You are on page 1of 6

Open in App

11
Home Answer Notifs

For civil engineers, how could I workout a rate analysis for shuttering
works?
4

Answer Follow Request More

3 Answers

Aveeral Jain, Civil Engineer, Project costing and commercials


Answered July 17, 2015

Rate Analysis can be furcated into the basic sub-heads

1. Material

2. Labor

3. Plant, Machinery, Vehicles, Tools and Tackles

4. Indirect Costs, Overheads and Bottom-line.

MATERIAL
Shuttering material can further be bifurcated into to sub-heads, System Material (Usually metal
components like MS Plates, Aluminium primary and secondary beams, base jacks, ledgers, verticals etc.)
and Shuttering consumables (Spigot pins, pine wood used as runners, battens, ply etc.)

Depending on your temporary loading requirement, scope of project, available funds and project timeline,
finalize the type of formwork system to be used (ref. Formwork or TYPES OF FORMWORK
(SHUTTERING)

System components usually can be used multiple times and hence one must account only the depreciation
for the period of time through which the system is being used. For a project as a whole, you must also
account for idling time. Details on methods to depreciate the system should be worked out based on the
lifetime, capital investment and time value of money.

Consumables should be estimated based on actual usage. It changes as per the elements like verticals
(columns and walls) and horizontals (slabs, beams etc.)

LABOR
Depending upon the type the formwork system implemented, labour requirements are as follows:

Labor for Shuttering making/fabrication - to fabricate panels of specific size and remaking of
previously used panels.

Labor for
Upvote · 10shifting/lifting
Share the required material
Opento all leads and lifts.
in App
Labor charges for Staging, Decking, Skin and Leveling. Extra charges for unconventional heights
and Extra for working at levels above ground floor.

Labor charges for Cross Bracing, Back Propping and other Misc. activities if necessary

Labor charges for De-shuttering, De-staging and Housekeeping.

- Determine a productivity based on past experience/local-national-international standard.


- Determine Wages taking in account minimum wage, Provident fund and other mandatory and
statutory requirements.
- Calculate the labor cost as per the wages and productivity determined.

Plant, Machinery, Vehicles, Tools and Tackles


If you are estimating for a project, you must take care of all the required P&M and load the same amount
on total quantity of shuttering. By this you'll get an average unit rate. E.g. Project wide tower crane expense
amounts to ₹10,000,000, on a project where roughly 1 Mi SqM of shuttering is to be done. This amount
need to be distributed on all the activities where tower crane will be used. Roughly load 30% of this on
Formwork.

= (10,000,000*30%)/1,000,000 = ₹3/sqm

Indirect Costs, Overheads and Bottom-line.


This includes all the expenses which cannot be directly attributed to, but are incurred to carry out the
proposed activity. E.g. salary of design engineer, fabrication supervisor, foreman and project manager or
office running expenses or water and electricity charges

Bottom line is the profit at which the firm wants to operate. End of day "Bottom line" is the final motivation
:P

Hope this helps. Comment for further inquiries.


7.6K views · View Upvoters

2 comments from CA Siddharth Jain

Ajinkya Joshi, Civil Engineer, Construction Freak.


Upvote · 8 Share
Answered July 16, 2015

I am assuming you are looking for a rate analysis for shuttering with an intention of quoting the rate in a
bid.

Rate analysis for shuttering changes quite a lot depending on the type of structure and the type of
shuttering scheme. For a building,you get a higher number of repetitions. The number of repetitions will
further depend on the material you will use. Similarly for shuttering for a water tank or a podium slab, you
will get fewer repetitions since the plan and the sections will not be typical for each time you use the
Open in App
material and cutting wastage increases. Continue Reading
g
As a general rule, work out th

Add a comment...

Related Spaces (More Answers Below)

The Engineering Mentor Structural Engineers UK TeensFo Geotechnical Analysis Expats in


Mentors helped me to UK structural Welcome to TeensFo. Geotechnical Analysis A space
engineering success, engineering resource for Here, you will LEARN, and Design of working
now I pay it forward CPD or preparing for th… SOCIALIZE and… subsurface structures Saudi Ara

Follow 13.2K Follow 1.6K Follow 84 Follow 94 Fo

View More Spaces

Asafa Khan, Civil Engineer


Upvote · 4 Share
Answered July 13, 2015
Originally Answered: This question related to my profession, any civil engineers can clarify my doubts. How to workout rate analysis
for shuttering works?
TABLE 1 PROFORMA FOR ANALYSIS OF UNIT RATE OF SHUTTERING/FORMWORK of Page on bis.org.in
3K views · View Upvoters · Answer requested by Viruthes Waran

Add a comment...

