Professional Documents
Culture Documents
April; 2021
Finfinne,Ethiopia
1
Executive summary
Project owner Adisu Mosisa
Project location Gelan town
Land size required 5 hectares
Project type Construction machinery assembly
Project composition Truck mounted mixer, portable concrete mixer, and tipper truck,
Dozer, Grader and Loader.
Total project cost 452,350,000
Production at full 589,000 items of various machineries and equipment
capacity
Target market 70% domestic and 30% export.
Financing Total capital 452,350,000out of 30% ( 135,705,000) owner’s
contribution and 70% (316,645,000) bank loan.
Employment 1. Permanent (skilled and Unskilled) 1385
opportunity 2170 Skilled 1000
Unskilled 385
2. Causal 758
skilled 58
Unskilled 700
Benefit of the It adds values to the economy
project for Source of government revenue
region/country Employment opportunity
Minimizing foreign currency expenditure /import substitution.
Benefit for the local community
Stimulate the local economy and technology transfer
The project employs software designing, automatic cutting and
modern Assembling machine which are labor intensive machineries
Technology and equipments are selected. Machinery spare parts will be
manufactured locally and technology transfer will be conducted.
2
1. Introduction
Ethiopian being of the Africa countries required continuous improvement in
Construction Machinery Assembly and manufacturing sector. In accomplish
the development on these sectors, the role of infrastructure is vital. the
development of the infrastructure in turn highly depend on the availability of
various types of construction like rollers, leaders, truck minted mixers,
portable concrete mixers tipper truck etc.
The country has been improving almost all of its industrial machinery and
equipment than aboard. According to the data abstained from Ethiopian
customs authority. The country is importing several types of machinery and
equipment from several countries. Chine, Italy, turkey, and Germany are the
dominant supplies
The investment project requires total capita of birr 452,350,000 million initial
investment to be financed both by equity and bank loan in proportion of 30; to
70, ratio respectively. The financial evaluation shows that the project will be
profitable and liquid for its estimated project life. The project will create
employment opportunity for more than 2170 workers of which 1385 are
permanent and the remain 758 are temporary.
The project uses part and auxiliary items as a major raw material to be
imported, thus the benefit multi – dimensional in foreign currency savings.
3
1.1. Back ground of the project
The project aims at state of the art manufacturing facility and equipment
around the especial zone of oromia surrounding Finfinne–Gelan town to meet
the increasing demand for construction machineries. In Ethiopia, the
construction sector has shown significant progress over the past few years and
the promoter plan to manufacture highly demand truck mounted concert
mixers, portable concerted mixer and tippers, Loader, Dozer and Graderhaving
different sizes to the sector.
1.3. Objectives
To engage in the production and assembly construction equipment and
related items
To contribute for h technologically transfer and capacity development in
the country
4
To share experience with TVET college student so, apparent ships and
employment opportunity
To open a market opportunity for small scale industries by out sourcing
non –core activity for the organization.
To generate income for the company in order to expand the operation and
other development activity
To contribute to the socio-economic development of the nation at large
and to the construing sector in particular
To pay its part in import substitution
Demand analysis
5
1.1. Ethiopian construction sector
6
Despite the growth registered over the past years, this sector is still one of
the lowest when we view the country‘sconstructionsrequirement. As all well
know, this country during the previous regime has been under war
situation where almost all the capital budget expenditure had been spend of
repurchase of ammunition, during this time there had been no or limited
effort on the part of the government to construct and reconstruct the
country. During this period the citizen’s per capital income is one of the
lowest bottoms where more than half of the population is living below the
absolute poverty line.
On the other sided, the role played by the private sector in boosting the
country ‘economy was almost legible. This is because the country ‘s
economy policy was command economy where the private sector is not
allowed to participate in any investment activity. Because of all these
factors the country’s economy was in general backwards and the
construction sector one of the poorest. It is because of this ugly situation
before that the present fast growth in the constructions sector couldn’t
attain the country ‘s growth requirement. Besides, the ever-increasing
population of the country, increase in per capital income citizens as well as
the growth in public and private increment associated with the country
attractive investment environment and resource potential eve increases the
construction requirement of the country. This conger is at early stage of
development where the growth trajectories are taking root towards
advancement. They require the realization of various development projects
and betterment of citizen’sincome. The forefront sector that needs to be
proofed during realization of development projects is the construction
industry. It requires the activation of this sector when one think of
constructing roads. Hydroelectric dam, manufacturing industries housing
construction, other building contractions, social service institutions etc.
