Project : PROPOSED 2-STOREY EXTENSION

Address : Gideo St., Metrogate Village, Marilao, Bulacan


Owner : Mr. Eduardo Yao
Subject : COST PROPOSAL

BILL OF QUANTITIES

ITEM DESCRIPTION UNIT QTY UNIT RATE TOTAL AMOUNT

DIVISION 01: BUILDING

1.1 FOUNDATION
Rebars kgs 850.00 20.00 17,000.00
Formworks sq.m 32.00 120.00 3,840.00
Concreting cu.m 17.00 185.00 3,145.00
Backfill & Compaction cu.m 45.00 75.00 3,375.00

1.2 FOOTING TIE BEAMS


Rebars kgs 2,960.00 20.00 59,200.00
Formworks sq.m 80.00 120.00 9,600.00
Concreting cu.m 12.00 185.00 2,220.00

1.3 SLAB ON FILL


Backfill & Compaction sq.m 160.00 20.00 3,200.00
Gravel Beddings cu.m 15.00 75.00 1,125.00
Rebars kgs 1,007.00 25.00 25,175.00
Concreting cu.m 24.00 185.00 4,440.00

1.4 COLUMNS
Rebars kgs 3,200.00 20.00 64,000.00
Formworks sq.m 117.00 120.00 14,040.00
Concreting cu.m 10.50 185.00 1,942.50

1.5 2ND FLOOR BEAMS/ SLAB/ STAIRS


Rebars kgs 6,300.00 20.00 126,000.00
Formworks sq.m 287.00 120.00 34,440.00
Concreting cu.m 38.00 185.00 7,030.00

1.6 ROOF BEAMS


Rebars kgs 2,620.00 20.00 52,400.00
Formworks sq.m 140.00 120.00 16,800.00
Concreting cu.m 18.10 185.00 3,348.50

1.7 MASONRY WORKS


6" CHB -
to Ground Floor sq.m 216.00 45.00 9,720.00
to Second Floor sq.m 193.00 45.00 8,685.00
to Parapet sq.m 38.00 45.00 1,710.00

4" CHB
to Ground Floor sq.m 80.00 45.00 3,600.00
to Second Floor sq.m 54.00 45.00 2,430.00
Project : PROPOSED 2-STOREY EXTENSION
Address : Gideo St., Metrogate Village, Marilao, Bulacan
Owner : Mr. Eduardo Yao
Subject : COST PROPOSAL

BILL OF QUANTITIES

ITEM DESCRIPTION UNIT QTY UNIT RATE TOTAL AMOUNT

DIVISION 01: BUILDING

1.8 PLASTERING WORKS


Exterior Wall Plastering
Front sq.m 65.00 55.00 3,575.00
Left sq.m 126.00 55.00 6,930.00
Right sq.m 188.00 55.00 10,340.00
Rear sq.m 125.00 55.00 6,875.00

Mouldings/ Linear/ Lintel/ SC


Linear Meter Plastering lm 442.00 55.00 24,310.00
Lintel Beam lm 35.00 55.00 1,925.00

Interior Wall Plastering


to Ground Floor sq.m 365.00 51.00 18,615.00
to Second Floor sq.m 311.00 51.00 15,861.00

1.9 PLUMBING WORKS


Downspouts/ Drainage System lot 1.00 10,000.00 10,000.00
Sanitary Line/ Septic Tank lot 1.00 13,103.00 13,103.00
Water Line, PPR Pipes lot 1.00 10,000.00 10,000.00

GRAND TOTAL AMOUNT 600,000.00