You are on page 1of 70

Classification: Internal

BOOT: PROJECT FINANCE


SIMPLIFIED - HEATHROW
Classification: Internal

LEARNING OBJECTIVES

1 Learn business case of a regulated airport

2 Understand the main PF components in a deal

3 Understand the complexities

4 Learn the process for optimizing a deal


Classification: Internal

HEATHROW - OVERVIEW
Project Inception
• In early 2010, the Department for Transport predicted a significant increase in
air passengers in England, and London specifically.
• In 2012 British Airports Authority (BAA), a privately held company, announced
record traffic figures for passengers, accelerating the need for expansion
• An independent body, the IAC (Independent Airports Commission) was
established by the Government to look at a possible expansion at currently
existing airports: Heathrow, Stanstead and Gatwick.
• In 2015, IAC unanimously recommended an additional runway at Heathrow
• In 2020, runway at Heathrow ruled illegal over climate change
Classification: Internal

HEATHROW - OVERVIEW
Classification: Internal

BUSINESS CASE OF AN AIRPORT


Take-off

Aero rev
Landing

Retail

Non-aero rev Carpark


Advertising
Other
Classification: Internal

BUSINESS CASE OF AN AIRPORT


Revenue comes from Aero + Non-Aero revenue

Take-off

Regulated Aero rev


Landing

Retail
Non-
Non-aero rev Carpark
regulated
Advertising
Other
Classification: Internal

FINANCING COSTS
Aero charges are regulated via a max WACC

Weighted average
cost of capital

60% Debt
5% p.a.

40% Equity 11% p.a.

WACC = 60% * 5% p.a. + 40% * 11% p.a.


3% p.a. + 4.4% p.a.
7.4% p.a.
Classification: Internal

FINANCING COSTS
Aero charges are regulated via a max WACC
The Civil Aviation Authority (CAA) are a public body responsible in part for value
for money for the consumer. They set the WACC for the project (e.g. = 6% p.a.)
for a 5 year regulatory period

Aero rev Opex

Capex
Non-aero rev
Financing
Classification: Internal

FINANCING COSTS
Calculate Aero charges after calculating Financing costs
Financing costs = WACC * RAB

Aero rev Opex

Capex
Non-aero rev
Financing
Classification: Internal

FINANCING COSTS
Financing the Investment
A return of the investment amount * WACC compensates for the cost of
financing the investment

RAB: Regulated
Asset Base

Investm
ent = RAB =
£10bn £Xbn ?
Classification: Internal

FINANCING COSTS
Financing the Investment
A return of the investment amount * WACC compensates for the cost of
financing the investment
Investm
ent
£10bn
RAB * RAB * RAB * RAB* RAB*
WACC WACC WACC WACC … WACC

Investm
ent =
£10bn
Classification: Internal

FINANCING COSTS
Financing the Investment
A return of the investment amount * WACC compensates for the cost of
financing the investment

RAB * RAB * RAB * RAB* RAB* RAB* RAB*


WACC WACC WACC WACC … WACC WACC WACC …

Investm
ent =
£10bn
Classification: Internal

REVENUE PER PAX


Aero revenue can now be calculated on a per passenger basis
E.g. If Opex + Capex + Financing = £1.75bn, non-aero revenue = £1bn

£1.75bn

Aero rev Opex

£1bn Capex
Non-aero rev
Financing
Classification: Internal

REVENUE PER PAX


Aero revenue can now be calculated on a per passenger basis
E.g. If Opex + Capex + Financing = £1.75bn, non-aero revenue = £1bn
Then aero revenue needs to be £0.75bn
Cost per PAX = £0.75bn / 30m passengers = £25

