút khói phải được bọc cách nhiệt bằng
Rockwool độ dày 50mm hoặc vật liệu khác chất lượng tương tự.
 Install thermostat for checking temperature inside room /lắp đặt nhiệt kế để kiểm tra nhiệt độ trong phòng này.
3. POWER CABLE INSTALL UNDER TABLE & CHAIRS/CÁP CẤP NGUỒN LẮP DƯỚI BÀN VÀ GHẾ:
 All Power cable under table & under chair should covered by insulation conduit or Flexible steel conduit (see table 1)/ Tất cả dây cáp đi nguồn đi dưới bàn
và ghế phải được bọc bởi ống luồn nhựa cứng hoặc ống mềm bằng sắt (xem bảng 1).
 Distance from Kitchen exhaust duct to Power cable minimum are 100mm/ khoảng cách từ ống hút khói nhà bếp tới cáp cấp nguồn tối thiểu phải cách
100mm.
4. LPG GAS System Install Under Table/ Hệ Thống GAS Lắp Đặt Dưới Bàn:
 All Gas Pipe must be test pressure 8.0 Kg/cm2 at least 10 hours / Tất cả đường ống GAS phải được kiểm tra áp lực 8.0 Kg/cm2 trong ít nhất 10 tiếng.
 At each Table using GAS need to install Gas leakage detector / tại mỗi bàn có dung GAS phải lắp đặt đầu dò GAS.
 All GAS Pipe, GAS detector, Valves … install under table should be easy for checking / Tất cả ống GAS, đầu dò GAS, Van …. Lắp đặt dưới bàn phải dễ
dàng kiểm tra được.
 Flexible hose from Steel Gas pipe to Gas Stove must be spared at least 300mm / ống mềm từ điểm cuối của ống Gas bằng thép tới bếp Gas phải làm dư ra
ít nhất 300mm.
 After finished install need to take picture for evident & Witness by Aeon Delight, Aeon Mall Operation/ sau khi đã hoàn thành lắp đặt cần phải chụp hình để
minh chứng và chứng giám bởi Aeon Delight, Ban Quản lý Aeon Mall.
5. Other M&E Items / Những hạng mục Cơ & Điện khác :
 All other items not required in this instruction, should follow Tenant hand book / Tất cả các hạng mục khác không yêu cầu trong hướng dẫn này, sẽ theo
hướng dẫn trong sổ tay khách thuê.
Page 71

E. DETAIL DRAWINGS
1. EXPANSION JOINT DETAILS
2. WATERPROOFING DETAILS (FOR REFERENCE)
Page 72
E‐1. EXPANSION JOINT DETAILS
E‐1‐01. EXPANSION JOINT TYPICAL DETAILS 01
Page 73
E‐1. EXPANSION JOINT DETAILS
E‐1‐02. EXPANSION JOINT TYPICAL DETAILS 02
Page 74
E‐1. EXPANSION JOINT DETAILS
E‐1‐03. EXPANSION JOINT TYPICAL DETAILS 1FL
Page 75
E‐1. EXPANSION JOINT DETAILS
E‐1‐04. EXPANSION JOINT TYPICAL DETAILS 2FL
Page 76
E‐1. EXPANSION JOINT DETAILS
E‐1‐05. EXPANSION JOINT TYPICAL DETAILS 3FL
Page 77
E‐1. EXPANSION JOINT DETAILS
E‐1‐06. EXPANSION JOINT TYPICAL DETAILS 4FL
Page 78
E‐2. WATERPROOFING DETAILS (FOR REFERENCE)
E‐2. WATERPROOFING TYPICAL DETAILS

You might also like