Summary description of the desired change: [write the summary or attach if there is a change proposal]
Microwave Service Cutover on Site WR5018.
The operation step as follow
1. Export history alarm.
2. Backup data On site.
3. Do cutover for BBU and EISU.
4. Querying history alarm after cutover.
5. Service Verification
Urgent
√ Standard
High √
2.Proposed change priority 3.Change
1 Normal
category
1 Medium
Low Major
√ Hardware Database Others(mention )
4. Change Type
Security
NO
10. Technology aspects (is a new technology being introduced?)
1. Identified risks:
Service will be down for 1 hour.
2. Risk mitigation plan: [attach the risk mitigation plan for the identified risk(s)] [
11.Risks during the No risk
implementation of the
3. Back-out strategy for the case of a failed Change implementation (with estimated
Change
duration):
Full name
Id Position