£0.75bn £1.75bn

Aero rev Opex

£1bn Capex
Non-aero rev
Financing
Classification: Internal

TIMELINE

8 years 7 years 25+ years

Project Development Construction Operations


Classification: Internal

TIMELINE

8 years 3 years 25/30 years

Project Development Construction Operations


Classification: Internal

TIMELINE

8 years

Project Development Construction Operations


Classification: Internal

PROCESS
Project Development
Construction Operations Negotiations

Construction

1 Uses of capital (e.g. £10bn construction + IDC + financing fees)

2 Sources of capital (e.g. debt + equity)


OVERVIEW OF PROCESS
Classification: Internal

Project Development
Construction Operations Negotiations

Operations – calculations

3 Revenue: aero (price x volume) & non-aero (not broken down)

4 Opex & Capex: Simple assumptions – no major lifecycle capex

5 Debt – Principal: Fixed repayment style vs annuity

6 Debt – Interest: All-in rate vs base rate + margin

7 Tax: Simple tax calculation vs tax depreciation & tax losses


OVERVIEW OF PROCESS
Classification: Internal

Project Development
Construction Operations Negotiations

Operations – cashflows & metrics

8 CFADS & CFAE – simple structure

9 DSCR – Debt Service Coverage Ratio – CFADS / [Interest + Principal]

10 LLCR – Loan Life Coverage Ratio – discount CFADS to today : Debt balance

11 Equity IRR – returns to equity holders

12 Project IRR – returns to debt & equity


Classification: Internal

PROCESS
Project Development
Construction Operations Negotiations

13 Negotiations & optimizations

i Debt – max gearing & min DSCR

ii Equity – min IRR

iii CAA – acceptable to consumers


Classification: Internal

PROCESS
Project Development
Construction Operations Negotiations

13 Negotiations & optimizations – using a scenario manager

i Debt – annuity style of repayment

ii Longer concession – an extra 5 years of revenues

iii Longer debt tenor – an extra 5 years to repay debt

iv Increased gearing – debt finance 80% of capex rather than 70%

v All changes – all simultaneously


Classification: Internal

FEASIBILITY
Project Development
Construction Operations Negotiations

Work done to-date

A Heathrow conducted feasibility study and submitted a master plan for the
construction of 3rd runway to the government.
B SPV estimated £10 bn for third runway expansion design & construction.
Financed with
£7bn debt, syndicated through a consortium of lenders
£3bn equity, provided by current owners (e.g. Ferrovial)
Classification: Internal

CONSTRUCTION (3 YRS)
Project Development
Construction Operations Negotiations

Construction

1 Uses: SPV estimates £10 bn for third runway expansion design & construction,
over 3 years of construction for
Design fees, Raw materials, Labor, Project management
Classification: Internal

CONSTRUCTION (3 YRS)
Project Development
Construction Operations Negotiations

Construction
2 Sources: Debt & equity is drawn pro-rata; financed by 70% debt, 30% equity

Uses Yr 1 Yr 2 Yr 3
Profile % 20.00% 50.00% 30.00%
Capex GBP M 10,000 2,000 5,000 3,000

Sources
Equity GBP M 3,000 600 1,500 900
Debt GBP M 7,000 1,400 3,500 2,100
Classification: Internal

CONSTRUCTION (3 YRS)
Project Development
Construction Operations Negotiations

Construction
2 Sources: Debt & equity is drawn pro-rata; financed by 70% debt, 30% equity

Uses Yr 1 Yr 2 Yr 3
Profile % 20.00% 50.00% 30.00%
Capex GBP M 10,000 2,000 5,000 3,000

Sources
Equity GBP M 3,000 600 1,500 900
Debt GBP M 7,000 1,400 3,500 2,100
Classification: Internal

OPERATIONS - REVENUE
Project Development
Construction Operations Negotiations

3 Heathrow is a regulated privately held asset. It will collect


• Aero: landing revenues at a regulated price (£25 per person, 30m passengers
arriving per annum)
• Non-aero: revenues from retail, car park, baggage, advertising (£1 bn p.a.)

Aero Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Passengers per annum Num M
GBP / PAX GBP / PAX
Regulatory charge GBP M - - - - - - -

Non-aero
Non aero revenue GBP M
Classification: Internal

OPERATIONS - REVENUE
Project Development
Construction Operations Negotiations

3 Heathrow is a regulated privately held asset. It will collect


• Aero: landing revenues at a regulated price (£25 per person, 30m passengers
arriving per annum)
• Non-aero: revenues from retail, car park, baggage, advertising (£1 bn p.a.)