All the description above indicates that the construction sector at present in
Ethiopian is growing at fastest rate but a lot remains to be done when
viewed with the country development equipment and h reconstruction that
needs to take place to achieve this since the country started the
reconstruction from the scratch.
8
Road development data
Asphalt Gravel Rural Load Total
Growt Growt Growt Growt Growt
Lengt h Lengt h Lengt h h Lengt h
h rate h rate h rate Length rate h rate
200/0 1246 1648 3287
1 3924 7 0 NA 1 0
2001/ 1256 1668 3329
02 4053 3.29 4 0.78 0 1.21 NA 7 1.3
2002/ 1234 1715 3385
03 4362 7.62 0 -1.78 4 2.84 NA 6 1.68
2003/ 1390 1795 3649
04 4635 6.26 5 12.68 6 4.68 NA 6 7.8
2004/ 1364 1840 3701
05 4972 7.27 0 -1.91 6 2.51 NA 8 1.43
2005/ 1431 2016 3947
06 5002 0.6 1 4.92 4 9.55 NA 7 6.64
2006/ 5452 1462 2234 57763 9149
07 0 8.99 8 2.22 9 10.84 .7 7 7.48
2007/ 1436 2393 70038 4435
08 6066 11.26 3 -1.8 0 7.07 .1 9 4.55
2008/ 1423 2564 4681
09 6938 14.38 4 -0.89 0 7.15 85767 2 5.53
2009/ 1437 2694 10038 4879
10 7476 7.75 3 0.98 4 5.09 4 3 4.23
2010/ 1413 3071 5314
11 8295 10.96 6 -1.65 2 13.98 854 3 10.67
2011/ 1467 3155 5610
12 9875 19.05 5 3.81 0 2.73 6.98 0 16.83
Source: Ethiopian road authority
9
Growth rate of community road total length does not include community road
as shown in the table above the construction of roads at national level is
growing by latest 16.83% in the year 2011/12, indirectly indicating the
demand for construction machinery
This project will not need aggressive product introduction and popularization
interventions with the aim to reach out the maximum possible buyer
The target market is 70% for domestic –import substitution and the remaining
30% will be export market.
a. Differentiation
b. Focus
10
1.7. The marketing mix
Based on the generic market strangely outlined above, the market analysis and
the competition discussed in the previous section, the marketing mixes of the
company are summarized below.
The major raw material is parts imported from original manufactures aboard.
Auxiliary items and accessories are supplements used to fix, decorate and
polish parts and parts therefore are also imported together with the original
parts.
1. Product / service: the product of the company are truck –mounted mixer
portable concrete mixer and tipper body with various ranges of
engineering products in order to comply with the differentiation strategy
2. The service shall have
Fit service shall be tailored to customer needs
Reliability, the company shall have reliability policy for clients.
these are quality and adequate delivery potential, and long –term
business relationships
11
III. Promotion: this includes all the advertising and selling efforts of the
marketing plan as with company’s service promotional efforts are guided by a
strategy. Thecompany shall implement pull strategies. Pull strategies are those
efforts that pull clients to the company
IV. Advertising it takes many forms television radio outdoor (billboards), and
magazine and newspaper. The two important to consider are the intended
message and the quantitative measurements of media goals. The company
shall focus to reach clients through TV, newspaper, web page exhibition, etc..
1.8.1. Location
The plant will be located Gelan town. The promoter will require at least 15
hectares envisaged project site selection is based up on the following criteria.
Proximity to market the project has to be located close to major market center
such as Addis Ababa, proximity to raw material.
The projects major raw material will be imported hence; the project has to be
located in close proximity Addis –Djibouti high way
12
A truck mountedconcerted mixer or agitator or transient mixer type to mixing
or /and transporting concrete and more particular to an improve mobile mixer
especially arranged to carry the maximum permissible load of concrete on a
moontruck of standard construction.
