International Journal of Pure and Applied Mathematics

Volume 119 No. 14 2018, 957-967


ISSN: 1314-3395 (on-line version)
url: http://www.ijpam.eu
Special Issue
ijpam.eu

   
IMPLEMENTATION OF LEAN CONSTRUCTION IN RESIDENTIAL BUILDING PROJECTS
P.SelvaPrasanth M.E1., S.Ranjitha2, R.Tharanyalakshmi2
1
Assistant professor/ Department of Civil Engineering – IFET College of Engineering
2
Final year student- IFET College of Engineering

ABSTRACT: The construction revolution for the past minimising waste of material, time and effort. The
twenty years had experienced a decline in productivity quality of product will be decreased due to poor
when compared to other industrial revolution. To fight workmanship and improper management. The main
against this circumstance, lean principles have been objective of the lean construction principles is “Use less
introduced in the field of construction. Lean construction of everything and drive more value”.
is a new construction management philosophy which
caused a revolution in the manufacturing planning, AIM:
supply and assembly. This method was evolved from 1. The aim of our project is to implement the lean
lean manufacturing principles to reduce the production of construction tools in residential building projects
waste. The goal of our project is to apply the lean such as apartments, compact homes, villas, etc.
techniques in small scale construction projects such as 2. In order to minimise the waste and duration of the
residential buildings. This project deals with the various project period when compared to conventional
lean tools which includes Last planner system, Increased method, the usage of lean construction should be
visualization, Total Quality management, 5S process and adopted.
Just in time. These tools helps us to improve the short 3. The understanding between the contractors, labours
term scheduling effort and communication. The essence and the client can be improved which enhances the
of lean construction is increased by the elimination of smooth functioning of the business.
nonvalue adding activities from the construction. 4. The quality of the construction should be achieved
Keywords: Lean construction, Last planner system, efficiently. The barriers in implementing lean
Increased visualization, Total quality management, 5S construction should be identified through survey.
process, JIT, Non value adding activities, small scale OBJECTIVE: The objectives of the implementation of
construction. lean construction in residential building are
INTRODUCTION: Lean construction, as defined by the 1. To eliminate the nonvalue adding activities in the
Lean Construction Institute (LCI), is a production construction site
management-based project delivery system emphasizing 2. To enhance the flow of work by minimising the
the reliable and speedy delivery of value. The lean waiting period
approach is a consideration of the environment which is 3. To reduce cost and duration of the project
becoming an increasingly important part of the 4. To avoid the unnecessary labour movement and
construction culture. The basic five principles of lean material handling
thinking are value, value stream, flow, pull and 5. To provide safety for the workers in the site
perfection. It changes the focus of management to be 6. To eradicate the poor management control
proper. The customer value and the key processes will be 7. To manage the resource related activities very
focused for its continuous improvement. The formulation effectively
of the theoretical foundation of lean construction in the
construction management process from lean production PURPOSE: The purpose of our project are as follows
concept was introduced by The International Group of
1. The performance level of the construction project
Lean Construction. It delivers a complex, uncertain and
will be improved
quick project results which is carried over by this new
2. Involvement of the workers in the project can be
project delivery system. Up to 30% of construction cost
increased by effective deliverance of the logical
are due to factors such as mistakes, delays, inefficiencies
sequence by using pull approach method
and poor communication through surveys. Improvement
3. Proper scheduling for the standardised work
of delivery system will be more. It is also defined as a
completion is adopted
absolute way to enhance the production system in order
to obtain maximum amount of product value by
  

