You are on page 1of 329

TRANSIENT PRESSURE

ANALYSIS IN VERTICAL
WELLS

A PROJECT
SUBMITTED TO THE DEPARTMENT OF
PETROLEUM ENGINEERING
OF AL-FATAH UNIVERSITY
IN PARTIAL FULFILLMENT OF
THE REQUIREMENTS
FOR THE DEGREE OF
BACHELOR OF SCIENCE IN
PETROLEUM ENGINEERING

By:

Haithem D. Alzanati
Waleed A. Algmati

Supervised by:

Dr. Said I. Aldbaib

Spring-2008
DEDICATION
This project is dedicated with all our heart to
our beloved Parents and to our dear brothers
and sisters

I
ABSTRACT
This work studied the well tests analysis and productivity
index evaluation of vertical wells in Amal oil fields.

First, different aspects of well testing where reviewed; including


objectives and Diffusivity equation solution, Limitations and
Applications.

Second, the Theory of Build-up Transient Pressure Analysis in


vertical wells was reviewed.

Third, the factors affecting pressure build-up behavior.

Finally, Three pressure build-up tests for three oil wells in Amal
field at different times to monitoring the reservoir parameters that
were estimated from these pressure tests, and pressure build-up
test for a certain well in Abu-Attiful field to investigate the
presence of parallel faults as outer boundary effect where analyzed
by Conventional Techniques (enhanced by a computer program).

I
ACKNOWLEDGEMENT

First of all we would like to thank Allah the Merciful and


Almighty for giving us the support and power to finish
this work

We would like to thank our families specially our parents for their
asking Allah for us to do this project successfully.

We are extremely grateful to our advisor Dr. Said I. Aldbaib for


his guidance and patience during this study.

We would like to extend my gratitude to the faculty staff and


colleagues in the Petroleum Engineering Department for providing
a cooperative and friendly atmosphere throughout our stay at
Al-Fateh University.

Special thanks to Planning Department in Al Harouge Oil


Company for supplying us with the data of Wells,

We would like to extend a special thanks to Eng. Sofian A. Ayad,


for helping us on several aspects of this work.

II
Contents
Abstract……………………………………………………………….. I
Acknowledgements………………………………………………….. II
Table of Contents……………………………………………………. III
List of Tables………………………………………………………… VI
List of Figures……………………………………………………….. VII

Chapter 1
Overview of Well Testing
1.1 Introduction………………………………………………….. 2
1.2 Well Testing Objectives………………………………......... 3
1.3 Diffusivity Equation…………………………………………. 3
1.3.1 Fluid Flow in Porous Media…………….………….. 4
1.3.2 Diffusivity Equation Assumption……..……………. 5
1.3.3 Radial Flow…………………………………..………. 6
1.3.4 Diffusivity Equation Solutions…………..…………. 7
1.4 Wellbore Storage……………………………………………. 11
1.5 Skin Effect……………………………………………………. 12
1.5.1 Reservoir Model……………………………………… 12
1.5.2 Effect of Wellbore Radius…………………………... 14
1.5.3 Positive Skin………………………………………….. 15
1.5.4 Negative Skin……………………………..………….. 15
1.6 Semi-Log Plot………………………………………………... 16
1.7 Pressure Derivative…………………………………………. 18
1.7.1 Derivative Computation…………………………….. 18

Chapter 2
Pressure Build-up Test Analysis
2.1 Introduction………………………….……………………….. 21
2.1.1 Test Objective……………..………...…………......... 21
2.1.2 How the Test is Run…………………………………. 21
2.2 Conventional BU Analysis Techniques…………………… 22
2.2.1 Basic Equations……………………………………… 22
2.2.2 The Semi-log Plots…………………………………… 24
2.2.3 Defining the Flow Rate and Production Time…… 27

III
2.2.4 Calculation of the Average Reservoir Pressure…. 29
2.2.5 The Super-Position Technique……………………... 32
2.2.6 Multi-phase Flow Analysis…………………………. 34

Chapter 3
Factors Affecting Pressure Build-up Behavior
3.1 Introduction……….………………………………………….. 37
3.2 Factors Affecting Early BU Period……………………….. 39
3.2.1 Well-bore Storage Effect……………………………. 39
3.2.2 Effect of Phase Redistribution in the well-bore….. 43
3.2.3 Effect of the Partial Penetration…………………… 44
3.2.4 Effect of Vertical Hydraulic Fracture……………... 46
3.3 Factors Affecting the Semi-log Straight Line Period…… 53
3.3.1 Pressure Behavior in Layered Reservoirs………… 53
3.3.2 Pressure Behavior in Naturally Fractured 56
Reservoirs………………………………………………
3.4 Factors Affecting Late BU Period………………………… 58
3.4.1 Effect of Linear Faults………………………………. 58
3.4.2 Effect of Interference from a near-by producer….. 68

Chapter 4
Well Test Interpretation Methodology
4.1 Introduction 72
4.2 Segmental Analysis Approach……………………………… 73
4.2.1 Advantages of the Segmental Analysis …….……… 75
4.2.2 Limitation of the Segmental Analysis……………… 75
4.3 Integrated Model Approach 76
4.3.1 Advantages of the Integrated Model Approach….. 77
4.3.2 Limitation of the Integrated Model Approach……. 77
4.4 Recommended Approach…………………………………… 78

Chapter 5
Field Cases
5.1 Introduction…………………………………………………... 92
5.2 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-27/1966………………………….. 94

IV
5.3 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-27/1973………………………….. 103
5.4 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-27/1975………………………….. 112
5.5 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-27/1983………………………….. 121
5.6 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-42/1966………………………….. 131
5.7 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-42/1972………………………….. 140
5.8 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-42/1973………………………….. 149
5.9 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-42/1980………………………….. 158
5.10 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-45/1972………………………….. 167
5.11 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-45/1983………………………….. 176
5.12 Conventional Analysis Procedures for Build-up
Pressure Test in Well B-45/1984………………………….. 186
5.13 Conventional Analysis Procedures for Build-up
Pressure Test in Well A-67/1996.………………………….. 196

Chapter 6
Conclusion and Recommendations
6.1 Conclusion……………………………………………………. 206
6.2 Recommendations……………………………………………. 208

Appendix A……………………………………………………………. 209


Appendix B……………………………………………………………. 215
Appendix C…………...………………………………………………. 254
Appendix D…………...………………………………………………. 308
References…………………………………………………………….. 315

V
List of Tables

Table

4.1 Reservoir parameters estimated for each flow


regime……………………………………………………….74
4.2 Step by step conventional analysis procedure for build-
up pressure test in vertical wells…………………...……79

B-1 Buildup test data (Pressure vs. Time) of well


B-27/1966…………………………………………………216
B-2 Buildup test data (Pressure vs. Time) of well
B-27/1973…………………………………………………217
B-3 Buildup test data (Pressure vs. Time) of well
B-27/1975…………………………………………………218
B-4 Buildup test data (Pressure vs. Time) of well
B-27/1983…………………………………………………219
B-5 Buildup test data (Pressure vs. Time) of well
B-42/1966…………………………………………………222
B-6 Buildup test data (Pressure vs. Time) of well
B-42/1972…………………………………………………223
B-7 Buildup test data (Pressure vs. Time) of well
B-42/1973……………………………………………..….224
B-8 Buildup test data (Pressure vs. Time) of well
B-42/1980…………………………………………………225
B-9 Buildup test data (Pressure vs. Time) of well
B-45/1972…………………………………………………228
B-10 Buildup test data (Pressure vs. Time) of well
B-45/1983…………………………………………………229
B-11 Buildup test data (Pressure vs. Time) of well
B-45/1984…………………………………………………231
B-12 Buildup test data (Pressure vs. Time) of well
A-67/1996…………………………………………………235
B-13 Shape Factors for Various Single-Well Drainage
Areas…………………………………………………….…254

VI
List of Figures
Figure
1-1 Infinite Acting Radial Flow………………………………. 4
1-2 Radial Flow………………………………………………… 6
1-3 Wellbore Storage………………………………………….. 11
1-4 Reservoir Model…………………………………………… 13
1-5 Finite Radius……………………………………………….. 14
1-6 Positive Skin……………………………………………….. 15
1-7 Negative Skin………………………………………………. 16
1-8 Semi Log Plot- Draw Down……………………………… 17
1-9 Pressure Derivative……………………………………….. 18

2-1 Production Rate and Pressure History of Two Rate


Flow Test…………………………………………………… 23
2-2 Horner Plot………………………………………………… 25
2-3 MDH Plot…………………………………………………... 26

3-1 Effect of Wellbore Storage on Log-Log Plot…………... 40


3-2 Effect of Wellbore Storage on MDH Plot………………. 40
3-3 Flow into a Vertical Hydraulic Fracture………………. 47
3-4 Effect of Vertical Hydraulic Fracture on Linear Plot… 49
3-5 Effect of Vertical Hydraulic Fracture on Log-Log
Plot…………………………………………………………... 49
3-6 Typical Build-up Curve for a Two-Layered System with
NO Cross Flow………………………………………. 55
3-7 Typical Build-up Curve for a Natural Fracture
System………………………………………………………... 57
3-8 Effect of a Single Sealing Fault…………………………... 60
3-9a Effect of Two Intersecting Faults (Case A)……………... 64
3-9b Effect of Two Intersecting Faults (Case B)……………... 64
3-10 Fluid Flow in Well Situated Between Two Parallel
Faults………………………………………………………... 65
3-11a Build-up a Well Located Between Two Parallel Faults
on MDH Plot……………………..…………….…………… 67

VII
3-11b Build-up a Well Located Between Two Parallel Faults
on Linear Plot………………………………………………. 67

4-1 Transient pressure performance in a vertical well 73

B – 27 (1966)
C-1 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 256
C-2 Log-Log plot of pressure drop vs. shut-in time 257
C-3 Log-Log plot of pressure derivative vs. shut-in time 258
C-4 Horner plot 259

B – 27 (1973)
C-5 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 260
C-6 Log-Log plot of pressure drop vs. shut-in time 261
C-7 Log-Log plot of pressure derivative vs. shut-in time 262
C-8 Horner plot 263

B – 27 (1975)
C-9 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 264
C-10 Log-Log plot of pressure drop vs. shut-in time 265
C-11 Log-Log plot of pressure derivative vs. shut-in time 266
C-12 Horner plot 267

B – 27 (1983)
C-13 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 268
C-14 Log-Log plot of pressure drop vs. shut-in time 269
C-15 Log-Log plot of pressure derivative vs. shut-in time 270
C-16 Horner plot 271

B – 42 (1966)
C-17 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 273

VIII
C-18 Log-Log plot of pressure drop vs. shut-in time 274
C-19 Log-Log plot of pressure derivative vs. shut-in time 275
C-20 Horner plot 276

B – 42 (1972)
C-21 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 277
C-22 Log-Log plot of pressure drop vs. shut-in time 278
C-23 Log-Log plot of pressure derivative vs. shut-in time 279
C-24 Horner plot 280

B – 42 (1973)
C-25 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 281
C-26 Log-Log plot of pressure drop vs. shut-in time 282
C-27 Log-Log plot of pressure derivative vs. shut-in time 283
C-28 Horner plot 284

B – 42 (1980)
C-29 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 285
C-30 Log-Log plot of pressure drop vs. shut-in time 286
C-31 Log-Log plot of pressure derivative vs. shut-in time 287
C-32 Horner plot 288

B – 45 (1972)
C-33 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 290
C-34 Log-Log plot of pressure drop vs. shut-in time 291
C-35 Log-Log plot of pressure derivative vs. shut-in time 292
C-36 Horner plot 293

B – 45 (1983)
C-37 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 294
C-38 Log-Log plot of pressure drop vs. shut-in time 295

IX
39 Log-Log plot of pressure derivative vs. shut-in time 296
C-40 Horner plot 297

B – 45 (1984)
C-41 Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 298
C-42 Log-Log plot of pressure drop vs. shut-in time 299
C-43 Log-Log plot of pressure derivative vs. shut-in time 300
C-44 Horner plot 301

A – 67 (1996)
Log-Log plot of pressure drop and pressure derivative
vs. shut-in time 303
Log-Log plot of pressure drop vs. shut-in time 304
Log-Log plot of pressure derivative vs. shut-in time 305
Linear plot of Shut-in pressure and pressure derivative
vs. shut-in time 306
Horner plot 307

X
Chapter One

Overview of Well Testing


Chapter 1 Overview of Well Testing

Overview of Well Testing


1.1 Introduction

Oil well test analysis is a branch of reservoir engineering.


Information obtained from flow and pressure transient tests
about in situ reservoir conditions are important to determining
the productive capacity of a reservoir. Pressure transient
analysis also yields estimates of the average reservoir pressure.

The reservoir engineer must have sufficient information


about the condition and characteristics of reservoir/well to
adequately analyze reservoir performance and to forecast future
production under various modes of operation. The production
engineer must know the condition of production and injection
wells to persuade the best possible performance from the
reservoir.

Pressures are the most valuable and useful data in


reservoir engineering. Directly or indirectly, they enter into all
phases of reservoir engineering calculations. Therefore
accurate determination of reservoir parameters is very
important.

A brief review of pressure transient analysis explains why


advances in technology have had such a significant impact on
well testing.

At the start of production, pressure in the wellbore drops


sharply and fluid near the well expands and moves toward the
area of lower pressure. This movement is retarded by friction
against the pore walls and the fluid’s own inertia and viscosity.
As the fluid moves, however, it in turn creates a pressure
imbalance that induces neighboring fluid to move toward the
well. The process continues until the drop in pressure that was
created by the start of production is dissipated throughout the
reservoir.

2
Chapter 1 Overview of Well Testing

1.2 Well Testing Objectives

Only Well Testing provides information on the Dynamic


Behavior of the reservoir. A well test depending on its design
may provide the following objectives:

1. Reservoir flow capacity (kh).


2. Near wellbore conditions (damage, stimulation).
3. Initial or average reservoir pressure.
4. Reservoir flow behavior.
5. Reservoir size.
6. Inflow performance response.
7. Communication between wells.
8. To determine whether all the drilled length of oil well is
also a producing in horizontal wells;

1.3 Diffusivity Equation

At the start of production, pressure in the wellbore drops


suddenly. The fluid in the vicinity to the well expands and moves
towards lower pressure; this movement is retarded by viscous,
inertial and frictional forces.

As the fluid moves, it will in turn create a pressure


imbalance and this will induce neighbouring fluids to move, the
process continues until the pressure drop is dissipated.

The physical process occurring in the reservoir can be


described by the Diffusivity Equation.

3
Chapter 1 Overview of Well Testing

Figure (1-1): Infinite Acting Radial Flow

In order to use the diffusivity equation it is necessary to


determine the boundary conditions, where the complex
boundary conditions may be solved by applying the “principle
of superposition” in space.

Variable flow rates can be tackled by applying the


“principle of superposition” in time that analyst to model the
effects that features such as faults and changes in reservoir size
could have on the pressure response.

The radial flow equation does not account for the drop in
pressure due to damage or improvement near the wellbore.
Instead, the term skin was invented. The early portion of the test
is also distorted by wellbore storage effects.

1.3.1 Fluid Flow in Porous Media:

The fluid flow in porous media can be expressed by


diffusivity equation; where this equation is combination of the
following equations:

4
Chapter 1 Overview of Well Testing

• Continuity Equation in Radial Coordinates

1∂
(ρ r v ) = − ∂ (ρ φ ) ………………………….…………. Eq (1.1)
r ∂r ∂t

• Darcy's Law in Radial Coordinates

k ∂p
v=− ………………………………..…………………. Eq (1.2)
μ ∂r

• Equation of State

Ct = C + C f ……………………………………….…………. Eq (1.3)

Where:
1 ∂φ
Cf = …………………………………….….…………. Eq (1.4)
φ∂p

1 ∂ρ
C= …………………………..………….….…………. Eq (1.5)
p∂p

1.3.2 Diffusivity Equation Assumption:

1. Single phase fluid.


2. Laminar flow.
3. The permeability, (k) is isotropic and constant
4. The (ct) and (μ) constant.
5. Reservoir is homogeneous.
6. Isothermal condition.
7. Small pressure gradient.

5
Chapter 1 Overview of Well Testing

The Radial Form of the Diffusivity Equation for Liquids:

∂2 p 1⎛ ∂ p ⎞ φ μ Ct ⎛ ∂ p ⎞
+ ⎜
⎜ ⎟
⎟ = ⎜⎜ ⎟⎟ ………………………. Eq (1.6)
∂ r r ⎝ ∂ r ⎠ 0.000264 k ⎝ ∂ t ⎠
2

Where:
0.000264 k
Hydraulic diffusivity index η =
φ μ Ct

1.3.3 Radial Flow (1-Dimension):

For steady state case;


1. Darcy’s Law
2. Laminar flow

∂p v μ
− = …………………………………………..………. Eq (1.7)
∂r k

Figure (1-2): Radial Flow

6
Chapter 1 Overview of Well Testing

1.3.4 Diffusivity Equation Solutions:

To solve of diffusivity equation we need to identify:

Initial Condition: t = 0 p = pi
Boundary Conditions: 1. r → ∞ p( t ,r ) → pi
kh ⎛ ∂p ⎞
2. r = rw qsf = 0.00708 ⎜r ⎟
βμ ⎝ ∂r ⎠ r = rw

There are three basic solutions for diffusivity equation:

Case (a): The Infinite Acting System

This condition is used to represent the early-time pressure


behavior at the well bore, so long as the effects of outer
boundaries are not felt, or can be negligible.

The exact solution in this case, normally termed the "Line


Source Solution", has the following form:

qμβ ⎛ φμCt rw2 ⎞


P ( r ,t ) = Pi + 70.6 Ei ⎜ − ⎟ ………………… Eq (1.8)
kh ⎝⎜ 0.00105 kt ⎟⎠

The Exponential Integral can be defined by the following


relationship:

∞ −y
e
− Ei (− x ) = ∫ dy …………………………………………. Eq (1.9)
x y

The Exponential Integral is defined numerically as follows:

∞ ( −1 )n x n
− Ei (− x ) = −γ − ln( x ) − ∑ ……………………. Eq (1.10)
n =1 n.n!

7
Chapter 1 Overview of Well Testing

The value of the summation term represents < 0.2% of the value
of –Ei (-x) for x< 0.01 and thus can be neglected, so:

− Ei (− x ) = − ln( x ) − 0.5772 ………………..…………… Eq (1.11)

Substitution of Equation (1.9) in Equation (1.8) would result in


the following equation, known in the literature as the
"Logarithmic Solution";

⎛ qμβ ⎛ kt ⎞⎞
P ( r ,t ) = Pi − ⎜⎜ 162.6 ⎜⎜ log − 3 . 23 ⎟⎟ ⎟ ……… Eq (1.12)

⎝ kh ⎝ φμC r
t w
2
⎠⎠

It is important to note that the solutions represented by Equation


(1.8) and (1.12) can be used so long as the effects of the
boundaries are not felt. Different authors have shown that the
effect of a boundary at a distance, (re) from the well bore can
always be neglected regardless of the boundary condition,
whether closed or at constant pressure, so long as the following
condition is stratified:

φμCt re2
t ≤ 948 ……………………………………………. Eq (1.13)
k

Case (b): The Closed Boundary System

In this case, the reservoir is considered to be of finite


radial extent, with no radial flow across the outer boundary,
thus:

dP
= 0 at r = re
dr

This condition is normally applied to wells producing in a


developed reservoir system or to a well in a volumetric system.

8
Chapter 1 Overview of Well Testing

The exact solution of the diffusivity equation using no flow


condition across the outer boundary is too complex and includes
infinite series of Bessell function. However, Ramey and cobb
(1971) were able to show that for the square, circular, and
hexagonal drainage system, the pressure behavior at the
producing well can be divided into two periods as follows:

φμCt re2
1) Transient period, t ≤ 948
k

During this period, the closed system behaves essentially


as infinite system, and, consequently, Equation (1.12) can be
used to represent the pressure behavior at the well bore.

φμCt re2
2) Pseudo (Semi) steady state period, t > 948
k

During this period the pressure change at the well bore is


a linear function of time, (i.e. dP/dt = constant). The bottom
hole flowing pressure in this case can be represented by the
following equation:

qμβ ⎛ 2( 0.000264 )kt re 3 ⎞


P wf = Pi − 141.2 ⎜⎜ + ln − ⎟ …… Eq (1.14)
kh ⎝ φμCt re2 rw 4 ⎟⎠

it is important to note that if the shape of the system deviates


considerably from the square, radial, or hexagonal shape, or if
the well is shifted from the centre of the system, then there exists
a transitional period between the transient and semi-steady state
period which cannot be analyzed by any of the previous
equations. Type curve analysis, or trial and error procedures
suggested by Muskat and developed by Matthews and Russell
can be used in such a case.

9
Chapter 1 Overview of Well Testing

Case (c): Constant Pressure at the Outer Boundary

In this case, the outer boundary of the drainage system is


maintained at a constant pressure, such as in the case of strong
natural water drive or water flood. This condition is represented
by (P=Pi at r=re).

The exact solution to this case problem is also too


complex. However, different investigators have shown that the
pressure behavior at the producing well can be divided into
three distinct periods as follows:

φμCt re2
1) Transient Period, t ≤ 948
k

During this period the system behaves essentially as an


infinite acting system, and consequently, Equation (1.12) can be
used to describe the pressure behavior at the well bore.

2) Transitional (Late Transient) Period

This period is defined for a circular drainage shape, by the


following relationship:

φμCt re2 φμCt re2


948 ≤ t ≤ 3800 …………………………Eq (1.15)
k k

Type curves analysis, or trial and error procedures, are


required to analyze the pressure behavior during this period.

φμCt re2
3) Steady State Period, t ≥ 3800
k

During this period, the pressure change at the well bore


(or at any point in the system) is independent of time, (i.e. dP/dt
= 0).

10
Chapter 1 Overview of Well Testing

The reservoir pressure at any point, r, in this case can be


evaluated by direct integration of the Darcy Equation as
follows;

qμβ ⎛ re ⎞
P ( r ,t ) = Pi − 141.2 .ln ⎜⎜ ⎟⎟ ……………….………… Eq (1.16)
kh ⎝ rw ⎠

1.4 Wellbore Storage

Figure (1-3): Wellbore Storage

Fluid filled wellbore: (


dpw q − qsf B
=
)
dt 24Vwb cwb

Rising liquid level:


=
( )
dpw q − qsf B ⎛ 5.615 ρ wb ⎞⎛ g ⎞
⎜⎜ ⎟⎟⎜⎜ ⎟⎟
dt 24 ⎝ 144 Awb ⎠⎝ g c ⎠

11
Chapter 1 Overview of Well Testing

General: (
dpw q − qsf B
=
)
dt 24C

Wellbore storage definition:


C≡
(q − qsf )B
dpw
24
dt

1.5 Skin Effect

Skin is a term used to reflect the existence of damage and


the degree of damage severity or the improvement of production
by stimulation.

1.5.1 Reservoir Model:

• Consider an undisturbed formation of thickness (h) and


permeability (k).

• Assume that something (drilling the well, producing fluid from


the well, injecting fluid into the well) changes the permeability
near the wellbore. One simple model of this effect is to
assume that this altered zone has uniform permeability (ka)
and radius (ra), and that the rest of the reservoir is
undisturbed.

• For generality, we allow the permeability in the altered zone


to be either smaller or larger than the permeability in the
undisturbed formation.

12
Chapter 1 Overview of Well Testing

Figure (1-4): Reservoir Model

• Added pressure difference due to Skin effect.

• Permeability around well can be damaged by well drilling


process, by fracture, acid or perforation. To accommodate for
this, Van Everdingen defined and area of infinitesimal size
around the wellbore

• Hawkins defined Skin of finite radius (rSkin) with (kSkin)

⎛ k ⎞ r
S = ⎜⎜ − 1⎟⎟ ln skin ……………….………….……… Eq (1.17)
⎝ k skin ⎠ rw

• Unfortunately, there is no unique (rSkin) , (kSkin) for any( S).

13
Chapter 1 Overview of Well Testing

Figure (1-5): Finite Radius

S = 0 if (ks = k or rs = rw)

1.5.2 Effect of Wellbore Radius

• Alternative treatment of Skin Effect is “effective wellbore


radius” (Matthews and Russel), the radius which makes the
pressure drop in an ideal reservoir equal to that of an actual
reservoir with Skin:

rwa = rw e − S ……………….……………………..……… Eq (1.18)

• This is equivalent to Hawkins with (kskin = inf)

• For Skin = 0, rwa= rw


• For Skin > 0, rwa < rw
• For Skin < 0, rwa > rw

14
Chapter 1 Overview of Well Testing

1.5.3 Positive Skin

If in the immediate vicinity close to the wellbore there is


an additional pressure drop due to skin, the well is said to be
damaged and (S > 0)

Figure (1-6): Positive Skin

1.5.4 Negative Skin

The mathematical equivalent to negative skin, is a larger


‘apparent’ wellbore, (rwa), the well is said to be stimulated and
(S < 0)

15
Chapter 1 Overview of Well Testing

Figure (1-7): Negative Skin

1.6 Semi Log Plot

During radial flow, the pressure change is related to the


logarithm of the time. In other words, if pressure is plotted
against the log of time, infinite-acting radial flow will give a
straight line. For this reason the classical approach to well test
interpretation has been the semi-log plot, of (P vs. log Δt):
The plot above is the ‘MDH’ (Miller-Dyes-Hutchinson) plot; for
a drawdown, but the principles described below apply equally
well to a build-up.

• Considering the ideal case, of putting on production a well


with no wellbore storage and no skin, the blue curve is
obtained. The straight line representing radial flow is
established almost instantaneously, and from the slope of the
line the permeability-thickness product, (kh), is obtained.

• With wellbore storage but no skin the red curve is obtained.


Initially production is only from decompression of the
wellbore fluid, so the bottom hole pressure remains constant

16
Chapter 1 Overview of Well Testing

for a short while, as if the well were still shut in. Once there
is movement of fluid through the sand face, the bottom hole
pressure starts to drop, and once the effects of storage are
over the red curve transitions onto the ideal curve.

• With skin but no storage, the green curve shows radial flow
immediately, parallel to but offset from the ideal blue line.
The offset on the y-axis corresponds to (ΔPs) at this flow rate
and the slope of the straight line can not be different, as it
represents the (kh) of the system.

• A typical test will reveal both wellbore storage and skin,


corresponding to the black curve transitioning on to the
green curve. The storage causes the delay, the skin the offset,
and once again the final straight line slope is unchanged, as
permeability is a reservoir property and is unaffected by
near-wellbore effects.

Figure (1-8): Semi Log Plot- Draw Down

17
Chapter 1 Overview of Well Testing

1.7 Pressure Derivative

The introduction of the pressure derivative in (1983)


transformed the science of well test interpretation, which until
that time had been based upon the semi-log plot by including the
pressure derivative plot with the log-log plot.

Figure (1-9): Pressure Derivative

The slope of the semi-log plot is evaluated at all points, of which


(7) key points are shown in the plot:

• The data starts at point (1), before eventually stabilizing at


slope m in Infinite-Acting Radial Flow, points (6) and (7).

• Points (1) and (2) fall on the wellbore storage unit-slope in


early time and, during the transition to IARF, the derivative
peaks at point (4). The transition is complete at point (6), as
the derivative flattens to a value equivalent to m.

1.7.1 Derivative Computation:

To compute pressure derivative, (ΔP), pressure change, must be


computed:

ΔP= Pi – Pwf (Δt)

18
Chapter 1 Overview of Well Testing

For drawdown data, and

ΔP= Pws (Δt) – Pwf (tp)

For build up data, where:

Pi = Initial formation pressure


Pwf = Bottom hole flowing pressure
Pws = Bottom hole shut-in pressure
Δt = Elapsed time since start of transient test
tp = Duration of production time prior to shut-in.

Compute (tp) as the cumulative production prior to the build up


test, divided by the last rate before shut-in.

Given drawdown transient data, the pressure derivative is


computed as the derivative of (ΔP) with respect to the natural
logarithm of the elapsed time:

dΔP p( ti +1 ) − p( ti −1 )
= ……………….………...… Eq (1.19)
d ln( Δt ) ln( ti +1 ) − ln( ti −1 )

For the elapsed time Δt = ti – t0

Where: t0 = the starting time for the transient data.