To perform small size of works there are many types of small portable concrete
mixers .a typical portable concrete mixer uses a small revolving drum to mix
the components .a gasoline engine may power portable concrete mixer,
although it is more common that they are powered by electric motors using
standard mains current
DRUM
13
Drum roller
Gear box
Rear ladder
New ladder design will be done which folds down and angle out for
Easier ascent by drivers. water plumbed to wash
Station and at ground level with diversion value
14
Real pendant control
New ladder design will be done which folds down and angles
out for
Easier ascent by drivers. water plumbed to wash
Station and at ground level with diversion value
Fenders
Fill width smooth tope steel extra strong fenders with center
bracing extra support
Each fender ha recessed stop , turn and tail light rear mud
flaps are standard from mud flaps can also fixed
Water tank
15
Mixer speed (rpm)-0.16
Mixer tank angle : 120
3. Production process
The production process starts with thedesign. Ideas for new model are
developed to respond to unmet public needs and preference. With the help of
computer –aided design equipment, designers develop basic concept drawing
that helps them visualize the proposed vehicle’s appearance
Placing the tools and the men in the sequence of the operation so that
each component part shall travel the least possible distance while in the
process of finishing
Step 2: fix the rear and front support for the shell
16
Step 3: out the outer shell as per the drawing, grind and polish
Step 4: roll the cut paces as per the manufacturing know drain
Step 10: assemble the shell with front and rear support
Step 11: fix the other remaining parts such as discharge nozzle, elevated
discharge
Step 12: fix the internal spiral bathe and weld as per the drawing
Step 13: mount the engine and calibrate the speed and the load
Step 14: mount the water tanker and fuel tank and make fittings with electrical
Step 15: test the mixer with water. The water will help to estimate feed and
discharge phenomena , capacity of the mixer and load analysis
Step 16: test drive and quality approval as per the design analysis and h
standard given by the nation authorities
Design
Material pro
linement
Arranging
17
Roll conform dome Truck cut and prepare
frustum and mixing side bar and base
chamber and weld
Designing
Detailing
Material procurement
18
Fitting of side and rare boards: cross
members rein for cement members’
winches gussets
Welding of joints
Sand blasting
Painting
19
4. Bench metal Central distance 300mm 1
5. Radial drilling machine Max.50mm 1
6. Power hack saw Size 300mm 1
7. Circular cutting machine Max.30mm 1
8. Horizontal milling machine 1
9. Threading machine 4pipe 1
10. Magnetic drilling machine Max 32mm 1
11. Air compressor 11bar 11
12. ARC compressor 400 A 1
13. MIG welding machine 300A 1
14. Spot welding machine 30kva 1
15. Airless spray painting gun 200-300 CC&6.5-7HP 11
16. Painting spray gun 1
17. Hand drill machine 16mm diameter 1
18. Hand grinding machine 180mm(3PCS)&125MM(2PCS)
19. Flame cutting set
20. Hose crimping machine About 3 “ hydraulic hose
21. Sand blasting machine
22. Forklift 7 ton
23. Overhead crane 10 ton
24. Miscellaneous tolls
20
Administration finance building 2000
Total 50,000
General Manager
General Service 21
Cashier
Accountants
Personal head
22
Marketing and sale 40 10000 4,800,000
Accountants 14 500 84,000
Marketing officer 20 5000 1,200,000
General service 50 4000 2,400,000
Cashiers 20 2500 600,000
Cleaners 50 1000 600,000
Guards 35 1000 420,000
Driver 30 2500 900,000
Production and technique
head 5 10000 600,000
Electrician 10 3000 360,000
Purchaser 10 3000 360,000
Store keeper 20 2000 480,000
Technician 20 3000 720,000
Production Forman 10 5000 600,000
Mechanical engineering 10 7000 840,000
Machine operators 50 2500 1,500,000
Ass. Operators 30 2000 720,000
Supporting stuff 900 2500 27,000,000
Subtotal permanent 1385 121500 50,484,000
Daily laborers 785 1500 14,130,000
Total 2170 64,614,000
23
4.3. Financial study
The financial resource is a prime resource of undertaking any activates hence
for implementing this project a total of 452,350,000eth birr required. From this
70%or 316,645,000 birr will be bank loan and 30% or 135,705,000.000 birr
will be contributed by the promoter of the project.
Therefore, the said amount of finance is needed for undertaking the following
24
.
2 Administration &finance boiling 2,750,000.
.
3 Show room 2,250,000.00
.
4 Parts warehouses 3,750,000
.
5 Paint room 1,150,000
.
6 Green area 1,600,000
.
7 Shade 1,750,000
.
8 Canteen, chine room and shower 2,100,000
.
9 Inside road 2,160,000
.
1 Machinery 150,000,000
10 Gourd house 1,250,000
Sub total 224,510,000
11 Site clearing 3,300,000
12 Working Capital 200,000,000
12 Design and supervision 400,000
13 Water line and electric installation 2,150,000
14 Land lease initial fee 10,500,000
Sub-total 216,350,000
15 Total 452,350,000
25
4.3.2 factory Machineries
The machineries or the plants for these construction materials producing
plants are imported from abroad. The cost required machinery and equipment
for different kinds of product intended to produce with all workshop
accessories and the total machine cost is estimated to be birr. 80,000,000.
based on the current exchange rate.
