You are on page 1of 15

Center for Continuing Education - UPES

Airport Planning & Management


Assignment 2

Total Questions: 56
Total Marks: 100

Assignment Information :

The examination will consist of only Objective type (multiple choice) questions
requiring candidates to Mouse-click their correct choice of alternatives against
the related question number. The questions would carry 1 to 5 marks each
depending on the difficulty level of the question as indicated in the table below:

Difficulty Level of Questions:

1 Mark - Direct, Memory based


2 Marks - Memory & Conceptual
3 Marks - Conceptual & Analytical
4 Marks - Analytical based on understanding of concepts
5 Marks - Application based on understanding of concepts
   The question paper will be for 100 marks and considering marks
allotted to each question, the total number of questions would be
around 56.
   There will not be negative marking for wrong answers.
   In case candidate does not want to attempt the question he I she
should not mouse-click any option.
   The students are allowed to save the responses and come back later
to resume, complete and "Save and Submit" the assignment. However,
if the Due Date has expired, then the assignment will not be accessible
and will be marked as zero. In such cases, the student can re-attempt
the assignment allocated after enrolling in the subsequent Semester.
   Once submitted, that answer sheet cannot be retreieved for any
editing. The student has to initiate a new attempt (if allowed), if he has
submitted the assignment by mistake.
   The students are normally allowed 3 chances to attempt and submit
the assignment. The number of attempts availed is displayed under the
"Test Information".
   The Highest Grade of the 3 attempts shall be considered for grading.
   The assignments are auto evaluated, and hence no chance of re-
evaluation/re-totalling is allowed to the student.
Multiple Attempts This Test allows 3
attempts. This is
attempt number 1.
Force Completion This Test can be
saved and resumed
later.
Your answers are
saved automatically.
 Question Completion Status
QUE S TION 1
1. 5.     The interface between the road in front of the PTB and the PTB entrance is
called________________.
5.     Pick-up
Forecourt
Pedestrian island
Interface

5 points   
QUE S TION 2
1. 35.     ACI has published a self-contained Excel Spread Sheet with which an inventory can
be prepared. This tool is known as Airport Carbon & Emissions Reporting Tool (ACERT).
The information needed for this are: a. Total aircraft, passenger and cargo movements’.
Fuel use by airport and tenant vehicles, buildings, emergency generators and fire
training’. b. Electricity purchased by the airport operator and tenants, Aircraft
movements categorized either by specific aircraft type, or by generic aircraft type, or
total fuel loaded on to aircraft, Aircraft taxi and APU usage times and engine run-ups,
information on sewage and waste disposal c. Either a detailed landside traffic study or
estimates of passenger and staff ground access such as use of public transport, and car,
taxi, bus and train activity, and Corporate travel by airport staff .d. Staff ground access
such as use of public transport, and car, taxi, bus and train activity, and Corporate travel
by airport staff.
35.                        Answer a&b
Answer a,b&c
Answer c
Answer d

5 points   
QUE S TION 3
1. 29.     What is the AGL system? a. Air And Ground Lighting b. Airfield Ground Lighting c.
Apron Ground Lighting d. Aircraft Ground lighting
29.                        Answer a
Answer b
Answer c
Answer d

5 points   
QUE S TION 4
1. The capacity of the airfield depends particularly on the runway that determines the
number of ATM it can handle, which can be specified for one hour and from there
computed for one day and then on an annual basis. ATM determines: a. All Time Money
b. Air Traffic Movement c. Automated Teller Machine d. Asynchronous Transfer Mode
36.                        Answer a
Answer b
Answer c
Answer d

5 points   
QUE S TION 5
1. Insurance, Advertisement, Business Promotion / Event management, Rent, Taxes (other
than corporate tax), Audit fee, Office expenses- Printing & Stationery, communication
etc., Collection charges, Community development, Conveyance Which category of
expense can these be put into? a. Consultancy expenses b. Operating expenses c.
Manpower Expenses d. Administration expenses
Answer A
Answer b
Answer c
Answer d

4 points   
QUE S TION 6
1. An Apron is a defined area, on a land aerodrome, intended to accommodate aircraft for
purposes of – a.loading or unloading passengers, mail or cargo, fueling, parking or
maintenance b.maintenance c.fueling and parking d.mail and cargo Choose the best
option.
Answer a
Answer b
Answer c
Answer d

4 points   
QUE S TION 7
1. Non-aeronautical revenues include a. Ground Handling concession fee b. Aviation fuel
concession fee c. Cargo Fee d. Airport charges
Answer a, b, c
Answer a,b
Answer a,d
Answer a, c

4 points   
QUE S TION 8
1. Infrastructure to be incorporated in the master plan in the interface between airside and
city side are Passenger terminal building(s), Cargo terminal building and Aircraft MRO. In
Aircraft, MRO stands for :
Maintenance Repair Operations
Medical Review Officer
Maintenance, Repair and Overhaul
None of these

4 points   
QUE S TION 9
1. Catering trucks coming into the airside from landside requires inspection by ____________
before they enter the airport.
Aviation Security
personnel
Check Point Personnel
Security Personnel
Emergency Personnel
None of these

