Professional Documents
Culture Documents
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
DOCUMENT REVIEW
Reviewer name:
Signature:
Date:
QUEST E & P
ATTENDEES
Name Title
1. Goke Dele MD/CEO
2. Bright Asianya Manager , HR
3. Adewale Adedotun Project Engineer
4. Evenlyn Barnabas Manager, Operations
5. Godwin Agada Manager, Finance
6. Nuvie Ohwoefe Manager, Business Development
7 Precious Ariote Manager, HSE
3 Trends in customer There was no Customer complaint on review • There were meetings with
satisfaction and of data collated from the Customer satisfaction client to ensure quality
feedback from relevant survey. service deliveries are
interested parties. No survey or feedback has been carried; this maintained as soon as
was due to no significant event on operations/ mobilization for projects
projects as of September 2021. begin.
• Bus & contracts lead( with
the aid of the MD/CEO) to
lead initiative on
Doc No: QOG11-NPDC-T2022004-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
acquisition of new
Customer.
4 The extent to which Objectives for the year 2021 was collated by • Objectives must be managed
quality objectives have top management and heads of department but by Team leads. Updates
been met. could not be cascaded down because top would be required at the Next
management needed to get clear directions on meeting.
the year 2021 . • All training conducted by
departments in 2021 shall be
However, the year 2021, team leads ran with update as appropriate by the
the set Objectives which they cascaded HR Team and archived for
their team members. The future references.
objective was analyzed and reviewed for
effectiveness of the QMS & OHS.
Departments were not able to achieve some of
their objectives because there was no project as
of September 2021.
But other project related objectives like trainings
were achieved.
5 Process performance No significant event or project was recorded • There were reports of
and service conformity. during this time, although meetings heard with client
discussion is on to mobilize to site as soon as with regards to projects.
possible.
Effectiveness of action All process risk has been managed by process Concerned Process owners to
taken risks and owners via a risk register, updated and update risk registers as soon as
opportunities communicated across board for the hazards and risk are identified.
effectiveness of the QMS & OHS. Hazards Due to remote working,
7 identified are managed (reporting and closing ergonomic risk were identified,
out) via SharePoint. this OHS hazard has been
communicated to all staff during
safety meetings, safety
moments and lesson learned.
Opportunities for If there are lessons learned, they are shared on Actions were assigned to process
improvement a weekly basis during weekly and monthly owners to document lesson
safety meeting. Safety moments are also shared learned.
during operation meeting for continual Meetings are recorded for future
8 improvement or for any opportunity for references.
improvement.
Most lessons shared this year 2021 were related
to the effect of the corona virus on global
economy, as the battle of the covid-
19 pandemic is ongoing.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
MINUTES OF MEETING
Date Created Rev Date:
Rev No: 0.1 Document Number: QEPCI-HSE-MOM-03:22 Page 1 / 2
22/03/2022 22/03/2022
ATTENDEES
1 PRECIOUS ARIOTE – HSEQ MANAGER
2 GODWIN AGADA- SITE ENGINEER
GOAL
➢ Achieve A Total Safety Culture in QUEST
AGENDA
HIGHLIGHT
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
➢ Safety Topic of the Month of February was read by Howard and reviewed by Vincent
➢ Safety slogan for the Month of August is Taking Ownership of Safety and
Slogan for the Month ‚‘‘ You see it, You Own it“
➢ The Meeting began with reviewing the HSEQ statistics (HOCs, HSE Meetings, Management
inspection) for March 2022.
➢ There was a deliberation on how to ensure that every staff/ personnel and talk about safety
at all times. Participation of staff in respect to
safety, awareness of Quality management QMS/OHS, support and the
resources needed to ensure safety would be driven at all times were pointed out.
1) Participation : Idowu reteirated the benefit of employee/staff participation using
references from ISO45001: 2018. In order to enhance employee participation and
enthusiasm in the organization, Vincent advised that every Thursday there should be a
review of the safety meeting slide with the persons to present for the week. Monthly
Hazard Hunt, Housekeeping Exercise, Quareterly fire drills (Were there are rotational fire
wardens amongst staff) were pointed out as part of encouraging employee partipation.
2) Awareness: Precious reiterated that there should be constant awareness on the company
HSE Objectives, Environmental and Quality management System.
3) There was a review of HSEQ OBJECTIVES for the year that includes, HSE trainings,
First Aid Simulation and Fire stimulation training. When reviewed, 3 out of 5 objectives
have been done. Precious advised that before the year 2019 is over, all the objectives this
year would be met.
AOB
1) There are plans to have the Lifesaving rules/ SPSAs incorporated into all staff our I.D.
cards
2) P.P.E stock and inventory should be sent to Precious, Godwin and Adewale to have a
proper stock of items.