Aero Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Passengers per annum Num M 30 30 30 30 30 30 30
GBP / PAX GBP / PAX 25 25 25 25 25 25 25
Regulatory charge GBP M 750 750 750 750 750 750 750

Non-aero
Non aero revenue GBP M 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Classification: Internal

OPEX & CAPEX


Project Development
Construction Operations Negotiations

4 Opex & Capex


• Opex = £0.50bn p.a.
• Labor
• Electricity
• Capex = £0.35bn p.a.
• Runway maintenance
• Baggage systems maintenance

Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Operating cost GBP M 500 500 500 500 500 500 500
Maintenance capex GBP M 350 350 350 350 350 350 350
Classification: Internal

DEBT - PRINCIPAL
Project Development
Construction Operations Negotiations

5 Debt is paid down at regular intervals


• Tenor = 20 years
• Fixed annual repayments

Counters End Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Debt tenor [1,0] Yr 23 1 1 1 1 1 1 1
Repayment periods remaining Num# 20 19 18 17 16 15 14

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 7,000 7,000 7,000 7,000 7,000 7,000
Drawdown GBP M - - - - - - -
Repayment GBP M
Balance c/f GBP M 7,000 7,000 7,000 7,000 7,000 7,000 7,000
Classification: Internal

DEBT - PRINCIPAL
Project Development
Construction Operations Negotiations

5 Debt is paid down at regular intervals


• Tenor = 20 years
• Fixed annual repayments → £7bn / 20 years = £0.35bn principal p.a.

Counters End Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Debt tenor [1,0] Yr 23 1 1 1 1 1 1 1
Repayment periods remaining Num# 20 19 18 17 16 15 14

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550
Classification: Internal

DEBT - INTEREST
Project Development
Construction Operations Negotiations

6 Interest is paid annually


• Fixed interest rate of 5% p.a.

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550

Debt service
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595
Classification: Internal

TAX PAYMENTS
Project Development
Construction Operations Negotiations

7 Tax is paid annually


• Tax rate = 17% of taxable income
• Depreciation is assumed to be equal to capex (£0.35bn p.a.)
• Assumed to be no tax losses
Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
EBITDA GBP M 1,250 1,250 1,250 1,250 1,250 1,250 1,250
Less interest GBP M (350) (333) (315) (298) (280) (263) (245)
Less depreciation GBP M (350) (350) (350) (350) (350) (350) (350)
Taxable income GBP M 550 568 585 603 620 638 655

Tax payable GBP M


Tax paid GBP M - - - - - - -
Classification: Internal

TAX PAYMENTS
Project Development
Construction Operations Negotiations

7 Tax is paid annually


• Tax rate = 17% of taxable income
• Depreciation is assumed to be equal to capex (£0.35bn p.a.)
• Assumed to be no tax losses
Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
EBITDA GBP M 1,250 1,250 1,250 1,250 1,250 1,250 1,250
Less interest GBP M (350) (333) (315) (298) (280) (263) (245)
Less depreciation GBP M (350) (350) (350) (350) (350) (350) (350)
Taxable income GBP M 550 568 585 603 620 638 655

Tax payable GBP M 94 96 99 102 105 108 111


Tax paid GBP M 94 96 99 102 105 108 111
Classification: Internal

CFADS
Project Development
Construction Operations Negotiations

8 Cashflow Available for Debt Service (CFADS)


• Revenue less expenses (less working capital, not shown here)
• Less capex
• Less tax
Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Revenue GBP M
Expenses GBP M
Operating cashflow GBP M

Capex GBP M
Tax GBP M
CFADS GBP M
Classification: Internal

CFADS
Project Development
Construction Operations Negotiations

8 Cashflow Available for Debt Service (CFADS)


• Revenue less expenses (less working capital, not shown here)
• Less capex
• Less tax
Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Revenue GBP M 1,750 1,750 1,750 1,750 1,750 1,750 1,750
Expenses GBP M (500) (500) (500) (500) (500) (500) (500)
Operating cashflow GBP M 1,250 1,250 1,250 1,250 1,250 1,250 1,250

Capex GBP M (350) (350) (350) (350) (350) (350) (350)


Tax GBP M (94) (96) (99) (102) (105) (108) (111)
CFADS GBP M 807 804 801 798 795 792 789
Classification: Internal