Given build up transient data, the preferred derivative


computation is

dΔP p( ti +1 ) − p( ti −1 )
= ……………….………….…...… Eq (1.20)
dτ τ i +1 −τ i −1

Where: τ = superposition time, and

t p + Δti
τ i = ln ……………….……………………...…...… Eq (1.21)
Δti

19
Chapter Two

Pressure Build-up Test


Analysis
Chapter 2 Pressure Build-up Test Analysis

Pressure Build-up Test Analysis


2.1 Introduction

2.1.1 Test Objectives:

The primary objectives of the Build-up Test are the


determination of:

1. The effective permeability-thickness product, (kh).


2. The skin factors, (S), and the pressure drop due to skin,
(∆Ps), and,
3. The average pressure, (P), in the drainage area.

Other information which can be obtained from the BU test


includes:

1. Hydraulic fracture length and orientation.


2. Detection of Faults and distance to nearest fault.
3. Qualitative and/or quantitative information about the well-
bore and reservoir conditions such as: phase segregation
in the well-bore, layering, natural fracturing, effective
interconnected porosity between wells, etc.

It is important to note that no one pressure BU test can be


providing all the abovementioned information. Consequently, it
is important to define Apriori the parameters that need to be
determined in order to make the proper choice and design of the
pressure build-up test.

2.1.2 How the Test Is Run:

1. The build-up test is run by maintaining the well at a


constant flow rate, (q), and prior to the start of the test.
The constant flow rate period is recommended mainly to
make the calculations as simple as possible.

21
Chapter 2 Pressure Build-up Test Analysis

2. Few hours prior to the shut down of the well, the pressure-
measuring device is lowered into the well bore, and the
measurement of the flowing bottom hole pressure, (Pwf), is
started.

3. The well is then shut down, and the bottom hole shut-in
pressure, (Pws), is recorded versus shut in time. The
duration of the shut-in period should be designed, apriori,
using the most probable formation and well-bore
parameters obtained from previous tests or from near-by
wells.

2.2 Conventional BU Analysis Techniques

2.2.1 Basic Equations:

If an oil well is produced at a constant flow rate, (q1), for a


certain time period, t, then the flow rate is changed to another
constant flow rate, (q2), figure (2-1), then the Super position
principle can be used to derive the following expression for the
pressure drop, (∆P), at the well bore at any time, (∆t), after the
rate change:

q1μB ⎛ t + Δt ⎞ q μB
P1 − Pwf = 162.6 ⎜ log ⎟ + 162.6 2 (log Δt )
kh ⎝ Δt ⎠ kh
q2 μB ⎛⎜ k ⎞
⎟ ......... Eq ( 2.1 )
+ 162.6 ⎜ log 2
− 3. 23 + 0. 87 S ⎟
kh ⎝ φμcrw ⎠

22
Chapter 2 Pressure Build-up Test Analysis

Figure (2-1): Production Rate and Pressure History of Two


Rate Flow Test

The build-up test can be considered as a two-rate test in which


the second flow rate, (q2), is equal to zero, i.e.

qμB ⎛ t + Δt ⎞
P1 − Pws = 162.6 ⎜ log ⎟ ………………………… Eq (2.2)
kh ⎝ Δt ⎠

Where:

t = Production time (in hours) at the second flow rate, q,


∆t = time in hours after shut-in, and
q = Stabilized production rate (STB/D) prior to shut-in.

If the production time, t, is much longer than the shut-in time,


∆t, then Equation (2.2) can be simplified into the following
form:

qμB qμB
P1 − Pws = 162.6 .log( t ) − 162.6 .log( Δt ) …..... Eq (2.3)
kh kh

23
Chapter 2 Pressure Build-up Test Analysis

2.2.2 The Semi-log Plots:

i. The Horner Plot:

The form of Equation (2.2) suggests that a plot of Pws versus


((t+∆t)/ ∆t) (normally known as the Horner Plot) should
produce a straight line on a semi-log plot. The slope of the
straight line would be equal to:

qμB qμB
m = 162.6 ,or , kh = 162.6 ….…..... Eq (2.4)
kh m

In order to calculate the skin factor, (S), consider the bottom


hole flowing pressure, (Pwf), at the instant prior to shutting the
well. Then:

qμB ⎛⎜ k ⎞

P1 − Pwf = 162.6 log − 3.23 + 0. 87 S
kh ⎜⎝ 2
φμcrw ⎟

Also consider the shut-in bottom hole pressure after exactly one
hour of shut-in time, (P1hr). Then substitution into Equation (2.2)
would result in the following relationship:

qμB
P1 − P1hr = 162.6 .log( t + 1 )
kh

If the flowing period is long enough such that log (t+1) is


approximately equal to log (t), then the above two equations can
be combined to derive the following expression for the skin
factor:

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟ ….………...... Eq (2.5)
m 2
φμcrw ⎟
⎝ ⎠

24
Chapter 2 Pressure Build-up Test Analysis

A typical Horner plot is shown in figure (2-2). The derivation


during the early period will be discussed in chapter (3) (Factors
affecting pressure BU behavior).

Horner Plot
4300

4100

3900

3700
Pws

3500

3300

3100

2900

2700
100 1000 10000 100000
Horner time

Figure (2-2): Horner Plot

ii. The MDH Plot:

The form of Equation (2.3) suggests that a plot of (Pws vs. ∆t)
(normally known as the Miller, Dyes, and Hutchenson, MDH
plot) should produce a straight line on a semi-log plot. In this
case, the values of (kh) and (S) can be calculated using the same
equations developed earlier for the Horner method, (i.e.
Equations 2.4 and 2.5).

Important Remarks

1. It is important to note that the MDH technique should not


be used for any data points falling in the range (∆t>t/10).
2. The Horner plot is superior to the MDH plot since it can
always be used regardless of how short or long is the
production time. Also because the Horner plot straightens

25
Chapter 2 Pressure Build-up Test Analysis

more data points than would the MDH plot. This could be
a big advantage for the Horner plot in wells suffering from
gas segregation in the tubing.
3. Finally, it should be noted that P1hr used in Equation (2.5)
(in the Horner and MDH techniques) is not the actual
measured pressure after one hour but rather the pressure
taken from the extension of the semi-log straight line at (∆t
= one hour).

A typical MDH plot is shown in figure (2-3). The derivation


during the early period will be discussed in chapter three
(Factors affecting pressure BU behavior).

MDH Plot
4300

4100

3900

3700
Pws

3500

3300

3100

2900

2700
0.1 1.0 10.0
Shut-in time

Figure (2-3): MDH Plot

26
Chapter 2 Pressure Build-up Test Analysis

2.2.3 Defining the Flow Rate and Production Time:

One of the main concerns in the analysis of the pressure Build-


up test is the definition or choice of the flow rate, (q), and of the
flowing time, (t), when the well has been producing at a variable
rate prior to shut-in. Improper choice of the values of (q) and (t)
would lead to erroneous estimates of (k), (S), and the average
pressure. Different approaches have been proposed. The main
objective of these approaches was to maintain the use of the
normal Horner plot (i.e. Pws vs. t+∆t/ ∆t) even in the case of
variable flow rates. Two approaches that are widely used by
practicing engineers are:

i. The Corrected Time Method:

This method was suggested by Horner, and it utilizes the last


stabilized flow rate, (qlast), with a correct flow time, (tc), to
simulate the production history prior to the shut-in period.
Consequently, Equation (2.2) is now re-written as follows:

q L μB ⎛ t + Δt ⎞
P1 − Pws = 162.6 ⎜ log c ⎟ ….………………...... Eq (2.6)
kh ⎝ Δt ⎠

Where, tc=Np/q(last)

And, Np=cumulative oil production prior to the BU test.

In a later study of this approach, Odeh and Napor have made


two important conclusions:

1. The Horner corrected time approach could create


substantial error in the result if the last flow rate prior to
the BU test was not allowed to stabilize for a minimum
time period > Φµre2/k
2. The shut-in data points which can be trusted in the
corrected time method to calculate meaningful and

27
Chapter 2 Pressure Build-up Test Analysis

accurate results are limited by (∆t<tL), where (tL) is the


duration of the last flow period with stabilized flow rate, (q
last).

ii. The Pseudo t*- q* Method:

In this approach a pseudo flow rate, (q*), and a pseudo flowing


time, (t*), are used in the Horner plot to account for the
changing flow rate prior to the test. The pseudo values are
calculated as follows:

⎛ − ⎞
* ⎜
t =2 t−
1 n −1
2
⎜ N p i =0 i i +1 i
(2

)
. ∑ ( q ) t − t / 2 ⎟ ….……………...... Eq (2.7)
⎝ ⎠

Where:

qi = average flow rate during the period ti to ti+1


n = number of rate changes
t = actual flow time in days
Np = cumulative production (STB)

The pseudo production rate is defined as:

Np
q* = ….……………………………………………...... Eq (2.8)
t*
Some investigators have indicated that this method is normally
liable to produce higher errors in the analysis of Horner plot, as
compared to the corrected time method.

Consequently, this approach should only be used in case the


Horner corrected time method cannot be used; for example if
the duration of the last stabilized rate does not satisfy the
criteria presented earlier by Odeh and Napor, or in case the
production is declining continuously due to damage (such as in
case of sand and asphaltene precipitations).

28
Chapter 2 Pressure Build-up Test Analysis

2.2.4 Calculation of the Average Reservoir Pressure:

Different techniques have appeared in the literature for the


calculation of the average pressure in the drainage area. Most
of these techniques are based on extrapolating the straight line
of the semi-log plot to a certain time, and developing
correlations between the pressure value read at that time and
the average pressure of the system. The most popular
correlations are:

1. Matthews, Brons, and Hazepbrooek (MBH) type curves,


2. Miller, Dyes, and Hutchinson (MDH) type curves,
3. Dietz correlation for MDH plots,
4. Ramey and Cobb technique for Horner plots.

i. MBH Type Curves:

Extrapolating of the straight line in the Horner plot to ((t+∆t)/


∆t=1) is equivalent to assuming that the well is shut in for an
infinite time, (i.e ∆t= ∞). Consequently, such extrapolating of
the straight line should result in the correct value of the average
pressure. However, this is not correct since the equations
derived in the above analysis are for the infinite acting system,
and do not represent the effect of the closed boundary system.

Consequently, the above-mentioned extrapolating would result


in a pressure value (termed P*) which is always higher than the
average pressure of the system, but less than or equal to the
initial pressure.

Type curves relating the extrapolated (normally termed false)


pressure, (P*), to the average pressure of the system were
developed by Mattews, Brons, and Hazepbroek Appendix (D-2).

29
Chapter 2 Pressure Build-up Test Analysis

These type curves correlate the difference between the false and
the average pressure as a function of the dimensionless
production time of the system, (tpDA), and are presented for
different drainage shapes and well locations, where:
tpDA=0.000264kt / ΦµcA and A = drainage area (ft2)

ii. MDH Type Curves:

The MDH plot of (Pws vs. ∆t) does not allow for extrapolation to
infinite shut-in time; i.e. to a false pressure, (P*). An alternative
method for the determination of the average reservoir pressure
was presented by Miller, Dyes, and Hutchinson in the form of
the type curves given in Appendix (D-1), which correlate the
pressure difference (P-Pws), (where Pws is the shut-in pressure
on the straight line portion at any time, ∆t) versus the
corresponding dimensionless shut-in time, (∆tDA) where in this
case ∆tDA=0.000264k∆t / ΦµcA

It is important to note that the MDH type curves include the No-
flow boundary case as well as the constant pressure boundary
case, which is the case of a producer surrounded by injectors.
However, the principle draw back is that the method is
restricted to the circular or square shapes.

Tracy G.W. gas extended the MDH method to read directly the
real shut-in time at which the static pressure can be read from
the MDH plot. The equation derived by Tracy as follows:

φμce A
Δt s = 120.7 (For a test well offset by producers)
k

φμce A
Δt s = 253.5 (For a test well offset by producers on one
k
side and injectors or a gas cap on the other side)

30
Chapter 2 Pressure Build-up Test Analysis

φμce A
Δt s = 253.5 or 537.1 (For a test well surrounded by
k
injectors on all sides)

Finally, it is also important to note that the end of the straight


line portion in the case of No-flow type curve occurs at
(∆tDA=0.009). This important result can be used to determine
the real time when the semi-log straight line on the MDH plot
should end and the flattening of the pressure data starts. This
time can be calculated as follows:

φμce A
0.009 = 0.000264 kΔtend / φμcA or Δtend = 34.1 hours
k

iii. Dietz Method:

This method is based on extrapolating the straight line-portion


of the MDH plot to a certain shut-in time, at which the reading
on the straight line will be equivalent to the average pressure of
the drainage area. This shut-in time can be calculated using the
following equation:

tp φμct A
( Δt )p = = ……………………… Eq (2.9)
C At DA 0.0002637 kC A

The value of (CA) is dependent on the drainage shape and on the


relative position of the well as seen in the tables presented in
Appendix-B (Table 13).

iv. Ramey and Cobb Technique:

This method is based on extrapolating the straight line-portion


of the Horner plot to a certain time, at which the reading on the
straight line will be equivalent to the average pressure of the
drainage area. This Horner shut-in time can be calculated using
the following equation:

31
Chapter 2 Pressure Build-up Test Analysis

⎛ t + Δt ⎞ 0.0002637 kC At p
⎜ ⎟ = C t
A DA = …………..……. Eq (2.10)
⎝ Δ t ⎠p φμct A

Important Remarks:

1. The Dietz and Ramey and Cobb methods are practical and
simple to use since they do not require graph reading.
However, their use will introduce some error in the
calculation if:
a) The skin factor is <-3 (i.e. hydraulic fracturing or
extensive acidization)
b) Production time, (t < tpss), where tpss is the time
required to reach pseudo-steady state which can be
calculated using the following equation:

φμct A
t pss = (t DA ) pss
0.0002637 k

The value of (tDA)pss is read directly from the tables


given in Appendix-B (Table 13).

2. The MBH type curves method is considered superior to all


other correlations since it encompasses the entire range of
production time. However, it still requires some
modification when used in highly stimulated wells (i.e. S<-
3).

2.2.5 The Super-Position Technique:

From analytical point of view, the most accurate solution would


involve expressing the pressure behavior as a multi-rate test
using the Super-Position principle. The equation representing
multi-rate conditions can be written as follows:

32
Chapter 2 Pressure Build-up Test Analysis

μB n −1
Pi − Pwf = 162.6 ∑ (q j +1 − q j ).log (tn − t j )
kh j =0

qn μB ⎛⎜ k ⎞
⎟ ......... Eq ( 2.11 )
+ 162.6 log − 3.23 + 0. 87 S
kh ⎜⎝ 2
φμcrw ⎟

In the case of build-up test, the last flow rate, (qn), represents
the shut-in period, (i.e. qn=0). Consequently, the above equation
can be re-written in the following form:

μB n −1
Pi − Pwf = 162.6 ∑ (q j +1 − q j ).log (tn − t j ) ……..…. Eq (2.12)
kh j =0

Where t0 = 0
q0 = 0
tj = time in hours when the flow rate is changed from qj
to qj+1
tn = shut-in time when Pws is measured, (i.e. total flow time
+ ∆t)

A plot of (Pws) vs. the summation term should produce a straight


qμB
line with a slope, m, and equal to 162.6 , from which the
kh
permeability-thickness product can be calculated.

This method is most suitable for computer use if an accurate


record of the actual well rates is available. In actual field
practice, however, such data is not always available since only
average rates (on monthly or bi-monthly basis) calculated from
the cumulative production are normally available.

33
Chapter 2 Pressure Build-up Test Analysis

2.2.6 Multi-phase Flow Analysis

The Perrine technique is used to analysis BU tests when more


than one phase is flowing toward the well-bore. Its main
assumption is that the saturations of the different phases are
uniform throughout the drainage area. This is normally a very
acceptable assumption when only oil and water are flowing.
However, some error should be expected if a gas phase is also
flowing in the system. The error would be increasing as the
average pressure continuous to decline below the bubble point
pressure.

The Horner method of analysis described previously can be


used in the build-up test analysis in case of multi-phase flow.
The slope, m, of the semi-log plot is related to the different
relative permeability of the different phases as follows:

qo μo Bo
ko = 162.6
mh
q μ B
k w = 162.6 w w w
mh

k g = 162.6
( )
q g − qo Rs / 100 μ g Bg
.................................. Eq ( 2.13 )
mh

The skin factor can be calculated using the following equation:

⎛ P1hr − Pwf λt ⎞
S = 1.151⎜⎜ − log 2
+ 3 . 23 ⎟ ……………. Eq (2.14)

⎝ m φμct rw ⎠
Where the total mobility of the system, λt is defined as follows:

ko kw kg
λt = + +
μo μw μg

34
Chapter 2 Pressure Build-up Test Analysis

Since the oil, gas, and water compressibility are changing with
pressure, the main problem would be the choice of the pressure
at which the total compressibility should be evaluated. The most
logical would be using a pressure which is average between the
bottom hole flowing pressure and the reservoir average
pressure. This would require a troublesome trial and error
procedure since the calculation of the average pressure requires
the knowledge of the total compressibility apriori.

Consequently, a simpler approach was suggested in which the


flowing bottom hole pressure is used as a basis for the
calculation of the individual compressibility. The oil and water
compressibility are calculated as follows:

− 1 dBo Bg dRs
Co = +
Bo dp 1000 Bo dp
− 1 dBw Bg dRsw
Cw = +
Bw dp 1000 Bw dp
and ,
Ct = Co S o + Cw S w + C g S g ...............................................Eq ( 2.15 )

The calculation of the average pressure in the case of multi


phase flow system would follow the same procedures described
previously for the single phase flow system.

35
Chapter Three

Factors Affecting
Pressure Build-up
Behavior
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Factors Affecting Pressure Build-up Behavior


3.1 Introduction

The pressure behavior at the well bore can be considered as a


reflection of all natural and human factors affecting the
dynamic flow of the fluids toward the well bore. This includes
the conditions at the outer boundaries, formation rock
properties, structural configuration, well bore conditions, and
production history.

Whenever a change is imposed at the well bore in the form of a


change in the flow rate, a corresponding change in the bottom
hole pressure will occur. Factors dominating the change in
pressure are:

o During the Early Period:

¾ The fluid properties inside the well bore such as:


1. Storage capacity of the fluids inside the well bore,
directly related to the fluid compressibility, and,
2. Phase redistribution (mainly, gas segregation), when
the well is opened to flow, or when the well is shut
down.

¾ Factors related to the change of the rock properties in the


area immediately surrounding the well bore such as:
1. Permeability damage caused by mud penetration
and/or asphalthene precipitation.
2. Permeability improvement resulting from stimulation
jobs.

¾ Factors related to the path which the fluids take to enter


into the well bore. This includes:
1. Effect of partial penetration (and to a lesser extent
perforation density) which increases the distance

37
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

which the fluid needs to travel to reach to the well-


bore, and, consequently, will result in a positive skin.
2. Effect of hydraulic fracturing, which allows the liquid
to travel directly to the infinite conductivity fracture,
instead of the normal radial flow toward the well-
bore, and thus, resulting in a negative skin.

Other factors obstructing the fluid movement inside the tubing,


such as sand-particles accumulation or wax precipitation, (and
liquid condensation in wet gas reservoirs), are normally
recognizable from the change of the skin factor with long term
production, and cannot be recognized, nor, evaluated from a
single pressure test.

o During the Semi-log Straight Line Period:

In addition to the value of (kh/μ) which determines the slope of


the build-up straight line, the main formation heterogeneities
which affect the shape of the BU straight line are:
1. Presence of natural fractures, and
2. Production from a multi-layer system.

o During the Late-time Period:

The outer boundary conditions are responsible for the late-time


pressure behavior. This includes:
1. Outer-boundary condition (closed or constant
pressure) which determines the average pressure of
the system.
2. Presence of one or more sealing faults, and,
3. Pressure interference caused by near-by oil producing
wells or water injection wells.

Finally it is important to note that in actual field practice, more


than one of the above mentioned factors would be affecting the
pressure build-up behavior. Consequently, it is most important
to judge the result of the pressure build-up analysis against all

38
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

the available data from well production, well completion,


reservoir geology and well log analysis prior to making the final
reservoir characterization.

3.2 Factors Affecting Early BU Period

3.2.1 Well-bore Storage Effect:

In practice, the well is usually closed at the surface, and fluids


would continue to flow into the well bore for sometimes after
shut down, due to the ability of the well bore fluids to be
compressed.

This will cause a lag in the pressure build up. The early data
points would fall below the ideal build up straight line, and, can
normally be identified as having the shape of a "lazy S" on the
MDH or Horner plots as seen in figure (3-1).

How to Identify Well-bore Storage Effect:

When the well is shut down at the surface, the liquids in the well
bore will be compressed, due to the continuing flow of liquids
from the formation into the well bore. This effect will continue
for some time. The bottom hole pressure during this period can
be represented by the following equation:

( )
log Pws − Pwf = log
q
Vwb .cwb
+ log (Δt ) ……...………….. Eq (3.1)

Where,
Vwb = volume of the wellbore
Cwb = compressibility of the fluids inside the wellbore

Consequently, a plot of (Pws-Pwf) vs. ∆t should produce a


straight line on log-log paper with a slope equal to unity (i.e.
450) as seen in figure (3-2).

39
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Log-Log Plot
1000
PD (Pws-Pwf)

Unit Slope
100

1 1/2 Cycle
10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (3-1): Effect of Wellbore Storage on Log-Log Plot

MDH Plot
300

Start of Semi-log Straight Line


250
PD (Pws-Pwf)

200

150

100

50
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (3-2): Effect of Wellbore Storage on MDH Plot

40
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

The data points falling on the unit slope line are representing
the fluid behavior in the well bore, and, consequently, do not
reflect any of the formation characteristics.

The same approach can be applied to the Draw Down test case,
and a plot of the pressure draw down, (Pi – pwf) versus the
production time, (t), should produce a unit slope line when
plotted on a log-log paper.

Duration of Well-bore Storage Effect

Ramey Formula for Draw-Down Tests:

The production time, (t), required to reach the correct straight


line portion on the semi-log plot of (Pwf) versus flowing time, (t),
can be estimated using the following relationship suggested by
Ramey:

t D = ( 60 + 3.5 S ) C D ……...……………………………….. Eq (3.2)

Where,
0.000264 kt
tD = dimension-less production time =
φμcrw2
5.615C
CD = dimension-less well bore storage coefficient=
2πφ ct hrw2
C = theoretical well bore storage coefficient, bbl/psi, =Vwb.Cwb,
(if the well bore is completely filled with a single phase
fluid),
25.65 Awb
= , (if the fluid level in the well bore is changing)
ρ wb
Awb= cross sectional area of well bore (ft2)
Ρwb= well bore fluid density (lb/ft3), and,
S = skin factor

41
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Equation, (3.2), can be simplified as to calculate the flowing


time, t, in hours, required to reach to the start of the correct
semi-log straight line, as follows:

t=
(200 ,000 + 12 ,000 S )C ……...………………………….. Eq (3.3)
(kh / μ )t

Chen Formula for Build-up Tests

The shut-in time, (∆t), required to reach the straight line period
(i.e. negligible well-bore storage effects), can be estimated using
the following relationships suggested by Chen:

Δt D = 50 C D .e0.14 S ........................................................... Eq ( 3.4 )


170 ,000C .e0.14 S
Δt = ....................................................... Eq ( 3.5 )
(kh / μ )t
The mathematical forms of Ramey formula and of Chen formula
indicate clearly that the duration of the well-bore storage effect
is dependent on the skin factor and on the formation
characteristics, in addition to the well-bore storage coefficient.
Consequently, tests run in damaged wells and/or producing
from low permeable formations; will require relatively much
longer time to reach the semi-log straight line.

Practical Aspects:

1. Equations (3.3 and 3.5) do not provide the practical


method of analysis, since their use requires the prior
knowledge of (k, S, and C).

Ramey has suggested that the approximate start of the semi-log


straight line will normally occur at approximately (1.5) cycles
after the time corresponding to the last data point on the
characteristic log-log unit-slope. In many cases, proceeding

42
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

(1.25) would be sufficient to define the start of the semi-log


straight line.

Consequently, this criteria is used to define the semi-log straight


line, and then Ramey or Chen equation are used, only, after
completing the Horner of MDH analysis, to check whether the
correct portion of the data was used in defining the semi-log
straight line or not.

2. The actual well-bore storage factor can be calculated


using the following formula:

qBΔt
C= ……...………………………………………….. Eq (3.6)
24 ΔP

Where ( Δ P) and ( Δ t) correspond to any point on the log-log


straight line. The calculated actual well bore storage factor is
normally different from the theoretical value of the well bore
storage coefficient mainly due to presence of free gas volume in
the well bore and/or inaccurate estimate of (Cwb) and (ρwb).

3.2.2 Effect of Phase Redistribution in the well-bore:

In addition to the distortion caused the well-bore storage effects,


some tests exhibit (what is normally termed as) a "humping"
effect, in which the bottom hole pressure builds to a "maximum"
value, then decreases, and finally starts building up again
toward the normal semi-log straight line .

This type of behavior is caused by "gas segregation", (or phase


re-distribution) in the tubing, where the rise of gas bubbles in
the tubing causes a back pressure on the formation.

There is no analytical definition of the magnitude or the


duration of the distortion caused by gas segregation in the
tubing.

43
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

This type of behavior is most evident in wells suffering from


considerable skin effect with restrictions to the flow near the
well-bore, where the effect of phase redistribution may continue
for very long period of time and may completely distort the
normal shape of build-up curve and would completely obscure
the unit slope line. In such cases, the (1.5) cycle rule would not
be applicable.

3.2.3 Effect of the Partial Penetration:

The different solutions presented in part-I have assumed that the


vertical well completely penetrates the formation, (i.e. the
producing interval is equal to the formation thickness).
However, it is a normal field practice to penetrate (or perforate)
only small section of the formation thickness, in order to keep a
safe vertical distance from the water table in strong bottom
water drive reservoir, and/or from the gas/oil contact in gas-cap
reservoirs, in order to minimize the coning problems.

Normal transient pressure analysis techniques can still be


applied to calculate the formation permeability and the initial
(or average) pressure. However, the skin factor calculated, in
such cases, is normally termed a total (or apparent) skin factor,
and represents the combined effect of two distinct factors,

• The first being the damage or stimulation of the formation


in the area immediately surrounding the well-bore
(mechanical skin), and,
• The second being the increased path length which the
fluids need to travel to reach to the well-bore, and the
change in the geometry of flow (dynamic skin).

The pressure behavior in the case of draw down or build-up


tests, in wells penetrating only a small section of the formation,
will be characterized by two straight lines on the semi-log as
illustrated by Kazemi and Seth.

44
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Normally, the first straight line would be obscured by well bore


storage and other effects, but it could be identified under ideal
conditions.

The transition period between the two straight lines would be


dominated by semi-spherical flow conditions, and its duration
would depend mainly on the ration between the perforated
thickness and the full formation thickness, as well as, on the
ratio between the vertical and horizontal permeability.

One of the simplest and most popular solutions, which assume


that the perforated interval is situated at the center of the
formation, was presented by Saidikowski, in the following form:

ht
St = .S D + S p ……...…………………………………….. Eq (3.7)
hp

Where,
St = Total skin factor calculated from the build-up or draw
down test
ht = Total thickness of the formation
hp = Thickness of the perforated interval
SD = Mechanical skin factor due to damage or stimulation

The value of Sp can be read directly from the plot presented by


Brons and Marting, can be calculated using the following
equation:

⎛h ⎞⎛ ⎛h kh ⎞ ⎞
S p = ⎜ t − 1 ⎟ .⎜ ln⎜⎜ t ⎟ − 2 ⎟ ………………..……….. Eq (3.8)

⎜ hp ⎟ ⎜ rw kv ⎟
⎝ ⎠⎝ ⎝ ⎠ ⎠

Where, (kh) and (kv) are the horizontal and vertical permeability
respectively. If the ratio (kh/kv) is not available from core
analysis, then it is recommended to use an average value from
nearest well. If this information was not available then it is
recommended to use a value of (kh/kv=1).

45
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Other more complex formula for calculating (Sp) and (SD) take
into consideration the position of the perforated interval with
respect to the total thickness. These forms give higher value of
(Sp) than does Saidikowski equation, which assumes that the
perforated interval is at the middle portion of the formation.
Consequently, it is recommended that the value of (Sp)
calculated by the Saidikowski equations should be considered as
a minimum.