4.3.3. Vehicles
No Commodity description Qty Unit cost Total cost
1 Truck 18-20m3 3 2,000,000 6,000,000
2 Truck with crane fixed, 3 800,000 2,400,000
10Tone
3 Pick-up car 5 800,000 4,000,000
4 Workers service car, 5 1,000,000 5,000,000
Minibus
Sub total 17,400,000
5 Fob 400,000
6 Shipping 150,000
7 Insurance 220,000
8 Transport from port to 140,000
site
Sub total 910,000
Grand total 18,310,000
26
5 Computer with its 4 11,000 44,000
accessories
6 Shelf 4 4,000 16,000
7 Filing cabinet 4 1,500 6,000
8 Guest chairs 16 500 8,000
9 Assembly halls tables 2 800 16,000
10 Assembly hall chairs 20 500 10,000
11 Cash register 2 5,000 15,000
12 TV set 3 5,000 15,000
13 Photocopy machine 1 15,000 15,000
Total 175,000
27
cost year
1 Business plan Set 1 4,865 4,865
2 Feasibility study Set 1 14,577.5 14,577.5
3 Environmental impact Set 1 14,577.5 14,577.5
assessment
4 Market study and Set 2 48,615 97,230
processing with suppliers
5 Import processing 2 24,308 48,615
6 License processing 2 24,308 48,615
7 Billboards 2 1,452.5 14,525
8 Management and 10 34,020 34,020
financial manuals and
systems
9 Developing administrative, 1 14,557.50
logistics and financial
formats
Total 291,602.50
1 Fixed investment
2 Operating expense
2.1 Raw material purchase 5,160,000
28
No Description Cost in birr
Total 95,368,000
The contingent costs will used for covering all other costs which are not
stated in the financial summary in addition to price fluctuation. For
example, the salary of the contractual workers, promotional costs and any
other costs which are not visible in the project.
Sources fund; -Source of fund to finance the project is planned to be from two
sources. These are promoter’s equity and bank loan. The loan is expected to be
obtained from one the local lending institutions. Since, the project is expected
to take some times take time to be repay its depts, the bank loan is assumed to
obtain on long term credit basis. Taking the financial position of the promoter
in to account, equity contribution and bank loan to finance the total
investment outlays of the project are assumed to be 30% and 70% respectively.
Accordingly, the total financial requirement from the source will be;
5. Source of fund
No Description %share amount
1 Owners share 30% 135,705,000
29
Total 100% 452,350,000
6. Project Assumption
Project basics
30
Portable concrete mixer 40 Pcs /year
Truck mounted concert 15 Pcs /year
mixer
Tipper body 20 Pcs /year
Product mix % No
Total production capacity in 75
unit
Tipper production capacity 27 20
pcs
Concrete mixer pcs 53 40
Truck mounted concert 20 15
mixers pcs
31
Average selling price
Portable concrete mixer 120,000 Per pcs
Truck mounted concert 650,000 Per pcs
mixer
Tipper body 800,000 Per pcs
REVENUE
Products Year 1 Year 2 >year 3
Portable concrete mixer 3,360,000 3,840,000 4,320,000
Truck mounted concert 6,825,000 7,800,000 8,775,000
mixer
Tipper body 11,200,000 12,800,000 14,400,000
Total 21385,000 24,440,000 27,495,000
32
8. Cost of production
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
Truck mounted
concert mixer parts
Coli form / frusta sheet sqm 964.00 41.50 623.00 600,000.00
conical shell metal .5mm
thick
Dome like head sheet sqm 2.59 39.00 49,632.00
metal .5mm 1,280.00
thick
Mixing sheet sqm 23.50 353.00 405,000.00
chamber/compartm metal .4mm 1,149.00
ent thick
Elevated discharge sheet sqm 9.00 135.00 187,500.00
shell metal .4mm 1,389.00
thick
Fixture, gussets, sheet sqm 2.50 38.00 90,000.00
brackets metal .5mm 2,400.00
thick
33
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
Bolts and nuts, m16 fine thread pcs 83.00 30.00 450.00 37,500.00
hinges
Support for mixer it is a part with set 5.00 75.00 277,500.00
from cabins side external bearing 3,700.00
and self aligning
The mixer is a set with round set 500.00 75.00 37,500.00
supported at rear gear 5,000.00
support, mixer frame
Drive wheels support the shell set 5.00 75.00 75,000.00
for reduction of 1,000.00
roiling friction
Drive coupling gear type set 5.00 75.00 90,000.00
mechanical 1,200.00
coupling 1 set
Engine set 40,000.0 5.00 300.00 3,000,000.0
0 0
Water tank sheet metal sqm 750.00 20.00 75.00 22,500.00
3mm,4
Piping and fittings set 1,500.0 5.00 263.00 112,500.00
34
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
0
Tank sheet metal sqm 857.00 17.50 105,000.0 22,500.00
3mm, 0
Level switches, flow set 1.00 7,000.00 18,000.00 105,000.00
rate measuring
devices
Frame RHS100*50*5.12 set 1.00 1,200.00 18,000.00 18,000.00
m
For all from 16m to pcs 56.00 12.00 180.00 10,050.00
24m , 12pcs
each
Set of mechanisms set 2,400.0 1.00 15.00 36,000.00
0
Sub total sqm 5,918,682.
