Professional Documents
Culture Documents
ABSTRACT
As a popular saying goes ' a penny saved is a penny gained' this will be apt in the field of
construction because it is facing huge losses because of internal reasons like wastage, delay, poor
quality of work, improper planning etc. These factors are directly affecting the industry on the
site rather than off the site, most of the traditional methods present today are trying to improve
on site performance from off the site in which they are failing miserably. Lean construction is a
concept which is derived from TPS which was designed by Toyota for manufacturing purpose,
after lot of Improvisation by many people it had been brought into the field of construction.
The main concept of lean method is 'Minimizing waste and Maximizing value' , main goals of
this method is to reduce the overall cost of the project, improve the quality of work done,
reducing wastage on site, increasing value and respect to the workers. In spite of the fast growth
in the Indian construction sector it is still running in losses due to various reasons like not
welcoming new improvisations in technique, latest machinery not being available and many
more. Lean techniques are being implemented in various countries on a very larger scale, but in
Indian scenario it is not being accepted. This paper is about implementation of lean techniques in
Indian scenario and testing its fitness. Six construction sites were selected where in after initial
observation the quantity of work done is calculated. From the six major techniques available best
techniques suitable in the site are suggested and implemented. The techniques majorly used are
5S, Daily Huddle Meetings, Increased Visualization and Last Planner. Cost per unit was also
calculated based on the wages given to the labours, In each site there was a variation in teaming
of mason and labours in order to find out which combination is cost effective While
implementation the quantity of work done is calculated on daily bases for ten weeks
KEYWORDS: Lean Construction, Implementation, 5S , Daily Huddle Meeting, Increased
Visualization.
INTRODUCTION
As a famous saying goes "a Penny saved is a Penny Gained". In construction industry we don't
need to generate extra profits instead the savings we'll manage will leave us with huge
profits.The main theme of this idea is “Maximize value and minimize waste”“…the application
of lean thinking to the design & construction process creating improved project delivery to
meet client needs and improved efficiency for constructors”1
In Indian construction industry there has been a lot of transformation in last two decades in spite
of that sufficient profits are not been made, which will hinder the growth of the industry. Even in
today's modern world where in latest technology and techniques are in use, in our country even
LITERATURE REVIEW
O. Salemand others (2006) stated that this article compares the techniques developed for lean
construction with those developed for lean manufacturing The assessment tool evaluates six lean
construction elements: last planner, increased visualization, huddle meetings, first-run studies,
five S’s, and fail safe for quality
A.A. Dania et al (2002)depicts thatConstruction Waste Management is an aspect of Sustainable
Development, which is fuelled by the growing concern for the effect of man’s activities on the
environment. . The study found out that specific Government legislation on wastes from
construction sites were non-existent and that the respondents considered other project goals of
timely project delivery, quality and cost as more important than the impact of the project on the
environment
Raid Al-Aomar (2012) analyzed the current lean construction practices amongst Abu Dhabi
construction companies and develop a practical framework for adapting lean construction
techniques and measuring its performance, the study identified 27 construction wastes in AD
Construction industry. It also found that by the implementation of lean techniques the amount of
waste generation had been drastically cut down, hence reducing te cost of the project
DATA COLLECTION
Five construction sites were selected for the implementation of lean technique; an initial
observation was done for a period of 10 days. During the observation various happenings at the
site were recorded along with the quantity of work done
Different forms of wastages/ delays occurring on the site
Due to improper cleaning to tools lot of rework had been done which was slowing down
the progress of work happening
As the workers didn't have specific target because of which they were not striving for
anything
Safety was also clearly lacking on the site which may prove fatal
Lot of hard work was put in instead of smart work
Very less technology was used on the site
Lack of knowledge about the new innovations
Lack of information about the alternate materials which can be used
Difficulty in movement of raw material from dumping place to working place.