957
International Journal of Pure and Applied Mathematics Special Issue

   
4. Just in time approach helps in materials the input of lean in managing is increased, then the
distribution in a proper way performance outcome can be increased.
5. Daily hurdle meetings assures the proper
execution of the work The issues in conducting the work can be
rectified by the different tools such as
SCOPE: The scope of our project are as follows
 Last planner system for production planning and
1. To implement the method of lean construction designing (which is also called as collaborative
not only for larger constructions but also for planning)
small scale  Increased visualization for safety commitments
2. constructions such as compact homes, villas,  5S process for sorting, shining, set in order, sustain
apartments, etc,. and standardize
3. To reach this lean concepts all over the  First run studies for planning, doing, acting and
developing countries checking
4. To improve the value creation that is what the  Just In Time for enhancing the flow of materials and
client really wants successfully from the owner its supply
5. To eradicate the waste completely during  Total quality management for commitment of
construction and to increase the profit labours with respect to various work specifications
ADVANTAGES: The points that enhances the view of DATA COLLECTED:
lean construction are as follows
FIELD STUDY: The construction site should be visited
1. Continuous improvement in construction before initiating the work. The soil condition should be
industry analysed by the engineer should be verified thoroughly.
2. Focus on smart work through companies The materials which are selected based on the size of the
management rather than hard work by adopting project, climatic condition, material flow, economic
strategic plans for future factors, transportation facilities etc., also be checked.
3. Reduces waste production in the field which is Although the major problems arise due to situations
useful in increasing the profit faced by the crew members such as insufficient space for
4. Reduces the cost of the project storing materials in nearby site (in crowded area), labour
5. Customer satisfaction can be increased accommodation (when labours are hired from far
6. Better and smooth communication among owner, distance), material supply chain and its availability,
customer, labours and over all uncertain thefts, work delay etc., are identified.
7. Productivity increases
WORK PLAN FOR CONSTRUCTION OF A
PROJECT OVERVIEW: After the proper study of RESIDENTIAL BUILDING:
various literatures on lean construction, the questionnaire
was prepared. All the questions were framed in PAPER WORK:
numbering format such as 5 for larger occurrence of
problem, 4 for lower than that and so on. The various  Plot sale agreement
construction companies were visited and survey was  Construction agreement
made. The proper explanation for the questions were  Contract specification
given to the respondent of the company. The work flow  Time duration
of the construction project was visualised. Through  Labour cost
probable analysing, the barriers in the work were  Material cost
identified.  Other contingencies
 Secure financing
The analysis helped us to understand that there was no  Preparation of drawing plan as per client
clear view about lean construction techniques in the requirement
companies. The major drawbacks were observed and  Approval of drawing and estimation from
suitable solutions were given for eliminating the flaws in client
the work progress. The various lean tools were split by
 Approval from City Development Authority
specific elements with their principles. The application of
tools in the project can improve the construction flow. If

  

