Professional Documents
Culture Documents
2 8
Net Cash Flow Typical cash flow
NCF(i) = Capex(i) + Opex(i) + Sales(i)
where
Capex(i) = Capital expenditure (drilling, facilities costs) for period i
2 9 2 10
2 11 2 12
Discounted cash flow (DCF) Effect of discount rate
Discounted Cash Flow (DCF) is calculated by The higher the discount rate assumed ,the less profitable the project will
appear. Typically in the oil industry discount rates between 6 and 10 %
used. The effect of this is shown below:
where
NCF = net undiscounted cash flow for period i
rD = discount rate (fraction)
n = number of time intervals
2 13 2 14
2 15 2 16
Net Present Value (NPV) NPV as cumulative DCF
If cash flows are in real terms (allowing for inflation) then a real NPV is generated. discounted cash flow & NPV10 (real) & total cash flow
(3% infla on)
If nominal cash flows are used (not allowing for inflation) then a nominal NPV is 1200
generated.
1000 DCF (real) at
The discount rate and the nominal or real basis should always be quoted. discount rate of
800 10.00%
So we can have for example: Cum DCF (real) at
600 discount rate of
• NPV10 (real), NPV0 (real),
mm $
10.00%
400
total discounted
• NPV10(nominal), NPV0(nominal) capex
200
0 NPV 10.00%
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
-200
-400 years
2 17 2 18
mm $
mm $
10.00% 22.00%
total discounted total discounted
0 capex 0 capex
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
NPV 10.00% NPV 22.00%
-500 -500
2 19 2 20
Payback time and Maximum exposure Profitability Index (PI)
The Payback time of a project is the length of time that will elapse before the cumulative PI= Profit to Investment Ratio
undiscounted real cash flow becomes positive (ie. before this costs outweigh income). Profit to Investment ratio (PI) – the discounted real PI is defined as
Maximum cash exposure is defined as the maximum negative undiscounted cumulative real net
cash flow.
where all the discounting is done at the same rate . This is sometimes known as ROI (return on
investment) as it is a simple measure of return on investment . It is independent of the time which
limits its usefulness as an economic indicator. It is always used in conjunction with other indicators.
2 21
PI
800 3
NPV
600
2
PI
400
1
200
0 0
0 200 400 600 800 1000
capex
2 23
Expected Monetary Value Expected Monetary Value
All of the above indicators assume a single production outcome. In reality there is
always uncertainty in predicted production profiles and oil or gas prices which Expected Monetary Value (EMV) is defined as:
should be taken into account in decision making.
When a single 'best estimate' case only is used the indicator is known as an un-
risked indicator, the indicator 'Expected Monetary Value' is a risked indicator. which is the weighted sum of the NPVs corresponding to different possible
outcomes
where
r = discount rate
Pi is the probability of outcome i
The sum of the probabilities must = 1
A normal assumption would be that we take three outcome cases P(P90 case) = 0.25,
P(P50 case) =0.5 , P(P10case) = 0.25
rate
𝑃𝑖 ∗ 𝑁𝑃𝑉(𝑥)𝑖
P50 case(best estimate)
𝑖
We then have a project monetary value (effectively an NPV10(real)) adjusted to where P10 case (upside)
allow for both technical and economic uncertainty or either one alone. x = discount rate
The result will depend on the relationship between the three cases which can skew
time
Pi is the probability of outcome i
the EMV up or down from the base case NPV.
P50 (median)
The sum of the probabilities must = 1
Relative Probability
mean
P90
Risked as well as unrisked cases should always be presented when investment A normal assumption would be
decisions are to be made. P(P90 case) = 0.25, P(P50 case) =0.5 , P(P10case) = 0.25 P10
1 2 3 4 5 6 7 8 9 10 11 12 13
2 27
Reserves (Tcf)
EMV examples Effect of various parameters
effect of variation in discount rate effect of oil price
1.6 45%
Downward skew EMV = NPV(50%) Upward skew $2,400,000
1.4
$2,400
$2,200,000 $2,200 40%
1.2
NPV 10
EMV = $15 mm $1,800,000 $1,800
NPV
0.8
P/I
45 NPV
35 $1,600,000 0.6 NPV $1,600 30%
35 40 $1,400,000 RROR
30 0.4 P/I $1,400
30 35 25%
$1,200,000 0.2 $1,200
25 25 30 $1,000,000 0 $1,000 20%
20 20 25 5 7 9 11 13 70 80 90 100 110
$mm
$mm
15
10 15 discount rate
5 10
10