Finally it is important to realize that a common mistake made,


by the practicing engineer, when calculating a positive skin
from the build-up test is to conclude that the well is damaged
and, consequently, requires an acid job, where as the well is
actually very much stimulated !!! And the positive skin
calculated was mainly the result of partial penetration.

3.2.4 Effect of Vertical Hydraulic Fracture:

There are two solutions to the diffusivity equation in case of a


vertical hydraulic fracture:

• The Uniform Flux Fracture Solution

Which assumes that the flow rate from the formation to the
fracture per unit area is the same at all points along the
fracture, and consequently, there is some pressure drop along
the fracture, and

• The Infinite Conductivity Fracture Solution

Meaning that the fracture has infinite conductivity, and,


consequently no pressure drop will occur within the hydraulic
fracture as the fluid travels along the fracture length to the well
bore.

Only the uniform flux solution will be considered here since


industry experience indicate that this solution gave reliable and

46
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

realistic results in more than (90%) of the fractured wells which


have been tested to-date.

For a uniform flux fracture, the flow into the fracture, and,
consequently, divided into three distinct periods as shown in
figure (3-3):

1. The first period dominated by Linear flow, followed by


2. A second period dominated by Elliptical flow, and finally,
3. A third period dominated by Pseudo-radial flow.

Figure (3-3): Flow into a Vertical Hydraulic Fracture

47
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

1- The Linear Flow Period:

The linear flow occurs at the early-time period of the BU test,


and, consequently, could be simplified into the following form:

μ
Pws − Pwf =
4.064 qB
( )
. Δt ………………….. Eq (3.9)
h kφx 2 f

Where, xf = fracture half-length, feet

Equation (3.9) clearly suggested that a linear plot of (Pws vs.


Δt ) should result in a straight line at the early period, with
slope (mL) figure (3-4 ). The slope (mL) of the straight line can
be used to calculate the permeability as follows:

2
⎛ 4.064 qB ⎞ μ
k =⎜ ⎟ . ……………………….…………… Eq (3.10)
⎜ mL hx f ⎟ φ ct
⎝ ⎠

Equation (3.9) can be re-written in the following form:

μ
(
Log Pws − Pwf = Log ) 4.064 qB
2
+
1
Log ( Δt ) ...Eq ( 3.11 )
h kφx f 2

Consequently, a log-log plot of the pressure change vs ( Δt )


should produce a straight line, with a slope equal to 1/2 unit, as
shown in figure (3-5).

Finally, the following relationship can be used to define the end


of the linear flow period:

φμct x 2f
teL = 600 . …………………………………………. Eq (3.12)
k

48
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Linear Plot
3400

3200

3000
Pws

2800

2600

2400

2200
0 10 20 30 40 50 60
0.5
(t) , (hours)

Figure (3-4): Effect of Vertical Hydraulic Fracture on Linear


Plot

Log-Log Plot
1000
PD (Pws-Pwf)

Slope = 1/2 Cycle

100

10
1.0 10.0 100.0 1000.0 10000.0
Shut-in time, (hours)

Figure (3-5): Effect of Vertical Hydraulic Fracture on Log-Log


Plot

49
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Final Remarks

• It is clear now that the log-log plot is a primary tool for


the practicing engineer. If a unit slope (i.e. 450 is present,
then this is indicate of the well bore storage effects. If, on
the other hand, the slope = (1/2 unit), then this is
indicative of the presence of a hydraulic fracture. In ideal
cases, the well bore storage effect (i.e. unit slope) should
precede the vertical hydraulic fracture effect.
• If the value of k is known from a previous test run prior to
the formation, then xf can be calculated from the linear
period using Equation (3.10).
• It is important to note that if the fracture is behaving as an
infinite conductivity fracture, then, the time required to
reach the end of the linear flow period will be reduced by,
approximately, (10 times).

2- The Elliptical Flow Period

The equation representing the bottom hole pressure, during the


Elliptical flow period, can be written in the following form:
141.2qμB ⎛⎜ ⎛ 1

⎞ 1 ⎛ − 1 ⎞⎞
⎟ E⎜ ⎟⎟
Pw = Pi − π .t Dxf .erf
kh ⎜ ⎜ 2 t Dxf ⎟ 2 i ⎜ 4t Dxf ⎟⎠ ⎟
⎝ ⎝ ⎠ ⎝ ⎠
...... Eq ( 3.13 )
Where,
0.000263kt 0.0002637 kΔt
t Dxf = ( for DD case ) or = ( for BU test )
φμct x f
2
φμct x f
2

erf (y)= error function of (y)

Pw = Pws, for the build-up case (or = Pwf, for the draw-down
case)

50
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Important Remarks

Conventional analysis techniques (i.e. semi-log and log-log


plots) cannot be used for the analysis of the elliptical flow
period. Consequently, type curves, available in the literature,
are needed.

The duration of the Elliptical flow period can be very long for
long fractures in low permeability reservoirs. The following
equation can be used to estimate the start and end of the
elliptical flow period:

φμct x 2f φμct x 2f
600 ≤ t ≤ 7 ,500 ……………...…………… Eq (3.14)
k k

3- The Pseudo-radial Flow Period

At the end of the Elliptical period, a pseudo-radial flow period


develops. This period can be analyzed using the conventional
semi-log techniques.

The equation representing the bottom hole pressure, during the


pseudo-radial flow period, can be simplified into the following
form:
162.6 qμB ⎜⎛ kt ⎞
Pw = Pi − log − 2.358 ⎟ …………….. Eq (3.15)
kh ⎜ 2
φμct x f ⎟
⎝ ⎠

The form of Equation (3.15) suggests that during the pseudo-


radial flow period, the conventional semi-log techniques can be
applied to calculate the average permeability-thickness product.

51
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Practical Aspects of Analysis

Normally in vertical hydraulic fracture systems, the value of kh


calculated based on the pseudo-radial flow equation (3.15) will
be higher than the actual value. This was attributed by Russell
and Truitt to the flattening of the semi-log slope due to the
presence of the hydraulic fracture. The degree of flattening will
depend mainly on the fracture radial penetration with respect to
the drainage radius. And consequently a correction factor to the
measured slope needs to be introduced as shown in the type
curve developed by Russell and Truitt figure (D-6).

The value of the correction factor is dependent on the fracture


half-length, which is also unknown. Consequently, the solution
requires a trial and error procedure as follows:

1) Assume a certain fracture length (start with a small fracture


length < 0.1 re).
2) Read the value of "R" from figure (D-6).
3) Calculate the fracture half length using the following
equation:

0.638 qBmR
2x f = …………………….……………… Eq (3.16)
mL hφ ce R

Where, mL = slope of the linear plot of (Pws vs. Δt ) (linear


flow period), and
mR = slope of the semi-log plot of (Pws vs Δt ) (pseudo-radial
flow period).
4) Compare the calculated fracture length to the assumed value.
If the two values are not approximately equal, use the new
calculated value for a second trial. Convergence should
occur within (3-4) trials.
5) Once convergence is achieved, calculate (kh) using the
following modified equation:

52
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

qμB
kh = 162.6 R …………………….…………………… Eq (3.17)
mR

Finally, it is important to note that the previous procedure


assumes an infinite-acting fracture in a closed boundary system
with (xf < 0.2re). It also assumes that the hydraulic fracture
thickness (hf) is equal to the formation thickness. If any of these
conditions were not met then some error will be introduced, and
consequently, type-curve analysis must be used.

3.3 Factors Affecting the Semi-log Straight Line Period

3.3.1 Pressure Behavior in Layered Reservoirs:

In general, the pressure analysis of a multi-layered system is


best accomplished by a trial and error procedure through
Numerical simulation of the layered system (using r-z, or x-y-z
coordinate models) if the individual permeability (or kh) of each
layer are to be calculated. Consequently, we restrict discussion
to the general BU features in a layered system without any
mathematical analysis.

The transient pressure behavior in layered systems is


categorized as follows:

• Layered systems with inter-layer cross flow, and


• Layered systems with no cross flow between the layers
except through the common well bore.

Layered Systems with Inter-Layer Cross Flow:

The transient pressure behavior in a system of two or more


vertically communicating layers can be simulated almost exactly
by an equivalent homogeneous one-layer system.

53
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

The permeability-thickness product determined from the slope of


the Horner plot represents the total capacity, (kh)t, of all the
layers in this case, where:

( kh )t = k1h1 + k 2 h2 + ........ + k n hn ……….……………… Eq (3.18)

And k1h1, k2h2, ….., knhn are the permeability-thickness product


of the individual layers.

For communicating layers, there is no direct method to identify


(or even to confirm) the presence of a multi-layer system from
the regular analysis of draw-down or build-up tests.

Layered Systems with No Cross Flow

A typical build-up curve of a two-layered system with no cross


flow, except through the common well bore, is characterized by
the following pressure performance as shown in figure (3-6):

¾ At the end of the well bore storage period (A), the pressure
build-up will have an initial straight line portion, (A-B),
¾ Followed by leveling off for a short period of time (B-C).
The duration of this period is a direct function of the
magnitude of permeability variation between the two
layers. If the two layers have relatively similar
permeability, then the leveling period, (B-C), might be
completely obscured,
¾ Afterwards, the pressure starts building up again (C-D) as
the less permeable, less depleted layer starts re-pressuring
the more permeable. The slope of the second straight line
will always be higher than the first straight line (A-B).
¾ Finally, the pressure starts converging to the average
reservoir pressure of the system, (D-E).

54
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Figure (3-6): Typical Build-up Curve for a Two-Layered System


with NO Cross Flow

Important Remarks

o The individual permeability and skin factor of each of the


two layers cannot be calculated separately, since each of
the two build-up straight lines is influenced by the rock
properties and production history of both layers. Separate
testing of each zone is always recommended for such
systems.
o If the above characteristic performance of a two-layered
system is detected in a homogeneous reservoir which well
log analysis assures it has no vertical permeability
barriers, then the presence of a casing leak would be the
most logical explanation.
o A three-layered system would show the same qualitative
pressure build-up behavior as a two-layered system, so the
number of layers cannot be detected from the pressure
test.

55
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

3.3.2 Pressure Behavior in Naturally Fractured


Reservoirs

A typical build-up curve of a naturally fractured system, is


characterized by the following pressure performance, shown in
figure (3-7):

¾ At the end of the well bore storage period, the pressure build-
up will have an initial semi-log straight line portion, (A-B),
¾ As the pressure in the more permeable fracture system starts
to stabilize, the pressure build-up curve starts leveling off for
a short period, (B-C),
¾ Afterwards, the pressure starts building up again, (C-D),
parallel to the first straight line (A-B) as the matrix starts
feeding (i.e. pressuring) the fracture system,
¾ Finally, the pressure starts converging to the average
reservoir pressure of the system, (D-E).

Warren and Roots use two parameters to characterize the


fracture system; the fracture storativity, (F), and the inter-
porosity flow parameter, ( ε ), where,

(φ c ) f α km rw2
F= and ,ε = …….……………… Eq (3.19)
(φ c ) f + (φ c )m kf

Where, α = matrix fracture geometric factor

The subscript (f) and (m) correspond the fracture and the matrix
respectively.

The fracture storativity can be calculated directly from the semi-


log plot, figure (3-7), using the following equation:

ΔP
F = 10 m …………………….…………………….……… Eq (3.20)

56
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Where, ΔP = vertical distance between the two parallel lines on


the semi-log plot
And, m = slope of the semi-log straight line

Figure (3-7): Typical Build-up Curve for a Natural Fracture


System

Final Remarks

ƒ If the compressibility value for the matrix and the fracture


are not available separately, then they are assumed to have
the same value. In this case, the fracture storativity, (F),
represents the percentage of fluid stored in the fractures.
ƒ Since most of the pore volumes is normally contained in the
matrix, rather than the fractures, consequently, the time
period between the end of the first straight line and the start
of the second parallel line can be very long, especially in the
early life of the reservoir. Consequently, this flattening period
is (in many instances) mistaken by the interpreter for the
pressure converging to the static reservoir pressure.

57
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

ƒ For reservoirs with very low matrix porosity and dense


fracture system, the flattening period might be very short and
might not be recognizable from the pressure plot. The
reservoir in this case will appear as a highly permeable,
single porosity system.

These remarks serve to point out the importance of consulting


the geological and petrophysical models based on other sources
of data (such as well completion history, well log analysis,
petrography, etc.) prior to interpreting any pressure test.

3.4 Factors Affecting Late BU Period

3.4.1 Effect of Linear Faults:

A- Case of One Sealing Fault

The case of one linear sealing fault can be simulated by


replacing the fault with an "image" well, at a distance (2d) from
the "real" well, having the same production history and the
same formation properties and well characteristics. Applying
the principle of Superposition, the bottom hole shut-in pressure,
(Pws), can be described by the following equations:
qμ B⎛ ⎛ φ μ c rw2 ⎞⎞
Pws = Pi + 70.6 ⎜ Ei ⎜ − ⎟⎟
kh ⎜⎝ ⎜⎝ 0.00105 k ( t + Δt ) ⎟⎠ ⎟⎠
qμ B⎛ ⎛ φ μ c rw2 ⎞ ⎞
− 70.6 ⎜ Ei ⎜ − ⎟⎟ ⎟
⎜ ⎜
kh ⎝ ⎝ 0.00105 kΔt ⎠ ⎟⎠
qμ B⎛ ⎛ φ μ c ( 2 d )2 ⎞ ⎞
+ 70.6 ⎜ Ei ⎜ −
⎜ ⎟⎟ ⎟
kh ⎝ ⎝ 0.00105 k ( t + Δt ) ⎠ ⎟⎠

q μ B ⎛ ⎛ φ μ c ( 2 d )2 ⎞ ⎞
− 70.6 ⎜ Ei ⎜ − ⎟⎟
kh ⎜⎝ ⎜⎝ 0.00105 kΔt ⎟⎠ ⎟⎠

For large production times, and early shut-in times, the


logarithmic approximation can be used to represent the first two

58
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

(Ei) terms due to the small value of (rw), the fourth term can be
considered negligible due to the large value of (2d)2 compared
to ( Δt ), and the third term can be considered constant, for all
practical purposes since ( Δt ) is small compared to the flowing
time. Consequently, for early shut-in periods, the above
equation can be modified into the following form:

qμ B⎛ t + Δt ⎞
Pi − Pws = 162.6 ⎜ log ⎟−
kh ⎝ Δt ⎠
q μ B ⎛⎜ ⎛⎜ φ μ c ( 2d )2 ⎞⎟ ⎞⎟
70.6 Ei − ............. Eq ( 3.21 )
kh ⎜⎝ ⎜⎝ 0.00105 kt ⎟⎠ ⎟⎠

Equation (3.21) clearly indicates that at early shut-in times the


(Ei) term will be negligible and consequently the regular Horner
or MDH plots should produce a straight line with slope, (m1),
which can be used to calculate (kh) and (S).

At late shut-in times, the logarithmic approximation can be


applied to all the four (Ei) terms. Consequently, the basic
equation can be modified into the following form:

qμ B⎛ t + Δt ⎞
Pi − Pws = 2( 162.6 ) ⎜ log ⎟ ……………….... Eq (3.22)
kh ⎝ Δt ⎠

This equation indicates that, at late shut-in times, the regular


Horner or MDH plots should produce a straight line with slope,
(m2=2m1) as shown in figure (3-8). This doubling of the slope is
the distinguishing feature of the pressure performance of a well
situated near a linear fault.

The following equation can be used to estimate the time


required to reach to the start of the second line:

5 φ μ cd2
Δt ≥ 3.81( 10 ) . ………………….……………… Eq (3.23)
k

59
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

The above equation indicates that the shut-in time required to


identify the second straight line will be very long for low
permeability reservoirs especially if the distance to the fault, (d)
is large.

Horner Plot
4500
m2 = 1220 psi/cycle
4000

3500

m1 = 620 psi/cycle
Pws

3000

2500

2000

1500
1000 10000 100000 1000000
Horner time

Figure (3-8): Effect of a Single Sealing Fault

Distance to Fault

1. Davis and Hawkins Formula:

kΔt x t + Δt x
d = 0.0122 for > 30
φμc Δt x
and ,
⎛ ⎛ Δt x ⎞ ⎞ kΔt x t + Δt x
d = 0.0122⎜⎜ 1 + 0.4⎜⎜ ⎟⎟ ⎟⎟ for < 30 .....Eq ( 3.24 )
⎝ ⎝ t + Δt x ⎠⎠ φ μ c Δ t x

Where,
Δt x = shut-in time read at the intersection of the two semi-log
straight lines.

60
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

2. Gray equation:

kΔtesl
d = 0.0328 ………………………...……………… Eq (3.25)
φμc
Where, Δtesl = shut-in time at the end of the first line segment

Important Remarks:

¾ Davis and Hawkins Equation (3.24) has a stronger


theoretical basis than Gray equation.
¾ Gray Equation (3.25) normally gives higher values of the
fault distances as compared to the Davis and Hawkins
equation (2-3 times in general).
¾ The Gray equation should be restricted to the cases where the
second straight line is not well defined, or for the case of two
(or more) intersecting faults.
¾ The slope of the first straight line should be used for
extrapolation to (P*).

Numerical technique to estimate distance to fault:

If the transition period between the end of the first straight line
and the start of the second line is very long and the second
straight line is not reached then it would not be possible to use
the Davis and Hawkins formula. Gray formula will normally
give much higher values for the distance to the fault than the
actual. In addition it is difficult sometimes to define ( Δtesl )
accurately on the semi-log plot. In such cases

If seismic data suggests the presence of a sealing fault, and the


BU test indicates a curving up-ward but is not run long enough
to identify the second slope, then the following numerical
procedure (involving the data points in the transition period) is
suggested by the author:

61
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

For large production times, the difference between the actual


measured pressure and the extrapolation of the first straight line
on the Horner plot can be approximated by the following
equation:

Pws ( measured ) − Pws ( extrapolated ) ≅


q μ B ⎛⎜ ⎛⎜ φ μ c ( 2 d )2 ⎞⎟ ⎞⎟
− 70.6 Ei − ............. Eq ( 3.26 )
kh ⎜⎝ ⎜⎝ 0.00105 kt ⎟⎠ ⎟⎠

Once the value of k has been determined using the first slope,
then Equation (3.26) can be applied to each data point in the
transition period to estimate the value of the distance to the
fault. Then all the calculated values of the distance, (d), are
averaged numerically to obtain the best estimate value.

It is important to remember that this procedure assumes apriori


the presence of only one fault. Consequently, the structural
maps must be consulted before applying this procedure.

B- Cases of Two Intersecting Faults

In this case, the shape of the increasing pressure at late shut-in


times will be dependent on the relative distances and orientation
of the two faults as follows:

• If the two faults are located at, practically, the same distance
from the shut-in well, then, the second slope will continue to
increase until it stabilizes at a value of (m2 > 2m1), figure (3-
9a )
• If, however, one fault is, relatively, much nearer than the
second fault, then the slope of the second line might stabilize
at (m2 = 2m1) for some time, until the effect of the second
fault is felt, and then, the slope will continue to increase until
it stabilizes at a new value (m3 > 2m1), figure (3-9b ).

62
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

If only two intersecting faults are affecting the system, then the
angle between the two faults can be calculated using the
following equation:

360
θ= ………………………………………………….. Eq (3.27)
m2
m1

Important Remarks:

¾ For a two (or more) fault system, Only the distance to the
nearest fault can be estimated using Gray's equation (3.25).
¾ The calculation of the distance to the second fault cannot be
obtained through conventional analysis techniques
¾ It is not possible to confirm whether only two or more faults
are causing the second slope to be greater than (2m1), since
there is no evident relationship between the number of faults
and the ratio between the two slopes.

63
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

Horner Plot
2740

2720 m2 = 65 psi/cycle

2700

2680
Pws

2660
m1 = 21 psi/cycle
2640

2620

2600

2580
1 10 100 1000 10000 100000
Horner time

Figure (3-9a): Effect of Two Intersecting Faults (Case A)

Horner Plot
2740

2720 m3 = 65 psi/cycle

2700

2680
m2 = 42 psi/cycle
Pws

2660

2640 m1 = 21 psi/cycle

2620

2600

2580
1 10 100 1000 10000 100000
Horner time

Figure (3-9b): Effect of Two Intersecting Faults (Case B)

64
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

C-Case of Parallel Faults

The case of a well situated between two (practically) parallel


faults is very similar to the case of a single well producing from
a long narrow reservoir (such as in the case of deltaic
channels).

As seen from the iso-potential diagram in figure (3-10), the flow,


in this case, will be radial in the regions nearest to the well-
bore, whereas, linear flow will be dominating away from the
well.

Figure (3-10): Fluid Flow in Well Situated Between Two


Parallel Faults

The Horner or MDH plots in this case, will result in the normal
semi-log straight line, m1, describing the radial flow around the
well-bore, then the pressure data points will continue to diverge
upward with an ever increasing slope, which is indicative of the
linear flow effect, figure (3-11a).

If seismic and geologic data suggests that the well is located


between two parallel faults or producing from a sand channel,
then a linear plot of (Pws vs. Δt ) (similar to the vertical
hydraulic fracture case) should be attempted, figure (3-11b). In
case the flowing time is short.

65
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

If the late data (of ever-increasing slope on the Horner or MDH


plots) defines a straight line on the linear plot, then this is
strong evidence that the well is producing from a parallel fault
system.

In the case of a well producing at the center of a long narrow


reservoir, the width of the producing channel can be calculated
using the following equation:

0.638 q B m1
w= ……………………………………….. Eq (3.28)
mL h φ ct

Where,
w = average width of the linear flow channel, feet
m1= slope of the semi-log Horner or MDH plots, and,
mL=slope of the straight line portion of the linear plot (Pws vs.
t + Δt − Δt ).

Equation (3.28) should give fairly good results in case the well
is situated very near to the center of the flow channel. The error
in the calculated value of w using equation (3.28) will increase
as the well is further away from the center of the channel.

66
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

MDH Plot

6000

5800

5600
Pws

5400

5200

5000

4800
0.001 0.010 0.100
Shut-in time, (hours)

Figure (3-11a): Build-up a Well Located Between Two Parallel


Faults on MDH Plot

Linear Plot
6350

6300

6250

6200
Pws

6150

6100

6050

6000
0 2 4 6 8 10 12
0.5
(t)

Figure (3-11b): Build-up a Well Located Between Two Parallel


Faults on Linear Plot

67
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

3.4.2 Effect of Interference from a near-by producer

If a producer is shut down for a build-up test, then the bottom


hole pressure will start increasing until the pressure stabilizes
at the reservoir average pressure.

However, if a near-by producer is kept on production, then the


pressure at the shut-in well will keep increasing until the effect
of the draw-down from the near-by producer is felt, then the
bottom hole pressure at the shut-in well will start decreasing
again.

A pressure build-up test specifically designed to feel the


interference from another producer (or injector) is normally
termed "Interference Test".

Interference Test Objectives

The main objectives of the interference test are:

¾ To validate the reservoir connectivity, and,


¾ To determine the directional flow patterns in the reservoir

A properly designed interference test is especially useful in the


determination of the orientation of a vertical hydraulic fracture,
and the orientation of the natural fracture system in the
reservoir.

All this information can be very useful as input to reservoir


simulation models. It also provides essential information in
planning EOR projects.

Other information which can be obtained from the analysis


includes: the determination of the average connected porosity
between the two wells, and the permeability and skin factor at
the shut-in well.

68
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

How the Test is Run

A normal Interference test is run by shutting down a well for


build-up test while one or more of the surrounding wells are
kept on production.

The production rates in the producing wells can be increased in


order to minimize the shut-in time requirements for the test.

The main objectives of running the test will dictate the proper
design of the test, and, the special setting of the surrounding
producers and their flow rates.

Mathematical Formulation

Only the simple case of one shut-in well and one near-by
producer will be considered here, for illustration.

Consider a well which was producing at a constant flow rate, q,


for a certain flowing period, t, prior to shut down. Also, assume
that another well "A" at a distance "d" from the first well was
producing at a constant flow rate, qA, for a time tA before the
observation well was shut down. Then, the total pressure drop at
the observation well at any time, Δt , after the shut down can be
calculated (using the Superposition Principle) as follows:

qμ B⎛ t + Δt ⎞
Pi − Pws = 162.6 ⎜ log ⎟
kh ⎝ Δt ⎠
q A μ B ⎛⎜ ⎛⎜ φ μcd2 ⎞⎞
⎟ ⎟ ......... Eq ( 3.29 )
− 70.6 Ei ⎜ −
kh ⎜⎝ ⎝ 0.00105 k ( t A + Δt ) ⎟⎠ ⎟⎠

At early shut-in time the Ei-term in Equation (3.29) will be


negligible since the Ei-argument will be large. Consequently, the
early shut-in time data should plot as a straight line on the
regular Horner plot the normal slope, m, which can be used to

69
Chapter 3 Factors Affecting Pressure Build-up Test Behavior

calculate the average permeability in the drainage area of the


observation well.

As the shut-in time, Δt , increases, the Ei-term representing the


additional pressure drop caused by the continuous production of
well "A" will cause a bending over of the build-up curve.

The difference between the extrapolated semi-log straight line,


(Pext), and the observed actual pressure data, (Pobs), will be
equal to,

q A μ B ⎛⎜ ⎛⎜ φ μ cd2 ⎞⎞
Pext − Pobs = 70.6 Ei ⎜ − ⎟⎟
kh ⎝ ⎝ 0.00105 k ( t A + Δt ) ⎟⎠ ⎟⎠

m qA ⎛ ⎛ φ μ c d 2 ⎞⎞
=− ⎜ Ei ⎜ − ⎟ ⎟...... Eq ( 3.30 )
2.303 q ⎜ ⎜ 0.00105 k ( t A + Δt ) ⎟ ⎟
⎝ ⎝ ⎠⎠

Once the values of m and k have been determined from the


straight line portion of the Horner plot, the above equation can
be solved for the average interconnected porosity using the data
points after the pressure curve starts bending.

It is recommended to calculate all the porosity values using the


values of (Pext- Pobs) at different ( Δt ), and then calculating the
arithmetic average. Values of porosity obtained from
interference testing can be very useful in the initialization of the
numerical simulation model of the reservoir.

The theory can be extended by the use of the principle of


Superposition to the case of multiple producers, and multiple
injectors. However, the analysis of such a test would normally
require numerical simulation.

70
Chapter Four

Well Test Interpretation


Methodology
Chapter 4 Well Test Interpretation Methodology

Well Test Interpretation Methodology

4.1 Introduction

Interpretation of well tests data is much more difficult and


important step in the vertical wells tests, because of a considerable
wellbore storage effect, the flow geometry, outer boundary effect,
and reservoir module used during interpretation.

The objectives of well test interpretation are to estimate the


reservoir/well parameters such as: wellbore storage coefficient,
vertical and/or horizontal permeabilities, mechanical skin factor,
and average of reservoir pressure.

The analysis of individual flow regimes provides relevant


information about important reservoir and well characteristics;
and the pertinent equations for calculating reservoir and well
parameters, can be found in the chapter two.

There are two methods to the interpretation of well test data;


the Segmental Analysis Approach, and the Integrated Model
Approach. In this section, we will discuss both of the methods,
followed by the advantages and disadvantages of each of which.

72
Chapter 4 Well Test Interpretation Methodology

4.2 Segmental Analysis Approach

In this method, two steps should be followed in the


interpretation of vertical well test data, Fluid Flow Regime
Identification, and Reservoir and Well Parameters Estimation.

¾ Fluid Flow Regime Identification:

The vertical well tests are best interpreted using a log-log


representation of the pressure-time data (ΔP vs. Δt) in conjunction
with the derivative curve (dΔP/d (logΔt) vs. Δt) to identify whether
the wellbore storage is affecting the early time readings or not,
and to diagnose the characteristics behavior of the system and
identify specific flow regimes as shown in the figure (4-1).
Log ( Pws-Pwfo ) or Log (d Pws / d log (∆t))

Pressure Drop Curve


( Pws -Pwfo )

Wellbore Storage Pressure Derivative Curve


(d Pws / d log (∆t ))
Effect

End of Radial flow


Wellbore
Storage Effect
Effect of Outer Boundary

Log ( ∆t )

Figure (4-1): Transient pressure performance in


a vertical well

73
Chapter 4 Well Test Interpretation Methodology

Figure (4-1) illustrates the character of the log-log plot in


relation to the flow regimes under ideal conditions. The wellbore
storage will result in unit (1) slope on a log-log plot of the
pressure-time data curve.