00
Concert mixer sqm -
Conform or frusta sheet metal sqm 964.00 8.30 125.00 120,000.00
conical shell 5mm thick
Dome like head sheet metal sqm 1,280.0 2.50 38.00 48,000.00
35
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
5mm thick 0
Mixing chamber/ sheet metal sqm 1,149.0 4.70 71.00 81,000.00
compartment 4mm thick 0
Elevated discharge sheet metal Pcs 1,389.0 1.80 27.00 375,008.00
shell 4mm thick 0
Fixture, gussets, sheet metal sqm 2,400.0 0.50 8.00 18,000.00
brackets 5mm thick 0
Bolts and nuts m16 fine thread pcs 83.00 6.00 90.00 7,500.00
hinges
Support for mixer it is a part with set 3,700.0 1.00 15.00 55,500.00
from cabins side external bearing 0
and self-aligning
The mixer is a set with round set 5,000.0 1.00 15.00 75,000.00
supported at rear, gear 0
rear support, mixer
frame
36
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
Drive wheels support the shell set 1,000.0 1.00 15.00 15,000.00
for reduction of 0
roiling friction
Drive couples gear type set 1,200.0 1.00 15.00 18,000.00
mechanical 0
coupling 1 set
Engine set 40,000. 1.00 15.00 600,000.00
00
Water tank sheet metal sqm 750.00 4.00 60.00 45,000.00
3mm,4
Piping and fittings set 1,500.0 1.00 15.00 22,500.00
0
Tank sheet metal with sqm 857.00 3.50 53.00 45,000.00
3mm
Level switches, flow set 1.00 3,000.00 45,000.00 45,000.00
rate measuring
devices
Frame RHS100*50*5.12 set 1.00 1,200.00 18,000.00 18,000.00
37
Item Material Measureme Unit Unit Total Total
requirement nt price(bir requireme requireme cost(birr)
r) nt (qty) nt (qty)
m
For all from 16m to pcs 56.00 12.00 180.00 10,050.00
24m , 12pcs
each
Set of mechanisms set 2,400.0 1.00 15.00 36,000.00
0
Sub total 1,297,050.
00
Grand total 7,215,732.
00
38
As clearly indicated in the project income statement part the project will
return its initial cost soon.
Assumptions
For equipment life time assumed to be 5 years and rate of dep. 20%
For building with the life time of 25 years with depreciation rate of 5%
For vehicles life 5 years dep. rate of 20%
From the income statement, the promoter of the project has sufficient
amount of money that enable them pays the bank loan with in a short
period of time and expand their investment on additional land of his
interest.
In general, the financial statement the project shows that the project under
discussion will cover its entire investment costs with in short period of time.
8.1. Profitability
According to the projected income statement, the recreation resort will start
generating profit in the 2 nd year of operation. Important ratios such as profit
to total sales, net profit to equity ( return on equity) and net profit plus
interest on total investment (return on total investment) show on increasing
trend during the life of the project.
The income statement and the other indicators of profitability show that the
project is viable.
39
8.2. Pay-back period
The investment cost and income statement projection are used to project
the pay-back period. The projects initial investment will be fully recovered
with in this shows that this project is a long term business.
40
plants recycle the excess powder generated during dry pressing as well as
the overspray produced during glazing. Waste glaze and rejected tile are
also returned to the body preparation process for reuse.
41
Contents
Executive summary..................................................................................................2
1. Introduction.......................................................................................................3
1.3. Objectives.......................................................................................................4
1.8.1. Location....................................................................................................10
42
4.2.2. Man power requirement.............................................................................21
4.3.3. Vehicles....................................................................................................23
5. Source of fund.................................................................................................26
6. Project Assumption..........................................................................................27
8. Cost of production...........................................................................................29
8.1. Profitability..................................................................................................32
43