958
International Journal of Pure and Applied Mathematics Special Issue

   
PLOT WORK: different materials such as bricks, concrete blocks, stone
etc., Cement or lime mortar are used for appropriate
 MARKINGS OF BOUNDARIES – The physical bonding of blocks. Generally masonry is a high durable
marker is used to identify the boundary of the form of construction.
property with its direction. Several types of markings
which are used such as pillars, corners and obelisks. LINTEL PROVISION: A structural horizontal which is
It shows the fixing position of boundary where the provided that spans the opening or space between two
land starts. vertical supports. It is also a decorative element which is
 CLEANING- Before initiating the construction the architective or combined ornamental structured elelment.
obstructions in the construction area is removed and It is used in openings such as doors, windows, etc,.
the soil is made firm. The tree roots, organic matters which acts as a actual supporting. The different types of
were removed to avoid structural damages. lintels are there such as timber, steel, concrete, stone,
 PREPARATION OF SITE LAYOUT- After brick and reinforced concrete lintels. For bearing
cleaning grading must be done to prevent flowing of provision some specifications must be adopted like
water for the better foundation. Cutting and filling 10cm, height of lintel beam, 1/10th to 1/12th of span of
that is levelling of soil is done at required area. The lintel.
soil is stabilised to reduce the settling effect because
ROOFING: It is a covering of a building structure at the
the settlement of foundation may cause development
top position of building which acts as a protection or
of cracks on the building.
shelter. It is a part of building envelope. The feature of
EARTHWORK roofing depends on the following factors like type of
building, architectural design, availability of roofing
 STRIP TOP SOIL- The removal of top soil materials, and local culture of construction. It depends on
containing soil nutrients after the removal of existing method of supporting.
vegetations. The soil is made firm. The soil is either ELECTRICIAN WORK: The electrical work plays a
sand or gravel proper striping is done for further vital role in building construction. In trend, these works
construction process.
are adopted during the construction itself as a internal
 FOUNDATION MARKING- It is the initial stage fittings. The wiring works are not visible outer in recent
of construction where the outline of foundation is techniques. It should possess the Indian Standard codal
marked using pegs, white powder and strings. The provisions. So the planning must be in proper way. Those
dimensions of the plan are easy to set through electrical services are handled carefully during provision.
markings.
 EXCAVATION- Either the soil is soft or hard the CARPENTRY WORK: The carpentry work denotes the
excavation must be done for required depth with wooden work needed for the residential construction. It
appropriate equipment. In small size buildings (when includes doors, windows, lintel provisions etc., The
there is no further construction after the ground absolute fittings and jointings are provided for those
floor) the excavation is not required and belt can be structures.
provided in such a case.
PLUMBING WORK: It advance a wide application
FOUNDATION: In the foundation, the columns were everywhere in construction to convey the fluids by using
raised as per room dimensions. A better structure differnet plumbing systems such as pipes, valves, tanks,
depends on the foundation which is provided. The type plumbing fixtures and some other apparatuses. The
of footing can be choose with respect to the soil plumbing infrastructure reveals the good sanitation. The
properties. The column acts as a support for the load various materials used in plumbing are steel, copper and
bearing wall and roof. After filling the excavated area, a plastics. Septic tanks and sewage connections through
water proofing agent known as damp proof course is pipe fittings are enough strong to convey it
provided above the ground to prevent the entry of systematically. The jointings are made by casting,
dampness. It act as a barrier to prevent moisture welding and extrusion for tubes.
condition raising by capillary action of water. It may
provided either in horizontal or vertical direction. EXTERIOR FINISHES: It acts as a protective covering
or coating for the external walls of a building from rain,
MASONRY WORK: It is mainly done in constructing heat, frost and other external factors. The appearance will
load bearing and non-load bearing wall which are known be pleasant and decorative finishes as a whole. The
as masonry units. The masonry walls can be laid by using materials used for finishing the surfaces are plaster,
  