2 points   
QUE S TION 10
1. What is the full form of ADM?
Aerodrome Design Manuals
Aircraft Design Manuals
Aerodrome Dimension Manuals
Aerodrome Digonal Manuals
None of these

2 points   
QUE S TION 11
1. Precision approach procedure is an instrument approach procedure using precision
lateral and vertical guidance
True
False
Partially True
Partially False
None of these

2 points   
QUE S TION 12
1. Annex 3 of Chicago Convention deals with:
The Safe Transport of Dangerous Goods by Air
Airworthiness of Aircraft
Meteorological Service for International Air Navigation
Airworthiness of Aircraft
None of these

2 points   
QUE S TION 13
1. The _________ process which include baggage or passenger screening for security
purposes, Passport Control, Customs etc. require proper spatial planning and correct
alignment for smooth passenger flow.
Equipment building
Technical building
Terminal building
Passenger Terminal building
None of these

2 points   
QUE S TION 14
1. Recommended Maximum Slope of PBB is __________.
11.50%
10.50%
12.50%
9.40%
None of these

2 points   
QUE S TION 15
1. Threshold is a defined rectangular area on a land aerodrome prepared for the landing
and take-off of aircrafts.
True
False
Partially True
Partially False
None of these

2 points   
QUE S TION 16
1. Facilities or infrastructure to be incorporated in the master plan for airside include:
Rescue and Fire Fighting (RFF) stations or Fire Stations
Ground support vehicle workshops
Choice 1 and 2
All of these
None of these

2 points   
QUE S TION 17
1. Aviation fuel storage facility is located as close to the aircraft apron as practical while
consideration given to clearance of _____________.
Foreign Object Debris
Runway visual range
Obstacle limitation surfaces
Airport Authority of India
None of these

2 points   
QUE S TION 18
1. The length of the take-off run available plus the length of the stop way, if provided.
Take-off distance available
Landing distance available (LDA)
Accelerate-stop distance available (ASDA)
Take-off run available
None of these

2 points   
QUE S TION 19
1. Datum elevation for transitional surface is:
Along the side of the approach surface
In the front of the approach surface
In the end of the approach surface
Along the surface of the approach surface
None of these

2 points   
QUE S TION 20
1. The performance measure parameters can be partial factor productivity performance
indicators or __________.
Absolute numbers
Natural numbers
Mean numbers
Whole numbers
None of these

2 points   
QUE S TION 21
1. Permissible Cross wind components for an aircraft is 24 KM/hour for reference field
between ___________.
1100 &1400 m
1200 &1500 m
1300 &1600 m
1400 &1700 m
None of these
2 points   
QUE S TION 22
1. In large Airports, multiple terminals needs to be interconnected through automatic
people mover (APM) system.
True
False
Partially True
Partially False
None of these

2 points   
QUE S TION 23
1. The linear option IN Check-In area is preferred for small airports where walking distances
is less.
True
False
Partially True
Partially False
None of these

2 points   
QUE S TION 24
1. Which of these is required as an airfield infrastructure:
Runway length, width
Number of Parallel taxiways
Airfield Ground Lighting (AGL) system requirement
Communication, Navigation & Surveillance (CNS) systems
None of these

2 points   
QUE S TION 25
1. ____________presently has one runway but the master planning provides for second
runway.
Pune Airport
Cochin Airport
Hyderabad airport
Mumbai airport
None of these

1 points   
QUE S TION 26
1. What is the full form of LoS?
Actual level of services
Passenger Services
Traffic Management Services
Level of Service
None of these

1 points   
QUE S TION 27
1. Instrument used for __________ is the Instrument Landing System, popularly known as ILS.
Runway Approach
Precision approach
Dependent Parallel Approach
Independent Parallel Approach
None of these

1 points   
QUE S TION 28
1. __________ could be a single level or multilevel depending on the capacity of the airport.
Automatic People Movers
Space Per Passenger
Passenger Boarding Bridge
Passenger Terminal Building
None of these

1 points   
QUE S TION 29
1. The objective of ___________ is to provide efficient, comfortable, convenient and reliable
services with highest standards of safety and a secure environment.
Aerodrome operations
Aircraft operations
Ariel operations
Airport operations
None of these

1 points   
QUE S TION 30
1. Runway location and orientation are based on:
Runway Slope
Wind Direction
Multiple Runways
Runway Length
None of these

1 points   
QUE S TION 31
1. The____________is the effect of the rotating air masses generated behind the wing tips of
large jet aircraft.
Wake turbulence
Time based Wake turbulence
Distance based Wake turbulence
Invisible turbulence
None of these

1 points   
QUE S TION 32
1. What is the full form of DME?
Distance Maintaining Instrument
Digital Measuring Instrument
Distance Measuring Indicator
Distance Measuring Instrument
None of these

1 points   
QUE S TION 33
1. Today, one third of worldwide Revenue Passenger Kilometres are performed by airlines
registered in _________.
Asia and Pacific
Asia and Africa
Pacific and North America
Pacific and Africa
None of these