The radial flow regime is characterized by the flattening of


the derivative curve (i.e., zero slopes). However, in many systems,
the duration of radial flow could be relatively short and can be
easily masked by wellbore storage effects.

The effect of outer boundary at late time, when the influence


of the constant pressure circle is seen, the pressure stabilizes and
the pressure derivative curve plunges.

¾ Reservoir and Well Parameters Estimation:

After the flow regimes are identified in the previous step;


then the specialized plots such as semi-log, square root, etc, must
be used to extract the effective reservoir /well parameters of each
flow regime, typically permeability and skin factor.

The following table summarizes the specialized plots and the


reservoir parameters estimated for each flow regime.

Table: 4-1

Pressure
Specialized Parameters
Transient Slope of the Best Straight line
Plots Estimated
Behavior
Wellbore C, wellbore
∆P vs. ∆t
Storage
on log-log plot
# storage
Effect coefficient
⎛ t + Δt ⎞ ⎛q μ B⎞
Radial Pws vs.⎜ ⎟ k
⎝ Δt ⎠ m = 162.6 ⎜⎜ ⎟⎟
Flow ⎝ k h ⎠ S
on semilog plot

74
Chapter 4 Well Test Interpretation Methodology

4.2.1 Advantages of the Segmental Analysis

1. The procedure traditional methods used for vertical well


testing. Most practicing engineers are familiar with these and
will easily transfer their skills to vertical well interpretation.

2. Identifying the various flow regimes gives the analyst a


qualitative feeling for the degree of reliability of the
parameters calculated.

4.2.2 Limitation of the Segmental Analysis

1. Often the individual flow regimes are not readily identifiable.


They can be masked by preceding regimes, or merged with
subsequent regimes to form a non-descript transition.

2. The duration of each flow regime is the subject of


controversy in the well testing literature; this is not
surprising, because the times quoted for the duration of each
flow period are approximate.

3. The segmental analysis approach is limited to relatively


simple reservoir models. Great care must be taken when
analyzing complex systems such as wells intercepting
multiple vertical fractures or in the presence of constant
pressure boundary (gas cap or water drive) effects.

4. Each flow or shut-in period is analyzed separately. Different


(and often conflicting) answers can be obtained from
different flow or shut-in period.

75
Chapter 4 Well Test Interpretation Methodology

4.3 Integrated Model Approach

In this approach, a wellbore and reservoir model is


postulated. This model describes the reservoir completely by
assuming such parameters as:

1. Directional permeability, (kx ), (ky ), and (kz ).


2. Reservoir dimensions, and reservoir thickness (h)
3. Vertical well dimensions and location.
4. Skin causing formation damage or improvement along the
wellbore
5. Inner boundary conditions such as constant rate, wellbore
storage, etc.
6. Outer boundary conditions such as infinite, no flow or
constant pressure, for the upper and lower boundaries as
well as the edges of the reservoir

Once the model has been specified, the appropriate


analytical equations (usually very complex) are utilized
[Thompson et al. (1991)] and rigorous superposition (convolution)
is applied to generate the synthetic pressures for the flow and time
durations of the test. These synthetic pressures are compared to
the corresponding measured pressures. If the fit between the two is
not very good, the reservoir description contained in the model is
altered. One or many of the variables can be modified and the
calculations are repeated until the comparison of synthetic and
measured pressures is acceptable. The model corresponding to this
match is considered to be the description of the reservoir. Usually
there exist options for numerical automating this iterative
procedure.

The procedure is also known as analysis by synthesis, or


history matching. It can be used for matching data from one flow
period or from many flow periods. The results reflect the
description of the reservoir as an integrated system, and include
simultaneous interaction of all the parameters contained in the
reservoir description.

76
Chapter 4 Well Test Interpretation Methodology

4.3.1 Advantages of the Integrated Model Approach:

1. When specific flow regimes are not evident (this means that
the segmental analysis procedure is not possible) or
transition periods between specific flow regimes constitute a
significant part of the data, the integrated model approach
allows us to analyze all of the data, regardless of whether it
belongs to a specific flow regime or a transition.

2. The sensitivity of the analysis to any one variable can be


easily determined by altering that variable and observing the
change in the synthetic pressure response.

3. Can be used over any portion or sequence of flows or shut-


ins. A multi-rate, multi-shut-in test can be modeled and
history-matched to yield a single best fit of reservoir
parameters for all flow periods, or alternatively, a portion of
the data can be best fitted, and this best fit set of parameters
applied to the total flow history for comparison only.

4.3.2 Limitation of the Integrated Model Approach

1. The major limitation is the non-uniqueness of the solution,


and the false sense of security resulting from an apparent
good match. The problem is that many good matches can
sometimes be obtained with totally different models.

2. If the best fit is based on the pressure data, the reservoir


parameters can be different from when it is based on the
derivative of the pressure.

3. The integrated model approach requires the use of computer


programs, and is not a manual analysis procedure.

77
Chapter 4 Well Test Interpretation Methodology

4.4 Recommended Approach

The two approaches discussed above have advantages and


disadvantages. From a practical standpoint, one needs to use both
approaches, whenever possible. The segmental analysis should be
used to identify the most likely model and to estimate the
appropriate reservoir characteristics. After that, the integrated
model should be used to confirm or fine tune the analysis of the
individual flow periods.

78
Chapter 4 Well Test Interpretation Methodology

STEP BY STEP CONVENTIONAL ANALYSIS


PROCEDURE FOR BUILD-UP PRESSURE TESTS IN
VERTICAL WELLS.
Table: 4-2
1. Preparation of Data
1.1 Prepare general data required for the analysis (As given in the Field
Case)
1.2 Read in the pressure test data (i.e., Pws vs. ∆t)
1.3 For each data point calculate the corresponding values of:
(Pws-Pwfo), (d(Pws)/d(log∆t)), ((t+∆t)/∆t): Horner time), (d(Pws)/d(log
((t+∆t)/ ∆t)).
(Note: it is normally sufficient to use the three point method to
calculate the derivatives)
2. Preliminary Identification of Different Flow Periods
(Log-Log Plot)
2.1 Prepare a log-log plot of (Pws-Pwfo) vs. ∆t, & (d(Pws)/d(log ∆t)) vs. ∆t
2.2 The first curve (Pws-Pwfo) vs. ∆t is mainly used to identify whether the
well bore storage is affecting the early-time reading or not. If it is
evident (in the form of a unit slope line on the log-log plot) then:
ƒ Read the time, tsd , when the pressure data starts deviating from
the unit slope line. Then proceed 1¼ cycle (i.e., tsd ×18) to
estimate the end of the well bore storage effect.
ƒ Pick any point on the unit slope line and read from the plot ∆t
(hours) and the corresponding ∆P= Pws-Pwfo .
ƒ Calculate the well bore storage coefficient, C=((qB∆t)/(24∆P))
(bbl/Psi).
2.3 The second curve (d (∆Pws)/d (log ∆t)) vs. ∆t is used to identify start
and end of the main flow regime. The radial flow which should
appear the end of the well bore storage effect in the form of a
horizontal line, followed by the effect of outer boundary. The ideal
shape of this curve is given in the Chapter (4), (figure 4-1).
3. Radial Flow (Semi-Log) Analysis.
3.1 Prepare a semi-log plot of Pws vs. tH* and of (d (Pws)/d (log tH)) vs. tH
(i.e., the slope of the pressure curve). The plot of the average slope is
always recommended by the Dr: Urayet to enhance the recognition of
the semi-log straight line portion and its duration.
3.2 Read from the slope curve m, tsr, ter.

79
Chapter 4 Well Test Interpretation Methodology

3.3 Calculate: k = 162.6 ⎛⎜ q μ B ⎞⎟


⎝ mh ⎠
4. Skin Factor Calculation.
4.1 Extrapolate the semi-log straight lines on the pressure curve to (1-
hour) and read the corresponding values of Pws (1hr).
⎛ P1hr − Pwf k ⎞
4.2 Calculate: S = 1.151⎜
⎜ − log + 3. 23 ⎟⎟
⎝ m φμcrw
2

4.3 Calculate pressure drop due to skin effect (ΔPs).
4.4 Calculate: ΔPs=0.87mS
5. False Reservoir Pressure Calculations.
5.1 Extrapolate the straight line portion to ((t+∆t)/∆t) =1 and read the
false pressure, (P*).
6. Dimensionless Calculations.
6.1 Dimensionless time calculation (tDA).
kt
6.2 Calculate: t DA = 0.000264
φμct A
6.3 Dimensionless pressure drop calculation (ΔPD(MBH)).
6.4 Assuming the well to be in the center of a circular drainage area,
choose the appropriate MBH type curve (figure (D-2)). Enter with the
calculated value of (tDA), and read the corresponding value of the
dimensionless pressure drop, (ΔPD(MBH)).
7. Average Pressure Calculations.
m
7.1 Calculate: P = P* − × PD( MBH )
2.303
8. Flow Efficiency Calculations.
P − Pwf − ΔPs
8.1 Calculate: FE =
P − Pwf
9. Productivity Index Calculations.
9.1 Theoretical Productivity Index Calculations:
9.2 Calculate:
PI theoretical =
7.08 × 10 3 × k × h
⎛ ⎛r ⎞ 3 ⎞
μo × β o × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠
9.3 Actual Productivity Index Calculation (based on pressure build-up
test data)

80
Chapter 4 Well Test Interpretation Methodology

q
9.4 Calculate: PI ( actual ) =
( Pr − Pwf )
9.5 Actual Productivity Index Calculation (based on average pressure
estimated)
q
9.6 Calculate: PI ( actual ) =
( Pr − Pwf )
10. Radius of Investigation Calculations.
k ×t
10.1 Calculate: rinv =
948 × φ × μο × ct

* tH = Horner time
** Application of this step-by-step procedure is illustrated in the
attached Field Cases.

81
Chapter 4 Well Test Interpretation Methodology

Log-Log plot of well tests data interpretation in the vertical wells


tests, considerable Wellbore Storage Effect, the Flow Geometry,
Outer Boundary Effect, and Reservoir Model.
Table: 4-3

Constant Wellbore Storage

Description:
At early time, both the pressure and the pressure derivative curves have a
unit slope in the log-log plot. Subsequently, the derivative plot deviates
downward. The derivative plot exhibits a peak if the well is damaged (that is
if skin is positive) or if an apparent skin exists due to the flow convergence
(for example, in a well with partial completion).

Infinite Acting Radial Flow

82
Chapter 4 Well Test Interpretation Methodology

Description:
The response is characterized by stabilization (flattening) of the pressure
derivative curve at a level that depends on the (k×h) product.

Closed Reservoir

Description:
At early time, before the circular boundary is seen, the response corresponds
to that of an infinite system. When the influence of the closed circle is seen,
the system goes into a pseudosteady state. For a drawdown, this type of flow
is characterized on the log-log plot by a unity slope on the pressure
derivative curve. In a buildup, the pressure stabilizes and the derivative
curve plunges.

83
Chapter 4 Well Test Interpretation Methodology

Constant Pressure Boundary

Description:
At early time, before the constant pressure circle is seen, the response
corresponds to that of an infinite system. At late time, when the influence of
the constant pressure circle is seen, the pressure stabilizes and the pressure
derivative curve plunges

Dual Porosity

Description:
At early time, only the fissures contribute to the flow, and a homogeneous
reservoir response may be observed, corresponding to the storativity and

84
Chapter 4 Well Test Interpretation Methodology

permeability of the fissures. A transition period develops, during which the


interporosity flow starts. It is marked by a "valley" in the derivative. The
shape of this valley depends on the choice of interporosity flow model. Later,
the interporosity flow reaches a steady state. A homogeneous reservoir
response, corresponding to the total storativity (fissures + matrix) and the
fissure permeability, may be observed.

Fault

Impermea ble
Bou nda ry

Description:
At early time, before the boundary is seen, the response corresponds to that
of an infinite system. When the influence of the fault is seen, the pressure
derivative increases until it doubles, and then stays constant. At late time the
behavior is like that of an infinite system with permeability equal to half of
the reservoir permeability.

85
Chapter 4 Well Test Interpretation Methodology

Intersecting Faults

Description:
At early time, before the first boundary is seen, the response corresponds to
that of an infinite system. When the influence of the closest fault is seen, the
pressure behavior may resemble that of a well near one sealing fault. Then
when the vertex is reached, the reservoir is limited on two sides, and the
behavior is like that of an infinite system with a permeability equal to
theta/360 times the reservoir permeability.

86
Chapter 4 Well Test Interpretation Methodology

Channel

Description:
At early time, before the first boundary is seen, the response corresponds to
that of an infinite system. At late time, when the influence of both faults is
seen, a linear flow condition exists in the reservoir. During linear flow, the
pressure derivative curve follows a straight line of slope 0.5 on a log-log
plot. If the L1 and L2 are large and much different, a doubling of the level of
the plateau from the level of the first plateau in the derivative plot may be
seen. The plateaus indicate infinite-acting radial flow, and the doubling of
the level is due to the influence of the nearer fault.

87
Chapter 4 Well Test Interpretation Methodology

Partial Completion

Description:
At early time, after the wellbore storage effects are seen, the flow is spherical
or hemispherical, depending on the position of the flowing interval.
Hemispherical flow develops when one of the vertical no-flow boundaries is
much closer than the other to the flowing interval. Either of these two flow
regimes is characterized by a -0.5 slope on the log-log plot of the pressure
derivative. At late time, the flow is radial cylindrical. The behavior is like
that of a fully completed well in an infinite reservoir with a skin equal to the
total skin of the system

Infinite Conductivity Fracture

88
Chapter 4 Well Test Interpretation Methodology

Description:
At early time, after the wellbore storage effects are seen, the flow is spherical
or hemispherical, depending on the position of the flowing interval.
Hemispherical flow develops when one of the vertical no-flow boundaries is
much closer than the other to the flowing interval. Either of these two flow
regimes is characterized by a -0.5 slope on the log-log plot of the pressure
derivative. At late time, the flow is radial cylindrical. The behavior is like
that of a fully completed well in an infinite reservoir with a skin equal to the
total skin of the system.

Finite Conductivity Fracture

Description:
At early time, bilinear flow, characterized by a 0.25 slope on the log-log plot
of the derivative, may develop later. Subsequently the linear flow (with slope
of 0.5) perpendicular to the fracture is recognizable. At late time, the
behavior is like that of a fully completed infinite reservoir with a low or
negative value for skin. An infinite-acting radial flow pattern may develop

89
Chapter 4 Well Test Interpretation Methodology

Radial Composite Reservoir

Description:
At early time, before the outer zone is seen, the response corresponds to an
infinite-acting system with the properties of the inner zone. When the
influence of the outer zone is seen, the pressure derivative varies until it
reaches a plateau. At late time the behavior is like that of a homogeneous
system with the properties of the outer zone, with the appropriate outer
boundary effects

90
Chapter Five

Field Cases
Chapter 5 Field Case

Field Case

5.1 Introduction

This section presents the details of the comprehensive


analysis of the pressure transient data using two techniques:

¾ Conventional Analytical Solution.

¾ Well-test 200 Software package developed by Schlumberger.

Also a comparison between the results of the two techniques is


presented.

Pressure transient tests were conducted on four vertical oil


wells namely:

¾ Build-Up pressure tests were run in three Wells B-27, B-42,


and B45 in Amal field belonging to AL HAROUGE Oil
Company.

¾ Build-Up pressure tests were run in one Well A-67 in Abu-


Attiful field belonging to ENI Oil Company.

The analysis of these buildup tests using the conventional


technique will follow the procedure suggested by Dr: A. A. Urayet
and shown in table (4-2).

92
Chapter 5 Field Case: Well B -27(1966)

93
Chapter 5 Field Case: Well B -27(1966)

5.2 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-27
Test Date December 7, 1966
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, qo 5610 STB/day
Water Production Rate, qw 33 STB/day
Water Cut, W.C 0.69 %
Producing Time, tp 6336 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 201 ft


Layer Porosity, ø 9.83 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

94
Chapter 5 Field Case: Well B -27(1966)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-1), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-1), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-1).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-2).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-3).

2.4) From figure (C-3), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(2.00 – 8.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-4), the slope
of the semi-log plot should also be shown on the same graph to
enhance the recognition of the radial flow periods and their
duration.

95
Chapter 5 Field Case: Well B -27(1966)

3.2) The semi-log plot of [Pws vs. ((t+∆t)/ ∆t))] and of its slope,
shows clearly that the Horner time from (tH=3169.25) to (tH
=793.06) can be fitted to a semi-log straight line as shown in
figure (C-4). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 43.22psi/cycle.

m = 43.22 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 5610 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 ⎜ ⎟
⎝ mh ⎠ ⎝ 43.22 × 201 ⎠

ko=133.66 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 33 × 1.00 × 1.05 ⎞
k = 162.6 ⎜ ⎟ 162.6 ⎜ ⎟
⎝ mh ⎠ ⎝ 43.22 × 201 ⎠

kw=0.65 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-4) to ∆t=1 hour, (i.e.
((t+∆t)/∆t) =6337.50), and read, P1hr , and then calculate ΔP1hr :

Pws (1hr) =4108 psi, and Pwfo = 2179 psi

ΔP1hr = P 1hr - Pwf=4108 - 2179= 1929 psi

96
Chapter 5 Field Case: Well B -27(1966)

⎛ P − Pwf k ⎞
S = 1.151 ⎜⎜ 1hr − log + 3. 23 ⎟⎟
⎝ m φμcrw
2

⎡ 1929 ⎛ 133.66 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 43.22 ⎝ 0.0983 × 0.95 × 9.5 × 10 × 0.292 ⎠ ⎦

S= 44.37

In this case the high value of skin factor mainly means that the well
had high damage; we note the number grater than (25).

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 43.22 × 44.37

ΔPs = 1668 Psi

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t) =1 and


read the false pressure, P*= 4257 psi.

P*= 4257 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

133.66 × 6336.50
t DA = 0.000264 ×
0.0983 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 3.10

97
Chapter 5 Field Case: Well B -27(1966)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 3.10, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 4.65.

ΔPD(MBH)= 4.65

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

43.22
P = 4257 - × 4.65
2.303

P =4169 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

4169 - 2179 - 1668


FE =
4169 - 2179

FE= 0.1619 =16.19%

From our interpretation, we note that the well has low flow
efficiency due to high damage or high pressure drop that is related
to the effect of drilling mud or high invasion.

98
Chapter 5 Field Case: Well B -27(1966)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 −3 × 133.66 × 201


PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 44.37 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=2.80 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 4142 Psi ) =
( Pr − Pwf )

5610
PI actual ( 4142 Psi ) =
(4142 - 2179)

PI(actual)=2.86 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI( actual 4169 Psi ) =
( Pr - Pwf )

5610
PI ( actual 4169 Psi ) =
(4169 - 2179)

99
Chapter 5 Field Case: Well B -27(1966)

PI(actual)=2.82 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PI Theoretical) 2.80
Actual Productivity Index, (PI Actual 4142) 2.86
Actual Productivity Index, (PI Actual 4169) 2.82

From the results above, we note that the high consistency in the
evaluation of Productivity Index for each method, the average
Productivity Index being (2.83).

Generally, in the actual we note the values of productivity index


from theoretical and actual (based on average reservoir pressure
estimated) closed of each to which, also we recommended to use
average reservoir pressure estimated to estimate productivity
index in the actual case.

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

133.66 × 8
rinv =
948 × 0.0983 × 0.95 × 9.5 × 10 −6

rinv=1127 ft

From log-log plot in figure (C-1), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

100
Chapter 5 Field Case: Well B -27(1966)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period (2-8)hours
Outer Boundary Non-appear

Test Results

Parameter Results Unit


Slope, (m) 43.22 psi/cycle
Effective Permeability to Oil, (ko) 133.66 md
Effective Permeability to Water, (kw) 0.63 md
Skin, (S) 44.37 #
Pressure Drop due to Skin, (ΔPs) 1668 Psi
False Reservoir Pressure, (P*) 4257 Psi
Dimensionless Time, (tDA) 3.10 #
Dimensionless Pressure Drop, (ΔPD)MBH 4.65 #
Average Pressure, ( P ) 4169 Psi
Flow Efficiency, (FE) 16.19 %
Theoretical 2.80 BOPD/Psi
Productivity
Actual4142 2.86 BOPD/Psi
Index, (PI)
Actual4169 2.82 BOPD/Psi
Radius of Investigation, (rinv) 1127 ft

101
Chapter 5 Field Case: Well B -27(1973)

102
Chapter 5 Field Case: Well B -27(1973)

5.3 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-27
Test Date June 11, 1973
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 3000 STB/day
Water Production Rate, qw 290 STB/day
Water Cut, W.C 11.29 %
Producing Time, tp 57010 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 201 ft


Layer Porosity, ø 9.83 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

103
Chapter 5 Field Case: Well B -27(1973)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-2), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-2), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-5).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-6).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-7).

2.4) From figure (C-7), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(11.00 – 14.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-8), the slope
of the semi-log plot should also be shown on the same graph to
enhance the recognition of the radial flow periods and their
duration.

104
Chapter 5 Field Case: Well B -27(1973)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 5183.79) to (tH
=4073.20) can be fitted to a semi-log straight line as shown in
figure (C-8). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 55.84 psi/cycle.

m = 55.84 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 3000 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 55.84 × 201 ⎠

ko=55.32 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 290 × 1.05 × 1.00 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 55.84 × 201 ⎠

kw=4.41 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-8) to ∆t=1 hour, (i.e.
((t+∆t)/∆t) =57011.73), and read, P1hr , and then calculate ΔP1hr :

Pws (1hr) =2618 psi, and Pwfo = 1488 psi

ΔP1hr = P 1hr - Pwf=2618 - 1488= 1130 psi

105
Chapter 5 Field Case: Well B -27(1973)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠
⎡ 1130 ⎛ 55.32 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 55.84 ⎝ 0.0983 × 0.95 × 9.5 × 10 × 0.292 ⎠ ⎦

S= 16.81

In this case the high value of skin factor mainly means the well still
had high damage, but less the value of skin obtained from the
previous test.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 55.84 × 16.81

ΔPs = 817 Psi

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t) =1 and


read the false pressure, P*= 2716 psi.

P*= 2716 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A
55.32 × 57010.73
t DA = 0.000264 ×
0.0983 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 11.50

106
Chapter 5 Field Case: Well B -27(1973)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 11.50 and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 5.90

ΔPD(MBH)= 5.90

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

55.84
P = 2716 - × 5.90
2.303

P =2572 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2572 - 1488 - 817


FE =
2572 - 1488

FE= 0.2463 =24.63%

From our interpretation, we note that the well still had low flow
efficiency due to high damage or high pressure drop; but also note
increase in the value of flow efficiency from (16.19 to 24.63) %,
mainly due to decrease in the value of skin factor.

107
Chapter 5 Field Case: Well B -27(1973)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:


7.08 × 10 −3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠
7.08 × 10 −3 × 55.32 × 201
PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 16.81⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=2.76 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2698 Psi ) =
( Pr - Pwf )

3000
PI actual ( 2698 Psi ) =
(2698 - 1488)

PI(actual)=2.48 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI( actual 2572 Psi ) =
( Pr - Pwf )

3000
PI( actual 2572 Psi ) =
(2572 - 1488)

PI(actual)=2.76 BOPD/Psi.

108
Chapter 5 Field Case: Well B -27(1973)

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PItheoretical) 2.76
Actual Productivity Index, (PI actual 2698) 2.48
Actual Productivity Index, (PI actual 2578) 2.76

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (2.67). But the value of actual
productivity index obtained from actual test data has different
value (less than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index)

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

41.10 × 20
rinv =
948 × .0983 × 0.95 × 9.50 × 10 -6

rinv=1147 ft

From log-log plot in figure (C-5), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re).

109
Chapter 5 Field Case: Well B -27(1973)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(11.00-14.00) hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 55.84 psi/cycle
Effective Permeability to Oil, (ko) 55.32 md
Effective Permeability to Water, (kw) 4.41 md
Skin, (S) 16.81 #
Pressure Drop due to Skin, (ΔPs) 817 Psi
False Reservoir Pressure, (P*) 2716 Psi
Dimensionless Time, (tDA) 11.50 #
Dimensionless Pressure Drop, (ΔPD)MBH 5.90 #
Average Pressure, ( P ) 2572 Psi
Flow Efficiency, (FE) 24.63 %
Theoretical 2.76 BOPD/Psi
Productivity
Actual4142 2.48 BOPD/Psi
Index, PI
Actual4172 2.76 BOPD/Psi
Radius of Investigation, (rinv) 1147 ft

110
Chapter 5 Field Case: Well B -27(1975)

111
Chapter 5 Field Case: Well B -27(1975)

5.4 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-27
Test Date January 6, 1975
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 1995 STB/day
Water Production Rate, qw 135 STB/day
Water Cut, W.C 15.61%
Producing Time, tp 98445 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 201 ft


Layer Porosity, ø 9.83 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

112
Chapter 5 Field Case: Well B -27(1975)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-3), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-3), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-9).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-10).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-11).

2.4) From figure (C-11), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(14.00 – 18.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-12), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

113
Chapter 5 Field Case: Well B -27(1975)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 7032.82) to (tH
=5470.19) can be fitted to a semi-log straight line as shown in
figure (C-12). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 27.64 psi/cycle.

m = 27.64 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 1995 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 27.64 × 201 ⎠

ko=74.32 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 135 × 1.00 × 1.05 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 27.64 × 201 ⎠

kw=4.15 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-12) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =58446.44), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =2544 psi, and Pwfo = 1141 psi

ΔP1hr = P 1hr - Pwf=2544 - 1141= 1403 psi

114
Chapter 5 Field Case: Well B -27(1975)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 1403 ⎛ 74.32 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 27.64 ⎝ 0.0983 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= 51.72

In this case the high value of skin factor mainly means the well had
high damage.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 27.64 × 51.72

ΔPs = 1243 Psi.

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t) =1 and


read the false pressure, P*= 2596 psi.

P*= 2596 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

74.32 × 98445.44
t DA = 0.000264 ×
0.0983 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 26.80

115
Chapter 5 Field Case: Well B -27(1975)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 26.8, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.0

ΔPD(MBH)= 6.0

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

27.64
P = 2596 - ×6
2.303

P =2524 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2524 - 1141 - 1244


FE =
2524 - 1141

FE= 0.10 =10.00%

From our interpretation, we note that the well had low flow
efficiency due to high damage or high pressure drop; so we note
increase in skin factor more than the previous test also increase in
water cut.

116
Chapter 5 Field Case: Well B -27(1975)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 74.32 × 201


PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 51.724 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=1.67 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2581Psi ) =
( Pr - Pwf )

1995
PI actual ( 2581Psi ) =
(2581 - 1141)

PI(actual)=1.39 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 2524 Psi ) =
( Pr - Pwf )
1995
PI ( actual 2524 Psi ) =
(2524 - 1141)

PI(actual)=1.44 BOPD/Psi.

117
Chapter 5 Field Case: Well B -27(1975)

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 1.67
Actual Productivity Index, (PI Actual 2581) 1.39
Actual Productivity Index, (PI Actual 2524) 1.44

From the results above, we note that the high consistency in the
evaluation of Productivity Index for each method, the average
Productivity Index being (1.50)

Generally, in the actual we note the values of productivity index


from theoretical and actual (based on average reservoir pressure
estimated) closed of each to which, also we recommended to use
average reservoir pressure estimated to estimate productivity
index in the actual case. On the hand we note decrease in flow
efficiency or productivity index one of these reasons are increase
in water cut.