DEBT COVENANTS - DSCR


Project Development
Construction Operations Negotiations

9 Debt Service Coverage Ratio (DSCR)


• DSCR = CFADS / (Interest + Principal)
• In period or annual ratio

Debt service Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595

CFADS GBP M 807 804 801 798 795 792 789

DSCR x
Classification: Internal

DEBT COVENANTS - DSCR


Project Development
Construction Operations Negotiations

9 Debt Service Coverage Ratio (DSCR)


• DSCR = CFADS / (Interest + Principal)
• In period or annual ratio

Debt service Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595

CFADS GBP M 807 804 801 798 795 792 789

DSCR x
Classification: Internal

DEBT COVENANTS - DSCR


Project Development
Construction Operations Negotiations

9 Debt Service Coverage Ratio (DSCR)


• DSCR = CFADS / (Interest + Principal)
• In period or annual ratio

Debt service Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595

CFADS GBP M 807 804 801 798 795 792 789

DSCR x
Classification: Internal

DEBT COVENANTS - DSCR


Project Development
Construction Operations Negotiations

9 Debt Service Coverage Ratio (DSCR)


• DSCR = CFADS / (Interest + Principal)
• In period or annual ratio

Debt service Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595

CFADS GBP M 807 804 801 798 795 792 789

DSCR x 1.15x 1.18x 1.20x 1.23x 1.26x 1.29x 1.33x


Classification: Internal

DEBT COVENANTS - LLCR


Project Development
Construction Operations Negotiations

10 Loan life coverage ratio (LLCR)


• LLCR = NPV of CFADS / Debt Balance
• Beginning of period ratio

Debt service Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Interest GBP M 350 333 315 298 280 263 245
Principal GBP M 350 350 350 350 350 350 350
Total debt service GBP M 700 683 665 648 630 613 595

CFADS GBP M 807 804 801 798 795 792 789


NPV of CFADS GBP M 9,721 9,403 9,073 8,729 8,371 7,998 7,609
Classification: Internal

DEBT COVENANTS - LLCR


Project Development
Construction Operations Negotiations

10 Loan life coverage ratio (LLCR)


• LLCR = NPV of CFADS / Debt Balance
• Beginning of period ratio

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550

NPV of CFADS GBP M 9,758 9,439 9,108 8,762 8,403 8,029 7,638

LLCR (beginning pd) x 1.47x 1.50x 1.53x 1.56x 1.60x 1.64x 1.68x
Classification: Internal

DEBT COVENANTS - LLCR


Project Development
Construction Operations Negotiations

10 Loan life coverage ratio (LLCR)


• LLCR = NPV of CFADS / Debt Balance
• Beginning of period ratio

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550

NPV of CFADS GBP M 9,758 9,439 9,108 8,762 8,403 8,029 7,638

LLCR (beginning pd) x 1.47x 1.50x 1.53x 1.56x 1.60x 1.64x 1.68x
Classification: Internal

DEBT COVENANTS - LLCR


Project Development
Construction Operations Negotiations

10 Loan life coverage ratio (LLCR)


• LLCR = NPV of CFADS / Debt Balance
• Beginning of period ratio

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550

NPV of CFADS GBP M 9,758 9,439 9,108 8,762 8,403 8,029 7,638

LLCR (beginning pd) x 1.47x 1.50x 1.53x 1.56x 1.60x 1.64x 1.68x
Classification: Internal

DEBT COVENANTS - LLCR


Project Development
Construction Operations Negotiations

10 Loan life coverage ratio (LLCR)


• LLCR = NPV of CFADS / Debt Balance
• Beginning of period ratio

Account Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Balance b/f GBP M 7,000 6,650 6,300 5,950 5,600 5,250 4,900
Drawdown GBP M - - - - - - -
Repayment GBP M (350) (350) (350) (350) (350) (350) (350)
Balance c/f GBP M 6,650 6,300 5,950 5,600 5,250 4,900 4,550

NPV of CFADS GBP M 9,758 9,439 9,108 8,762 8,403 8,029 7,638

LLCR (beginning pd) x 1.47x 1.50x 1.53x 1.56x 1.60x 1.64x 1.68x
Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Evaluate the Equity IRR


• Cash flow after paying the debt service is distributed to equity
• IRR is calculated using the net equity cashflow i.e. Distributions less
investment
Equity IRR Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7
Investment GBP M (3,000) (600) (1,500) (900) - - - -
Distributions GBP M 8,625 - - - 107 121 136 150
Total GBP M (600) (1,500) (900) 107 121 136 150

XIRR % p.a.
Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Evaluate the Equity IRR