959
International Journal of Pure and Applied Mathematics Special Issue

   
mortar, metal cladding, ceramic tiles, glass etc., It also HANDOVER TO CLIENT: After the completion of all
fills the gaps or any voids presence in the surface of the works in structure with appropiate plannings, a whole
structure. An important purpose for plastering are fire structure must be inspected. If any fails to be occurred,
resistor and excess environmental changes. the work must be terminated properly. Atlast the
structure must be handover to the client with
FLOOR FINISHES: Any finishing materials provided satisfication.
in a floor to make it as a walking surfaces. The flooring
depends on the following factors such as cost, endurance, COMPANIES VISITED: The various companies
effectiveness, comfort, noise insulation and cleaning visited to propagate a study on the conventional method
effort. It should posses better slip resistance factor. The of construction and the understanding of lean concepts in
flooring also depends on the client desires. Depend on business administration are as the following
the nature and usages of building various follrings are
adopted.  Kishoure Construction
 AG Construction
PAINTING: It is applied in solid surface both in the  Panimalar Builders
external and internal surfaces of the building structure. It  Alaya Construction
will provide a aesthetical view of appearance. Also the
painting acts as a protective layer to prevent the structure The questionnaire has been raised to the companies and
from environmental conditions, weather impacts, water the highlighted problems faced by them are analysed
proofing, termite attack and increses the surface properly. The respondent plays an important role in
durability. answering the questions based on their real time
experience. The work flow can be analysed by supply
INTERIOR TRIM: Any trim provided around the chain of the materials and labours which is major part in
windows, doors, stairs, baseboards and as a internal the completion of the project work. The process of
finish. It is also referred to be molding or millwork for construction is considered as the manufacturing process
framing. The most common types of interior trim are as and the finished work is considered as product. The
follows- Shoe molding, Baseboard, Head jamb, Base cap, exclusion of non-value adding activities is very important
Head casing, Side jamb, Side casing, Chair railing, on the business phase. The idea of the organisation plan
Wainscoting, Crown, Ceiling medallion, Grille, Stool, should be considered as a part of managing power. The
Apron and Plinth block. build in character of the project work with respect to
customer satisfaction is found out through this
PLUMBING TRIM: It is a final stage of plumbing
experiment. The completion of work within the time and
work preliminary to terminal inspection. It includes pipe
job satisfaction along with perfection in the work up to
connections in fittings, fixtures and appliances.
expectance level is very much required for a business to
EXTERIOR LANDSCAPING: It deals with the visible run successfully.
appearance in external surface of the building. The area
KISHOURE CONSTRUCTION: Even though
of land must be landscaped for aesthetical views. It
Kishoure construction is one of the blooming companies
includes gardening, water bodies, lightings, landforms
in Villupuram it has some uncertain conditions which
and terrain provisions. The layout and the outcomes will
requires additional care to get rectified. In this
be good while landscaping contractor adopting the work.
construction, frequent waste categories are identified
HARDWARE FIXINGS: The hardwares in building such as Rework, Unnecessary material handling,
includes the fasteners like bolts, nuts, screws, spikes and Excessive surveillance, Clarifications required highly in
other metal fittings which usually supports the fixtures their working environment. Rather than these wastes,
like windows, doors and cabinets. The other materials are material wastes and damaged material also be found as
taps, faucets, sanitaries, door hinges, door handles, major waste categories. According to their Management
latches, switch plates and door knockers. It is often related, poor management control and excessive
available in following materials like brass, steel, bureaucracy, paperwork are found. In their Resources
aluminium, iron, plastic and stainless steel. The related, shortages, misuse, poor quality and theft are
hardwares are grouped under following categories such major problems faced. In their Information related,
as Bathroom hardware, Door hardware, Safety and delaying of project, unclear works are occurred.
Security hardware, Cabinet hardware, Plumbing
hardware, Furniture hardware and Curtain hardware.

  

960
International Journal of Pure and Applied Mathematics Special Issue

   
6 6
5
4
5
3
2
4 1
0
3

1
Fig 4 Chart of information related works at Kishoure
0
construction
UNNECESSARY MATERIAL HANDLING
UNCOMPLETED WORK
REWORK

UNNECESSARY LABOUR MOVEMENT

EXCESSIVE SUPERVISION
EXCESSIVE SPACE
DEFECTS
INTERRUPTIONS
MATERIAL WASTED

EXCESSIVE SURVEILLANCE

DELAYS
INEFFECTIVE WORK

DAMAGED MATERIAL

EXTRA PROCESSING
CLARIFICATIONS NEEDED
ABNORMAL EQUIPMENT WEARING

AG CONSTRUCTION: In this construction, only the


delaying of project and completion of the project would
be delayed sometimes. It is due to the situation across the
work when it was adopted. Except the delaying other
categories were slightly varied but no problem evolved
due to their proper planning. According to their
Management related, only the poor management control
was done. In their Resources related, excessive amount
was needed due to material cost in the market. Also the
Information related, it was seemed to be late and unclear
in their processing.

