KMS Construction Schedule

NO WORK ITEM UNIT Q'TY APR REMARK


15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
A. PILE WORK
R&D Center Building EA 149
EMI Building EA -
Walfare Building EA 79
Security Building EA -
UT Building EA -

LINE 4

LINE 3

P V
LINE 2 LINE 5
A I
R S
K I
I T
N O
G R

D L
O O
C A
K D
I
N
G

220408_Hans Jaya_Wekkly Schedule


LINE 1
KMS Construction Schedule

NO WORK ITEM UNIT Q'TY APR REMARK


15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
B. CIVIL WORK
OK VISITOR PARKING LOT & MAIN GATE 2 M3 130 토사반출 다짐 림스톤 정리 OK
OK LOADING DOCK 1차 M3 500 토사반출 다짐 림스톤

OK DRAINAGE "LINE 1" M 15.8 관로 완료 맨홀작업

OK DRAINAGE "LINE 2" M 21.8 관로 완료 맨홀작업 협의후 시작

DRAINAGE "LINE 3" M Holding_Checking


32.5 the batch basin type 관로 작업 맨홀작업 라인 변경중

DRAINAGE "LINE 4" M 46.7 관로작업


Holding_checking canopy foundation
SEWAGE "LINE 5" M 149 오수 관&맨홀
Holding_Checking RC Structure progress