0 5 effect of reserves
5
-5 downside best estimate upside effect of cost
0 0 45%
-10 downside best estimate upside 45% $2,400
downside best estimate upside $2,400
-15 $2,200 40%
$2,200 40%
$2,000
$2,000 35%
NPV 10
35% $1,800
NPV 10
RROR
$1,800 NPV
$1,600 30%
$1,600 30% NPV
$1,400 RROR
$1,400 RROR 25%
25% $1,200
$1,200
$1,000 20%
$1,000 20% 90 100 110 120 130 140 150
1000 1200 1400 1600 1800 2000 reserves (mmbbl)
costs
Uncertainties
relative effect on NPV10 of uncertainties in oil price,
facilities costs and reserves effect of plateau rate
4 2.5
$2,200 3.5
2
3
$2,000
2.5 1.5
NPV10 $ billions
AP/I
2
$1,800 NPV10
NPV10
1.5 1
oil price
P/I
1
$1,600 cost 0.5
0.5
$1,400 reserves 0 0
0 50 100 150
DEPRECIATION
• Expected Monetary Value (EMV)
• Real Rate of Return (RROR)
• Profit to Investment Ratio (PI)
• Payback time
• All need to be taken into account in Full
Investment Decision (FID)
INPUTS
Production profile –from the Reservoir Engineer
Capital Expenditure profile (CAPEX)
Operating costs (OPEX)
Taxation
Oil/gas price assumptions
Discount rate
Assumptions on inflation
Depreciation Depreciation
Companies invest capital in exploration and appraisal activities
Net Book Value with depreciation
120
When a field is discovered it is added to company value as an Intangible Asset (as where 100
NBV
60
Once a field starts production you must allow that this value obviously depreciates. (1P)i = proved reserves at start of year i 20
7
10
13
16
19
22
25
years
qi = production in year i
NBVi+1 = NBVi –Di ( the net book value at the start of year i+1)
Proved reserves = 1P reserves
2 36
Depreciation
• All reserves are regularly re-estimated.
• We would normally expect 1P reserves to gradually increase to the 2P number as the field is
produced.
• If production data shows the field performs better than expected so that 1P reserves can be
increased more than expected this results in less depreciation and better NBV in the annual
company reports. FINANCIAL ARRANGEMENTS
• If production data shows the field is not as good as expected, so that 1P reserves must be
decreased, NBV will decrease more than expected and company value will decrease.
• Proved reserves can change due to either technical of economic factors
• For example a drop in oil prices will mean that the economic field life will decrease so that 1P
reserves decrease
• Significant decrease here is known as Impairment
2 37
Royalty is a payment made to the owner of a resource and is normally fixed as part of a licence
agreement. It is a payment directly related to volume or to sales [rather than to profit].
2 42
Company (NOC) and an International Oil Company, IOC, and is for petroleum oil rate bopd
gas rate
mmscf/d
wells drilled
in each year
Facilities
(fraction spent oil produc on
Exploration and/or Production rights. The IOC is a Contractor to NIOC and never year
0 6,108 7.33E+01 8
in year)
0.5
14,000
12,000
failities cost
annual opex
$400 mm
$1.00 mm
Discount rate
Price Elevation, %
10.00%
3.00%
gains Equity Rights in oil or gas ,being reimbursed in cash after completing an
1 11,662 1.40E+02 8 0.5 tax rate 40.00%
2 11,662 1.40E+02 0 0 10,000 oil price/stb $ 60
3 11,662 1.40E+02 0 0 gas price $/mmscf 4.00 NPV RATE 13.00%
agreed scope of work. The Reimbursement includes cost recovery and an agreed
8,000
o il ra te b o p d
4 11,662 1.40E+02 0 0 NPV ($mm) = 1,369.99
5 11,662 1.40E+02 0 0 6,000 PI= 1.50
Rate of Return. 6
7
8
11,662
11,662
11,662
1.40E+02
1.40E+02
1.40E+02
0
0
0
0
0
0
4,000
2,000 discounted cash flow & NPV10 (real) & total cash flow
9 11,662 1.40E+02 0 0 0 (3% infla on)
10 7,954 9.55E+01 0 0 1600
0 5 10 15 20 25 30
11 3,726 4.47E+01 0 0 1400 DCF (real) at
years discount rate of
12 3,113 3.74E+01 0 0 1200
mm $
10.00%
16 1,884 2.26E+01 0 0 total discounted
600
17 1,691 2.03E+01 0 0 2.00E+02 capex
18 1,527 1.83E+01 0 0 400
19 1,385 1.66E+01 0 0 200 NPV 10.00%
1.50E+02
g a s ra te (m m s cf/ d )
20 1,247 1.50E+01 0 0
0
21 0 0.00E+00 0 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
22 0 0.00E+00 0 0 1.00E+02 -200 years
23 0 0.00E+00 0 0
24 0 0.00E+00 0 0 5.00E+01
25 0 0.00E+00 0 0
26 0 0.00E+00 0 0 0.00E+00
27 0 0.00E+00 0 0 0 5 10 15 20
28 0 0.00E+00 0 0 -5.00E+01
2 43 29 0 0.00E+00 0 0 2 years 44
recovered 5.14E+07 6.17E+05
stb mmscf