• Cash flow after paying the debt service is distributed to equity
• IRR is calculated using the net equity cashflow i.e. Distributions less
investment
Equity IRR Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7
Investment GBP M (3,000) (600) (1,500) (900) - - - -
Distributions GBP M 8,625 - - - 107 121 136 150
Total GBP M (600) (1,500) (900) 107 121 136 150

XIRR % p.a. 6.66%

Inbuilt IRR function


in Excel
Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Equity IRR – setting the discount rate so investments balance the distributions

3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Equity IRR – setting the discount rate so investments balance the distributions

3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23
(1,000)

(2,000)

(3,000)

(4,000)

(5,000) As the discount rate


(6,000) increases, cashflows
Investment Distributions Debt service Capex Tax Operation cost further away decrease
Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Putting distributions in context: Adding back debt service gives us CFADS

3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal

EQUITY IRR
Project Development
Construction Operations Negotiations

11 Putting distributions in context: Adding back all cashflows gets up to revenue to


all stakeholders
3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal

PROJECT IRR
Project Development
Construction Operations Negotiations

12 Project IRR
• The project IRR assumes that no debt is used for the project
• I.e. the investment amount equals the construction capex (+ development
costs)
• The outflows (net project cashflow) is the cash generated by the project.
• The IRR is the % which sets the NPV = 0; i.e. discounted outflows = the
discounted investment of these cash flows.
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS


Project Development
Construction Operations Negotiations

13 Here’s where the negotiations begin – the interests of each party

Debt
• Max debt = GBP [8] bn
• Max gearing = 80%
• Min DSCR = 1.20x [project has demand risk]
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS


Project Development
Construction Operations Negotiations

13 Here’s where the negotiations begin – the interests of each party

Debt
• Max debt = GBP [8] bn
• Max gearing = 80%
• Min DSCR = 1.20x [project has demand risk]

Equity
• Min IRR – 11% p.a.
• Min equity to invest: GBP 2bn
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS


Project Development
Construction Operations Negotiations

13 Here’s where the negotiations begin – the interests of each party

Debt
• Max debt = GBP [8] bn
• Max gearing = 80%
• Min DSCR = 1.20x [project has demand risk]

Equity
• Min IRR – 11% p.a.
• Min equity to invest: GBP 2bn

Regulator
• CAA wants to keep the aero charge as low as
possible for public welfare
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 Here’s where the negotiations begin

Senior debt
Metric Unit Current Optimised Target Assessment
Amount Invested GBP M 7,000 8,000 8,000
7,000 OK • Max debt = GBP [8] bn
Gearing % 70.00% 80.00% 80.00% OK • Max gearing = 80%
Min DSCR x 1.15x 1.33x 1.20x OK
Error • Min DSCR = 1.20x [project has demand risk]

Equity
Metric Unit Current Optimised Target? Assessment
IRR x 6.66% 11.05% 11.00% OK
Error • Min IRR – 11% p.a.
NPV @ Target IRR GBP M (1,016) 8 - OK
Error • Min equity to invest: GBP 2bn
Amount Invested GBP M 3,000 2,000 4,000 OK

CAA
Metric Unit Current Optimised • CAA wants to keep the aero charge as low as
Aero Charge USD / PAX 25.00 25.20 possible for public welfare
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 Here’s where the negotiations begin

Senior debt
Metric Unit Current Optimised Target Assessment
Amount Invested GBP M 7,000 8,000 8,000 OK • Max debt = GBP [8] bn
Gearing % 70.00% 80.00% 80.00% OK • Max gearing = 80%
Min DSCR x 1.15x 1.33x 1.20x OK • Min DSCR = 1.20x [project has demand risk]

Equity
Metric Unit Current Optimised Target? Assessment
IRR x 6.66% 11.05% 11.00% OK • Min IRR – 11% p.a.
NPV @ Target IRR GBP M (1,016) 8 - OK • Min equity to invest: GBP 2bn
Amount Invested GBP M 3,000 2,000 4,000 OK

CAA
Metric Unit Current Optimised • CAA wants to keep the aero charge as low as
Aero Charge USD / PAX 25.00 25.20 possible for public welfare
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 What levers do we have?