4.5
Fig 1 Chart of frequent waste categories at Kishoure 4
construction 3.5
3
6 2.5
5 2
4 1.5
3
2 1
1 0.5
0 0
UNNECESSARY LABOUR…
UNNECESSARY…

ABNORMAL EQUIPMENT…
EXCESSIVE SURVEILLANCE
DEFECTS

DAMAGED MATERIALS

EXCESSIVE SUPERVISION

DELAYS
EXTRA PROCESSING
INEFFECTIVE WORK

EXCESSIVE SPACE
UNCOMPLETED WORK
REWORK

INTERRUPTIONS
MATERIALS WASTED

CLARIFICATIONS NEEDED

Fig 2 Chart of management related jobs at Kishoure


construction

6
4 Fig 5 Chart of frequent waste categories at AG
2 construction
0

Fig 3 Chart of resource related works at Kishoure


construction
  

961
International Journal of Pure and Applied Mathematics Special Issue

   
3.5 only the slight defective or damages may occur in any of
3 their projects.
2.5
2
1.5
6
1
0.5
0 5

3
5 5 5
2 4
Fig 6 Chart of management related jobs at AG
construction
1 2
6 1 1 1 1 1 1 1 1 1 1 1
5 0
4

DELAYS
UNNECESSARY MATERIAL HANDLING
EXCESSIVE SURVEILLANCE

EXCESSIVE SPACE
UNCOMPLETED WORK
REWORK

INTERRUPTIONS

UNNECESSARY LABOUR MOVEMENT

EXCESSIVE SUPERVISION

EXTRA PROCESSING
CLARIFICATIONS NEEDED
ABNORMAL EQUIPMENT WEARING
INEFFECTIVE WORK
DEFECTS

DAMAGED MATERIAL
MATERIAL WASTED
3
2
1
0

Fig 7 Chart of resource related works at AG construction

3.5
3
2.5
2
1.5 Fig 9 Chart for frequent waste categories at Panimalar
1
0.5
0
builders

6
5
4
3
Fig 8 Chart of information related jobs at AG
2
construction
1
PANIMALAR BUILDERS: In this construction 0
company, the major frequent waste categories identified
BUREAUCRACY,PAPER
MANAGEMENT
REQUIREMENT

POOR MANAGEMENT

POOR PLANNING
UNNECESSARY

in their environment were excessive surveillance and


EXCESSIVE

CONTROL

supervision. The material storing during the project was


EXCESSIVE
CONTROL

WORK

highly required. In the congested area, it is highly


complicated to store the material in a place. According to
their Management related, excessive management control
is required. Also the bureaucracy and paperwork is
necessary. In their Resources related, the major problem
was excessive amount is required to complete the project Chart of management related jobs at Panimalar builders
due to market price values. In their Information related,

  

962
International Journal of Pure and Applied Mathematics Special Issue

   
4.5 6
4
3.5 5
3
2.5 4
2
1.5 3
1
0.5
0 2

UNNECESSARY LABOUR…
UNNECESSARY MATERIAL…

ABNORMAL EQUIPMENT…
DEFECTS

DAMAGED MATERIAL

DELAYS
EXTRA PROCESSING
EXCESSIVE SURVEILLANCE
EXCESSIVE SUPERVISION
EXCESSIVE SPACE
UNCOMPLETED WORK

INEFFECTIVE WORK
REWORK

INTERRUPTIONS

CLARIFICATIONS NEEDED
MATERIALS WASTED
Chart of resource related works at Panimalar builders

2.5
2
Fig 10 Chart for frequent waste categories at Aalaya
1.5
construction
1
0.5
0 6
5
4
3
2
1
0
Chart of information related jobs at Panimalar builders BUREAUCRACY,P
MANAGEMENT

MANAGEMENT

POOR PLANNING
REQUIREMENT
UNNECESSARY

EXCESSIVE

APERWORK
CONTROL

CONTROL

EXCESSIVE

AALAYA CONSTRUCTION: In this construction, the


POOR

frequent waste categories which were highly possible


such as excessive surveillance, supervision and space
required for materials storage in the construction site.
Also the damaged materials were obtained due to
improper purchasing. According to their Management Fig 11 Chart of management related jobs at Aalaya
related, the most complicated thing was the excessive construction
management control and also poor management control.
In their Resources related, excessive amount for project
rather than estimation, poor quality of material handling,
misusing the materials were found. In their Information
related, defective and damages of the structures were
slightly occurred.

