You are on page 1of 3

PROJECT: PROPOSED 1-STOREY RESIDENTIAL HOUSE

LOCATION: LOT 10, BLOCK 7, SANDARI BATULAO, BRGY. CAYLAWAY, NASUGBU, BATANGAS
OWNER: MR. & MRS. PERSEVERANDO & FLAVIANA CASTILLO

AREA: 85 sq.m.

SUBJECT: BILL OF MATERIALS


MATERIALS LABOR
ITEM SCOPE OF WORK QTY. UNIT TOTAL COST TOTAL ITEM COST
UNIT TOTAL UNIT TOTAL
I GENERAL REQUIREMENTS 60,000.00
A Site Preparation/Clearing 1.00 lot 25,000.00
B. Temporary Facilities 1.00 lot 25,000.00
C. Layout & Staking 1.00 lot 10,000.00
II EARTHWORKS 130,000.00
A Excavation works 1.00 lot 35,000.00
Column Footing
Wall Footing
Septic Tank, Catch Basin
B. Back Filling 1.00 lot 25,000.00
Column Footing
Wall Footing
C. Gravel Bedding 1.00 lot 20,000.00
D. Common Borrow 1.00 lot 15,000.00
E. Soil Poisoning 1.00 lot 10,000.00
F. Hauling of Debris/Cleaning 1.00 lot 25,000.00
III FORMWORKS & SCAFFOLDING 200,000.00
1.00 lot 200,000.00
Column footing,Wall Footing, Column, Slab on Fill, Masonry Wall,
Beams

IV CONCRETING (CLASS A CONCRETE MIX) 280,000.00


1.00 lot 280,000.00
Column footing,Wall Footing, Column, Slab on Fill, Masonry Wall,
Beams

V REBAR WORKS (dia. 9mm, 10mm, 12mm) 250,000.00


Column Footing 1.00 lot 250,000.00
Wall Footing
Columns
Slab (On fill)
Slab (Suspended)
Beams
Stair
#16 G.I. Tie Wire
VI MASONRY WORKS 270,000.00
A. CHB Laying 1.00 lot 120,000.00
B. Mortar & Filler 1.00 lot 80,000.00
Sand (Black), Cement, Rebar, Gi wire
C. Plastering 1.00 lot 70,000.00
Wall
Columns
Beams
VII DOORS AND WINDOWS 157,000.00
A. DOORS & JAMBS 1.00 lot 77,000.00
Flush Door Hollow Core (Marine Plywood)
B. DOOR JAMBS (Tanguile or equivalent) 40,000.00
C. Hardwares 40,000.00
Main Entrance & Service Door Lockset (Amerilock)
Interior Lockset (Amerilock)
Toilet/Bath Lockset (Amerilock)
Hinges (Stanley or Approved equal)

VIII CEILING WORKS 150,000.00


A. Ceiling Eaves (Spandrel) 1.00 lot 150,000.00
IX TRUSSES AND ROOFING WORKS 278,000.00
A. TRUSSES 1.00 lot 190,000.00
3.5mm x 50mm x 100mm, 3.5mm x 38mm x 38mm Angle Bar
1.0mm x 50mm x 75mm, 1.00mm x 50mm x 175mm G.I C-Purlins
B. ROOFING AND ACCESSORIES 1.00 lot 80,000.00
APO "Rib-Type" Ga. 26 Pre-Painted Long Span Color Roofing
C. 5mm Thk. P.E. Foam Insulation (1-side Aluminum) 1.00 lot 8,000.00
X SANITARY WORKS 205,000.00
A. WATER LINE (Ordinary blue pipes) 85,000.00
B. SEWER LINE (Ordinary Orange pipe) 60,000.00
C. FIXTURES WC 60,000.00
XI ELECTRICAL WORKS 190,000.00
A. Electrical Works 1.00 lot 190,000.00
XII PAINTING WORKS 250,000.00
Painting Works 1.00 lot 250,000.00
TOTAL COST P 2,420,000.00

Prepared By: Conforme by:

MR. & MRS. PERSEVERANDO & FLAVIANA CASTILLO


ENGR. JOMIN DENNIS M. MIEMBRO
Civil Engineer House Owner
PROJECT: PROPOSED 1-STOREY RESIDENTIAL HOUSE
LOCATION: BRGY. GUMAMELA, BALAYAN, BATANGAS
OWNER: MA. CONCEPCION ABELLERA
AREA: 63.8 sq.m.