• Debt repayment type: Fixed → Annuity
• Longer concession (30 years)
• Longer debt tenor (25 years)
• Increased gearing (80%)
• The aero revenue (landing fee)
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 Scenarios
1. Base
2. Debt repayment type: Fixed → Annuity
3. Longer concession (30 years)
4. Longer concession (30 years) & debt tenor (25 years)
5. Longer concession, debt tenor & increased gearing (80%)
6. Longer concession & debt tenor, increased gearing & annuity
7. All of these + the take-off and landing fee

EXERCISE
SET THESE UP IN THE SCENARIO MANAGER
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 How does the model help us get there?

Scenario manager
Case number Case 1

Live Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7


Name Name Base Base Annuity Longer concession
Longer concession
Longer
+ debt
& Increased
tenor
All gearingAll + aero up
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s)
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s)
Gearing ratio % 70.00% 70.00% 80.00% 80.00% 80.00%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 How does the model help us get there?

Scenario manager
Case number Case 1

Live Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7


Name Name Base Base Annuity Longer concession
Longer concession
Longer
+ debt
& Increased
tenor
All gearingAll + aero up
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s)
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s)
Gearing ratio % 70.00% 70.00% 80.00% 80.00% 80.00%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 How does the model help us get there?

Scenario manager
Case number Case 1

Live Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7


Name Name Base Base Annuity Longer concession
Longer concession
Longer
+ debt
& Increased
tenor
All gearingAll + aero up
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s)
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s)
Gearing ratio % 70.00% 70.00% 80.00% 80.00% 80.00%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS


13 What levers do we have?
• Debt repayment type: Fixed → Annuity
800
8,000
FIXED 7,000
700
600
6,000
5,000 500
4,000 400
3,000 300
2,000 200
1,000 100
- -
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Principal Interest
600
8,000
ANNUITY 7,000 500
6,000
400
5,000
4,000 300
3,000 200
2,000
1,000 100

- -
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Principal Interest
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS Data validation


Data validation
Name Gearing Min DSCR Equity IRR
Base Name Gearing
70.00% Min DSCR 1.15x Equity IRR
6.66%
Scenario manager Base
1 Base 70.00% 1.15x 6.66%
1
2 Base
Annuity 70.00% 1.15x
1.34x 6.66%
7.02%
Case number Case 1
2
3 Annuity
Longer concession 70.00% 1.34x
1.15x 7.02%
7.80%
Live Case 1 Case 2 Case3
4 3Longer concession
Case 4 + Case 70.00%
debt 5tenor Case 6 1.15x
1.28x
Case 7 7.80%
8.28%
Name Name Base Base Annuity Longer4 Longer concession
5concession
& Increased
Longer +gearing
debt
concession
Longer &tenor
+ debt 70.00%
80.00%
Increased
tenor
All 1.28x
gearingAll + aero up 8.28%
1.13x 9.42%
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 305 Longer
6 Yr(s)
All & 30
Increased
Yr(s) gearing 80.00%30 Yr(s) 1.13x
30 Yr(s) 9.42%
1.32x30 Yr(s)10.84%
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 6
7 All + aero 25
upYr(s) 80.00%25 Yr(s) 1.32x
25 Yr(s) 1.33x25 Yr(s)10.84%
11.05%
Gearing ratio % 70.00% 70.00% 7 All + aero up 80.00%80.00%80.00% 1.33x 80.00% 11.05%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24 Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS Data validation