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

74.32 × 22
rinv =
948 × 0.0983 × 0.95 × 9.50 × 10 -6

rinv=1394 ft

From log-log plot in figure (C-9), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

118
Chapter 5 Field Case: Well B -27(1975)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(14.00-18.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 27.64 psi/cycle
Effective Permeability to Oil, (ko) 74.32 md
Effective Permeability to Water, (kw) 4.15 md
Skin, (S) 51.72 #
Pressure Drop due to Skin, (ΔPs) 1244 Psi
False Reservoir Pressure, (P*) 2596 Psi
Dimensionless Time, (tDA) 26.80 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 2524 Psi
Flow Efficiency, (FE) 10.00 %
theoretical 1.67 BOPD/Psi
Productivity
Actual2581 1.39 BOPD/Psi
Index, PI
Actual2524 1.44 BOPD/Psi
Radius of Investigation, (rinv) 1394 ft

119
Chapter 5 Field Case: Well B -27(1983)

120
Chapter 5 Field Case: Well B -27(1983)

5.5 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-27
Test Date September 16, 1983
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 1651 STB/day
Water Production Rate, qw 670 STB/day
Water Cut, W.C 31.66 %
Producing Time, tp 189783 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 201 ft


Layer Porosity, ø 9.83 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

121
Chapter 5 Field Case: Well B -27(1983)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-4), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-4), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-13).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is
clearly indicates the characteristics of wellbore storage effect. The
plot is shown in figure (C-14).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-15).

2.4) From figure (C-15), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(5.25 – 12.25) hours.

Step (3): Wellbore Storage Coefficient Calculation.

3.1) Read the time (tsd), when the pressure data starts deviating
from the unit slope line, then proceed 1 1 cycle (i.e., tsd × 18) to
4
estimate the end of wellbore storage effect. (tsd = 0.17 hrs).

The end of wellbore storage effect estimation:


tsd × 18 = 0.17 × 18 = 3.06 hrs.

122
Chapter 5 Field Case: Well B -27(1983)

3.2) Pick any point on the unit slope line and read from the plot
(∆t, hours) and the corresponding (∆P= Pws-Pwfo).

Then, ∆t=0.17 hrs and ∆P= 154.80 psi.

3.3) Calculate the wellbore storage coefficient.

⎛ qBΔt ⎞ ⎛ 1651 × 1.34 × 0.17 ⎞ =0.101 bbl/psi


C =⎜ ⎟=⎜ ⎟
⎝ 24 ΔP ⎠ ⎝ 24 × 154.8 ⎠

C =0.101 bbl/psi.

Step (4): Analysis of the Radial Flow Period.

4.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-16), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

4.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 36150.14) to (tH
=15493.49) can be fitted to a semi-log straight line as shown in
figure (C-16). This could be interpreted as the effect of radial flow.

4.3) Read the slope directly from the plot, m = 17.66 psi/cycle.

m = 17.66 psi/cycle.

4.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 1651 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 17.66 × 201 ⎠

ko=96.25 md.

123
Chapter 5 Field Case: Well B -27(1983)

4.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 670 × 1.05 × 1.00 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 17.66 × 201 ⎠

kw=32.22 md.

Step (5): Skin Factor Calculations.

5.1) Extrapolate the straight line in figure (C-16) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =189784.00), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =2807 psi, and Pwfo = 2604 psi

ΔP1hr = P 1hr - Pwf=2807 - 2604 = 203 psi

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 203 ⎛ 96.25 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟
+ 3.23⎥
⎣ 17.66 ⎝ 0.0983 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= 6.47

In this case we note decrease in the value of skin factor.

5.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 17.66 × 6.47

ΔPs = 99.38 Psi.

124
Chapter 5 Field Case: Well B -27(1983)

Step (6): False Reservoir Pressure Calculations.

6.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 2847 psi.

P*= 2847 psi.

Step (7): Dimensionless Calculations.

7.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

96.25 × 188783
t DA = 0.000264 ×
0.0983 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 66.55

7.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 66.55, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.00

ΔPD(MBH)= 6.0

Step (8): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

17.66
P = 2847 - ×6
2.303

125
Chapter 5 Field Case: Well B -27(1983)

P =2801 psi

Step (9): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2801 - 2604 - 99.38


FE =
2801 - 2604

FE= 0.4924 =49.24%

From our interpretation, we note that the well had increase in flow
efficiency due to decrease pressure drop due to skin.

Step (10): Productivity Index Calculations

10.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 99.38 × 201


PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 6.47 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=7.79 BOPD/Psi.

10.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2835 Psi ) =
( Pr - Pwf )

126
Chapter 5 Field Case: Well B -27(1983)

1651
PI actual ( 2835 Psi ) =
(2835 - 2604)

PI(actual)=7.15 BOPD/Psi.

10.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI( actual 2801 Psi ) =
( Pr - Pwf )

1651
PI( actual 2801 Psi ) =
(2801 - 2604)

PI(actual)=8.39 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 7.79
Actual Productivity Index, (PI Actual 2835) 7.15
Actual Productivity Index, (PI Actual 2801) 8.39

From the results above, we note that the high consistency in the
evaluation of Productivity Index for each method, the average
Productivity Index being (7.78)

Step (11): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

97.28 × 30.25
rinv =
948 × 0.0983 × 0.95 × 9.50 × 10 -6

127
Chapter 5 Field Case: Well B -27(1983)

rinv=1870 ft

From log-log plot in figure (C-13), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

128
Chapter 5 Field Case: Well B -27(1983)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators:

Wellbore Storage Clearly indicates during period


(0.08-0.17) hours
Radial Flow Clearly indicates during period
(5.25-12.25) hours
Outer Boundary Non-appear

Test Results:

Parameter Result Unit


Slope, (m) 17.66 psi/cycle
Effective Permeability to Oil, (ko) 96.25 md
Effective Permeability to Water, (kw) 32.22 md
Skin, (S) 6.46 #
Pressure Drop due to Skin, (ΔPs) 99.38 Psi
False Reservoir Pressure, (P*) 2847 Psi
Dimensionless Time, (tDA) 66.55 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 2801 Psi
Flow Efficiency, (FE) 49.24 %
theoretical 7.79 BOPD/Psi
Productivity
Actual2835 7.15 BOPD/Psi
Index, PI
Actual2801 8.39 BOPD/Psi
Radius of Investigation, (rinv) 1870 ft

129
Chapter 5 Field Case: Well B -42(1966)

130
Chapter 5 Field Case: Well B -42(1966)

5.6 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-42
Test Date December 8, 1966
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, qo 9250 STB/day
Water Production Rate, qw 0
Water Cut, W.C 0
Producing Time, tp 1920 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 74 ft


Layer Porosity, ø 9.67%
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

131
Chapter 5 Field Case: Well B -42(1966)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-5), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-5), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-17).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-18).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-19).

2.4) From figure (C-19), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(3.00 – 5.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-20), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

132
Chapter 5 Field Case: Well B -42(1966)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH=641.10) to (tH
=385.06) can be fitted to a semi-log straight line as shown in
figure (C-20). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 455.30 psi/cycle.

m = 455.30 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 9250 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 ⎜ ⎟
⎝ mh ⎠ ⎝ 455.30 × 74 ⎠

ko=56.83 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 0 × 1.00 × 1.05 ⎞
k = 162.6 ⎜ ⎟ 162.6 ⎜ ⎟
⎝ mh ⎠ ⎝ 455.30 × 74 ⎠

kw=0 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-20) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =1921.31), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =3488 psi, and Pwfo = 2731 psi

ΔP1hr = P 1hr - Pwf=3488 - 2731 = 757 psi

133
Chapter 5 Field Case: Well B -42(1966)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 757 ⎛ 56.83 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 455.30 ⎝ 0.0967 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= -4.59

In this case the negative value of skin factor mainly means the well
had stimulation.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 455.30 × (-4.59)

ΔPs = -1819 Psi

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 4986 psi.

P*= 4986 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

56.83 × 1920
t DA = 0.000264 ×
0.0967 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 0.41

134
Chapter 5 Field Case: Well B -42(1966)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 0.29, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 2.3

ΔPD(MBH)= 2.55

Step (7): Average Pressure Calculations.

m
P = P* - × PD( MBH )
2.303

455.30
P = 4986 - × 2.55
2.303

P =4481 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

4481 - 2731 - (-1819)


FE =
4481 - 2731

FE=2.04=204%

From our interpretation, we note that the well had high value of
flow efficiency due to negative value of skin; consequently the
value of pressure drop due to skin was negative.

135
Chapter 5 Field Case: Well B -42(1966)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 3 × 56.83 × 74
PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + ( −4.59 ) ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=4.20 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 3930 Psi ) =
( Pr − Pwf )

9250
PI actual ( 3930 Psi ) =
(3930 - 2731)

PI(actual)=7.71 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 4481 Psi ) =
( Pr - Pwf )

9250
PI ( actual 4481 Psi ) =
(4481 - 2731)

136
Chapter 5 Field Case: Well B -42(1966)

PI(actual)=5.28 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 4.20
Actual Productivity Index, (PI Actual 3930) 7.71
Actual Productivity Index, (PI Actual 4481) 5.28

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (4.74). But the value of actual
productivity index obtained from actual test data has different
value (greater than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index).

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

56.83 × 9
rinv =
948 × 0.0967 × 0.95 × 9.50 × 10 -6

rinv=786 ft

From log-log plot in figure (C-17), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

137
Chapter 5 Field Case: Well B -42(1966)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(3.00-5.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 455.31 psi/cycle
Effective Permeability to Oil, (ko) 56.83 md
Effective Permeability to Water, (kw) 0.00 md
Skin, (S) -4.59 #
Pressure Drop due to Skin, (ΔPs) -1819 Psi
False Reservoir Pressure, (P*) 4986 Psi
Dimensionless Time, (tDA) 0.41 #
Dimensionless Pressure Drop, (ΔPD)MBH 2.55 #
Average Pressure, ( P ) 4481 Psi
Flow Efficiency, (FE) 204 %
theoretical 4.20 BOPD/Psi
Productivity
Actual3930 7.71 BOPD/Psi
Index, PI
Actual4481 5.28 BOPD/Psi
Radius of Investigation, (rinv) 786 ft

138
Chapter 5 Field Case: Well B -42(1972)

139
Chapter 5 Field Case: Well B -42(1972)

5.7 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-42
Test Date March 11, 1972
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 4177 STB/day
Water Production Rate, qw 0
Water Cut, W.C 0
Producing Time, tp 62371 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 74 ft


Layer Porosity, ø 0.0967 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

140
Chapter 5 Field Case: Well B -42(1972)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-6), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-6), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-21).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-22).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-23).

2.4) From figure (C-23), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(6.00 – 9.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-24), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

141
Chapter 5 Field Case: Well B -42(1972)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 10396.30) to (tH
=6931.20) can be fitted to a semi-log straight line as shown in
figure (C-24). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 371.95 psi/cycle.

m = 371.95 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 4177 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 371.95 × 74 ⎠

ko=31.42 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 0 × 1.00 × 1.05 ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 371.95 × 74 ⎠

kw=0 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-24) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =62372.82), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =1815 psi, and Pwfo = 1418 psi

ΔP1hr = P 1hr - Pwf=1815 - 1418 = 397 psi

142
Chapter 5 Field Case: Well B -42(1972)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 397 ⎛ 31.42 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 371.95 ⎝ 0.0967 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= -4.98

In this case the negative value of skin factor mainly means the well
had stimulation.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 371.95 × (-4.28)

ΔPs = -1612 Psi.

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3598 psi.

P*= 3598 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

31.42 × 62371.82
t DA = 0.000264 ×
0.0967 × 0.95 × 9.50 × 10 −6 × 1865 × 43560

tDA= 7.29

143
Chapter 5 Field Case: Well B -42(1972)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA=7.29, and read the corresponding value
of the dimensionless pressure drop, ΔPD(MBH)= 5.45

ΔPD(MBH)= 5.45

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

371.95
P = 3598 - × 5.45
2.303

P =2718 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2718 - 1418 - (-1612)


FE =
2718 - 1418

FE= 2.24 =224%

From our interpretation, we note that the well had high value of
flow efficiency due to negative value of skin; consequently the
value of pressure drop due to skin was negative.

144
Chapter 5 Field Case: Well B -42(1972)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 31.42 × 74
PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + ( −4.98 ) ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=2.45 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2275 Psi ) =
( Pr - Pwf )

4177
PI actual ( 2275 Psi ) =
(2275 - 1418)

PI(actual)=4.87 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 2718 Psi ) =
( Pr - Pwf )

4177
PI ( actual 2718 Psi ) =
(2718 - 1418)

145
Chapter 5 Field Case: Well B -42(1972)

PI(actual)=3.21 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 2.45
Actual Productivity Index, (PI Actual 2275) 4.87
Actual Productivity Index, (PI Actual 2718) 3.21

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (2.83). But the value of actual
productivity index obtained from actual test data has different
value (greater than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index).

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

31.42 × 20.20
rinv =
948 × 0.0967 × 0.95 × 9.50 × 10 -6

rinv=876 ft

From log-log plot in figure (C-21), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

146
Chapter 5 Field Case: Well B -42(1972)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(6.00-9.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 371.95 psi/cycle
Effective Permeability to Oil, (ko) 31.42 md
Effective Permeability to Water, (kw) 0.00 md
Skin, (S) -4.98 #
Pressure Drop due to Skin, (ΔPs) -1612 Psi
False Reservoir Pressure, (P*) 3598 Psi
Dimensionless Time, (tDA) 7.29 #
Dimensionless Pressure Drop, (ΔPD)MBH 5.45 #
Average Pressure, ( P ) 2718 Psi
Flow Efficiency, (FE) 2.24 %
theoretical 2.45 BOPD/Psi
Productivity
Actual2275 4.87 BOPD/Psi
Index, PI
Actual2718 3.21 BOPD/Psi
Radius of Investigation, (rinv) 876 ft

147
Chapter 5 Field Case: Well B -42(1973)

148
Chapter 5 Field Case: Well B -42(1973)

5.8 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-42
Test Date June 7, 1973
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 3727 STB/day
Water Production Rate, qw 21 STB/day
Water Cut, W.C 0.67 %
Producing Time, tp 57010 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 74 ft


Layer Porosity, ø 9.67 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

149
Chapter 5 Field Case: Well B -42(1973)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-7), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-7), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-25).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-26).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-27).

2.4) From figure (C-27), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(9.00 – 14.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-28), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

150
Chapter 5 Field Case: Well B -42(1973)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 8874.27) to (tH
=5705.24) can be fitted to a semi-log straight line as shown in
figure (C-28). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 453.88 psi/cycle.

m = 453.88 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 3727 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 453.88 × 74 ⎠

ko=22.97 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 21 × 1.05 × 1.00 ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 453.88 × 74 ⎠

kw=0.11md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-28) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =79860.39), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =1450 psi, and Pwfo = 1233 psi

ΔP1hr = P 1hr - Pwf=1450 - 1233 = 217 psi

151
Chapter 5 Field Case: Well B -42(1973)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 217 ⎛ 22.79 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 453.88 ⎝ 0.0967 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= -5.40

In this case the negative value of skin factor mainly means the well
had stimulation.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 453.88 × (-5.40)

ΔPs = -2133 Psi

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3772 psi.

P*= 3772 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

22.97 × 79859.39
t DA = 0.000264 ×
0.0967 × 0.95 × 9.50 × 10 −6 × 1865 × 43560

tDA= 6.83

152
Chapter 5 Field Case: Well B -42(1973)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 6.83, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 5.4

ΔPD(MBH)= 5.4

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

453.88
P = 3772 - × 5.4
2.303

P =2708 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2708 - 1233 - (-2133)


FE =
2708 - 1233

FE= 2.45 =245 %

From our interpretation, we note that the well had high value of
flow efficiency due to negative value of skin; consequently the
value of pressure drop due to skin was negative.

153
Chapter 5 Field Case: Well B -42(1973)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 22.97 × 74
PI theoretical =
⎛ ⎛ 5085 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + ( −5.40 ) ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=2.59 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2073 Psi ) =
( Pr - Pwf )

3727
PI actual ( 2073 Psi ) =
(2073 - 1233)

PI(actual)=4.44 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 2708 Psi ) =
( Pr - Pwf )

3727
PI ( actual 2708 Psi ) =
(2708 - 1233)

154
Chapter 5 Field Case: Well B -42(1973)

PI(actual)=2.53 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 2.56
Actual Productivity Index, (PI Actual 2073) 4.44
Actual Productivity Index, (PI Actual 2708) 2.53

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (2.55). But the value of actual
productivity index obtained from actual test data has different
value (greater than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index).

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

22.97 × 20
rinv =
948 × 0.0967 × 0.95 × 9.50 × 10 -6

rinv=745 ft

From log-log plot in figure (C-25), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

155
Chapter 5 Field Case: Well B -42(1973)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(9.00 – 14.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 453.88 psi/cycle
Effective Permeability to Oil, (ko) 22.97 md
Effective Permeability to Water, (kw) 0.11 md
Skin, (S) -5.40 #
Pressure Drop due to Skin, (ΔPs) 2133 Psi
False Reservoir Pressure, (P*) 3772 Psi
Dimensionless Time, (tDA) 6.83 #
Dimensionless Pressure Drop, (ΔPD)MBH 5.40 #
Average Pressure, ( P ) 2708 Psi
Flow Efficiency, (FE) 245 %
theoretical 2.56 BOPD/Psi
Productivity
Actual2073 4.44 BOPD/Psi
Index, PI
Actual2708 2.53 BOPD/Psi
Radius of Investigation, (rinv) 745 ft

156
Chapter 5 Field Case: Well B -42(1980)

157
Chapter 5 Field Case: Well B -42(1980)

5.9 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-42
Test Date June 16, 1980
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 2160 STB/day
Water Production Rate, qw 85 STB/day
Water Cut, W.C 4.38 %
Producing Time, tp 198183 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 74 ft


Layer Porosity, ø 9.67 %
Total Compressibility, Ct 9.50×10-6 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

158
Chapter 5 Field Case: Well B -42(1980)

Oil Viscosity, μo 0.95 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-8), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-8), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-29).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-30).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-31).

2.4) From figure (C-31), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(5.00 – 14.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-32), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

159
Chapter 5 Field Case: Well B -42(1980)

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 39637.75) to (tH
=12387.49) can be fitted to a semi-log straight line as shown in
figure (C-32). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 303.50 psi/cycle.

m = 303.50 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ ⎛ 2160 × 0.95 × 1.34 ⎞ ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎜ ⎟⎟
⎝ mh ⎠ ⎝ ⎝ 303.50 × 74 ⎠ ⎠

k=19.91 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 85 × 1.00 × 1.05 ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 303.50 × 74 ⎠

kw=0.65 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-32) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =198184.77), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =1670 psi, and Pwfo = 1387 psi

ΔP1hr = P 1hr - Pwf=1670 - 1387 = 773 psi

160
Chapter 5 Field Case: Well B -42(1980)

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 773 ⎛ 19.91 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 303.50 ⎝ 0.0967 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= -4.92

In this case the negative value of skin factor mainly means the well
had stimulation.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 303.50 × (-4.92)

ΔPs = -1300 Psi.

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3261 psi.

P*= 3261 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

19.91 × 198183.77
t DA = 0.000264 ×
0.0967 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 14.70

161
Chapter 5 Field Case: Well B -42(1980)

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 14.70, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.00

ΔPD(MBH)= 6.00

Step (7): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

303.5
P = 3261 - ×6
2.303

P =2710 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2710 - 1387 + 1300


FE =
2710 - 1387

FE= 1.98 =198 %

From our interpretation, we note that the well had high value of
flow efficiency due to negative value of skin; consequently the
value of pressure drop due to skin was negative.

162
Chapter 5 Field Case: Well B -42(1980)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 19.91 × 74
PI theoretical =
⎛ ⎛ 5086 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - − 4.92 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=1.54 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2068 Psi ) =
( Pr - Pwf )

2160
PI actual ( 2068 Psi ) =
(2068 - 1387)

PI(actual)=3.17 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 2710 Psi ) =
( Pr - Pwf )

2160
PI ( actual 2710 Psi ) =
(2710 - 1387)

163
Chapter 5 Field Case: Well B -42(1980)

PI(actual)=1.63 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 1.54
Actual Productivity Index, (PI Actual 2068) 3.17
Actual Productivity Index, (PI Actual 2710) 1.63

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (1.59). But the value of actual
productivity index obtained from actual test data has different
value (greater than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index).

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

19.91 × 24
rinv =
948 × 0.0967 × 0.95 × 9.50 × 10 -6

rinv=760 ft

From log-log plot in figure (C-29), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re)

164
Chapter 5 Field Case: Well B -42(1980)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(5.00 – 14.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 303.50 psi/cycle
Effective Permeability to Oil, (ko) 19.91 md
Effective Permeability to Water, (kw) 0.65 md
Skin, (S) -4.92 #
Pressure Drop due to Skin, (ΔPs) -1300 Psi
False Reservoir Pressure, (P*) 3261 Psi
Dimensionless Time, (tDA) 14.70 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 2710 Psi
Flow Efficiency, (FE) 198 %
theoretical 1.54 BOPD/Psi
Productivity
Actual2068 3.17 BOPD/Psi
Index, PI
Actual2710 1.63 BOPD/Psi
Radius of Investigation, (rinv) 760 ft

165
Chapter 5 Field Case: Well B -45(1972)

166
Chapter 5 Field Case: Well B -45(1972)

5.10 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-45
Test Date March 16, 1972
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Cased Hole
Last Oil Production Rate, q 4273 STB/day
Water Production Rate, qw 4 STB/day
Water Cut, W.C 0.10 %
Producing Time, tp 50300 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 37 ft


Perforation Thickness, hp 32 ft
Layer Porosity, ø 18.67 %
Total Compressibility, Ct 9.50×10-6 /psi

167
Chapter 5 Field Case: Well B -45(1972)

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB
Oil Viscosity, μo 0.95 cp
Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-9), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-9), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-33).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-34).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-35).

2.4) From figure (C-35), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(6.00 – 8.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-36), the
slope of the semi-log plot should also be shown on the same graph

168
Chapter 5 Field Case: Well B -45(1972)

to enhance the recognition of the radial flow periods and their


duration.

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH=8384.39) to (tH
=6288.54) can be fitted to a semi-log straight line as shown in
figure (C-36). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 160.88 psi/cycle.

m = 160.88 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 4273 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 160.88 × 37 ⎠

ko=148.59 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ ⎛ 4 × 1.05 × 1.00 ⎞ ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎜ ⎟⎟
⎝ mh ⎠ ⎝ ⎝ 160.88 × 37 ⎠ ⎠

kw=0.12 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-36) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =50301.34), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =2748 psi, and Pwfo = 1324.37 psi

169
Chapter 5 Field Case: Well B -45(1972)

ΔP1hr = P 1hr - Pwf= 2748 - 1324.37 = 1423.63 psi

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 1423.63 ⎛ 148.59 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 160.88 ⎝ 0.1867 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= 2.90

In this case the positive value of skin factor mainly means the well
had damage.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 160.88 × 2.90

ΔPs = 406 Psi.

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3366 psi.

P*= 3366 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

148.59 × 50300.34
t DA = 0.000264 ×
0.1867 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

170
Chapter 5 Field Case: Well B -45(1972)

tDA= 14.41

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 14.41, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.00

ΔPD(MBH)= 6.00

Step (7): Average Pressure Calculations.

m
P = P* - × PD( MBH )
2.303

160.88
P = 3366 - ×6
2.303

P =2947 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

2947 - 1324 - 406


FE =
2947 - 1324

FE= .7495 =74.95 %

From our interpretation, we note that the well has high flow
efficiency due to low damage or low pressure drop due to skin.

171
Chapter 5 Field Case: Well B -45(1972)

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 148.59 × 37
PI theoretical =
⎛ ⎛ 5086 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 2.90 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=2.55 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 2891Psi ) =
( Pr - Pwf )

4273
PI actual ( 2891Psi ) =
(2891 - 1324 )

PI(actual)=2.73 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 2947 Psi ) =
( Pr - Pwf )

4273
PI ( actual 2947 Psi ) =
(2947 - 1324 )

172
Chapter 5 Field Case: Well B -45(1972)

PI(actual)=2.63 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 2.55
Actual Productivity Index, (PI Actual 2891) 2.73
Actual Productivity Index, (PI Actual 2947) 2.63

From the results above, we note that the consistency in the


evaluation of Productivity Index for each method, the average
Productivity Index being (2.64).

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

148.59 × 22.05
rinv =
948 × 0.1867 × 0.95 × 9.50 × 10 -6

rinv=1432 ft

From log-log plot in figure (C-33), we can indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is greater
than the drainage radius (the test reaches to the outer boundary
because (rinv> re)

173
Chapter 5 Field Case: Well B -45(1972)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(6.00 – 8.00)hours
Outer Boundary Non Appear

Test Results

Parameter Result Unit


Slope, (m) 160.88 psi/cycle
Effective Permeability to Oil, (ko) 148.59 md
Effective Permeability to Water, (kw) 0.12 md
Skin, (S) 2. 90 #
Pressure Drop due to Skin, (ΔPs) 406 Psi
False Reservoir Pressure, (P*) 3366 Psi
Dimensionless Time, (tDA) 14.41 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 2947 Psi
Flow Efficiency, (FE) 74.95 %
theoretical 2.55 BOPD/Psi
Productivity
Actual2891 2.73 BOPD/Psi
Index, PI
Actual2947 2.63 BOPD/Psi
Radius of Investigation, (rinv) 1432 ft

174
Chapter 5 Field Case: Well B -45(1983)

175
Chapter 5 Field Case: Well B -45(1983)

5.11 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-45
Test Date July 30, 1983
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Cased Hole
Last Oil Production Rate, q 967 STB/day
Water Production Rate, qw 572 STB/day
Water Cut, W.C 43.09 %
Producing Time, tp 398312 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 37 ft


Perforation Thickness, hp 32 ft
Layer Porosity, ø 18.67 %
Total Compressibility, Ct 9.50×10-6 /psi

176
Chapter 5 Field Case: Well B -45(1983)

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB
Oil Viscosity, μo 0.95 cp
Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-10), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-10), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-37).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-38).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-39).

2.4) From figure (C-39), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(14.83 – 38.83) hours.

177
Chapter 5 Field Case: Well B -45(1983)

Step (3): Wellbore Storage Coefficient Calculation.

3.1) Read the time (tsd), when the pressure data starts deviating
from the unit slope line, then proceed 1 1 cycle (i.e., tsd × 18) to
4
estimate the end of wellbore storage effect. (tsd = 0.14 hrs).

The end of wellbore storage effect estimation:


tsd × 18 = 0.14 × 18 = 2.52 hrs.

3.2) Pick any point on the unit slope line and read from the plot
(∆t, hours) and the corresponding (∆P= Pws-Pwfo).

Then, ∆t=0.08 hrs and ∆P= 86.60 psi.

3.3) Calculate the wellbore storage coefficient.

⎛ qBΔt ⎞ ⎛ 967 × 1.34 × 0.08 ⎞ =0.05 bbl/psi


C =⎜ ⎟=⎜ ⎟
⎝ 24 ΔP ⎠ ⎝ 24 × 86.60 ⎠

C =0.05 bbl/psi.

Step (4): Analysis of the Radial Flow Period.

4.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-40), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

4.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 26859.50) to (tH =
10258.83.75) can be fitted to a semi-log straight line as shown in
figure (C-40). This could be interpreted as the effect of radial flow.

4.3) Read the slope directly from the plot, m = 29.89 psi/cycle.

m = 29.89 psi/cycle.

178
Chapter 5 Field Case: Well B -45(1983)

4.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 967 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 29.89 × 37 ⎠

ko= 181.00 md.

4.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 572 × 1.00 × 1.05 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 29.89 × 37 ⎠

kw=88.30 md.

Step (5): Skin Factor Calculations.

5.1) Extrapolate the straight line in figure (C-40) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) = 398313), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =3155 psi, and Pwfo = 2532 psi

ΔP1hr = P 1hr - Pwf= 3155 - 2532 = 622.80 psi

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟
m 2
φμcrw ⎟
⎝ ⎠

⎡ 622.80 ⎛ 137.44 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 29.89 ⎝ 0.1867 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= 17.08

179
Chapter 5 Field Case: Well B -45(1983)

In this case the high value of skin factor mainly means the well still
had high damage, but greater than the value of skin obtained from
the previous test.

5.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 29.89 × 17.08

ΔPs = 443 Psi

Step (6): False Reservoir Pressure Calculations.

6.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3322 psi.

P*= 3322 psi.

Step (7): Dimensionless Calculations.

