MIXING RATIO 1 PART WATER: 3 PART LEAK PLUG. APPLY
TO CORNERS OF WALL OR PARAPET.
COVERAGE: 25 KG= 25 LINEAR METER
3. SAPAL RTU – STIR SAPAL RTU THOROUGHLY BEFORE USING.
4. APPLY SAPAL RTU ON THE PARAPET USING A ROLLER.
5. APPLY 3 COATS. WAIT FOR 2 HOURS BEFORE APPLYING
EACH COAT.
AREA COVERAGE: 16 LITERS = 104 SQ.M. PER COAT
4 LITERS= 26 SQ. M PER COAT 6. PREPARE EPOCOAT MB STIR PART A THOROUGHLY. (ACT AS A MOISTURE BARRIER) AREA COVERAGE: 1 GALLON (4LITERS) = 12 SQ.M. PER COAT
7. ADD PART B INTO PART A WHILE MIXING USING A LOW
SPEED ELECTRIC PADDLE MIXER. 8. MIX THOROUGHLY UNTIL IT BECOMES HOMOGENOUS. 9. POUR THE MIXTURE INTO THE SUBSTRATE SPREAD IT EVENLY ON THE AREA USING A SQUEEGEE & ROLLER. 10.LET IT CURE FOR 24 HRS. 11.PREPAPER CLEVERSIL. STIR IT THOUROUGHLY USING PADDLE MIXER. AREA COVERAGE: 15 SQ.M. PER 20 KG. (PER COAT)
12.USING ROLLER, APPLY THE FIRST COAT OF CLEVERSIL INTO
THE SUBSTRATE.
13.LET IT CURE FOR 2-3 HRS.
14.FOLLOWING A CRISS-CROSS PATTERN, APPLY THE 2ND COAT
HORIZONTALLY IF THE FIRST COAT WAS APPLIED VERTICALLY.
15. LET IT CURE FOR 7 DAYS.
TESTING AND COMMISSIONING PROCESS.
1. FLOOD THE AREA WITH WATER FOR 48 HRS. 2. CHECK BOTTOM OF SLAB FOR WATER PENETRATION.