QUEST E & P HSE ORGANOGRAM
SITE SUPERVISOR SITE SAFETY OFFICER BASIC SAFETY OFFICER FIRST AIDER (DFA)
SUB-CONTRACTOR
OTHER EMPLOYEES
EMPLOYESS
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
HSSEQ
CONTRACT HSSE PLAN
HSSEQ-PLN-003
This is an electronically generated document, which has been reviewed and approved by the QUEST Management System.
An audit trail of review and approval is available within the electronic system. The screen version of this document is the
CONTROLLED COPY at all times. When printed it is considered a FOR INFORMATION ONLY copy, and it is the
holder’s responsibility that he/she holds the latest valid version. ©, QUEST or a subsidiary thereof, Copyright 2021 and
design right reserved. Copying and/or disclosure of the confidential information contained herein is prohibited without
the written permission of the proprietor.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 12
2. HSE POLICY ................................................................................................................... 13
3. ORGANISATION ............................................................................................................ 13
3.1 Management Strategies .................................................................................................................. 14
3.2 Project-specific HSE Plan/Task Procedure ............................................................................... 14
3.3 Responsibilities................................................................................................................................ 15
3.3.1 Management commitment ........................................................................................................ 15
3.3.2 Quality Assurance Manager ...................................................................................................... 15
3.3.3 Worker's Involvement in HSE ................................................................................................. 15
3.3.4 Responsibilities of HSE Manager ............................................................................................ 15
3.4 Relationship with Client................................................................................................................. 16
3.5 Relationship with sub-contractors................................................................................................ 16
3.5.1 Sub-Contractor Safety Policy .................................................................................................... 16
3.5.2 Sub-Contractor Pre-Qualification ............................................................................................ 16
3.5.3 Sub-contractors Pre-Job Considerations................................................................................. 16
3.6 Communications ............................................................................................................................. 17
3.6.1 Safety meetings ........................................................................................................................... 17
3.6.2 Toolbox meetings ....................................................................................................................... 18
1. INTRODUCTION
QUEST’s HSE management system is based on the philosophy that HSE issues can only be
effectively managed when the tasks involved are aimed toward a common mission and total
participation.
It is also based on the fact that success is assured when all employees accept full responsibility
for the activities, which are assigned to them.
It is our policy to carry out operations in such a way that the safety of our employees, as well as
others that may be affected, are managed properly to eliminate or control RISK where possible
or otherwise reduce RISKS to the lowest practical level.
Along with other corporate objectives, QUEST will give equal attention to HSE management.
QUEST’s HSE management system will be a guide for planning and actions to prevent or
reduce accidents as much as possible. This target will only succeed if we are all working within
an open communication structure with safe behavior at all levels. This HSE management system
is intended to be an evolutionary document and will be updated to reflect lessons learned during
projects.
It is the responsibility of QUEST management to ensure the implementation of this HSE
management system and to ensure that all staffs are aware of its contents. It is the responsibility
of all employees and subcontractor employees to ensure that the safety of all is guaranteed.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
2. HSE POLICY
3. ORGANISATION
QUEST is structured in an organized and systematic way such that HSE responsibilities are
assigned to managers, supervisors, and employees. Management set HSE objectives and
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
monitors them through the HSEQ Department.
3.1 Management Strategies
The following strategies will be used to achieve the desired accident-free workplace.
• Strict compliance with all specific project HSE plans supported by safety meetings, held at the
Site and the Project Management Base. “Tool Box Talks” will be initiated at the start of each shift activity.
• Investigate any accident to reveal all elements responsible to eliminate any further occurrences.
• Ensure that adequate instructions are given to all employees on all aspects of their jobs using job
safety analysis.
• Ensure that employees and sub-contractors attend/receive relevant SAFETY courses/training
and enhance job hazard awareness.
• Improve quality/quantity of Unsafe Acts Audits and maintain Records.
• Provide and ensure proper tools and personal protective equipment are used for every job.
• Extend safety education to our host communities to create a safe work environment.
• Reduce fire potential at all our facilities by training our workforce in safe working practices.
• Ensure that incidence and near-miss reporting are improved and analyzed. Ensure that findings
are disseminated to other departments. Use the root cause analysis to determine the causes of the
incident.
3.3 Responsibilities
3.3.1 Management commitment
• Management commitment will be expressed by playing a leadership role in all HSE matters. To
this effect, management will ensure the presence of a safety officer on all QUEST projects.
• Management will safely train workers to execute their jobs.
• Management will provide safety protective equipment such as coveralls, safety helmets, safety
boots, safety glasses, body harnesses, personal floatation devices (PFD), and hand gloves.
• Management will provide the resources needed to eliminate hazards in the workplace.
• The HSE Coordinator will visit work sites regularly to get firsthand information on HSE
proceedings
A Safety Officer will be appointed, who will be responsible for enforcing the QUEST safety
plan, providing safety advice and conducting safety meetings.
Souvenirs such as a T-Shirt or cap will be given to workers who exhibit outstanding safety
performance.