Due to monsoon season lot of external plastering had been damaged due to regular rains
Improper planning for the next day
The above factors are affecting the work at site indirectly and have been ignored for a long time
hence the productivity has been reducing on regular bases. Different events observed are Brick
Work in three levels i.e. (0'-3', 3'-7',7'-10') , two coats of plastering (first and second), putty and
painting. The average work for ten days had been mentioned for various sites
Table 1: Data collected at various sites
400
500 350
Quantity of work done
in cubic feet
300
400 250
in cubic feet
300 200
150 before
200 before
100 after
after
100 50
0 0
Site Site Site Site Site Site Site Site Site Site
1 2 3 4 5 1 2 3 4 5
250 500
in square feet
200
in cubic feet
400
150 before 300 before
100 after 200 after
50 100
0 0
1 2 3 4 5 Site Site Site Site Site
te te te te te
Si Si Si Si Si 1 2 3 4 5
Plastering 2coat
2000
1800
Quantity of work done in
1600
1400
square feet
1200
1000 before
800 after
600
400
200
0
Site 1 Site 2 Site 3 Site 4 Site 5
Painting Putty
2500 1200
1000
Quantity of work done
in square feet
1500
600
1000 before before
400
after after
500 200
0 0
Site Site Site Site Site Site
3 4 5 3 4 5
TEAMING
The main aim of showing the variation in teaming is to find out effectiveness in each
combination. The cost analysis is the comparison between the cost paid per team and the quantity
of work done by that team. Cost analysis helps in giving the exact numbers which in long run
saves lot of money.
Table5: Cost per unit work done before and after implementation
DISCUSSIONS
Site-1: On an average of all the techniques implemented an improvement of 32% is observed in
first level of brick work, 28% in second level of brick work, 23% in third level of brick work,
29% in first coat of plastering and 60% in second coat of plastering.
Site-2: On an average of all the techniques implemented an improvement of 32% is observed in
first level of brick work, 24% in second level of brick work, 30% in third level of brick work,
31% in first coat of plastering and 60% in second coat of plastering.
Site-3: On an average of all the techniques implemented an improvement of 36% is observed in
first level of brick work, 31% in second level of brick work, 33% in third level of brick work,
35% in first coat of plastering, 58% in second coat of plastering, 29% in putty application and
45% in painting.
Site-4: On an average of all the techniques implemented an improvement of 27% is observed in
first level of brick work, 30% in second level of brick work, 29% in third level of brick work,
30% in first coat of plastering, 52% in second coat of plastering, 38% in putty application and
54% in painting
Site-5: On an average of all the techniques implemented an improvement of 37% is observed in
first level of brick work, 37% in second level of brick work, 30% in third level of brick work,
36% in first coat of plastering, 64% in second coat of plastering, 37% in putty application and
57% in painting
CONCLUSION
From the above values of implementation we can conclude that Lean Construction is
advantageous even in small and medium scale Indian construction sites. There had been a
growth of about 25%-35% in major events. The values which are obtained on site are the
ones with minimal training, if these techniques are used professionally with improved
training and advanced aids can give even better results. Hence it is concluded that lean
Construction is suitable locally in small and medium scale construction in Indian Scenario.
FUTURE SCOPE
• In this project the techniques are individually implemented, these techniques can be
implemented together. Implementation of Last Planner along with other lean techniques
is the best way to implement Lean Construction and obtain desired results.
• Modular construction satisfies all the necessities of lean construction, so the work on
modular construction based on lean can be followed as next step.
REFERENCES
Salem, O., et al. "Site implementation and assessment of lean construction techniques." Lean
Construction Journal 2.2 (2005): 1-21.
Dania, A. A., J. O. Kehinde, and K. Bala. "A study of construction material waste management
practices by construction firms in Nigeria." Proceedings of the 3rd Scottish Conference for
Postgraduate Researchers of the Built and Natural Environment, Glasgow. 2007.
Mossman, Alan. "Forum Paper." Lean Construction Journal (2009): 13.
Howell, Greg, and Glenn Ballard. "Implementing lean construction: understanding and
action." Proc. 6 th Ann. Conf. Intl. Group for Lean Constr. 1998.
More, Vinaya D., ShrikantCharhate, and Madhulika Sinha. "Lean Construction Techniques in
Indian Construction Industry: Some Analysis.“
Howell, Greg, and Glenn Ballard. "Implementing lean construction: understanding and
action." Proc. 6 th Ann. Conf. Intl. Group for Lean Constr. 1998.Johansen, Eric, and Lorenz
Walter. "Lean construction: Prospects for the German construction industry." Lean Construction
Journal 3.1 (2007): 19-32.
Mossman, Alan. "Why isn’t the UK construction industry going lean with gusto?." Lean
Construction Journal 5.1 (2009): 24-3