7.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

181.00 × 398311.55
t DA = 0.000264 ×
0.1867 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 139.04

7.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 139.04, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.00

180
Chapter 5 Field Case: Well B -45(1983)

ΔPD(MBH)= 6.00

Step (8): Average Pressure Calculations.

m
P = P* - ×P
2.303 D( MBH )

29.89
P = 3322 - ×6
2.303

P =3244 psi

Step (9): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

3244 - 2532 - 443


FE =
3244 - 2532

FE= 0.377 =37.70 %

From our interpretation, we note that the well still had low flow
efficiency due to high damage or high pressure drop; also we note
decrease in the value of flow efficiency from (74.95 to 37.70) %,
mainly due to increase in the value of skin factor.

Step (10): Productivity Index Calculations

10.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

181
Chapter 5 Field Case: Well B -45(1983)

7.08 × 10 -3 × 181 × 37
PI theoretical =
⎛ ⎛ 5086 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 17.08 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=1.42 BOPD/Psi.

10.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 3208 Psi ) =
( Pr - Pwf )

967
PI actual ( 3208 Psi ) =
(3208 - 2532)

PI(actual)=1.43 BOPD/Psi.

10.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI ( actual 3244 Psi ) =
( Pr - Pwf )

967
PI ( actual 3244 Psi ) =
(3244 - 2532)

PI(actual)=1.36 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 1.42
Actual Productivity Index, (PI Actual 3208) 1.43
Actual Productivity Index, (PI Actual 3244) 1.36

182
Chapter 5 Field Case: Well B -45(1983)

From the results above, we note that the high consistency in the
evaluation of Productivity Index for each method, the average
Productivity Index being (1.40).

Step (11): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

181.00 × 61.83
rinv =
948 × 0.1867 × 0.95 × 9.50 × 10 -6

rinv=2647 ft

From log-log plot in figure (C-37), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re).

183
Chapter 5 Field Case: Well B -45(1983)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(14.83 – 38.83)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 29.89 psi/cycle
Effective Permeability to Oil, (ko) 181.00 md
Effective Permeability to Water, (kw) 88.30 md
Skin, (S) 17.08 #
Pressure Drop due to Skin, (ΔPs) 443 Psi
False Reservoir Pressure, (P*) 3322 Psi
Dimensionless Time, (tDA) 139.04 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 3244 Psi
Flow Efficiency, (FE) 37.70 %
Theoretical 1.42 BOPD/Psi
Productivity
Actual3208 1.43 BOPD/Psi
Index, PI
Actual3244 1.36 BOPD/Psi
Radius of Investigation, (rinv) 2647 ft

184
Chapter 5 Field Case: Well B -45(1984)

185
Chapter 5 Field Case: Well B -45(1984)

5.12 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Al Harouge Operating Company


Field Name Amal
Well No B-45
Test Date August 8, 1984
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Cased Hole
Last Oil Production Rate, q 2160 STB/day
Water Production Rate, qw 85 STB/day
Water Cut, W.C 4.38 %
Producing Time, tp 198183 hrs
Well Radius, rw 0.292 ft
Drainage Area, A 1865 acre

Rock Properties

Layer Net Thickness, h 37 ft


Perforation Thickness, hp 32 ft
Layer Porosity, ø 18.67 %
Total Compressibility, Ct 9.50×10-6 /psi

186
Chapter 5 Field Case: Well B -45(1984)

Fluid Properties

Oil Formation Volume Factor, Bo 1.34 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB
Oil Viscosity, μo 0.95 cp
Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-11), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-11), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-41).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-42).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-43).

2.4) From figure (C-43), we can indicate radial flow period which,
can be clearly identified by a horizontal line during the period
(13.00 – 37.00) hours.

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-44), the
slope of the semi-log plot should also be shown on the same graph

187
Chapter 5 Field Case: Well B -45(1984)

to enhance the recognition of the radial flow periods and their


duration.

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH= 333763.42) to (tH
=11863.49) can be fitted to a semi-log straight line as shown in
figure (C-44). This could be interpreted as the effect of radial flow.

4.3) Read the slope directly from the plot, m = 43.70 psi/cycle.

m = 43.70 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 888 × 0.95 × 1.34 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 43.70 × 37 ⎠

ko= 113.67 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 85 × 1.05 × 1.00 ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 43.70 × 37 ⎠

kw=8.98 md.

Step (4): Skin Factor Calculations.

4.1) Extrapolate the straight line in figure (C-44) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =438913.10), and read, P1hr , and then calculate
ΔP1hr :

Pws (1hr) =3241 psi, and Pwfo = 2454 psi

188
Chapter 5 Field Case: Well B -45(1984)

ΔP1hr = P 1hr - Pwf=3241 – 2454 = 787 psi

⎛ P1hr − Pwf k ⎞
S = 1.151⎜⎜ − log + 3. 23 ⎟⎟
⎝ m φμcrw
2

⎡ 787 ⎛ 113.67 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -6 2 ⎟ + 3.23 ⎥
⎣ 43.70 ⎝ 0.1867 × 0.95 × 9.50 × 10 × 0.292 ⎠ ⎦

S= 14.20

In this case the high value of skin factor mainly means the well still
had high damage, but less than the value of skin obtained from the
previous test.

4.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 43.70 × 14.20

ΔPs = 540 Psi.

Step (5): False Reservoir Pressure Calculations.

5.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 3485 psi.

P*= 3485 psi.

Step (6): Dimensionless Calculations.

6.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

189
Chapter 5 Field Case: Well B -45(1984)
113.67 × 438912.10
t DA = 0.000264 ×
0.1867 × 0.95 × 9.50 × 10 -6 × 1865 × 43560

tDA= 96.22

6.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 96.22, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 6.00

ΔPD(MBH)= 6.00

Step (7): Average Pressure Calculations.

m
P = P* - × PD( MBH )
2.303

43.70
P = 3485 - ×6
2.303

P =3371 psi

Step (8): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

3371 - 2454 - 540


FE =
3371 - 2454

FE= 0.4111 =41.11 %

190
Chapter 5 Field Case: Well B -45(1984)

From our interpretation, we note that the well still had low flow
efficiency due to high damage or high pressure drop; also we note
small increase in the value of flow efficiency from (37.70 to 41.11)
%, mainly due to decrease in the value of skin factor from (17.08
to 14.20).

Step (9): Productivity Index Calculations

9.1) Theoretical Productivity Index Calculations:

7.08 × 10 -3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 113.67 × 37
PI theoretical =
⎛ ⎛ 5086 ⎞ 3 ⎞
0.95 × 1.34 × ⎜ ln⎜ ⎟ - + 14.20 ⎟
⎝ ⎝ 0.292 ⎠ 4 ⎠

PI(theoretical)=1.01 BOPD/Psi.

9.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 3330 Psi ) =
( Pr - Pwf )

2160
PI actual ( 3330 Psi ) =
(3330 - 2454)

PI(actual)=2.47 BOPD/Psi.

9.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

191
Chapter 5 Field Case: Well B -45(1984)
q
PI ( actual 3371 Psi ) =
( Pr - Pwf )

2160
PI ( actual 3371 Psi ) =
(3371 - 1387)

PI(actual)=1.09 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 1.01
Actual Productivity Index, (PI Actual 3330) 2.47
Actual Productivity Index, (PI Actual 3371) 1.09

From the results above, we note that the high consistency in the
evaluation of Productivity Index from the theoretical and actual
based on average reservoir pressure estimated, where the average
Productivity Index being (1.05). But the value of actual
productivity index obtained from actual test data has different
value (greater than); as mentioned before (we recommended using
average reservoir pressure estimated to estimate productivity
index)

Step (10): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

113.67 × 96
rinv =
948 × 0.1867 × 0.95 × 9.5 × 10 -6

rinv=2614 ft

192
Chapter 5 Field Case: Well B -45(1984)

From log-log plot in figure (C-41), we cannot indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is less than
the drainage radius (the test does not reach to the outer boundary
because (rinv< re).

193
Chapter 5 Field Case: Well B -45(1984)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(13.00-37.00)hours
Outer Boundary Non-appear

Test Results

Parameter Result Unit


Slope, (m) 43.70 psi/cycle
Effective Permeability to Oil, (ko) 113.67 md
Effective Permeability to Water, (kw) 8.98 md
Skin, (S) 14.20 #
Pressure Drop due to Skin, (ΔPs) 540 Psi
False Reservoir Pressure, (P*) 3485 Psi
Dimensionless Time, (tDA) 96.20 #
Dimensionless Pressure Drop, (ΔPD)MBH 6.00 #
Average Pressure, ( P ) 3371 Psi
Flow Efficiency, (FE) 41.11 %
theoretical 1.01 BOPD/Psi
Productivity
Actual3330 2.47 BOPD/Psi
Index, PI
Actual3371 1.09 BOPD/Psi
Radius of Investigation, (rinv) 2614 ft

194
Chapter 5 Field Case: Well A -67(1996)

195
Chapter 5 Field Case: Well A -67(1996)

5.13 Conventional Analysis Procedures for Build-up


Pressure Test.

Step (1): Prepare General Data Required for the Analysis.

General Information

Company Eni Oil Company


Field Name Abu-Attufil
Well No A-67
Test Date January 28, 1996
Test Type Buildup Test.

Well Information

Well Orientation Vertical


Well Completion Open Hole
Last Oil Production Rate, q 684 STB/day
Water Production Rate, qw 0
Water Cut, W.C 0
Producing Time, tp 1500 hrs
Well Radius, rw 0.25 ft
Drainage Area, A 103 acre

Rock Properties

Layer Net Thickness, h 59 ft


Layer Porosity, ø 11 %
Total Compressibility, Ct 2.15×10-5 /psi

Fluid Properties

Oil Formation Volume Factor, Bo 1.86 res bbl/STB


Water Formation Volume Factor, Bw 1.05 res bbl/STB

196
Chapter 5 Field Case: Well A -67(1996)

Oil Viscosity, μo 0.31 cp


Water Viscosity, μw 1.00 cp

The pressure data versus time data (i.e. Pws vs. ∆t) is shown in
table (B-12), Appendix-B

1.1) Read in the pressure test data (i.e. Pws vs. ∆t) and for each
data point calculate the corresponding value of (Pws-Pwf), (d
(ΔPws)/d (log ∆t)), ((t+∆t)/∆t): Horner time), (d (ΔPws)/d (log
((t+∆t)/ ∆t)). As shown in table (B-12), Appendix-B

Step (2): Identification of Wellbore Storage Effect and Flow


Periods.

2.1) Prepare a log-log plot of pressure drop (Pws-Pwf) and PD' vs.
∆t, as shown in figure (C-45).

2.2) From the log-log plot of (Pws-Pwf) vs. ∆t, unit slope line is not
evident then there is no wellbore storage effect. The plot is shown
in figure (C-46).

2.3) Prepare a pressure derivative (d (ΔPws)/d (log ((t+∆t)/ ∆t)) vs.


∆t on a log-log graph. The plot is shown in figure (C-47).

2.4) From figure (C-47), two flow periods can be clearly


identified:

¾ The radial flow appearing as horizontal line during the


period (1.00 – 4.00) hours.

¾ The linear flow period appearing as a half unit slope line


approximately during the period (20.00 – 100.00) hours.

Note: This case is similar to a well producing from a parallel fault


system (a long narrow reservoir).

197
Chapter 5 Field Case: Well A -67(1996)

Step (3): Analysis of the Radial Flow Period.

3.1) Plot pressure data versus Horner time function, Pws vs.
((t+∆t)/ ∆t)) on semi-log paper as shown in figure (C-49), the
slope of the semi-log plot should also be shown on the same graph
to enhance the recognition of the radial flow periods and their
duration.

3.2) The semi-log plot of Pws vs. ((t+∆t)/ ∆t)) and of its slope,
shows clearly that the Horner time from (tH=102.00) to (tH
=26.25) can be fitted to a semi-log straight line as shown in figure
(C-49). This could be interpreted as the effect of radial flow.

3.3) Read the slope directly from the plot, m = 33.14 psi/cycle.

m = 33.14 psi/cycle.

3.4) From this flow period the equivalent permeability (k) can be
calculated:

⎛q μ B⎞ = ⎛ 684 × 0.31 × 1.86 ⎞


k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 33.14 × 59 ⎠

k=32.80 md.

3.5) From this flow period the equivalent permeability (kw) can be
calculated:

⎛q μ B⎞ = ⎛ 0 × 1.05 × 1.00 ⎞
k = 162.6 ⎜ ⎟ 162.6 × ⎜ ⎟
⎝ mh ⎠ ⎝ 33.14 × 59 ⎠

k=0 md.

198
Chapter 5 Field Case: Well A -67(1996)

Step (4): Analysis of Linear Flow Period.

4.1) Plot pressure data versus ( tp + Δt − Δt ) on linear paper as


shown in figure (C-48), the slope of the linear plot should also be
shown on the same graph to enhance the recognition of the linear
flow periods and their duration.

4.2) The linear plot of Pws vs. ( tp + Δt − Δt ) and of its slope,


shows clearly that the square root time from
[ ( tp + Δt − Δt ) =6.88] to [ ( tp + Δt − Δt ) =4.20] can be
fitted to a linear straight line as shown in figure (C-48). This could
be interpreted as the effect of a linear flow.

4.3) Read the slope directly from the plot, mL=18.32 psi/hr0.5.

4.4) The average width of the linear flow channel:

0.638 qBm
w=
mL hφ ct

0.638 684 × 1.86 × 32.14


w=
18.32 59 × 0.11 × 2.15 × 10 − 5

w =596 ft.

Step (5): Skin Factor Calculations.

5.1) Extrapolate the straight line in figure (C-49) to ∆t=1 hour,


(i.e. ((t+∆t)/∆t) =102), and read, P1hr , and then calculate ΔP1hr :

Pws (1hr) =6318 psi, and Pwf = 4908 psi

ΔP1hr = P 1hr - Pwf= 6318 - 4908 = 1410 psi

199
Chapter 5 Field Case: Well A -67(1996)

⎛ P − Pwf k ⎞
S = 1.151⎜⎜ 1hr − log + 3. 23 ⎟⎟
⎝ m φμcrw
2

⎡ 1410 ⎛ 32.80 ⎞ ⎤
S = 1.151 × ⎢ - log ⎜ -5 2 ⎟ + 3.23 ⎥
⎣ 33.14 ⎝ 0.11 × 0.31 × 2.15 × 10 × 0.25 ⎠ ⎦

S= 39.75

In this case the high value of skin factor mainly means that the well
had high damage.

5.2) Calculation pressure drop due to skin effect:

ΔPs=0.87mS =0.87 × 33.14 × 39.75

ΔPs = 1146 Psi.

Step (6): False Reservoir Pressure Calculations.

6.1) Extrapolate the straight line portion to ((t+∆t)/∆t)=1 and read


the false pressure, P*= 6318 psi.

P*= 6318 psi.

Step (7): Dimensionless Calculations.

7.1) Dimensionless Time Calculations:

kt
t DA = 0.000264
φμct A

32.80 × 101.00
t DA = 0.000264 ×
0.11 × 0.31 × 2.15 × 10 -5 × 103 × 43560

tDA= 0.27

200
Chapter 5 Field Case: Well A -67(1996)

7.2) Dimensionless Pressure Drop Calculations:

Assuming the well to be in the center of a circular drainage area,


choose the appropriate MBH type curve (figure (D-2)). Enter with
the calculated value of tDA = 0.27, and read the corresponding
value of the dimensionless pressure drop, ΔPD(MBH)= 2.20

ΔPD(MBH)= 2.20

Step (8): Average Pressure Calculations.

m
P = P* - × PD( MBH )
2.303

33.14
P = 6318 - × 2.2
2.303

P =6286 psi

Step (9): Flow Efficiency Calculations.

P - Pwf - ΔPs
FE =
P - Pwf

6286 - 4907 - 1146


FE =
6286 - 4907

FE= .1690 =16.90 %

From our interpretation, we note that the well has low flow
efficiency due to high damage or high pressure drop due to skin.

201
Chapter 5 Field Case: Well A -67(1996)

Step (10): Productivity Index Calculations

10.1) Theoretical Productivity Index Calculations:

7.08 × 10 −3 × k × h
PI theoretical =
⎛ ⎛r ⎞ 3 ⎞
μo × Bo × ⎜⎜ ln⎜⎜ e ⎟⎟ - + S ⎟⎟
⎝ ⎝ rw ⎠ 4 ⎠

7.08 × 10 -3 × 32.80 × 59
PI theoretical =
⎛ ⎛ 1200 ⎞ 3 ⎞
0.31 × 1.86 × ⎜ ln⎜ ⎟ - + 39.75 ⎟
⎝ ⎝ 0.25 ⎠ 4 ⎠

PI(theoretical)=0.50 BOPD/Psi.

10.2) Actual Productivity Index Calculation (based on pressure


build-up test data):

q
PI actual ( 6330 Psi ) =
( Pr - Pwf )

684
PI actual ( 6330 Psi ) =
(6330 - 4907 )

PI(actual)=0.48 BOPD/Psi.

10.3) Actual Productivity Index Calculation (based on average


reservoir pressure estimated):

q
PI( actual 6286 Psi ) =
( Pr - Pwf )

684
PI( actual 6286 Psi ) =
(6286 - 4907)

202
Chapter 5 Field Case: Well A -67(1996)

PI(actual)=0.49 BOPD/Psi.

The following table summarizes the Productivity Index estimation


for each method:

Method Result
Theoretical Productivity Index, (PITheoretical) 0.50
Actual Productivity Index, (PI Actual 6330) 0.48
Actual Productivity Index, (PI Actual 6286) 0.49

From the results above, we note that the high consistency in the
evaluation of Productivity Index for each method, the average
Productivity Index being (0.49)

Step (11): Radius of Investigation Calculations

k ×t
rinv =
948 × φ × μο × ct

32.80 × 101.00
rinv =
948 × 0.11 × 0.31 × 2.15 × 10 -5

rinv=2183 ft

From log-log plot in figure (C-45), we can indicate or see the


effect of the outer boundary, also, when we calculate the radius of
investigation founded that the radius of investigation is greater
than the drainage radius (the test reaches to the outer boundary
because (rinv> re)

203
Chapter 5 Field Case: Well A -67(1996)

The following tables summarize the results obtained from pressure


build-up interpretation.

Flow Pressure Behavior Indicators

Wellbore Storage NO Wellbore Storage Effect


Radial Flow Clearly indicates during period
(1.00-4.00)hours
Linear Flow Clearly indicates during period
(20.00-100.00)hours
Outer Boundary Appear

Test Results

Parameter Result Unit


Slope, (m) 33.14 psi/cycle
Effective Permeability to Oil, (ko) 32.80 md
Effective Permeability to Water, (kw) 0 md
Skin, (S) 39.75 #
Pressure Drop due to Skin, (ΔPs) 1146 Psi
False Reservoir Pressure, (P*) 6305 Psi
Dimensionless Time, (tDA) 0.27 #
Dimensionless Pressure Drop, (ΔPD)MBH 2.20 #
Average Pressure, ( P ) 6286 Psi
Flow Efficiency, (FE) 16.90 %
Theoretical 0.50 BOPD/Psi
Productivity
Actual6330 0.48 BOPD/Psi
Index, PI
Actual6286 0.49 BOPD/Psi
Radius of Investigation, (rinv) 2183 ft

204
Chapter Six

Conclusions
and
Recommendations
Chapter 6 Conclusions and Recommendations

Conclusions and Recommendations

6.1 Conclusions

The work presented in this study can be summarized as


follows:

1. Only Well Testing provides information on the Dynamic


Behavior of the well and/or reservoir; as a function of oil
production, water cut, and average reservoir pressure.

2. The pressure response, which depends on the rock and fluid


properties beyond the wellbore, is then used to describe the
unknown reservoir system; and performed to improve the
characterization of the reservoir.

3. Well tests are performed on any well to evaluate well


productivity. Generally; during our analysis and
interpretation we note the values of productivity index from
theoretical and actual (based on average reservoir pressure
estimated) closed of each to which, also we recommended to
use average reservoir pressure estimated to evaluate the
productivity index.

4. The average value of reservoir permeability in the range


between (20-150 md), and productivity index between (1.5-3
BOPD/Psi); that is depending on well condition, well
location, reservoir rock and fluid properties.

5. There are different values of parameters estimated for each


well at different times due to the depletion of reservoir
pressure, which caused decreasing in oil production or
increase in value of water cut.

6. The well has high value of skin factor or high pressure drop
due to skin has low value of productivity index or vice versa.

206
Chapter 6 Conclusions and Recommendations

7. The main flow regimes that had detected in these reservoirs


are volumetric behavior, radial flow, and linear flow.

207
Chapter 6 Conclusions and Recommendations

6.2 Recommendations

From the course of this work, the following are the main
recommendation in build-up tests:

1. We recommend using the average reservoir pressure to


evaluate the productivity index.

2. At least two digital gauges should be used instead of


Amerada gauge to measure the pressure test data to get clear
flow regimes.

3. We recommend in build-up tests, downhole shut-in should be


performed in order to minimize the effect of wellbore storage
on the quality of the test, and to better identify the flow
regimes.

208
Appendix-A
Appendix-A Nomenclature

Nomenclature
∆t = Shut-in time, (hour)
∆tend = End of duration time, (hour)
∆ts = shut-in time at static pressure, (hour)
A = Drainage area, (ft2)
Awb = Area of wellbore, (ft2)
C = Wellbore storage coefficient, (bbl/psi)
CA = Shape factor conversion constant
Ce =
Cf =
Cg = Gas compressibility, (psi-1)
Co = Oil compressibility, (psi-1)
Ct = Total compressibility, (psi -1)
Cw = Water compressibility, (psi-1)
Cwb = Compressibility of fluid in wellbore, (psi-1)
d = Distance to fault, (feet)
Ei =
g = Acceleration of gravity, (32.2 ft/sec2)
gc = Gravitational constant, (32.2 lbf ft/sec2/lbm)
h = Formation thickness, (feet)
hp = Thickness of the perforated interval, (feet)
ht = Total thickness of the formation, (feet)
k = Absolute permeability,(md)
kg = Effective permeability to gas, (md)

210
Appendix-A Nomenclature

kh = Horizontal permeability, (md)


ko = Effective permeability to oil,(md)
kskin = Permeability of disturbed zone
kv = Vertical permeability, (md)
kw = Effective permeability to water,(md)
Kx = Permeability in x-direction, (md)
Ky = Permeability in y-direction, (md)
Kz = Permeability in z-direction, (md)
mL = Slope of the linear plot of (Pws vs. )
mR = slope of the semi-log plot of (Pws vs )
n = Number of rate changes
Np = Cumulative oil production, (STB)
P = Pressure, (psi)
P1hr = Extrapolating Pws from straight line to ∆t= 1 hr, (psi)
Pext = Extrapolated pressure of semi-log straight line
Pi = Initial reservoir pressure, (psi)
Pobs = Observed actual pressure, (psi)
Pw =
Pwf = Flowing wellbore pressure, (psi)
Pws = Shut-in wellbore pressure, (psi)
q = Oil production rate, (STB/day)
q* = Pseudo flow rate, , (STB/day)
qi = Average flow rate during the period ti to ti+1, (STB/day)
Last oil production rate before the shut of reservoir,
qlast (STB/day)

211
Appendix-A Nomenclature

qsf = Flow rate into wellbore at sand face, (STB/D)


re = Drainage radius, (feet)
rskin = Wellbore radius of disturbed zone, (feet)
rw = Wellbore radius, (feet)
rwa Apparent wellbore radius, (feet)
S = Skin
SD = Mechanical skin factor due to damage or stimulation
Total skin factor calculated from the build-up or draw
St = down test
t = Flowing time, (hour)
t* = Pseudo flowing time, (hour)
teL = End time of linear flow, (hour)
tp = Producing time, (hour)
tpDA = Dimensionless production time of the system, (hour)
tpss = Time required to reach pseudo-steady state, (hour)
v = Velocity,(ft/sec)
Vwb = Wellbore volume, (bbl)
βg = Gas formation volume factor, (scf/STB)
βo = Oil formation volume factor, (res bbl/STB)
βw = Water formation volume factor, (bbl/STB)
ΔP = Pressure drop, (psi)
ΔPs = Pressure drop due to skin, (psi)
Δtesl = shut-in time at the end of the first line segment
Δtx = shut-in time read at the intersection of the two semi-log
straight lines.