Safety training will start at project safety orientation and will continue throughout the project.
This will be conducted by the safety officer or by the QUEST HSE Manager. Training will
generally be relevant to the type of activities to be performed in such a project. All Supervisors
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
will be encouraged to learn the content of the project safety plan. All staff will be given
appropriate PPE.
4.4.2 Health
QUEST will make use of retainer clinics to provide medical services to its employees. Currently,
QUEST employs the services of Queens along Wimpy Road, Port Harcourt. One Safety officer
who will provide first aid will be dedicated to the work area. Industrial health matters such as
ergonomics, hearing protection, eye protection, etc will be discussed in safety meetings.
Subcontractors to QUEST will be responsible for the routine medical care and health
maintenance of their employees.
The HSE Manager will report the following statistics.
• The number of persons examined at each clinic.
• Nature of complaints or visits for each visit.
• Length of illness.
• Referrals.
• Emergency, nature of the emergency, and action are taken.
• Total man-hours worked
• LTIs
• TRIs
Safety officers, Supervisors, and other employees will receive first aid training. First aid kits will
be available at all times both at QUEST base and at projects locations.
The possession of mood-altering drugs, both stimulants and depressants will be strictly
forbidden on the work site except for legitimate medical uses prescribed by medical staff. Such
drugs include, but are not limited to, alcoholic drinks, marijuana, heroin, cocaine, opium,
barbiturates, etc.
All hazardous materials will be transported, stored, and handled in conformance with the safety
data accompanying such materials.
All hazardous materials delivered by QUEST suppliers will be accompanied by material safety
data sheets.
4.4.3 Environment
QUEST HSE Manager will be responsible for identifying and prioritizing critical hazard areas
for incorporation in project safety plans to eliminate, minimize or control the hazards identified.
QUEST and its sub-contractors will carry out their operations in such a way that there will be
minimal disturbance to its environment and will be committed to cleaning up waste generated
during its operations.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
During audits of QUEST sites by the Client, QUEST’s Supervisor will co-operate with the
Client’s inspectors by producing records on-demand and ensuring that inspectors have access
to the site for environmental inspections.
Environmental complaints from the community where QUEST works will be investigated to
see if there is any validity in the complaint(s).
For a complaint to be valid, the act complained about must have occurred and the act must
have been a violation of applicable Nigerian environmental laws, regulations, or guidelines.
5. RISK MANAGEMENT
Different types of work activities carry different types of risks. Some of these activities, their
hazards, and the ways to manage them form a major part of our safety program.
To effectively manage the risks a comprehensive job safety analysis of our operations has been
carried out. The result is an outline of different activities, the hazards associated with these
activities, work planning, and safety precautions to eliminate, control, or reduce these hazards.
We are also aware that certain job activities have a higher risk factor than others. In tackling
these high-risk factors, safety plans are designed to achieve a near-zero frequency of occurrence,
most especially risks with high consequences. However, these plans are reviewed regularly to
meet the challenges of various projects.
We also have a proactive approach to risk and safety issues. This is the reason why we maintain a strong
HSEQ department.
Analyze Risks
Evaluate Risks
Collaborate
Modify
Risk Control Decision
Quest’s model for managing risk focuses on a multi-part risk assessment process supported through ongoing
communication and consultation and regular monitoring and evaluation.
6.3 Housekeeping
Good housekeeping is a sign of a safe operation. It is impossible to have a safe working
environment when tripping hazards or slip hazards are present. Poor housekeeping also creates
fire hazards. Accumulation of trash is a fire hazard; therefore all sites will be cleared of debris
daily.
Supervisors will make certain that employees are attentive to good housekeeping practices, and
that spills are promptly wiped up, that waste is not carelessly thrown down in the work area,
that the work area is policed frequently to prevent the accumulation of waste. For specific
projects, Waste management, segregation, and deposit will be per the Client and standard
operating procedures for waste management and disposal.
The principle of clean-up before work commences, clean-up trash as they are produced and
clean-up at the end of work will always apply.
Regularly, the state of housekeeping will be audited and corrective items rectified where
applicable.
6.4 Safety Signs and Barricades
Safety signs and barricades will be used to define or indicate and warn workers about the
presence of hazards in the work area. Some safety sign provides information on the control or
prevention measures required to avoid accidents.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Respiratory protection
Hazards associated with respiration include fumes, dust, vapours, and gases
Hand protection
Hand gloves are used to protect the hand from injury, chemical hazards, and other hand-related
hazards. The selection of hand gloves will be determined by job/task and hazard type.
Rubber hand gloves will be used for chemicals.
Hand gloves made from leather and thick cotton will be used for handling metal and wire mesh.
Welding hand gloves will have long arms.
• No smoking signs will be positioned in gas and other easily flammable materials area.
• Smoking and use of naked flames such as matches and lighters will be prohibited in
flammable areas.
