PROJECT NAME: ELEVATOR SHAFT (STEEL TUBULAR)

PROJECT LOCATION: Davao City


SCHEDULE

Duratio
Item No. Activity Start Finish
n (days)
A GENERAL WORKS
A.1 Mobilization 1 6-Sep-22 7-Sep-22
A.2 Site Clearing 1 6-Sep-22 7-Sep-22
A.3 Demobilization 1 3-Oct-22 4-Oct-22
B STRUCTURAL STEEL
B.1 Installation of Base Plate 1 7-Sep-22 8-Sep-22
B.2 Steel Erection (Column) (Basement to Ground FFL) 2 8-Sep-22 10-Sep-22
B.3 Steel Erection (Beam) (Basement to Ground FFL) 2 10-Sep-22 12-Sep-22
B.4 Full Welding (Basement to Ground FFL) 3 12-Sep-22 15-Sep-22
B.5 Steel Erection (Column) (Ground to Second FFL) 3 15-Sep-22 18-Sep-22
B.6 Steel Erection (Beam) (Ground to Second FFL) 3 19-Sep-22 22-Sep-22
B.7 Full Welding (Ground to Second FFL) 3 23-Sep-22 26-Sep-22
B.8 Steel Erection (Column) (Second to Third FFL) 3 26-Sep-22 29-Sep-22
B.9 Steel Erection (Beam) (Second to Third FFL) 3 29-Sep-22 2-Oct-22
B.10 Full Welding (Second to Third FFL) 3 3-Oct-22 6-Oct-22
B.11 Steel Erection (Column) (Third FFL to Apex) 3 6-Oct-22 9-Oct-22
B.12 Steel Erection (Beam) (Third FFL to Apex) 3 10-Oct-22 13-Oct-22
B.13 Full Welding (Third FFL to Apex) 3 13-Oct-22 16-Oct-22
C PAINTING WORKS
C.1 Painting of Steel Tubulars (Columns & Beams) (inc. rust conversion) 12 3-Oct-22 16-Oct-22

PREPARED BY:

CONTRACTOR