  

963
International Journal of Pure and Applied Mathematics Special Issue

   
6 improvement of the process. The process involved in
Last Planner system are as the following
5
4 1. Master schedule
2. Phase schedule
3 3. Look ahead schedule
2 4. Weekly work plan
1
INCREASED VISUALIZATION: The increased
0 visualization is generally done to enhance the quality of
the project along with the safety factor. It comes under
controlling process in a firm. The standards are
established and the measure of actual performance is
taken into account. The actual performance of the work
is compared with the standard schedule. The results of
the comparison are considered and corrective actions are
Fig 12 Chart of resource related works at Aalaya made to control the prospect. The control made over
construction progress helps in enhancing productivity standards, cost
standards, time standards and quality standards. The
supervisor should possess the ability to use the power
and also the ability to handle the labours with good
4.5 motivation. The power of motivation can encourage the
4
3.5 working denomination with full involvement. The
3 empowered lay man is responsible the safety note in the
2.5
2 construction site. The various process involved in the
1.5 increased visualization are as the following
1
0.5 SAFETY COMMITMENTS: The safety commitments
0
are vital role for the workers in their working
environment. The need for safety lies a significance for
the life issues. Some of the rules to be adopted by the
management are as follows,

1. Restriction on entry to site of non-essential personnel


Fig 13 Chart of information related jobs at Panimalar 2. Establish controlled entry points to site
constructions 3. Coordinate operations of various trades working in
the same areas
LEAN CONSTRUCTION TOOLS
4. Provide fundamental site rules and orientation
LAST PLANNER SYSTEM: Production planning training to all persons at risk
system designed to produce predictable work flow and 5. Establish adequate lay down areas
rapid learning in programming, design, construction and 6. Everyone is obligated to refuse unsafe work
commissioning of projects is known as Last planner 7. All injuries are preventable
system. In USA it is known as pull planning system and 8. All levels of supervision are accountable for safety
in UK the system is well known as collaborative system. performance
The team that are ambitious, challenged and ready to 9. Our work is never so urgent or important that we
change with the circumstances suits this kind of system. cannot take time to do it safely
A strong reinforced coaching is required for adoption of
this last planner system. The idea of the work flow SAFETY SIGNS: The most popular construction site
according to the schedule is insisted into the minds of the warning signs are,
workers through orientation programs. The 1. Construction site keep out warning signs
implementation of the techniques are evaluated from the 2. Danger Men at work warning signs
result. The co-operation of the labours with the team 3. Asbestos removal in progress warning sign
leaders or engineers is very much required for the greater 4. Movement and equipment warning sign

  