• Oily rags will be kept in containers that are emptied at frequent intervals.
• Only approved containers for diesel and other fuel will be used.
• When pouring or pumping diesel or similar materials a metallic contact will be maintained
between the containers. A bonding strap will be used.
9.1 Fire fighting
• Firefighting equipment will be positioned in designated areas.
• There will be no smoking in the flammable area.
• Persons not trained in firefighting will not fight fire
11.1 Responsibilities
Responsibilities in environmental matters will be defined and assigned as stated in section 3.3
of this document.
11.2 Training
Training requirements will be determined and treated following section 8.0 of this document.
11.3 Communication
Environmental hazards will be identified and communicated to all through reports and hazard
signs.
11.4 Documentation
Environmental hazards will be reported and closed out using our Safety observation card.
Too much Sun, headlight, reflection Use visor, look away from strong light
Too little Sundown, Light up when dark, replace burnt bulb
12.5.3 Disembarking
• No passenger will disembark if the boat has not finally stopped and been secured.
• Disembarking from the boat/barge will be done in an orderly manner.
• Unauthorized movement from the site aboard QUEST boat / public boats will not be allowed.
• The quartermaster will be in total control of his boat.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
13.5 Evacuation
If the need to evacuate a work platform arises the following steps will be taken:
• Personnel will assemble at the muster point and will wait for further instructions from the safety
officer
• The safety officer at the location will ensure that all personnel is accounted for.
• The safety Officer will establish emergency communication by radio or telephone.
16.7 Security
QUEST engages the service of a security company – Klassic Security Services. Security is
provided for all our work sites by employing guards to control movement in and out of the site.
They will also ensure that materials and equipment are safeguarded. For specific projects, a
security plan will be prepared where necessary.
16.8 Access
Every visitor will be required to put on and display conspicuously the visitors’ identity card.
Workers will be required to wear their identity cards whilst on the premises. All vehicles entering
and leaving the premises will be subject to checking and cross-checking (NO EXCEPTIONS)
16.9 Project-Specific Community Relation Plan
A community relations plan will be prepared for all projects outside the QUEST base. The plan
will act as a guideline for establishing a mutual relationship with the host community.
1. The plan will among other things establish the following
2. Pre-mobilization meeting with the host community
3. Employment of labour from the community
4. Procedure for Settlement of disputes
5. Communication
6. Relationship with the host community
7. Respect for community festivals, religion, and customs
8. Assistance to community
MD
Project Manager
Project Engineer
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Site Activities
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
MD
Project Engineer
Site Activities
MD
Site Activities
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Interface Management
QUEST E & P has primary and secondary interface management systems in our dealing with clients and
our project teams.
In the secondary interface management system , the Project Manager interfaces between QUEST E &
P and our clients. He is also the head of our technical team, interfacing between the team and the
management and also between the management and our technical partners.
In the primary interface management system, the Project Engineers interface between the project teams
& sites activities and the management via Project Manager.
Below is the schematic diagram representing QUEST E & P primary and secondary interface
management systems.
➢ Interface Management
Project Manager
Project Engineer
Project Team
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
HAZARDS AND EFFECT MANAGEMENT PROCESS FOR COMPLETION FLUIDS ENGINEERING SERVICES
e) Power Pack Loading i. Risk of injury form pressurized a) We need to connect our power
hydraulic fluid. pack to a load before putting it
on.
f) Rotating parts of the power pack. i. Injury from flying object due to Un- a) All rotating parts of the power
caged and un-isolated rotating parts pack must be isolated from the
with wire-mesh. personnel
g) Electric power unit i. Risk of electric shock/electrocution. a) Ensure that all cabled are
Surrounding to be dried always. properly insulated.
b) Power Unit to be earthed
before switching on.
c) Spider a) Possible injury to the body a.) Need to bleed off the line before
especially the hands and fingers. touching the Elevator.
6) RIG-UP PROCEDURE
a) Hose lines a) Possible bursting of hose. a) All hose lines must be properly secured.
b) Hoisting shackles a) Possible falling of Tong. a) All hoisting shackles must be properly
put in place.
c) Lifting a) Equipments should be lifted from the
proper lifting points.
d) Banks Man a) Confusion that could lead to a) Only one banks man should exist at a
accident. time.
e) Attitude to work a) Accidents a) Cordial working relationship should
exist amongst TECON staff on the Rig.
f) Tagging a) It can mess up job on the Rig. a) All equipments should be properly
tagged to show their present state.
7) STABBER
a) Drilling Mud a) Can make the Elevator slip off a) Whenever the drilling mud flows to the
the Stabbers hand. surface, the elevator and the Rig floor
should be properly cleaned to avoid
possible slipping.
b) Proper observation of the a) This can cut off the Stabbers a) The stabber should not put his finger
movement of the Top drives by finger. while the top drive is coming down.
the Stabber.
c) Stabbing Board a) The Stabber can fall of the a) The Stabber should inspect the stabbing
Stabbing Board. Board before work commences.