212
Appendix-A Nomenclature

η = Hydraulic diffusivity index


μg = Water viscosity,(cp)
μo = Oil viscosity,(cp)
μw = Water viscosity,(cp)
ρwb = Density of fluid in wellbore, (lbm/ft3)
τ = Superposition time,(hour)

Latin Abbreviation

α = Time parameter defined by (α =157.952 φ μ ct)


μ = Oil viscosity, (cp)
φ = Porosity, fraction
λt = total mobility of the system
α = matrix fracture geometric factor

213
Appendix-B
Appendix-B Pressure Test Data: Well B -27/1966

Table: (B-1)

Buildup Test Data (Pressure vs. Time) of Well: B-27 (1966) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 2179.0 0.0 --- --- ---
0.25 2904.0 725.0 25347.00 4209.55 4209.55
0.30 3560.0 1381.0 21122.67 5405.94 3815.56
0.45 4005.0 1826.0 14082.11 1388.99 1682.02
1.00 4092.0 1913.0 6337.50 187.35 322.27
1.25 4104.0 1925.0 5070.20 267.39 243.89
1.30 4111.0 1932.0 4875.23 247.65 198.24
1.45 4115.0 1936.0 4371.00 49.33 67.14
2.00 4117.0 1938.0 3169.25 32.72 36.01
3.00 4126.0 1947.0 2113.17 53.57 49.78
4.00 4133.0 1954.0 1585.13 48.65 45.08
5.00 4137.0 1958.0 1268.30 20.64 26.58
6.00 4137.0 1958.0 1057.08 29.87 30.37
7.00 4141.0 1962.0 906.21 38.50 38.50
8.00 4142.0 1963.0 793.06 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

216
Appendix-B Pressure Test Data: Well B -27/1973

Table: (B-2)

Buildup Test Data (Pressure vs. Time) of Well: B-27 (1973) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 1488.0 0.0 --- --- ---
1.00 2358.0 870.0 57011.73 499.37 499.37
2.00 2615.0 1127.0 28506.37 537.61 414.24
3.00 2654.0 1166.0 19004.58 142.75 207.58
4.00 2662.0 1174.0 14253.68 52.65 68.70
5.00 2666.0 1178.0 11403.15 45.90 45.32
6.00 2670.0 1182.0 9502.79 32.73 30.72
7.00 2671.0 1183.0 8145.39 7.47 13.74
8.00 2671.0 1183.0 7127.34 19.55 17.81
9.00 2673.0 1185.0 6335.53 19.55 21.82
10.00 2673.0 1185.0 5702.07 36.24 40.23
11.00 2676.0 1188.0 5183.79 75.93 65.91
12.00 2679.0 1191.0 4751.89 62.10 64.70
14.00 2682.0 1194.0 4073.20 65.52 71.55
16.00 2687.0 1199.0 3564.17 111.53 103.94
18.00 2694.0 1206.0 3168.26 112.13 112.13
20.00 2698.0 1210.0 2851.54 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

217
Appendix-B Pressure Test Data: Well B -27/1975

Table: (B-3)

Buildup Test Data (Pressure vs. Time) of Well: B-27 (1975) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 1141.0 0.0 --- --- ---
1.00 2045.0 904.0 98446.44 719.79 719.79
2.00 2433.0 1292.0 49223.72 900.00 691.76
3.00 2523.0 1382.0 32816.15 311.58 394.98
4.00 2537.0 1396.0 24612.36 123.10 160.47
5.00 2550.0 1409.0 19690.09 123.90 116.57
6.00 2559.0 1418.0 16408.57 79.24 84.32
7.00 2562.0 1421.0 14064.63 65.52 69.58
8.00 2567.0 1426.0 12306.68 72.43 63.76
9.00 2570.0 1429.0 10939.38 39.75 42.72
14.00 2574.0 1433.0 7032.82 27.67 27.83
16.00 2576.0 1435.0 6153.84 27.02 25.45
18.00 2577.0 1436.0 5470.19 20.70 26.03
20.00 2578.0 1437.0 4923.27 47.17 47.17
22.00 2581.0 1440.0 4475.79 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

218
Appendix-B Pressure Test Data: Well B -27/1983

Table: (B-4)

Buildup Test Data (Pressure vs. Time) of Well: B-27 (1983) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 2675.2 70.9 --- --- ---
0.08 2759.1 154.8 2372288.50 135.38 135.38
0.17 2776.9 172.6 1116371.59 181.28 136.39
0.25 2788.9 184.6 759133.00 73.07 89.04
0.50 2794.3 190.0 379567.00 35.26 39.81
0.75 2799.2 194.9 253045.00 34.94 35.23
1.00 2802.1 197.8 189784.00 34.57 33.96
1.25 2804.7 200.4 151827.40 31.38 32.37
1.50 2807.0 202.7 126523.00 33.60 33.66
1.75 2811.1 206.8 108448.43 35.96 33.98
2.25 2812.2 207.9 84349.00 25.09 24.98
2.75 2813.2 208.9 69013.00 13.20 16.68
3.25 2815.0 210.7 58395.77 21.37 22.73
3.75 2817.6 213.3 50609.80 38.40 34.99
4.25 2820.2 215.9 44655.82 38.08 35.26
5.25 2821.2 216.9 36150.14 20.77 22.27
6.25 2822.3 218.0 30366.28 15.14 16.99
7.25 2823.6 219.3 26177.97 20.12 19.22
8.25 2824.4 220.1 23005.00 19.63 19.59
9.25 2825.4 221.1 20518.08 19.27 18.88
10.25 2826.4 222.1 18516.41 17.67 17.99
12.25 2828.0 223.7 15493.49 18.64 20.05
14.25 2830.0 225.7 13319.11 29.71 26.87
16.25 2675.2 70.9 11679.95 23.48 23.34

219
Appendix-B Pressure Test Data: Well B -27/1983

Horner ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf PD’ ⎜⎜ ⎟⎟
time ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
18.25 2830.6 226.3 10400.07 17.02 17.32
20.25 2831.6 227.3 9373.00 11.07 12.94
22.25 2831.6 227.3 8530.57 17.39 16.55
24.25 2832.9 228.6 7827.10 17.39 16.37
26.25 2832.9 228.6 7230.83 12.54 18.14
28.25 2833.7 229.4 6718.98 41.16 41.16
30.25 2835.4 231.1 6274.82 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

220
Appendix-B Pressure Test Data: Well B -42/1966

Table: (B-5)

Buildup Test Data (Pressure vs. Time) of Well: B-42 (1966) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 2731.0 0.0 --- --- ---
0.25 3238.0 507.0 7682.24 893.12 893.12
0.30 3372.0 641.0 6402.03 1061.96 767.96
0.45 3448.0 717.0 4268.36 289.33 375.02
1.00 3499.0 768.0 1921.31 279.49 298.77
2.00 3623.0 892.0 961.16 438.79 414.51
3.00 3705.0 974.0 641.10 460.95 455.13
4.00 3762.0 1031.0 481.08 455.13 456.09
5.00 3806.0 1075.0 385.06 454.34 458.61
6.00 3842.0 1111.0 321.05 481.26 479.27
7.00 3876.0 1145.0 275.33 495.35 492.53
8.00 3904.0 1173.0 241.04 495.55 495.55
9.00 3930.0 1199.0 214.37 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

222
Appendix-B Pressure Test Data: Well B -42/1972

Table: (B-6)

Buildup Test Data (Pressure vs. Time) of Well: B-42 (1972) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 1418.0 0.0 --- --- ---
1.00 1629.0 211.0 62372.82 416.21 416.21
2.00 1869.0 451.0 31186.91 710.97 576.71
3.00 1979.0 561.0 20791.61 528.44 545.18
4.00 2033.0 615.0 15593.96 422.48 439.65
5.00 2073.0 655.0 12475.36 402.13 403.72
6.00 2104.0 686.0 10396.30 389.94 388.52
7.00 2130.0 712.0 8911.26 366.62 370.51
8.00 2150.0 732.0 7797.48 367.93 366.84
9.00 2170.0 752.0 6931.20 359.40 354.23
10.00 2185.0 767.0 6238.18 320.94 314.15
11.00 2198.0 780.0 5671.17 236.42 239.81
12.00 2204.0 786.0 5198.65 169.01 188.69
14.00 2216.0 798.0 4456.13 218.95 226.53
16.00 2231.0 813.0 3899.24 315.05 311.40
18.00 2250.0 832.0 3466.10 393.34 397.34
20.00 2269.0 851.0 3119.59 901.84 901.84
20.20 2275.0 857.0 3088.71 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

223
Appendix-B Pressure Test Data: Well B -42/1973

Table: (B-7)

Buildup Test Data (Pressure vs. Time) of Well: B-42 (1973) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
1.00 1233.0 0.0 --- --- ---
2.00 1276.0 43.0 39930.70 463.26 463.26
3.00 1414.0 181.0 26620.80 1728.50 1493.53
4.00 1748.0 515.0 19965.85 1522.39 1335.88
5.00 1784.0 551.0 15972.88 356.23 580.47
6.00 1811.0 578.0 13310.90 394.55 410.71
7.00 1841.0 608.0 11409.48 534.45 514.46
8.00 1877.0 644.0 9983.42 554.76 536.99
9.00 1902.0 669.0 8874.27 473.84 487.45
10.00 1923.0 690.0 7986.94 471.06 471.03
11.00 1943.0 710.0 7260.94 466.52 468.99
12.00 1960.0 727.0 6655.95 471.40 466.85
14.00 1993.0 760.0 5705.24 444.77 475.33
16.00 2016.0 783.0 4992.21 608.84 557.99
18.00 2058.0 825.0 4437.63 443.32 432.15
20.00 2061.0 828.0 3993.97 315.94 315.94
21.00 2073.0 840.0 3803.83 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

224
Appendix-B Pressure Test Data: Well B -42/1980

Table: (B-8)

Buildup Test Data (Pressure vs. Time) of Well: B-42 (1980) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 1387.0 0.0 --- --- ---
0.02 1397.0 10.0 9909189.50 136.05 136.05
0.04 1478.0 91.0 4954595.25 206.77 168.44
0.05 1492.0 105.0 3963676.40 153.62 167.35
0.10 1541.0 154.0 1981838.70 146.69 152.42
0.15 1564.0 177.0 1321226.13 177.36 179.45
0.20 1592.0 205.0 990919.85 215.24 207.70
0.25 1612.0 225.0 792736.08 216.85 222.27
0.30 1630.0 243.0 660613.57 245.73 244.11
0.40 1663.0 276.0 495460.43 266.21 239.22
0.50 1689.0 302.0 396368.54 170.69 183.82
1.00 1711.0 324.0 198184.77 220.84 207.75
1.30 1753.0 366.0 152450.05 267.15 239.45
2.00 1784.0 397.0 99092.89 264.07 253.38
2.30 1806.0 419.0 86167.86 254.89 234.01
3.00 1823.0 436.0 66062.26 169.71 190.62
4.00 1847.0 460.0 49546.94 250.83 246.76
5.00 1877.0 490.0 39637.75 306.33 297.05
6.00 1901.0 514.0 33031.63 311.63 313.71
8.00 1941.0 554.0 24773.97 330.34 321.70
10.00 1974.0 587.0 19819.38 290.24 293.96
12.00 1993.0 606.0 16516.31 276.82 281.79
14.00 2014.0 627.0 14156.98 286.17 277.63
16.00 2029.0 642.0 12387.49 246.62 246.84

225
Appendix-B Pressure Test Data: Well B -42/1980

⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf Horner time PD’ ⎜⎜ ⎟⎟
⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
18.00 2041.0 654.0 11011.21 204.71 215.95
20.00 2049.0 662.0 9910.19 232.37 229.30
22.00 2061.0 674.0 9009.35 237.57 237.57
24.00 2068.0 681.0 8258.66 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

226
Appendix-B Pressure Test Data: Well B -45/1972

Table: (B-9)

Buildup Test Data (Pressure vs. Time) of Well: B-45 (1972) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 1324.4 0.0 --- --- ---
1.00 2565.7 1241.3 50301.34 433.44 433.44
2.00 2764.3 1440.0 25151.17 424.05 351.11
3.00 2802.8 1478.4 16767.78 189.47 234.14
4.00 2817.6 1493.2 12576.09 142.38 152.13
5.00 2839.2 1514.8 10061.07 169.57 199.70
6.00 2851.1 1526.8 8384.39 126.53 136.70
7.00 2858.0 1533.6 7186.76 134.47 136.72
8.00 2867.7 1543.3 6288.54 152.96 142.11
9.00 2874.8 1550.4 5589.93 106.87 109.95
10.00 2878.2 1553.8 5031.03 78.56 73.97
11.00 2881.6 1557.2 4573.76 43.83 44.29
16.00 2882.5 1558.1 3144.77 19.36 26.18
18.00 2884.2 1559.8 2795.46 60.20 55.20
20.00 2888.1 1563.8 2516.02 77.92 72.94
22.00 2891.0 1566.6 2287.38 34.43 34.43
22.05 2891.0 1566.6 2282.19 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

228
Appendix-B Pressure Test Data: Well B -45/1983

Table: (B-10)

Buildup Test Data (Pressure vs. Time) of Well: B-45 (1983) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 2532.2 0.0 --- --- ---
0.08 2618.8 86.6 4978895.38 129.42 129.42
0.16 2691.4 159.2 2489448.19 167.28 167.28
0.25 2709.5 177.3 1593247.20 167.78 185.60
0.33 2738.7 206.5 1207005.70 260.49 249.34
0.42 2767.9 235.7 948361.83 308.44 293.41
0.50 2793.5 261.3 796624.10 261.35 276.18
0.58 2805.4 273.2 686745.05 271.88 294.30
0.83 2861.3 329.1 479894.43 420.07 397.23
1.08 2916.3 384.1 368807.99 383.71 375.91
1.33 2942.2 410.0 299483.37 312.31 339.95
1.58 2967.5 435.3 252096.92 400.32 388.27
1.83 2997.0 464.8 217657.58 427.10 409.52
2.33 3038.1 505.9 170950.16 348.68 353.25
2.83 3063.9 531.7 140747.13 306.35 311.70
3.33 3085.6 553.4 119614.08 290.17 292.58
3.83 3102.2 570.0 103998.79 289.55 286.44
4.33 3118.5 586.3 91989.81 266.72 263.96
4.83 3129.3 597.1 82467.16 228.19 230.85
5.83 3148.0 615.8 68322.02 200.96 199.62
6.83 3159.9 627.7 58318.94 164.90 167.74
7.83 3169.2 637.0 50870.93 142.54 139.41
8.83 3175.9 643.7 45109.90 106.47 107.32
10.83 3183.4 651.2 36779.54 73.54 73.64

229
Appendix-B Pressure Test Data: Well B -45/1983

⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf Horner time PD’ ⎜⎜ ⎟⎟
⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
12.83 3188.0 655.8 31046.33 45.56 47.70
14.83 3189.8 657.6 26859.50 29.25 32.65
18.83 3192.9 660.7 21154.03 32.28 31.51
22.83 3195.8 663.6 17447.85 30.17 28.77
26.83 3197.6 665.4 14846.75 19.46 23.07
30.83 3198.4 666.2 12920.61 31.17 32.08
34.83 3201.0 668.8 11436.88 47.84 40.97
38.83 3203.2 671.0 10258.83 23.30 25.36
42.83 3203.2 671.0 9300.83 11.61 13.84
46.83 3204.1 671.9 8506.48 11.61 13.23
50.83 3204.1 671.9 7837.15 22.80 23.25
54.83 3205.6 673.4 7265.48 35.88 35.87
58.83 3206.4 674.2 6771.55 54.75 54.75
61.83 3208.2 676.0 6443.04 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

230
Appendix-B Pressure Test Data: Well B -45/1984

Table: (B-11)

Buildup Test Data (Pressure vs. Time) of Well: B-45 (1984) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf tH = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.00 2454.0 0.0 --- --- ---
0.25 2637.0 183.0 1755649.40 176.40 176.40
0.50 2733.0 279.0 877825.20 372.41 372.41
0.75 2808.0 354.0 585217.13 449.07 442.51
1.00 2867.0 413.0 438913.10 504.41 500.38
1.25 2919.0 465.0 351130.68 539.82 525.39
1.50 2962.0 508.0 292609.07 488.12 491.37
1.75 2991.0 537.0 250807.91 458.00 477.55
2.00 3019.0 565.0 219457.05 544.43 528.42
2.25 3050.0 596.0 195073.04 532.49 523.49
2.50 3071.0 617.0 175565.84 471.06 477.14
2.75 3091.0 637.0 159605.40 440.06 438.40
3.00 3106.0 652.0 146305.03 399.84 414.92
3.25 3120.0 666.0 135050.88 449.93 438.98
3.50 3136.0 682.0 125404.46 432.12 426.00
3.75 3147.0 693.0 117044.23 379.79 389.99
4.00 3158.0 704.0 109729.03 386.13 379.30
4.25 3168.0 714.0 103274.44 351.04 381.22
4.50 3176.0 722.0 97537.02 501.84 466.05
4.75 3192.0 738.0 92403.55 430.48 396.64
5.00 3196.0 742.0 87783.42 160.57 208.08
5.25 3199.0 745.0 83603.30 169.78 173.78
5.50 3203.0 749.0 79803.20 202.59 180.89
5.75 3207.0 753.0 76333.54 103.60 121.22

231
Appendix-B Pressure Test Data: Well B -45/1984

⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf Horner time PD’ ⎜⎜ ⎟⎟
⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
6.00 3207.0 753.0 73153.02 112.81 164.77
6.25 3211.0 757.0 70226.94 435.71 398.64
6.50 3222.0 768.0 67525.94 536.44 496.86
6.75 3229.0 775.0 65025.01 403.48 390.97
7.00 3235.0 781.0 62702.73 189.94 210.64
7.25 3235.0 781.0 60540.60 101.88 128.91
7.50 3238.0 784.0 58522.61 172.10 167.10
7.75 3240.0 786.0 56634.82 215.27 209.12
8.00 3244.0 790.0 54865.01 219.88 207.58
8.25 3246.0 792.0 53202.47 151.96 170.75
8.50 3248.0 794.0 51637.72 196.28 196.46
8.75 3251.0 797.0 50162.38 241.75 240.45
9.00 3254.0 800.0 48769.01 271.66 265.10
9.50 3261.0 807.0 46202.27 261.28 259.20
10.00 3266.0 812.0 43892.21 230.21 229.39
10.50 3271.0 817.0 41802.15 192.23 196.03
11.00 3274.0 820.0 39902.10 177.84 190.47
11.50 3278.0 824.0 38167.27 238.86 225.59
12.00 3283.0 829.0 36577.01 219.86 210.24
12.50 3286.0 832.0 35113.97 143.32 136.57
13.00 3288.0 834.0 33763.47 58.71 66.81
15.00 3288.0 834.0 29261.81 35.68 37.19
16.00 3290.0 836.0 27433.01 54.67 53.17
17.00 3291.0 837.0 25819.36 79.42 72.49
18.00 3294.0 840.0 24385.01 60.43 64.24
19.00 3294.0 840.0 23101.64 67.34 66.74
20.00 3297.0 843.0 21946.61 67.34 63.87
21.00 3297.0 843.0 20901.58 49.50 50.25
22.00 3299.0 845.0 19951.55 49.50 44.05
24.00 3299.0 845.0 18289.00 28.20 34.32

232
Appendix-B Pressure Test Data: Well B -45/1984

⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf Horner time PD’ ⎜⎜ ⎟⎟
⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
25.00 3300.0 846.0 17557.48 58.12 52.09
27.00 3302.0 848.0 16257.00 62.14 56.76
29.00 3304.0 850.0 15135.90 32.22 34.79
31.00 3304.0 850.0 14159.45 18.41 20.99
33.00 3305.0 851.0 13301.37 18.41 25.31
35.00 3305.0 851.0 12541.35 62.15 49.18
37.00 3308.0 854.0 11863.49 62.15 55.56
45.00 3308.0 854.0 9754.60 25.26 31.16
54.00 3312.0 858.0 8129.00 67.85 59.25
57.00 3314.0 860.0 7701.21 65.59 63.51
63.00 3316.0 862.0 6967.86 60.97 63.81
69.00 3319.0 865.0 6362.04 79.39 74.94
75.00 3322.0 868.0 5853.16 71.34 73.70
81.00 3324.0 870.0 5419.67 78.25 75.25
87.00 3327.0 873.0 5045.97 65.60 68.35
93.00 3328.0 874.0 4720.48 89.79 89.79
96.00 3330.0 876.0 4573.00 --- ---

PD’ = Pressure Derivative.


tH = Horner time.

233
Appendix-B Pressure Test Data: Well A -67/1996

Table: (B-12)

Buildup Test Data (Pressure vs. Time) of Well: A-67 (1996) for the
Test Interpretation Analysis by Conventional Technique

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.000 4907.81 0.00 --- --- ---
0.006 4907.84 0.03 17315.29 #NUM! #NUM!
0.006 4907.87 0.06 16528.27 2.04 #NUM!
0.006 4907.92 0.11 15809.70 2.92 3.07
0.007 4907.98 0.17 15151.00 4.73 4.79
0.007 4908.09 0.28 14545.00 6.92 6.84
0.007 4908.22 0.41 13985.62 8.70 8.76
0.008 4908.38 0.57 13467.67 10.90 11.34
0.008 4908.57 0.76 12986.71 15.86 15.89
0.008 4908.87 1.06 12538.93 21.05 21.04
0.008 4909.20 1.39 12121.00 26.30 26.99
0.009 4909.63 1.82 11730.03 35.77 36.14
0.009 4910.20 2.39 11363.50 47.61 47.88
0.009 4910.92 3.11 11019.18 61.26 61.54
0.009 4911.81 4.00 10695.12 76.82 77.38
0.010 4912.88 5.07 10389.57 96.03 96.63
0.010 4914.19 6.38 10101.00 119.09 119.50
0.010 4915.75 7.94 9828.03 144.98 145.20
0.011 4917.59 9.78 9569.42 172.51 172.43
0.011 4919.69 11.88 9324.08 199.94 200.84
0.011 4922.04 14.23 9091.00 233.22 232.27
0.011 4924.75 16.94 8869.29 261.08 260.75

235
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.012 4927.57 19.76 8658.14 287.38 289.28
0.012 4930.69 22.88 8456.81 325.43 325.00
0.012 4934.14 26.33 8264.64 361.30 360.76
0.013 4937.82 30.01 8081.00 394.39 394.86
0.013 4941.75 33.94 7905.35 430.70 430.70
0.013 4945.95 38.14 7737.17 468.18 467.49
0.013 4950.40 42.59 7576.00 501.86 501.88
0.014 4955.03 47.22 7421.41 536.05 536.33
0.014 4959.90 52.09 7273.00 572.29 572.69
0.014 4964.97 57.16 7130.41 611.37 612.08
0.014 4970.31 62.50 6993.31 655.08 654.60
0.015 4975.91 68.10 6861.38 696.32 695.82
0.015 4981.72 73.91 6734.33 734.94 735.14
0.015 4987.73 79.92 6611.91 775.16 774.93
0.016 4993.96 86.15 6493.86 814.36 814.13
0.016 5000.36 92.55 6379.95 852.54 852.84
0.016 5006.95 99.14 6269.97 892.87 892.62
0.016 5013.73 105.92 6163.71 932.02 934.55
0.017 5020.67 112.86 6061.00 977.83 980.59
0.017 5034.98 127.17 5865.52 1040.94 1043.45
0.018 5049.83 142.02 5682.25 1110.94 1110.44
0.018 5065.13 157.32 5510.09 1179.07 1178.26
0.019 5080.86 173.05 5348.06 1243.29 1243.23
0.019 5096.89 189.08 5195.29 1308.12 1307.40
0.020 5113.32 205.51 5051.00 1369.41 1367.73
0.021 5129.93 222.12 4914.51 1421.49 1421.35
0.021 5146.69 238.88 4785.21 1473.48 1474.08
0.022 5163.61 255.80 4662.54 1529.81 1531.67

236
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.022 5180.76 272.95 4546.00 1598.14 1590.28
0.023 5198.31 290.50 4435.15 1619.48 1619.32
0.023 5215.08 307.27 4329.57 1640.81 1646.69
0.024 5232.24 324.43 4228.91 1697.45 1694.48
0.024 5249.37 341.56 4132.82 1736.97 1746.37
0.025 5266.53 358.72 4041.00 1803.66 1809.56
0.028 5351.14 443.33 3637.00 1909.02 1912.56
0.031 5432.64 524.83 3306.45 2007.93 2001.22
0.033 5509.99 602.18 3031.00 2070.58 2065.29
0.036 5582.79 674.98 2797.92 2103.68 2098.29
0.039 5650.80 742.99 2598.14 2105.18 2099.74
0.042 5713.64 805.83 2425.00 2073.64 2069.93
0.044 5771.10 863.29 2273.50 2018.60 2015.73
0.047 5823.42 915.61 2139.82 1944.29 1936.36
0.050 5870.62 962.81 2021.00 1832.85 1825.71
0.054 5931.95 1024.14 1865.62 1673.82 1666.68
0.058 5982.91 1075.10 1732.43 1479.69 1477.79
0.063 6024.14 1116.33 1617.00 1267.06 1269.77
0.067 6056.60 1148.79 1516.00 1064.07 1068.69
0.071 6082.14 1174.33 1426.88 882.62 887.22
0.075 6101.88 1194.07 1347.67 723.83 729.81
0.079 6117.20 1209.39 1276.79 596.91 602.19
0.083 6129.26 1221.45 1213.00 498.64 502.78
0.088 6138.92 1231.11 1155.29 422.96 425.92
0.092 6146.80 1238.99 1102.82 363.37 365.66
0.096 6153.30 1245.49 1054.91 316.32 316.05
0.100 6158.77 1250.96 1011.00 273.83 274.11
0.108 6167.52 1259.71 933.31 231.81 230.75

237
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.117 6174.34 1266.53 866.71 189.39 186.86
0.125 6179.34 1271.53 809.00 129.82 133.39
0.133 6181.94 1274.13 758.50 90.82 97.96
0.142 6184.28 1276.47 713.94 93.58 94.24
0.150 6186.72 1278.91 674.33 100.25 99.60
0.158 6189.12 1281.31 638.89 103.18 102.76
0.167 6191.44 1283.63 607.00 103.77 103.19
0.183 6195.72 1287.91 551.91 100.79 100.34
0.200 6199.43 1291.62 506.00 95.12 95.14
0.217 6202.63 1294.82 467.15 89.37 89.53
0.233 6205.42 1297.61 433.86 84.39 84.54
0.250 6207.88 1300.07 405.00 80.12 80.28
0.267 6210.07 1302.26 379.75 76.67 76.76
0.283 6212.05 1304.24 357.47 73.66 73.66
0.300 6213.84 1306.03 337.67 70.55 70.64
0.317 6215.46 1307.65 319.95 67.94 67.79
0.333 6216.95 1309.14 304.00 64.97 64.83
0.367 6219.56 1311.75 276.45 61.03 61.00
0.400 6221.79 1313.98 253.50 57.41 57.50
0.433 6223.73 1315.92 234.08 54.16 54.19
0.467 6225.42 1317.61 217.43 50.95 51.11
0.500 6226.90 1319.09 203.00 48.60 48.66
0.533 6228.24 1320.43 190.38 46.50 46.60
0.567 6229.43 1321.62 179.24 44.96 44.15
0.600 6230.54 1322.73 169.33 38.33 39.93
0.633 6231.29 1323.48 160.47 41.56 41.30
0.667 6232.43 1324.62 152.50 45.33 43.45
0.750 6234.45 1326.64 135.67 37.99 38.39

238
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
0.833 6236.12 1328.31 122.20 35.28 35.49
0.917 6237.53 1329.72 111.18 33.70 33.80
1.000 6238.79 1330.98 102.00 32.87 32.80
1.250 6241.93 1334.12 81.80 31.48 31.44
1.500 6244.35 1336.54 68.33 29.99 30.15
1.750 6246.32 1338.51 58.71 29.37 29.41
2.000 6248.02 1340.21 51.50 28.93 29.96
2.250 6249.48 1341.67 45.89 35.03 34.66
2.500 6251.38 1343.57 41.40 38.76 37.49
2.750 6252.87 1345.06 37.73 35.20 35.58
3.000 6254.17 1346.36 34.67 33.74 33.84
3.250 6255.32 1347.51 32.08 32.85 32.87
3.500 6256.37 1348.56 29.86 32.00 32.04
3.750 6257.31 1349.50 27.93 31.38 31.47
4.000 6258.19 1350.38 26.25 31.27 31.58
4.250 6259.01 1351.20 24.76 33.10 30.66
4.500 6259.88 1352.07 23.44 19.87 21.37
4.750 6259.99 1352.18 22.26 16.03 18.94
5.000 6260.60 1352.79 21.20 29.27 27.41
5.250 6261.26 1353.45 20.24 31.66 31.76
5.500 6261.91 1354.10 19.36 34.73 34.56
5.750 6262.63 1354.82 18.57 36.77 36.23
6.000 6263.30 1355.49 17.83 35.61 35.77
6.250 6263.92 1356.11 17.16 35.39 35.47
6.500 6264.53 1356.72 16.54 35.60 35.59
6.750 6265.11 1357.30 15.96 35.74 35.94
7.000 6265.68 1357.87 15.43 37.07 37.07
7.250 6266.26 1358.45 14.93 38.39 38.15

239
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
7.500 6266.83 1359.02 14.47 38.32 38.36
7.750 6267.37 1359.56 14.03 38.54 38.59
8.000 6267.91 1360.10 13.63 39.04 38.90
8.250 6268.43 1360.62 13.24 38.74 39.11
8.500 6268.93 1361.12 12.88 40.73 40.46
8.750 6269.47 1361.66 12.54 41.06 40.86
9.000 6269.95 1362.14 12.22 40.21 40.61
9.250 6270.44 1362.63 11.92 41.74 41.67
9.500 6270.93 1363.12 11.63 42.87 42.50
9.750 6271.42 1363.61 11.36 41.73 41.87
10.000 6271.86 1364.05 11.10 41.46 41.75
10.250 6272.32 1364.51 10.85 42.95 42.63
10.500 6272.77 1364.96 10.62 42.54 42.53
10.750 6273.20 1365.39 10.40 42.07 42.15
11.000 6273.62 1365.81 10.18 42.04 42.20
11.250 6274.03 1366.22 9.98 43.00 42.82
11.500 6274.45 1366.64 9.78 42.88 42.69
11.750 6274.84 1367.03 9.60 41.66 41.92
12.000 6275.22 1367.41 9.42 42.00 42.18
12.250 6275.60 1367.79 9.24 43.44 43.35
12.500 6275.99 1368.18 9.08 44.32 44.12
12.750 6276.37 1368.56 8.92 44.03 44.12
13.000 6276.74 1368.93 8.77 44.30 44.30
13.250 6277.11 1369.30 8.62 44.54 44.84
13.500 6277.47 1369.66 8.48 46.64 46.33
13.750 6277.86 1370.05 8.35 46.83 46.51
14.000 6278.21 1370.40 8.21
14.250 6278.56 1370.75 8.09

240
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
14.500 6248.91 1341.10 7.97
14.750 6279.27 1371.46 7.85
15.000 6279.64 1371.83 7.73
15.250 6279.97 1372.16 7.62 47.06 47.40
15.500 6280.31 1372.50 7.52 47.82 47.58
15.750 6280.64 1372.83 7.41 47.14 47.38
16.000 6280.96 1373.15 7.31 47.90 47.77
16.250 6281.29 1373.48 7.22 47.88 47.88
16.500 6281.60 1373.79 7.12 47.88 48.13
16.750 6281.92 1374.11 7.03 49.37 49.11
17.000 6282.24 1374.43 6.94 49.31 49.05
17.250 6282.55 1374.74 6.86 47.65 47.78
17.500 6282.84 1375.03 6.77 46.74 47.01
17.750 6283.13 1375.32 6.69 47.41 47.27
18.000 6283.42 1375.61 6.61 47.24 47.38
18.250 6283.70 1375.89 6.53 47.91 47.62
18.500 6283.99 1376.18 6.46 46.84 46.98
18.750 6284.25 1376.44 6.39 46.64 47.07
19.000 6284.53 1376.72 6.32 49.00 48.71
19.250 6284.81 1377.00 6.25 49.64 49.19
19.500 6285.09 1377.28 6.18 47.58 48.02
19.750 6285.34 1377.53 6.11 48.22 48.21
20.000 6285.62 1377.81 6.05 48.80 48.65
20.250 6285.87 1378.06 5.99 48.50 48.50
20.500 6286.14 1378.33 5.93 48.13 48.13
20.750 6286.38 1378.57 5.87 47.79 47.94
21.000 6286.64 1378.83 5.81 48.34 48.18
21.250 6286.88 1379.07 5.75 47.96 48.28