1 points   
QUE S TION 34
1. It includes a part of non-aeronautical revenue is considered along with the aeronautical
revenue for the cost recovery principle to decide the aeronautical charges.
Single till approach
Dual till approach
Fragile Object
Hybrid till approach
None of these

1 points   
QUE S TION 35
1. ___________supports the single till principle under which airport non-aeronautical
revenues are considered to offset the aeronautical charges.
International Air Transport Association
Indian Air Transport Association
International Airodrome Transport Association
International Air Transact Association
None of these

1 points   
QUE S TION 36
1. What is the full form of TODA?
Take-off distance available
Turn-off distance available
Take-off distance approach
Take-off distant available
None of these

1 points   
QUE S TION 37
1. Secondary radar__________ provides the altitude
Monopulse Secondary Surveillance Radar
Mono Secondary Surveillance Radar
Monopulse System Surveillance Radar
Monopulse Secondary Security Radar
None of these

1 points   
QUE S TION 38
1. _________ is installed at about 300 m from the threshold towards the runway and offset
by 120 m from the runway centre line.
Localizer
Glide Path
Radar
VOR
None of these

1 points   
QUE S TION 39
1. ____________ is a portion of an apron designated as a taxiway and intended to provide
access to aircraft stands only.
Parallel Taxiway
Aircraft stand Taxi lane
Apron taxiway
All of these
None of these

1 points   
QUE S TION 40
1. In many countries, the issue of airport construction is governed by _______________ of
construction sites.
National legislation
General legislation on planning and
development
Navigation Service Providers
All of these
None of these

1 points   
QUE S TION 41
1. ___________ is defined as an area including a taxiway intended to protect an aircraft
operating on the taxiway and to reduce the risk of damage to an aircraft accidentally
running off the taxiway.
Apron
Clearway
Taxiway strip
Runway
None of these

1 points   
QUE S TION 42
1. What is the full form of GBAS VDB?
Ground Based Aviation System VCF Data Broadcast
Ground Briefing Augmentation System VVF Data Broadcast
Gravity Based Augmentation System VcF Data Broadcast
Ground Based Augmentation System VHF Data Broadcast
None of these

1 points   
QUE S TION 43
1. The location, size and configuration of the airport has a significant impact on __________,
__________, __________, ________and other land uses of the area.
Residential
Industrial
Commercial
Agricultural
All of these

1 points   
QUE S TION 44
1. Governments looks challenging while more __________ involvement is anticipated for the
airport development and subsequently for operations and management.
Private sector
Allied Sector
Public Sector
Defence
None of these

1 points   
QUE S TION 45
1. __________ is responsible for managing the revenues and expenditure.
Support Functions
Finance function
HR Function
Security Function
None of these

1 points   
QUE S TION 46
1. _____________should be planned and developed based on the wide consultations with
airlines, manufacturers close to the airport who may use the facility, freight forward
agents and others who may use the facility.
Bypass Facility
Cargo handling facility
Storage Facility
Catering Facility
None of these

1 points   
QUE S TION 47
1. Runway designation is determined by their ___________.
Heading
Zero Elevation
Apron taxiway
Aircraft stand Taxi lane
None of these
1 points   
QUE S TION 48
1. A runway intended for the operation of an aircraft using visual approach procedures or
an instrument approach procedure to a point beyond which the approach may continue
in visual meteorological conditions.
Non-Instrument runway
Instrument runway
Precision Approach Runway
Non-Precision Approach Runway
None of these

1 points   
QUE S TION 49
1. What is the full form of ATA?
Actual Time of Departure
Scheduled Time of Departure
Actual Time of Arrival
Scheduled Time of Arrival
None of these

1 points   
QUE S TION 50
1. ____________ is for the purpose of funding or financing the costs of upgradation or
expansion or development of the airport. The fee can also be to establish and develop a
new airport.
Departure Fee
Development Fee
Divisional Fee
Landing Fee
None of these

1 points   
QUE S TION 51
1. What is the full form of ASDE?
Airport Surveillance Detection Equipment
Airport Surface Development Equipment
Airport Surface Detection Equipment
Airport Speed Detection Equipment
None of these

1 points   
QUE S TION 52
1. What is the full form of ANSP?
Aviation Navigation Service Provider
Aerodrome Navigation Service Provider
Air Navigation Service Provider
Air National Service Provider
None of these

1 points   
QUE S TION 53
1. ___________ and taxiway shoulder dimensions depends on the aerodrome code.
Taxiway Shoulder
Runway shoulder
Pavement Shoulder
All of these
None of these

1 points   
QUE S TION 54
1. What is the full form of GPU?
Ground Planned Unit
Ground Power Unit
Ground plant unit
Government Planned
Unit
None of these

1 points   
QUE S TION 55
1. Airlines operating cost increases due to more fuel consumption, more aircraft idle time is
the result of?
Poor OTP
Peak Point ATM
Ground Handler
Air Traffic Control
None of these

1 points   
QUE S TION 56
1. A defined area including the runway and stop way, if provided, is intended to reduce the
risk of damage to aircraft running off a runway.
Runway strip
Taxiway strip
Clearway
Stopway
None of these

You might also like