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Hazard Identification and Risk Evaluation Criteria and Risk Level indicator
RISK ASSESSMENT MATRIX (RAM)
Increasing Probability
RATING People Assets Environment Reputation 1 2 3 4 5
RARE UNLIKELY POSSIBLE LIKELY = ALMOST
= Never = Heard of = Has Happens CERTAIN
heard of in the occurred in several times = Happens
in industry the per year in the several
Industry organisation organisation times per
more than year at the
once per year location
in the industry
Consequences
No Injury or
1 health effect No Damage No effect No Impact Acceptable but manage for Continuous Improvement
Minor injury
or health
effect (FAC,
MTC, RWC Minor Minor or Limited
2 ) Damage Minor Effect impact
Major injury Moderate or
(LTI) or Moderate Moderate or Considerable
3 health effect damage Localised effect impact Incorporate Risk
Major Reduction Measures
4 Fatality damage Major Effect Major Local impact
Massive (Major
Multiple Massive International)
5 Fatalities damage Massive Effect impact Intolerable
SIGNIFICANT 15
Doc No: QOG11-NPDC-T202200-004
Doc.
TENDER FORM D: COMPANY/PROJECT ORGANISATION
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
No. Sequence of BASIC STEPS Potential RISKS / HAZARDS Recommended SAFE Procedures
Check sling tag to verify inspection date. Clear hand signals, make sure both elevators are
Pinched fingers, Dropped hand tools,struck by the correct size and type.
2 Change out casing elevator.
crane loads.
Watch hand and finger placement. Use proper rigging techniques.
Check slings,swivel, and secure shackle with safety wire, ensure elevators are hanging
3 Rig up / pick up elevators. Pinched fingers, sling comes off.
center when hanging straight down.
Pinched fingers/hand struck by tools and Watch hand and finger placement. Don't stand where you can be struck/hit by man
Rig up mud fill line, and support
4 equipment, stabbing board not at correct hight swinging hammer to tighten unions, ensure stabbing board can be easily adjusted for
equipment including stabbing board.
or alignment, operator over reaching. correct height when stabbing.
Keep casing as close to rotary as possible 3-4 ft from mouse hole. Keep catwalk wet at all
Casing getting caught on beams in derrick times while pulling casing into derrick, and go as slowly as needed to keep casing from
5 Rig up casing on catwalk.
causing sling to part. breaking friction and swing into the derrick/rig floor. Paint line up drill pipe stands, and
do not set box end of casing joint any closer to to rotary table than the line.
Pick up and run casing, latch joint Safety pin jumps out, elevator upside Be observant,check tail rope closely,use leather gloves, keep catwalk wet. Keep Drillers
6
with pick up elevators. down,joint swings into derrick, struck by. view clear. Tell driller to stop if you see something wrong.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Hold onto protector while removing, keep hand above threaded, good communication
Remove threaded protector and stab Struck by, pinched fingers, miss stabbed csg,
7 between driller and stabbing board hand, know what type of threads the csg has (refer
into joint in rotary table difficulty in stabbing joint.
manufactures instructions if in doubt) pin while stabbing.
Pinch fingers, back injury, slips,fall on path of Pull slips equally, keep holding onto slips at all times, and release together.Use legs to lift
9 Pull slips.
tool joint while lowering casing. not your back.
Set slips and latch onto another joint Hit by, pinched fingers, slips break up while Keep an eye on pick up elevator while casing being run in hole make sure all of the slips
10
with pick up elevators. setting. enter the rotary bushing together.
Truck Collision Injury/Asset Speed limit; Use of Install anti-collision Alarp demonstrated
Movement/ Damage LH/LP flagman barrier for critical
5 3 15 N 3 2 6
Positioning /E/R infrastructures;
warning signs
Hose/Nozz Improper Product Good design, Alarp demonstrated
le insertion insertion; Splash; Training/Compete
LH/E 3 4 12 Y 3 2 6
into man- burst hose pollution ncy development
hole
Loading Pumping of Fuel Fire/Explosi No Smoking; Close monitoring
/Offloading fuel into flammabili on proper earthing;
Operations tank/tanker ty
LH/LP
Safe System of
5 3 15 Work; No mobile Y 5 2 10
/E/R
phones; warning
signs; Suppression
System
Dipping of Fall from Injury/ Safe System of Effective supervision Alarp demonstrated
product height fatality work; PPE (fall
volume (tanker) LH 5 3 15 arrestor); safety N 1 2 3
signs
QUEST E & P ensures all processes are adhered to before Work which includes:
1. Appoint a Project Work Supervisor for the Nigerian Petroleum Development Company Limited for
the project
2. The Supervisor shall ;
• Be an experienced personnel for Casing/Tubular Running Services contract
• Attend and fully participate in daily morning meeting as may be organized by Nigerian
Petroleum Development Company or discuss daily operations/drilling reports with Nigerian
Petroleum Development Company drilling representative, and follow through such
communication back to QUEST E & P Base.
