Guidelines for the Management of Change for Process Safety

by Center for Chemical Process Safety


Copyright © 2008 American Institute of Chemical Engineers, Inc

APPENDIX C:
EXAMPLES OF MOC SYSTEM
PROCEDURE WORK FLOW CHARTS
AND MOC REVIEW DOCUMENTATION
FORMS

The following figures provide examples of MOC system procedure work flow
charts and MOC review documentation forms. These charts and forms should
be considered advisory; they should not be used directly without going
through the proper MOC system design and development activities discussed
in Chapters 3 and 4.

Figure C. 1. Example of an MOC system procedure work flow chart.


Figure C.2. Example of a simple MOC review documentation form.
Figure C.3. Example of a moderate MOC review documentation form.
Figure C.4. Example of a complex MOC review documentation form
(including checklists).

123
Yes

Initial Review

Classification
Review

Hazard Review

Figure C.l Example of an MOC System Procedure Work Flow Chart

125
126 GUIDELINES FOR MANAGEMENT OF CHANGE

f
Complete tasks
identified as
required before
implementation

Authorization
Review

Close-out
Review

Figure C.l Example of an MOC System Procedure Work Flow Chart (cont 'd)
APPENDIX 127

Change description and rationale:

If the change is temporary, list the


pertinent dates. Dates valid:

Originator
This change has met the appropriate review requirements and has been
approved. Safety, health, and environmental concerns have been addressed,
procedures have been revised, the appropriate training and/or communication
activities have occurred, and all affected process safety information is being
updated.

RFC Authorizer

FIGURE C.2. Simple MOC Review Documentation Form


128 GUIDELINES FOR MANAGEMENT OF CHANGE

Unit or Area: RFC No.:

Description and reason for change: Date:

Orignator

• Temporary Change Removal Date:


Environmental, health, and safety reviews are complete and all concerns have been addressed.

EH&S Review Team Leader


Operating maintenance, and emergency procedures have been reviewed

Area Procedures Coordinator


All affected personnel have been informed of the change. The appropriate trailing has taken place.

Are a Tr aining C ο or dinator


All affected process safety inform edi on is scheduled for revision.

Unit Engneer

• PSSR Required PSSR No.:

This change has met the appropnate review requirements and has been approved.

Area Manager

FIGURE C.3. Moderate MOC Review Documentation Form


APPENDIX 129

REQUEST FOR CHANGE FORM

Standard Change • RFC No. .


Emergency Change • Date Requested,
Temporary Change • Date Required,

Unit System or Equipment

Description (include technical basis for change):

Originator

I. TensOrary Changes (slap for permanent changes). This inicematian maybe provided in a temporary procedure (attach copy)
Whyis this designated a tempztraiy change?
Additionalpiecaxticns required:
Contingency plan
Dates valid:
Feisonresponsiblefbrtemoving the change:

II. Safety, HealtH and Environmental Reviews


Reqd' Responsible Target Date
(Y/N) Party Date Complete Initials
Process S afcty (specify rnetliod) Y
Ocoipatianal Safe tyJlndustiul Hygiene
Enviraunenta] Review (s)

* Complete = Actianitems with immediate iripact are resclved and planis inplace to address long range items.

III. FfrcceduresRevised
Reqd' Responsible Target Date
(Υ/Μ) Party Date Complete Initials
StaitupfthitdaviVErnejgeiry Shitdcwn Y
Normal Operation
Maintenance
Emeigency Response
Other (e.g., administrative)
** Complete = Revised procedures issued ;ary obsolete proaeduies discaidel.

FIGURE C.4. Complex MOC Review Documentation Form (including


checklists)
130 GUIDELINES FOR MANAGEMENT OF CHANGE

I. Training

W4 Individuals or Responsible Taiget Date


(Y/N) Groups to be trained ftrty Date Complete Initials
Operations Y
Mainterustce
Cortactor
Other
' Complete = AU specified peEcemel lave teceived and undeistood training. Responsibility fcf Any changetopermanent training
(e.g., learning blocks) is assigned and scheduled.

II. Process Safety Irfomi«ionRevised


Reqd' Responsible Date Target
(YiN) Party Coxtflete" Date Initials
WD Y
Access Flow Diagram
Electrical System Dooimentation
Reliefs ystemDooimentatkn
Spare Parts List
MSES
Documented Operating Limits
Other
* Ccetffeteif the» are aiy Yes responses:
Folow-up Responsib ility
PS S R Responsibility
PSSR No.

III. Authorization
This change has net the appropriate leviewrequiietnenband has been appioved.

Aiea Operations Manager Area Engineering Manager


IV. Close-out Review
All of the indicated process sa&ty infce-rraticffi revisions (S action V) hac^e been completed. This MOC action is complete.

FIGURE C.4. Complex MOC Review Documentation Form (including


checklists) (cont'd)
APPENDIX 131

P lant modifi c ation tracking no.: G Off-hours review


MOC initiation dale
Modification title: R e quire d implem e ntati on date

Permanent G TemporaxyG Expires


Requestor: Date:
Unit: Ο FCCU Ο ΗF-Alky G Crude G Quality Control • H£
G Reformer G Terminal G Maintenance G Other
Estimated costs of modification: Parts, material, equipment Labor Total
Description of change D oes a sketch accompany this form? G Y es G Ν ο

Purpose (technical basis)

Ρ otential impact on safety, health and the environment (including the public)

Reviews

G Approved
Area Manager Dete G Denied
C omments, conditions, or reasons for denial

Ηaz«dreview required Q Yes Q No Technique: Ο MOC G WhaUif Ο HAZOP Q Other


Initials

G Approved

Area Engineer Dcte Ο D eti e d


C omments, conditions, or reasons for denial

Deagnresponsibility assigiedto Design review required DYes D No

FIGURE C.4. Complex MOC Review Documentation Form (including


checklists) (cont fd)