Data validation
Name Gearing Min DSCR Equity IRR
Base Name Gearing
70.00% Min DSCR 1.15x Equity IRR
6.66%
Scenario manager Base
1 Base 70.00% 1.15x 6.66%
1
2 Base
Annuity 70.00% 1.15x
1.34x 6.66%
7.02%
Case number Case 1
2
3 Annuity
Longer concession 70.00% 1.34x
1.15x 7.02%
7.80%
Live Case 1 Case 2 Case3
4 3Longer concession
Case 4 + Case 70.00%
debt 5tenor Case 6 1.15x
1.28x
Case 7 7.80%
8.28%
Name Name Base Base Annuity Longer4 Longer concession
5concession
& Increased
Longer +gearing
debt
concession
Longer &tenor
+ debt 70.00%
80.00%
Increased
tenor
All 1.28x
gearingAll + aero up 8.28%
1.13x 9.42%
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 305 Longer
6 Yr(s)
All & 30
Increased
Yr(s) gearing 80.00%30 Yr(s) 1.13x
30 Yr(s) 9.42%
1.32x30 Yr(s)10.84%
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 6
7 All + aero 25
upYr(s) 80.00%25 Yr(s) 1.32x
25 Yr(s) 1.33x25 Yr(s)10.84%
11.05%
Gearing ratio % 70.00% 70.00% 7 All + aero up 80.00%80.00%80.00% 1.33x 80.00% 11.05%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24 Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal Data validation
NEGOTIATIONS & OPTIMIZATIONS Data validation
DataName
validation Gearing Min DSCR Equity IRR
Base Name Gearing
70.00% Min DSCR 1.15x Equity IRR
6.66%
Base Name
1 Base Gearing
70.00% Min DSCR 1.15x Equity IRR
6.66%
Scenario manager 2 Base
1 Annuity
Base 70.00% 1.15x
1.34x 6.66%
7.02%
1
3 Base
2 Longer
Annuityconcession 70.00% 1.34x
1.15x 6.66%
7.02%
7.80%
Case number Case 1
2
4 Annuityconcession + debt tenor
3 Longer 70.00% 1.34x
1.15x
1.28x 7.02%
7.80%
8.28%
Live Case 1 Case 2 Case3
4 3Longer &
5 concession
Increased
Case 4 +gearing
Case 70.00%
debt 5tenor
80.00%Case 6 1.15x
1.28x
1.13x
Case 7 7.80%
8.28%
9.42%
Name Name Base Base Annuity Longer45 Longer
6concessionconcession
& Increased
All Longer +gearing
debt
concession
Longer &tenor
+ debt 70.00%
80.00%
Increased
tenor
All 1.28x
1.13x
1.32x
gearingAll 8.28%
9.42%
+ aero up10.84%
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 5
307 Longer
6 Yr(s)
All & 30
+ aero Increased
upYr(s) gearing 1.13x
80.00%30 Yr(s) 1.33x
30 Yr(s) 9.42%
1.32x30 Yr(s)11.05%
10.84%
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 6
7 All + aero 25
upYr(s) 80.00%25 Yr(s) 1.32x
25 Yr(s) 1.33x25 Yr(s)10.84%
11.05%
Gearing ratio % 70.00% 70.00% 7 All + aero up 80.00%80.00%80.00% 1.33x 80.00% 11.05%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
3,000

2,000

1,000

-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24 Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33
(1,000)

(2,000)

(3,000)

(4,000)

(5,000)

(6,000)

Investment Distributions Debt service Capex Tax Operation cost


Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS DataName


Data
1 Base Name
validation Gearing
Base validation 70.00%
Min DSCR Equity IRR

70.00% Min DSCR


Gearing
1.15x
1.15x Equity
6.66%
6.66%
IRR
Base Name
2 Annuity Gearing
70.00% Min DSCR 1.15x Equity
1.34x IRR
7.02%
6.66%
Scenario manager 3 Base concession
1 Longer
Base 70.00% 1.15x 6.66%
7.80%
1
4 Base
2 Longer
Annuityconcession + debt tenor 70.00% 1.15x
1.28x
1.34x 6.66%
8.28%
7.02%
Case number Case 1
2
5 Annuity&
3 Longer 70.00%
Increased gearing 80.00%
concession 1.34x
1.13x
1.15x 7.02%
9.42%
7.80%
Live Case 1 Case 2 Case3
6 Longer concession
4 3All Case 4 + Case 70.00%
80.00%
debt 5tenor Case 6 1.15x
1.32x
1.28x 7.80%
Case 7 10.84%
8.28%
Name Name Base Base Annuity Longer74 Longer
All
5concessionconcession
+ Longer
aero
& Increased +gearing
debt
upconcession
Longer &tenor
+ debt 70.00%
80.00%
Increased
tenor
All 1.28x
1.33x
gearingAll 8.28%
+ aero up11.05%
1.13x 9.42%
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 305 Longer
6 Yr(s)
All & 30
Increased
Yr(s) gearing 80.00%30 Yr(s) 1.13x
30 Yr(s) 9.42%
1.32x30 Yr(s)10.84%
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 6
7 All + aero 25
upYr(s) 80.00%25 Yr(s) 1.32x
25 Yr(s) 1.33x25 Yr(s)10.84%
11.05%
Gearing ratio % 70.00% 70.00% 7 All + aero up 80.00%80.00%80.00% 1.33x 80.00% 11.05%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
2,000
1,800
1,600
1,400
1,200
1,000
800
600
400
200
-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24 Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33