• The project Supervisor shall ensure that all equipment and handling tools/baskets/cargo boxes
for any jobs are inspected, function tested and properly color-coded well in advance, prior to
mobilization. Relevant documentation and certification shall be made available to Nigerian
Petroleum Development Company.
• The Project Supervisor ensures crew teams’ attitude to work, observable equipment performance,
defect etc is in top notch prior to job mobilization. If any observable equipment defects is noticed,
he shall follow through with the maintenance supervisor and close out all necessary action points.
EXECUTION OF WORK
• The Project Supervisor ensures that a service technician is mobilized for every job. The service
technician also acts as a Computer Torque Engineer.
• He will lead a pre-mobilization meetings/ pre-task tool box meetings before personnel or
equipment leave the base.
• Alongside the Project Base Manager, the Project Supervisor shall plan ahead of any job, the
requisite full compliment of equipment and most suited personnel for prompt and efficient service
delivery to ensure optimum value for money.
• Prior to work execution on the Field, the Project Supervisor and his team will check and function
test all tools and Equipment on location. He will communicate this progress to the Clients Rep.
on location as well as the Crew and Project coordinators.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
• During the execution of the job, QUEST E & P team will ensure strict adherence to standards,
guidelines, procedures and processes to ensure that Nigeran Petroleum Development
Company Limited jobs are effectively executed without any hitch
ENGINEERING DESIGN
1. QUEST E & P shall devote and maintain specific sets of handling plugs/nubbin for all sizes of tools for
Nigerian Petroleum Development Company Limited.
2. All certifications will be put in place and documentations on them made available before
commencement of job.
3. We shall fully utilize our remarkable tool management inventory . This tool is a
management system specifically designed for equipment tracking, consumables
tracking, and service tracking. It will be of immense help as it gives advance notification
as to expiration of certification on equipment.
MATERIALS/EQUIPMENT
QUEST E & P prides in its owns several sets of Tubular Running tools, Piling tools, sourced from companies
with best practices in designs, manufacturing and maintenance that meet up with API
and IADC specifications.
PROJECT MANAGEMENT
A. INFORMATION MANAGEMENT
Management of information will be sole responsibility of QUEST E & P to provide adequate effective
communication gadgets to their workers on site to enable them communicate easily in case of any
emergency or without disturbing other on site, e.g Back to back radio or GSM. QUEST E & P to give
good instruction to those who will manage the project in a safe manner. Proper induction to the visitors
and new staff to enable them know do’s and don’ts on site. Sufficient information to the workers on
site of what to do and how to do it. There must be a useful training related to the job on site for the
workers to enable them manage the issue of health, safety and personnel on site in order to work safely
and to have a good housekeeping. There must be a proper supervision on site to enable the workforce
to work safely.
All official communication on the project between QUEST E & P and PPMC shall be written in English
Language and transmitted via issuance of project note shall be courier/hand delivered, facsimile
transmission or electronic mail (in ready-only format) will be used when necessary and shall be backed-
up by hard copies deliveries. An orderly flow of correspondences shall be ensured between QUEST E
& P and PPMC through effective identification and numbering system. A transmittal note will be used
to deliver all physical items such as project documents, CD-ROM, etc.
All communication correspondences between QUEST E & P and Client shall be through the QUEST
E & P’s nominated Project Manager and Client’s (designated) Representative. Each correspondence
shall deal with only one subject, or with closely related subjects.
C. INFORMATION SECURITY
A project specific Information Security Management Procedure will be prepared for this project. The
procedure will be applicable to all project activities and at all project locations during execution of the
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
project. The procedure provide the guidelines for securing information and document i.e. electronic
data, software and hardware, and hard copy documents that shall be secured against unauthorized access
and disclosure and for preventing damage by all kinds of incidents (unexpected events, such as
earthquake, fire, hurricane, and flood, etc, computer operator mistake, intrusion by hackers or infection
by a computer virus, etc). All vendors or subcontractors involved in the use of any form of confidential
information shall be made to be aware of the procedure and also sign a Secrecy Agreement.
The Project Manager shall be responsible for implementation of the Information Security Management
Procedure. The nominated Document Controller on the project shall be responsible for maintaining the
distribution status for reproduced confidential information. Each individual working on the project shall
be given the security awareness training and keep his password to access the electronic file from being
disclosed.
QUEST E & P has a functional communications & reporting procedures with the lastest state of art
technology .
We have Glo VPN facilities for staffers .
Our offices are fully internet compliance (internet facilities completely installed and functional) and thus
have easy access to our selves & OEM websites from our desktop computers and laptops any time.
