4.3 Crane/Hoist
4.5 Transporters
5 General
5.1 Estimated concrete quantity ………………….m3
5.2 Estimated period of concreting………………hrs
5.3 Mix proportion/Grade…………………………………………
5.4 Openings in beams/slabs
5.5 Anchor bolts/Fan hooks
5.6 Special features (drops in slabs)
5.7 Conduits, surface blocks etc
5.8 No of test cubes…………………..
5.9 Slum……….mm and test
6 Curing
6.1 Curing Start……………………… up to……………………..
6.2 7 days cube strength
6.3 28 cube strength
6.4 Honeycombs etc…………