Distributions Debt service Capex Tax Operation cost


Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS DataName


Data
1 Base Name
validation Gearing
Base validation 70.00%
Min DSCR Equity IRR

70.00% Min DSCR


Gearing
1.15x
1.15x Equity
6.66%
6.66%
IRR
Base Name
2 Annuity Gearing
70.00% Min DSCR 1.15x Equity
1.34x IRR
7.02%
6.66%
Scenario manager 3 Base concession
1 Longer
Base 70.00% 1.15x 6.66%
7.80%
1
4 Base
2 Longer
Annuityconcession + debt tenor 70.00% 1.15x
1.28x
1.34x 6.66%
8.28%
7.02%
Case number Case 1
2
5 Annuity&
3 Longer 70.00%
Increased gearing 80.00%
concession 1.34x
1.13x
1.15x 7.02%
9.42%
7.80%
Live Case 1 Case 2 Case3
6 Longer concession
4 3All Case 4 + Case 70.00%
80.00%
debt 5tenor Case 6 1.15x
1.32x
1.28x 7.80%
Case 7 10.84%
8.28%
Name Name Base Base Annuity Longer74 Longer
All
5concessionconcession
+ Longer
aero
& Increased +gearing
debt
upconcession
Longer &tenor
+ debt 70.00%
80.00%
Increased
tenor
All 1.28x
1.33x
gearingAll 8.28%
+ aero up11.05%
1.13x 9.42%
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 305 Longer
6 Yr(s)
All & 30
Increased
Yr(s) gearing 80.00%30 Yr(s) 1.13x
30 Yr(s) 9.42%
1.32x30 Yr(s)10.84%
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 6
7 All + aero 25
upYr(s) 80.00%25 Yr(s) 1.32x
25 Yr(s) 1.33x25 Yr(s)10.84%
11.05%
Gearing ratio % 70.00% 70.00% 7 All + aero up 80.00%80.00%80.00% 1.33x 80.00% 11.05%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20
2,000
1,800
1,600
1,400
1,200
1,000
800
600
400
200
-
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24 Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33

Distributions Debt service Capex Tax Operation cost


Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS


Scenario manager
Case number Case 1

Live Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7


Name Name Base Base Annuity Longer concession
Longer concession
Longer
+ debt
& Increased
tenor
All gearingAll + aero up
Concession tenor Year(s) 25 Yr(s) 25 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s) 30 Yr(s)
Debt tenor Year(s) 20 Yr(s) 20 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s) 25 Yr(s)
Gearing ratio % 70.00% 70.00% 80.00% 80.00% 80.00%
Repayment type Selection Fixed Fixed Annuity Annuity Annuity
Aero charge GBP / PAX 25.00 25.00 25.20

Data validation
Name Gearing Min DSCR Equity IRR
Base 70.00% 1.15x 6.66%
1 Base 70.00% 1.15x 6.66%
2 Annuity 70.00% 1.34x 7.02%
3 Longer concession 70.00% 1.15x 7.80%
4 Longer concession + debt tenor
70.00% 1.28x 8.28%
5 Longer & Increased gearing 80.00% 1.13x 9.42%
6 All 80.00% 1.32x 10.84%
7 All + aero up 80.00% 1.33x 11.05%
Classification: Internal

NEGOTIATIONS & OPTIMIZATIONS

13 Here’s where the negotiations begin

Senior debt
Metric Unit Current Optimised Target Assessment
Amount Invested GBP M 7,000 8,000 8,000 OK • Max debt = GBP [8] bn
Gearing % 70.00% 80.00% 80.00% OK • Max gearing = 80%
Min DSCR x 1.15x 1.33x 1.20x OK • Min DSCR = 1.20x [project has demand risk]

Equity
Metric Unit Current Optimised Target? Assessment
IRR x 6.66% 11.05% 11.00% OK • Min IRR – 11% p.a.
NPV @ Target IRR GBP M (1,016) 8 - OK • Min equity to invest: GBP 2bn
Amount Invested GBP M 3,000 2,000 4,000 OK

CAA
Metric Unit Current Optimised • CAA wants to keep the aero charge as low as
Aero Charge USD / PAX 25.00 25.20 possible for public welfare

You might also like