We also have two way Radio UHF/VHF system for communication in remote areas/site and between
Riggers and workers on ground.
The reporting system is simple and strictly adhered to. Below is a Block diagram of the reporting system
of the QUEST E & P.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Managing Director
Safety Manager
Project Engineer
Project Teams
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
E. Progress Meetings
Regular Progress meetings shall be held to review progress, any scope changes, problem areas, etc. The
progress Meetings shall be held on a weekly basis. Even though there is a minimal amount of personnel
involved, formal project meetings shall always be held but shall be kept to a reasonable minimum. The
project Manager shall keep the project team, Client and QUEST E & P Management informed on a
weekly basis as to project status through e-mail or daily project communication.
Once the Project Scope, Deliverables List and Preliminary Schedule have been prepared, an internal
Kick-off Meeting shall be held to inform team members of the requirements of the Project, answer any
questions, etc.
Personnel who shall attend this meeting are:
• All lead discipline engineers or their designates (Civil, Electrical, mechanical, etc.)
These meetings shall be held as a minimum, on a monthly basis. Items to be reviewed at the meeting will
be the items outlined in the Monthly Progress Reports. It is the responsibility of the Project Manager or
Project Engineer to schedule these meetings.
These meetings shall be scheduled with the Client. The frequency of these meeting will vary depending
on the particular Client, but shall be held every two weeks as a minimum.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
I. Field Meetings
Field Meetings shall be scheduled to ensure buy-in from field operations and construction. The
requirement for Field Meetings shall be reviewed with the Client.
Request or call for project related meetings on this project shall be channeled through the QUEST E &
P’s project manager and/or Client’s Representative. A minimum of 12 hours shall be allowed from the
time of call for a meeting and the meeting scheduled time. Following any meetings on the project at which
QUEST E & P is represented, QUEST E & P shall issue all minutes of meeting on the project within 12
hours after the meeting. The minutes of meetings shall be recorded on QUEST E & P’s standard Project
Minutes of Meeting Format showing including Meeting/discussion title, date, venue, list of participants,
record of discussions, record of agreed action parties etc. All minutes of meeting shall be numbered
consecutively. All minutes of meetings shall be duly agreed to by QUEST E & P’s Project Manager and
Client’s Representative before filing for record purpose.
All schedules shall be developed using Microsoft’s Project for Windows 98.
Depending on the Project, a more detailed Schedule may be required once information becomes
available (i.e. during the Basic Engineering Phase).
The Project Schedule must be approved by the Client and shall be reviewed with QUEST E & P
Management.
The Project Schedule along with the Engineering Man-hour Estimate are dynamic indicators of the
progress on the project. Thus, they require regular review.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
L. ESTIMATES
An Engineering Man-hour Estimate shall be prepared in order for QUEST E & P Management to
have an accurate assessment of the personnel that will be required to execute the Project and also as a
means of controlling the engineering progress and costs on the project. The Engineering Man-hour
Estimate shall be done during the Basic Engineering Phase when the scope of the project has been
better detailed. The Client’s requirements may dictate it being done at an earlier date. The Engineering
Man-hour Estimate shall still be reviewed during the Basic Engineering Phase to ensure it is still realistic.
The Engineering Man-hour Estimate shall be reviewed with the various disciplines before it is finalized.
The final Engineering Man-hour Estimate shall require Management approval before being formally
issued to the Client.
A Capital Cost Estimate shall be done on the Project for the Client’s AFE purposes. This is important as
it is a means for controlling the total costs on a project. The timing of the estimate may vary depending
on the Client’s requirements, but as a minimum shall be done at the end of the Basic Engineering Phase
when the Project is well defined. If the estimate was generated at an earlier time, it shall be reviewed and
updated at the end of the Basic Engineering to ensure it is still realistic.
The Capital Cost Estimate shall be done in conjunction with the other discipline personnel and will need
Management approval before being formally issued to the Client.
A dedicated document controller shall be nominated for this project who shall be responsible for all
document control activities on the project in line with the company Corporate Engineering Document
Control Procedure (Document No.: PEL-PP-007) and Project Document Control Plan. The document
controller shall utilize the Document Control Register (DCR) described in Section
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
3.2 above for document distribution and tracking. The distribution of checked engineering documents
is controlled by means of the IDC control/routing sheet.
The documents will be giving out on need to have bases.
The Project Manager shall complete the Document Distribution Matrix and forward it to Document
Control. This is the basis for document distribution and must be kept up to date.
The Project Manager shall instruct the Document Controller to set up hard copy files for both
documents and drawings. The location of files shall be provided to all personnel associated with the
project and QUEST E & P Management.
The Project Manager shall be responsible for setting up the electronic filling system.
The Project Manager shall ensure that all soft files associated with the project have been properly filed
in the computer. Once the Project Manager is satisfied that this has been accomplished, he shall advise
the computer maintenance group and document controller to archive the project. The Project Manager
shall assign a single person to be responsible for the project filing. This person shall work in conjunction
with Document Controller.