964
International Journal of Pure and Applied Mathematics Special Issue

   
FIRST RUN STUDIES: First run studies (as lean 2. Field office huddles limit the opportunity to see
construction defines) are used to redesign critical concerns first hand. If a trade crew leader needs help
assignments, part of continuous improvement effort and with completing an operation or making an
include productivity. Studies and review work methods adjustment to the workflow for the following day it
for redesigning and streamlining the different functions is much easier to work through and agree on an
are involved. The criteria or change occurs by first run adjustment when everyone can directly see the work.
studies are, 3. Huddles in the field make the daily planning and
learning more visible to the crews. It’s important for
1. Actions on the site people to see that workflow reliability is a concern
2. Team effort and that leaders are engaged in supporting the work
3. Knowledge of the crews. People cannot see that when the
4. Communication meetings are behind closed doors.
5. Relation with other tools 4. Huddles in the field are one more opportunity to be
in the field observing the work. Seeing what is
5S PROCESS: The objective of 5S is to create a neat happening in the field is a far better way of
and orderly workplace with “a place for everything and understanding how to improve workflow than seeing
everything in its place”. The material, man power, what is happening on a computer screen or plan
machine, money and method are the basic 5Ms involved table.
in any construction process. The key elements of any 5S 5. Huddles in the field are an opportunity to mentor
program are: newer and assistant superintendents. Many projects
1. Sort – go through the tools, materials and equipment will require more than one daily huddle at certain
and keep only what is necessary to complete the stages of the construction. This is a chance for the
work. All else is eliminated or stored offsite senior superintendent to let less senior members of
2. Shine – clean up the workplace so it is an efficient the team gain leadership experience.
place where people are proud to work TOTAL QUALITY MANAGEMENT: The quality of
3. Set in Order – label and organize the space so it’s the project can be increased by improving supervision at
clear where everything belongs. A “shadow board” the site and by using good quality materials. Setting
for tools hung on the wall is a perfect example of objectives of the project according to the work
this. requirement and future goals is very important. The
4. Standardize – use standardized work to keep the availability of the material at the work place itself or near
space organized and maintain the progress by is the important factor to be considered on planning.
5. Sustain – sustain the improvement by empowering The reduction of cost is the main aim of the owner but
individuals to take responsibility for the space and good quality materials may lead to increase in the
develop new improvements regularly. investment for a project. This can be avoided by making
DAILY HURDLE MEETINGS: The main approach bond between the builders and the suppliers. The
dealt in lean construction is daily huddle meetings which performance depends upon the quality of the material
is contributed to increase work flow ability. The major used.
reasons for adopting huddle meetings in construction site CONCLUSION: The issues in conducting the work can
are as follows, be rectified by the different tools such as
1. Field office huddles generally takes more time. Trade 1. Last planner system for production planning and
crew leaders need to leave the place of the work, designing (which is also called as collaborative
travel to the field office and once the huddle is planning)
complete travel back to the place of the work for 2. Increased visualization for safety commitments
inducing correct way of approach in the construction. 3. 5S process for sorting, shining, set in order, sustain
Lean thinkers will recognize that extra travel as and standardize
waste of time and money. An additional time 4. First run studies for planning, doing, acting and
consideration is that field office meetings are often checking
sit-down meetings, and sit-down meetings have a 5. Total quality management for commitment of
way of inviting necessary conversation with the labours with respect to various work specifications
workers.

  

965
International Journal of Pure and Applied Mathematics Special Issue

   
REFERENCES
[1] Vinaya D.more, Dr.Shrikant Charhate and
Madhulika Sinha (2016) - Lean construction
techniques in Indian Construction Industry:Some
Analysis.
[2] Shaik Md Sami Pasha, B. Harish Naik (2016)- An
analysis of lean construction in Tamilnadu
construction industry.
[3] U.Vimal Kumar, Ganapathy Ramasamy (2016)- A
critical study of various lean techniques in practice
and developing a framework for different
construction building projects.
[4] Giorgio locatelli, Mauro Mancini, Giulia Gastaldo,
Federica Mazza (2013)- Improving Projects
Performance With Lean Construction: State Of
The Art, Applicability And Impacts.
[5] J.Rajprasad, Shuaibu Saminu, S.Harish Babu
(2012)- A Study and Application of Lean
Construction Techniques Using Last Planner
Concept in Residential Building.
[6] Ankit Bhatla, Dr. Bulu Pradhan (2010)-
Implementation of Lean construction in IIT
Guwahati.
[7] Bulent Algan Tezel (2007)- A Statistical approach
to lean construction implementations of
construction companies in Turkey.
[8] O.Salem, J.Solomon, A.Genaidy, I.Minkarah
(2006)- Lean Construction: From Theory to
Implementation.
[9] Aditi Javkhedkar (2006)- Applying lean
construction to concrete construction projects.
[10] Grey Howell, Glenn Ballard (1998)- Implementing
lean construction: understanding and action.

  

966
967
968