SUBJECT: BILL OF MATERIALS


MATERIALS LABOR
ITEM SCOPE OF WORK QTY. UNIT TOTAL COST TOTAL ITEM COST
UNIT TOTAL UNIT TOTAL
I GENERAL REQUIREMENTS 18,060.00
1.00 lot

D. Site Preparation/Clearing 1.00 lot 6,000.00


E. Temporary Facilities 1.00 lot 5,980.00
F. Layout & Staking 1.00 lot 6,080.00
II EARTHWORKS 35,000.00
A Excavation works 1.00 lot 15,000.00
Column Footing
Wall Footing
Septic Tank, Catch Basin
B. Back Filling 1.00 lot 8,000.00
Column Footing
Wall Footing
C. Gravel Bedding 1.00 lot 2,000.00
D. Common Borrow 1.00 lot 1,500.00
E. Soil Poisoning 1.00 lot 1,500.00
F. Hauling of Debris/Cleaning 1.00 lot 7,000.00
III FORMWORKS & SCAFFOLDING 24,500.00
Column footing 1.00 lor 24,500.00
Wall footing
Column
Slab on fill
Suspended Slab
Masonry wall
Beams
Stairs
IV CONCRETING (CLASS A CONCRETE MIX) 240,000.00
Column Footing 1.00 lot 240,000.00
Wall Footing
Columns
Beams
Roof Beam
Slabs (On Fill/Suspended)
Stair
V REBAR WORKS (dia. 9mm, 10mm, 12mm) 340,000.00
Column Footing 1.00 lot 340,000.00
Wall Footing
Columns
Slab (On fill)
Slab (Suspended)
Beams
Stair
#16 G.I. Tie Wire
VI MASONRY WORKS 220,000.00
A. CHB Laying 1.00 lot 80,000.00
CHB 5"
CHB 4"
B. Mortar & Filler 1.00 lot 70,000.00
Sand (Black)
Cement
10mm dia. x 6m Def. Bars
#16 G.I. Tie Wire
Labor 70,000.00
C. Plastering (Black Sand) 1.00 lot
Wall
Columns
Beams
VII WATER PROOFING 21,500.00
A. Integral Type (GreenSeal) 1.00 lot 21,500.00
Viewing Deck, Second Floor T&B
VIII TILE WORKS 71,000.00
A. Living Room & Terrace 1.00 lot 25,000.00
B. Masters Bedroom 1.00 lot 17,000.00
C. Bedroom 1 1.00 lot 19,000.00
D. Toilet 1.00 lot 10,000.00
IX DOORS AND WINDOWS 65,000.00
A. DOORS & JAMBS 1.00 lot 25,000.00
2-Sets Solid Panel Door (Tanguile or equivalent)
6-Sets Flush Door Hollow Core (Marine Plywood)
B. DOOR JAMBS (Tanguile or equivalent) 10,000.00
C. Hardwares 8,000.00
Main Entrance & Service Door Lockset (Amerilock)
Interior Lockset (Amerilock)
Toilet/Bath Lockset (Amerilock)
Hinges (Stanley or Approved equal)
D. WINDOWS AND FRAMES (w/ out Insect Screen) 1.00 lot 22,000.00
SLIDING DOOR & FRAMES (w/ out Insect Screen)
Aluminum Frame Analok Finish w/ 6mm Thk. Bronze Glass
X CARPENTRY WORKS 27,000.00
A. Kitchen Cabinet (Plyboard) 1.00 lot 13,000.00
B. Bedroom Closet (Plyboard) 1.00 lot 14,000.00
XI CEILING WORKS 35,000.00
A. Interior Ceiling (9.0mm Thk. Gypsum Board on Metal Framing) 1.00 lot 25,000.00
C. Ceiling Eaves (4.5mm Thk. Ficemboard on Metal Framing) 1.00 lot 10,000.00
XII TRUSSES AND ROOFING WORKS 70,500.00
A. TRUSSES 1.00 lot 45,000.00
3.5mm x 50mm x 50mm, 3.5mm x 38mm x 38mm Angle Bar
1.0mm x 50mm x 75mm, 1.00mm x 50mm x 175mm G.I C-Purlins
B. ROOFING AND ACCESSORIES 1.00 lot 22,000.00
APO "Rib-Type" Ga. 26 Pre-Painted Long Span Color Roofing
C. 5mm Thk. P.E. Foam Insulation (1-side Aluminum) 1.00 lot 3,500.00
XIII SANITARY WORKS 47,000.00
A. WATER LINE (Ordinary blue pipes) 20,000.00
B. SEWER LINE (Ordinary Orange pipe) 17,000.00
C. FIXTURES WC 10,000.00
XIV ELECTRICAL WORKS 65,000.00
A. Electrical Works 1.00 lot 65,000.00
XV PAINTING WORKS 60,000.00
A. Painting WOrks 1.00 lot 60,000.00
TOTAL COST P 1,339,560.00

Prepared By: Conforme by:

ENGR. JOMIN DENNIS M. MIEMBRO MA. CONCEPCION ABELLERA


Civil Engineer House Owner

You might also like