Related Questions & Answers

How do I work out rate analysis for shuttering works for columns, beams, etc.?
Najaf Ali, Masters in Structural and Earthquake Engineering
Answered July 16, 2015

Originally Answered: How do I must workout rate analysis for shuttering works for columns, beams etc.? Provided with an example.
To start off, I need to let you know that I have construction experience in Pakistan, I will tell you how things
are done here and it will most probably be the same in many parts of the world. For example, the column
dimensions under consideration are 2'x2' concrete column Read More

What is the analysis of rate for supply and fixing reinforcement in columns using 20mm
steel? Open in App
Prasanta Dey, 8 years of experience in construction field
Answered September 7, 2016

Originally Answered: what is the analysis of rate for supply and fixing reinforcement in columns using 20mm steel?
For analysis of rate u have to calculate under following :- 1. Materials 2. Labours 3. P&M 4. Overhead
5. Profit Lets clear it with an example… Considering 1MT of reinforcement work, A) Materials:- 1. Cost of
TMT Bars - 1.03MT at the rate of Rs.48,000/MT = Rs.49440/- 2. Cost of Binding Wire - 7Kg at theReadrate of…
More

What is the standard method of rate analysis in civil works?


Guru Raj, studied Civil Engineering at Indian Institutes of Technology (2012)
Answered October 3, 2018

The rate analysis is the very toughest task in the project budget. The rate analysis of civil works has
contains different activity like the cost of material, manpower and equipment, etc. Rate Analysis 1. To
Determine the project value. 2. Estimate the required resource. 3. Based on the project value we Read
couldMore
in

How can one rate the analysis for the shuttering works of slabs, columns, beams, etc.?
Aveeral Jain, Civil Engineer, Project costing and commercials
Answered July 21, 2015

Refer my answer Aveeral Jain's answer to For civil engineers, how could I workout a rate analysis for
shuttering works?

Why are water charges of 1% added to the analysis of rates for civil works?
Vishal Godhwani
Answered March 8, 2017

Water that is used for construction activities is charged by the municipal corporation. They charge about
0.5 Rs/litre. So the civil contractor either includes water charge of 1% of total amount at the end of bill or
calculates the volume of water required and multiplies it with rate while calculating Read More

What is the labour rate for cutting and fixing reinforcement in footing, stub columns
and plinth beams?
Rajat Kalinga
Answered November 26, 2017

The question has many things missing. As the rate not only depends on specific work it also depends on
state wise(locality) according to available source,weather condition,local trend beside this various other
factor even working time schedule to achieve the target is also considered. However to get Read More

How do I calculate the number of props required for a 1000 sq. ft. slab area?
Pankaj Goel
Answered July 5, 2018

Very easy steps for calculating no of props : Area of shuttering plate is = (900 X 600) mm =0.54 sq mt
1000 sq feet area = 92.94 sq mt No of sheet = (92.94/0.54) = 172 Nos Total no of MS sheet required for
1000 sq feet area is = 172 Nos Total no of span required for 1000 sq feet area is = (172 / 5) = 35Read
N More

Is there any thumb rule to calculate the shuttering quantities in construction when a
Open in App
concrete quantity is known?
Vivek Kumar, Planning Engineer Civil
Answered January 4, 2018

Yes there is a thumb rule for it. It surely depends on the structural elements to be concreted. For eg: take a
beam of size 200*300 mm and length 5m. Then the total concrete required will be l*b*h i.e .2*.3*5 = 0.3
m3. Now let's calculate it's shuttering quantity. Suppose it's not a plinth beam and Read More

How much quantity of steel required for 1m3 concrete?


Ashwath Krishnan, BTech Civil Engineering & Lpg Industry, SASTRA University, Thanjavur
(2016)
Answered May 2, 2017

Quantity of steel is not dependent on the volume of concrete, but on the structure where it is being used.
Slabs: 0.7 to 1.0%, Beams: 1% to 2%, Columns: 1% to 5% It may vary depending upon the loading condition
as well For Example Lets take example of RCC Column, where reinforcement required is 2 % of Read More

Related Questions

How do I work out rate analysis for shuttering works for columns, beams, etc.?
9,169 Views

What is the analysis of rate for supply and fixing reinforcement in columns using 20mm steel?
10,805 Views

What is the standard method of rate analysis in civil works?


2,637 Views

How can one rate the analysis for the shuttering works of slabs, columns, beams, etc.?
3,534 Views

Why are water charges of 1% added to the analysis of rates for civil works?
2,331 Views

What is the labour rate for cutting and fixing reinforcement in footing, stub columns and plinth
beams?
999 Views

How do I calculate the number of props required for a 1000 sq. ft. slab area?
20,687 Views

Is there any thumb rule to calculate the shuttering quantities in construction when a concrete
quantity is known?
10,163 Views

How much quantity of steel required for 1m3 concrete?


176,613 Views

Can a civil engineer work as an architect?


66,308 Views

Ask New Question

Open in App
Open in App

You might also like