P. LIST OF RELEVANT APPLICABLE DOCUMENTS
Iv. Progress Report with ‘s’ curve, histogram and bar schedule
Q. PERSONNEL ASSIGNMENT
Senior personnel from each discipline (the department head or their designated) shall have input into the
Project and shall also sign off on all key documents in their area of expertise. These personnel shall also
be informed of the Project Scope and Schedule Milestones so that they can ensure that the requirements
of Projects are met.
Following is a list of these personnel:
• Electrical
• Civil/Structural
• Mechanical Piping
If any of the above personnel cannot commit or commit others to the Project Manager, shall be
immediately notified so that the problem can be rectified early in the project.
It shall be noted that certain documents on domestic projects require the Permit to Practice stamp. The
Project Manager or the discipline leader shall keep the appropriate people informed of these
requirements.
Project Documentation falls under the control of the Project Manager and Document Control is the
Project Manager’s responsibility to inform Document Control that a project has started and what the
project will entail.
Document Control is ultimately responsible for setting up the hard copy files, stock files, and
distribution of documents, receipt of documents, stamping of documents, and transmittal of documents,
document control (registers) and collection of information for Data Books. Drafting stock files shall be
set up by the lead designer on the project. Coordination and management of these stock files shall be
done in conjunction with individual disciplines and project manager on the project.
The Project Manager and discipline leaders shall be responsible to ensure that all soft copies of files
associated to the project are properly filed in the electronic filing system.
Document Control will be designated a hanging file location, file drawer and/or file drawers for in-
house, vendor and as-built drawings. A separate file will be kept for superseded drawings. A hanging file
will be designated for stock files.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
A file drawer of flat file drawer will be located in the Project Filing Area for documentation, data sheet
and drawing filing. Document Control will set up and organize these files.
Document Control shall be responsible for receiving vendor drawings, logging vendor drawings in,
distributing vendor drawings to the appropriate disciplines, designating time for drawing review (in
conjunction with the Project Manager), logging vendor drawings out and sending drawings back to
vendors.
Document Control shall be responsible for distributing QUEST E & P generated drawings to
appropriate disciplines, designating time for drawing review (in conjunction with the Project Manager),
and maintaining log as to when they were sent out to the client, what revision was sent and when they
were received back from the Client.
A data collection box will be set up in the document control area for storage of information that is
required for the Data Books and start up Manual. The Project Manager will set up the Table of Contents
(use QUEST E & P Standard for the Data Books and startup Manual or provide specific information
to Document Control what information shall be collected.
A copy of the Data Books and Start up Manual will be kept by Document Control in the Project Library.
All photographs from completed projects shall be submitted to Document Control. Document Control
shall keep photographs of all projects.
Project Manager shall be responsible for completing the Project Summary located in the BD drive of
the computer.
When a project is completed all documentation created during the execution of the project shall be
submitted to Document Control. If an Engineer wants to keep any of their information for future
reference they must make a copy for Document Control. This includes but not limited to the following;
• Project procedures
• Project specifications
• Schedules
• Cost/man-hour control
• Telephone conversations
• Meeting notes
• Minutes of meetings
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
• Process calculations
• Instrument calculations
• Electrical calculations
• Engineering reports
• Drawings
• Sketches
• Data sheets
• Vendor data
• Construction report
Document Control will set up and store the documentation in archive storage
boxes. These boxes will then be removed to an off site storage facility.
On this project, the above information / data will be generated on a weekly basis
and reported in the man-hour and man-cost progress summary reports. This
information is digested on a weekly basis to analyze trends of performance.
Doc No: QOG11-NPDC-T2022004-003
Doc.
TENDER FORM C: WORK EXECUTION PLAN
Description:
NIGERIAN PETROLEUM DEVELOPMENT
Project No 2022004 Client Name Rev: 0.1
COMPANY LIMITED
Project Name: PROVISION OF TUBING RUNNING SERVICES FOR NPDC OPERATIONS
Action(s) is (are) taken to resolve problem areas and safeguard milestone dates /
overall schedules and budgets.
FABRICATION YARD/WORKSHOP
Quest E&P Limited (Quest’s), for the purpose of this project shall utilize the fabrication yard/workshop
is located at, Army Shooting Range, Igwuruta, Port-Harcourt, Rivers State. Nigeria.
This fabrication yard/workshop belongs to our partner De Grills Integrated Services Ltd, a major
subcontractor on this project.
The yard seats on 12,150 Square Meters area with an existing 1,500 square meters’ provision for
expansion and has a Covered Workshop area of 675 Square Meters with 700 Tons Bearing Weight.
Its’ location is very strategic, and has easy access to the International Airport, Choba Jetty and the
Trans-Amadi Industrial Layout.