241
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
21.500 6287.13 1379.32 5.70 49.51 49.01
21.750 6287.38 1379.57 5.64 48.07 48.57
22.000 6287.61 1379.80 5.59 49.66 49.66
22.250 6287.87 1380.06 5.54 51.22 51.05
22.500 6288.11 1380.30 5.49 51.82 51.64
22.750 6288.37 1380.56 5.44 51.32 51.14
23.000 6288.60 1380.79 5.39 49.79 50.31
23.250 6288.84 1381.03 5.34 51.39 51.40
23.500 6289.08 1381.27 5.30 53.03 52.67
23.750 6289.33 1381.52 5.25 52.49 52.49
24.000 6289.56 1381.75 5.21 51.95 51.95
24.250 6289.80 1381.99 5.16 51.36 51.17
24.500 6290.02 1382.21 5.12 49.64 50.40
24.750 6290.24 1382.43 5.08 52.44 52.06
25.000 6290.48 1382.67 5.04 52.95 52.37
25.250 6290.70 1382.89 5.00 49.99 50.18
25.500 6290.91 1383.10 4.96 48.14 48.53
25.750 6291.11 1383.30 4.92 48.62 49.22
26.000 6291.32 1383.51 4.88 52.69 51.90
26.250 6291.55 1383.74 4.85 51.96 51.96
26.500 6291.75 1383.94 4.81 51.27 45.92
26.750 6291.97 1384.16 4.78 18.31 22.41
27.000 6291.90 1384.09 4.74 10.07 16.70
27.250 6292.05 1384.24 4.71 41.43 37.51
27.500 6292.23 1384.42 4.67 49.41 48.79
27.750 6292.44 1384.63 4.64 53.67 52.82
28.000 6292.65 1384.84 4.61 52.86 53.51
28.250 6292.85 1385.04 4.58 55.96 55.52

242
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
28.500 6293.08 1385.27 4.54 56.42 55.76
28.750 6293.28 1385.47 4.51 52.96 53.39
29.000 6293.48 1385.67 4.48 52.08 52.75
29.250 6293.67 1385.86 4.45 55.24 55.02
29.500 6293.89 1386.08 4.42 57.05 56.37
29.750 6294.09 1386.28 4.39 54.80 55.02
30.000 6294.29 1386.48 4.37 53.87 53.87
30.250 6294.48 1386.67 4.34 52.94 53.40
30.500 6294.67 1386.86 4.31 54.78 54.79
30.750 6294.87 1387.06 4.28 56.64 56.17
31.000 6295.07 1387.26 4.26 55.67 55.67
31.250 6295.26 1387.45 4.23 54.69 55.17
31.500 6295.45 1387.64 4.21 56.58 56.58
31.750 6295.65 1387.84 4.18 58.49 57.75
32.000 6295.85 1388.04 4.16 55.99 56.48
32.250 6296.03 1388.22 4.13 56.45 55.94
32.500 6296.23 1388.42 4.11 53.86 54.11
32.750 6296.39 1388.58 4.08 52.80 53.30
33.000 6296.58 1388.77 4.06 54.70 54.71
33.250 6296.75 1388.94 4.04 56.67 56.93
33.500 6296.95 1389.14 4.01 60.16 58.87
33.750 6297.14 1389.33 3.99 55.94 56.98
34.000 6297.31 1389.50 3.97 57.95 57.68
34.250 6297.51 1389.70 3.95 58.34 58.08
34.500 6297.68 1389.87 3.93 57.21 57.47
34.750 6297.87 1390.06 3.91 57.60 57.07
35.000 6298.04 1390.23 3.89 54.80 55.33
35.250 6298.21 1390.40 3.87 55.19 55.46

243
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
35.500 6298.38 1390.57 3.85 57.22 56.68
35.750 6298.56 1390.75 3.83 55.96 55.96
36.000 6298.72 1390.91 3.81 54.71 58.40
36.250 6298.89 1391.08 3.79 85.14 121.74
36.375 6299.06 1391.25 3.78
36.500 6295.53 1387.72 3.77
36.625 6292.00 1384.19 3.76
36.750 6299.57 1391.76 3.75
37.000 6299.67 1391.86 3.73 42.63 326.23
37.250 6299.82 1392.01 3.71 53.18 51.19
37.500 6299.98 1392.17 3.69 51.80 51.80
37.750 6300.12 1392.31 3.68 50.42 50.71
38.000 6300.27 1392.46 3.66 50.74 51.04
38.250 6300.41 1392.60 3.64 52.86 52.86
38.500 6300.57 1392.76 3.62 54.96 54.37
38.750 6300.72 1392.91 3.61 53.53 54.13
39.000 6300.87 1393.06 3.59 55.68 55.38
39.250 6301.03 1393.22 3.57 56.03 55.42
39.500 6301.18 1393.37 3.56 52.75 53.96
39.750 6301.32 1393.51 3.54 56.76 56.77
40.000 6301.49 1393.68 3.53 60.78 59.56
40.250 6301.65 1393.84 3.51 57.46 58.07
40.500 6301.80 1393.99 3.49 57.82 57.20
40.750 6301.96 1394.15 3.48 54.40 55.03
41.000 6302.09 1394.28 3.46 54.77 55.40
41.250 6302.25 1394.44 3.45 58.88 58.26
41.500 6302.40 1394.59 3.43 59.25 59.25
41.750 6302.56 1394.75 3.42 59.60 59.28

244
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
42.000 6302.71 1394.90 3.40 58.02 58.02
42.250 6302.86 1395.05 3.39 56.42 57.40
42.500 6303.00 1395.19 3.38 60.69 60.04
42.750 6303.17 1395.36 3.36 61.01 60.69
43.000 6303.31 1395.50 3.35 59.42 60.07
43.250 6303.47 1395.66 3.34 61.74 61.08
43.500 6303.62 1395.81 3.32 60.10 60.09
43.750 6303.77 1395.96 3.31 58.42 58.76
44.000 6303.91 1396.10 3.30 58.77 58.77
44.250 6304.06 1396.25 3.28 59.09 59.09
44.500 6304.20 1396.39 3.27 59.44 60.12
44.750 6304.35 1396.54 3.26 63.89 62.17
45.000 6304.51 1396.70 3.24 58.00 58.35
45.250 6304.63 1396.82 3.23 54.19 56.27
45.500 6304.77 1396.96 3.22 62.87 60.43
45.750 6304.93 1397.12 3.21 56.86 57.91
46.000 6305.04 1397.23 3.20 57.22 57.93
46.250 6305.20 1397.39 3.18 61.75 60.69
46.500 6305.33 1397.52 3.17 59.97 60.68
46.750 6305.48 1397.67 3.16 62.43 61.71
47.000 6305.62 1397.81 3.15 60.60 61.33
47.250 6305.76 1397.95 3.14 63.11 63.11
47.500 6305.91 1398.10 3.13 65.62 64.53
47.750 6306.06 1398.25 3.12 61.56 62.29
48.000 6306.19 1398.38 3.10 61.90 61.90
48.250 6306.34 1398.53 3.09 62.20 61.84
48.500 6306.47 1398.66 3.08 60.31 60.30
48.750 6306.61 1398.80 3.07 58.36 59.86

245
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
49.000 6306.73 1398.92 3.06 65.47 63.96
49.250 6306.90 1399.09 3.05 63.47 63.10
49.500 6307.01 1399.20 3.04 59.29 61.19
49.750 6307.16 1399.35 3.03 66.44 64.15
50.000 6307.30 1399.49 3.02 59.86 61.39
50.250 6307.42 1399.61 3.01 62.50 63.27
50.500 6307.57 1399.76 3.00 69.77 67.05
50.750 6307.72 1399.91 2.99 60.74 62.30
51.000 6307.83 1400.02 2.98 61.09 61.08
51.250 6307.98 1400.17 2.97 61.34 60.56
51.500 6308.09 1400.28 2.96 56.93 59.30
51.750 6308.22 1400.41 2.95 66.74 65.55
52.000 6308.37 1400.56 2.94 69.44 68.24
52.250 6308.51 1400.70 2.93 64.96 64.55
52.500 6308.64 1400.83 2.92 58.01 59.63
52.750 6308.75 1400.94 2.91 60.75 61.56
53.000 6308.89 1401.08 2.91 68.34 65.90
53.250 6309.03 1401.22 2.90 61.29 62.10
53.500 6309.14 1401.33 2.89 59.14 60.78
53.750 6309.27 1401.46 2.88 66.84 65.60
54.000 6309.41 1401.60 2.87 67.14 67.14
54.250 6309.54 1401.73 2.86 67.46 67.88
54.500 6309.68 1401.87 2.85 70.27 69.02
54.750 6309.82 1402.01 2.84 65.54 65.12
55.000 6309.94 1402.13 2.84 58.25 60.36
55.250 6310.05 1402.24 2.83 63.63 63.20
55.500 6310.19 1402.38 2.82 66.44 65.16
55.750 6310.31 1402.50 2.81 61.62 62.90

246
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
56.000 6310.43 1402.62 2.80 64.48 63.62
56.250 6310.56 1402.75 2.80 62.16 62.59
56.500 6310.67 1402.86 2.79 62.46 62.89
56.750 6310.80 1402.99 2.78 65.33 64.90
57.000 6310.92 1403.11 2.77 65.63 65.63
57.250 6311.05 1403.24 2.76 65.91 65.91
57.500 6311.17 1403.36 2.76 66.20 66.65
57.750 6311.30 1403.49 2.75 69.15 66.92
58.000 6311.43 1403.62 2.74 58.74 60.97
58.250 6311.52 1403.71 2.73 61.73 61.72
58.500 6311.66 1403.85 2.73 64.63 64.19
58.750 6311.76 1403.95 2.72 64.96 65.85
59.000 6311.90 1404.09 2.71 70.63 69.28
59.250 6312.02 1404.21 2.70 68.22 67.76
59.500 6312.15 1404.34 2.70 63.00 63.92
59.750 6312.25 1404.44 2.69 63.30 64.22
60.000 6312.38 1404.57 2.68 69.07 67.69
60.250 6312.50 1404.69 2.68 66.59 66.59
60.500 6312.62 1404.81 2.67 64.08 64.54
60.750 6312.73 1404.92 2.66 64.35 64.82
61.000 6312.85 1405.04 2.66 67.42 66.95
61.250 6312.97 1405.16 2.65 67.70 67.70
61.500 6313.09 1405.28 2.64 67.97 67.97
61.750 6313.21 1405.40 2.64 68.25 67.30
62.000 6313.33 1405.52 2.63 62.80 64.23
62.250 6313.43 1405.62 2.62 65.95 65.95
62.500 6313.56 1405.75 2.62 69.07 69.07
62.750 6313.67 1405.86 2.61 72.26 72.26

247
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
63.000 6313.81 1406.00 2.60 75.42 75.43
63.250 6313.93 1406.12 2.60 78.66 78.66
63.500 6314.08 1406.27 2.59 81.87 80.90
63.750 6314.21 1406.40 2.58 79.27 79.27
64.000 6314.35 1406.54 2.58 76.62 76.62
64.250 6314.47 1406.66 2.57 73.98 74.47
64.500 6314.60 1406.79 2.57 74.25 75.25
64.750 6314.72 1406.91 2.56 80.53 79.03
65.000 6314.87 1407.06 2.55 77.80 76.31
65.250 6314.98 1407.17 2.55 66.11 69.61
65.500 6315.09 1407.28 2.54 75.43 75.43
65.750 6315.23 1407.42 2.54 84.78 80.74
66.000 6315.37 1407.56 2.53 69.88 69.87
66.250 6315.46 1407.65 2.52 54.92 60.51
66.500 6315.55 1407.74 2.52 73.53 70.47
66.750 6315.70 1407.89 2.51 73.74 70.67
67.000 6315.79 1407.98 2.51 55.54 60.68
67.250 6315.88 1408.07 2.50 68.16 66.09
67.500 6316.01 1408.20 2.50 68.36 68.37
67.750 6316.10 1408.29 2.49 68.66 69.18
68.000 6316.23 1408.42 2.49 72.01 70.45
68.250 6316.33 1408.52 2.48 66.01 68.63
68.500 6316.44 1408.63 2.47 75.72 75.73
68.750 6316.57 1408.76 2.47 85.49 84.44
69.000 6316.71 1408.90 2.46 88.97 87.38
69.250 6316.85 1409.04 2.46 82.90 82.90
69.500 6316.97 1409.16 2.45 76.81 78.41
69.750 6317.09 1409.28 2.45 80.31 78.70

248
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
70.000 6317.22 1409.41 2.44 74.13 74.12
70.250 6317.32 1409.51 2.44 67.94 69.02
70.500 6317.43 1409.62 2.43 68.17 68.18
70.750 6317.53 1409.72 2.43 68.43 68.43
71.000 6317.64 1409.83 2.42 68.66 67.57
71.250 6317.74 1409.93 2.42 62.34 65.07
71.500 6317.83 1410.02 2.41 72.46 71.36
71.750 6317.96 1410.15 2.41 75.98 73.78
72.000 6318.06 1410.25 2.40 66.31 67.97
72.250 6318.16 1410.35 2.40 66.54 67.10
72.500 6318.26 1410.45 2.39 70.12 69.56
72.750 6318.37 1410.56 2.39 70.35 70.91
73.000 6318.47 1410.66 2.38 73.97 72.85
73.250 6318.59 1410.78 2.38 70.82 71.39
73.500 6318.68 1410.87 2.37 71.10 72.22
73.750 6318.80 1410.99 2.37 78.11 76.41
74.000 6318.91 1411.10 2.36 74.97 75.54
74.250 6319.02 1411.21 2.36 75.23 75.23
74.500 6319.13 1411.32 2.36 75.48 76.05
74.750 6319.24 1411.43 2.35 79.18 77.45
75.000 6319.36 1411.55 2.35 72.51 74.24
75.250 6319.45 1411.64 2.34 76.26 75.68
75.500 6319.58 1411.77 2.34 76.47 76.48
75.750 6319.67 1411.86 2.33 76.77 76.76
76.000 6319.80 1411.99 2.33 76.98 75.81
76.250 6319.89 1412.08 2.32 70.24 73.16
76.500 6320.00 1412.19 2.32 81.03 78.69
76.750 6320.12 1412.31 2.32 77.75 78.34

249
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
77.000 6320.22 1412.41 2.31 78.02 79.20
77.250 6320.34 1412.53 2.31 85.38 81.82
77.500 6320.46 1412.65 2.30 71.36 74.33
77.750 6320.54 1412.73 2.30 75.22 75.21
78.000 6320.67 1412.86 2.29 79.00 77.81
78.250 6320.76 1412.95 2.29 75.69 77.49
78.500 6320.88 1413.07 2.29 83.14 80.73
78.750 6320.99 1413.18 2.28 76.15 77.36
79.000 6321.09 1413.28 2.28 76.41 77.01
79.250 6321.20 1413.39 2.27 80.29 77.85
79.500 6321.31 1413.50 2.27 69.54 71.37
79.750 6321.39 1413.58 2.27 69.80 71.02
80.000 6321.50 1413.69 2.26 77.36 77.99
80.250 6321.60 1413.79 2.26 88.72 86.25
80.500 6321.74 1413.93 2.25 85.24 83.38
80.750 6321.83 1414.02 2.25 70.66 72.51
81.000 6321.93 1414.12 2.25 67.13 68.38
81.250 6322.01 1414.20 2.24 71.11 73.61
81.500 6322.12 1414.31 2.24 90.09 87.59
81.750 6322.25 1414.44 2.24 94.11 89.71
82.000 6322.37 1414.56 2.23 71.72 74.23
82.250 6322.44 1414.63 2.23 64.41 66.93
82.500 6322.54 1414.73 2.22 72.18 70.92
82.750 6322.63 1414.82 2.22 72.41 73.05
83.000 6322.73 1414.92 2.22 76.45 75.81
83.250 6322.83 1415.02 2.21 76.68 76.68
83.500 6322.93 1415.12 2.21 76.91 78.83
83.750 6323.03 1415.22 2.21 88.72 88.73

250
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
84.000 6323.16 1415.35 2.20 100.58 95.42
84.250 6323.29 1415.48 2.20 81.45 84.68
84.500 6323.37 1415.56 2.20 81.75 84.34
84.750 6323.50 1415.69 2.19 97.57 93.02
85.000 6323.62 1415.81 2.19 86.11 86.75
85.250 6323.72 1415.91 2.18 78.52 81.14
85.500 6323.82 1416.01 2.18 86.63 85.98
85.750 6323.94 1416.13 2.18 90.82 88.85
86.000 6324.05 1416.24 2.17 83.16 83.16
86.250 6324.15 1416.34 2.17 75.46 76.78
86.500 6324.24 1416.43 2.17 75.69 77.69
86.750 6324.34 1416.53 2.16 87.90 85.24
87.000 6324.46 1416.65 2.16 84.12 83.45
87.250 6324.55 1416.74 2.16 76.35 79.02
87.500 6324.65 1416.84 2.15 84.63 81.26
87.750 6324.76 1416.95 2.15 72.72 73.39
88.000 6324.83 1417.02 2.15 64.85 69.58
88.250 6324.92 1417.11 2.14 85.36 81.98
88.500 6325.04 1417.23 2.14 85.57 84.89
88.750 6325.13 1417.32 2.14 81.75 81.75
89.000 6325.24 1417.43 2.13 77.86 79.23
89.250 6325.32 1417.51 2.13 82.23 83.60
89.500 6325.44 1417.63 2.13 94.79 89.29
89.750 6325.55 1417.74 2.13 74.37 78.51
90.000 6325.62 1417.81 2.12 78.78 78.08
90.250 6325.74 1417.93 2.12 78.94 76.86
90.500 6325.81 1418.00 2.12 66.69 70.16
90.750 6325.90 1418.09 2.11 75.23 73.14

251
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
91.000 6325.99 1418.18 2.11 71.24 73.34
91.250 6326.07 1418.26 2.11 79.86 79.86
91.500 6326.18 1418.37 2.10 88.48 84.27
91.750 6326.28 1418.47 2.10 71.81 73.21
92.000 6326.35 1418.54 2.10 63.56 67.09
92.250 6326.43 1418.62 2.09 76.48 74.36
92.500 6326.53 1418.72 2.09 76.66 76.67
92.750 6326.61 1418.80 2.09 76.89 78.32
93.000 6326.71 1418.90 2.09 85.66 84.23
93.250 6326.81 1419.00 2.08 85.89 85.89
93.500 6326.91 1419.10 2.08 86.12 86.12
93.750 6327.01 1419.20 2.08 86.35 87.79
94.000 6327.11 1419.30 2.07 95.25 91.63
94.250 6327.23 1419.42 2.07 82.44 83.89
94.500 6327.30 1419.49 2.07 78.36 80.53
94.750 6327.41 1419.60 2.07 87.26 83.62
95.000 6327.50 1419.69 2.06 74.37 77.28
95.250 6327.58 1419.77 2.06 78.97 80.43
95.500 6327.68 1419.87 2.06 92.36 89.43
95.750 6327.79 1419.98 2.05 88.18 87.44
96.000 6327.88 1420.07 2.05 79.58 81.05
96.250 6327.97 1420.16 2.05 79.78 79.04
96.500 6328.06 1420.25 2.05 75.54 76.28
96.750 6328.14 1420.33 2.04 75.75 77.24
97.000 6328.23 1420.42 2.04 84.88 82.65
97.250 6328.33 1420.52 2.04 80.60 79.85
97.500 6328.41 1420.60 2.04 71.84 74.08
97.750 6328.49 1420.68 2.03 76.53 76.53

252
Appendix-B Pressure Test Data: Well A -67/1996

t + Δt ⎛ d ( Pws ) ⎞
Δt Pws Pws - Pwf t H = PD’ ⎜⎜ ⎟⎟
Δt ⎝ d (log( t H )) ⎠
(hrs) (Psia) (Psia) # # #
98.000 6328.58 1420.77 2.03 81.24 81.24
98.250 6328.67 1420.86 2.03 85.97 85.97
98.500 6328.77 1420.96 2.03 90.72 89.21
98.750 6328.87 1421.06 2.02 86.40 85.64
99.000 6328.96 1421.15 2.02 77.50 79.02
99.250 6329.04 1421.23 2.02 77.71 78.47
99.500 6329.13 1421.32 2.02 82.48 81.72
99.750 6329.22 1421.41 2.01 82.69 82.69
100.000 6329.31 1421.50 2.01 82.89 81.35
100.250 6329.40 1421.59 2.01 73.86 75.39
100.500 6329.47 1421.66 2.00 74.06 75.61
100.750 6329.56 1421.75 2.00 83.51 83.51
101.000 6329.65 1421.84 2.00 #NUM! #NUM!

PD’ = Pressure Derivative.


tH = Horner time.

253
Appendix-B Shape Factors for Closed Drainage Areas

Table: (B-13)

Shape Factors for Various Single-Well Drainage Areas

254
Appendix-C
Appendix-C Well: B -27(1966)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100

10
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-1): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

256
Appendix-C Well: B -27(1966)

Log-Log Plot
10000

Unit Slope

NO Wellbore
Storage Effect
PD (Pws-Pwf)

1000

100
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-2): Log-Log plot of pressure drop vs. shut-in time

257
Appendix-C Well: B -27(1966)

Log-Log Plot
10000

1000
PD'

Radial Flow
100

10
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-3): Log-Log plot of pressure derivative vs. shut-in time

258
Appendix-C Well: B -27(1966)

Horner Plot
4300 4500
m = 43.22 psi/cycle
4100 4000

3500
3900
3000
3700
2500

PD'
Pws

3500
2000
3300
1500
3100
1000

2900 500

2700 0
100 1000 10000 100000
Horner time

Figure (C-4): Horner plot

259
Appendix-C Well: B -27(1973)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-5): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

260
Appendix-C Well: B -27(1973)

Log-Log Plot
10000

Unit Slope
PD (Pws-Pwf)

NO Wellbore
Storage Effect
1000

100
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-6): Log-Log plot of pressure drop vs. shut-in time

261
Appendix-C Well: B -27(1973)

Log-Log Plot
1000

Radial Flow
PD'

100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-7): Log-Log plot of pressure derivative vs. shut-in time

262
Appendix-C Well: B -27(1973)

Horner Plot
2800 600

2750
m = 55.84 psi/cycle
500
2700

2650
400
2600

PD'
Pws

2550 300

2500
200
2450

2400
100
2350

2300 0
1000 10000 100000
Horner time

Figure (C-8): Horner plot

263
Appendix-C Well: B -27(1975)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-9): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

264
Appendix-C Well: B -27(1975)

Log-Log Plot
10000

Unit Slope
PD (Pws-Pwf)

NO Wellbore
Storage Effect
1000

100
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-10): Log-Log plot of pressure drop vs. shut-in time

265
Appendix-C Well: B -27(1975)

Log-Log Plot
1000
PD'

100
Radial Flow

10
0 1 10 100
Shut-in time, (hours)

Figure (C-11): Log-Log plot of pressure derivative vs. shut-in time

266
Appendix-C Well: B -27(1975)

Horner Plot
2600 800

700
2500 m = 27.64 psi/cycle
600
2400
500

PD'
Pws

2300 400

300
2200
200
2100
100

2000 0
1000 10000 100000
Horner time

Figure (C-12): Horner plot

267
Appendix-C Well: B -27(1983)

Log-Log Plot
1000
PD (Pws-Pwf) & PD'

100

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-13): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

268
Appendix-C Well: B -27(1983)

Log-Log Plot
1000
Unit Slope

Wellbore
Storage Effect
PD (Pws-Pwf)

100

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-14): Log-Log plot of pressure drop vs. shut-in time

269
Appendix-C Well: B -27(1983)

Log-Log Plot
1000

Wellbore
PD'

Storage Effect
100

Radial Flow

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-15): Log-Log plot of pressure derivative vs. shut-in time

270
Appendix-C Well: B -27(1983)

Horner Plot
2850 160

2830
140
2810
m = 17.66 psi/cycle 120
2790

2770 100

PD'
Pws

2750 80

2730 60
2710
40
2690
20
2670

2650 0
1000 10000 100000 1000000 10000000
Horner time

Figure (C-16): Horner plot

271
Appendix-C Well: B -42(1966)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-17): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

273
Appendix-C Well: B -42(1966)

Log-Log Plot
10000

Unit Slope

NO Wellbore
Storage Effect
PD (Pws-Pwf)

1000
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-18): Log-Log plot of pressure drop vs. shut-in time

274
Appendix-C Well: B -42(1966)

Log-Log Plot
1000

Radial Flow
PD'

100
0.1 1.0 10.0
Shut-in time, (hours)

Figure (C-19): Log-Log plot of pressure derivative vs. shut-in time

275
Appendix-C Well: B -42(1966)

Log-Log Plot
4000 1000
m = 455.30 psi/cycle
3900 900

3800 800

3700 700
Pws

3600 600

3500 500

3400 400

3300 300

3200 200
100 1000 10000
Horner time

Figure (C-20): Horner plot

276
Appendix-C Well: B -42(1972)

Log-Log Plot
1000
PD (Pws-Pwf) & PD'

100
1 10 100
Shut-in time, (hours)

Figure (C-21): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

277
Appendix-C Well: B -42(1972)

Log-Log Plot
1000
Unit Slope

NO Wellbore
PD (Pws-Pwf)

Storage Effect

100
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-22): Log-Log plot of pressure drop vs. shut-in time

278
Appendix-C Well: B -42(1972)

Log-Log Plot
1000

Radial Flow
PD'

100
1 10 100
Shut-in time, (hours)

Figure (C-23): Log-Log plot of pressure derivative vs. shut-in time

279
Appendix-C Well: B -42(1972)

Horner Plot
2300 1000

900
2200
m = 371.95 psi/cycle 800
2100
700
2000 600

PD'
Pws

1900 500

400
1800
300
1700
200

1600 100
1000 10000 100000
Horner time

Figure (C-24): Horner plot

280
Appendix-C Well: B -42(1973)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100

10
1 10 100
Shut-in time, (hours)

Figure (C-25): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

281
Appendix-C Well: B -42(1973)

Log-Log Plot
1000

Unit Slope
PD (Pws-Pwf)

100

NO Wellbore
Storage Effect

10
1 10 100
Shut-in time, (hours)

Figure (C-26): Log-Log plot of pressure drop vs. shut-in time

282
Appendix-C Well: B -42(1973)

Log-Log Plot
10000
PD'

Radial Flow
1000

100
1 10 100
Shut-in time, (hours)

Figure (C-27): Log-Log plot of pressure derivative vs. shut-in time

283
Appendix-C Well: B -42(1973)

Horner Plot
2200 1600
m = 453.88 psi/cycle
2100
1400
2000

1900 1200

1800
1000

PD'
Pws

1700
800
1600

1500 600
1400
400
1300

1200 200
1000 10000 100000
Horner time

Figure (C-28): Horner plot

284
Appendix-C Well: B -42(1980)

Log-Log Plot
1000
PD (Pws-Pwf) & PD'

100

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-29): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

285
Appendix-C Well: B -42(1980)

Log-Log Plot
1000
PD (Pws-Pwf)

Unit Slope
100

NO Wellbore
Storage Effect

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-30): Log-Log plot of pressure drop vs. shut-in time

286
Appendix-C Well: B -42(1980)

Log-Log Plot
1000

Radial Flow
PD'

100
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-31): Log-Log plot of pressure derivative vs. shut-in time

287
Appendix-C Well: B -42(1980)

Horner Plot
2200 500

2100

2000
400
1900 m = 300.50 psi/cycle

1800

PD'
Pws

1700 300

1600

1500
200
1400

1300

1200 100
1000 10000 100000 1000000 10000000 100000000
Horner time

Figure (C-32): Horner plot

288
Appendix-C Well: B -45(1972)

Log-Log Plot
10000
PD (Pws-Pwf) & PD'

1000

100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-33): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

290
Appendix-C Well: B -45(1972)

Log-Log Plot
10000

Unit Slope

NO Wellbore
Storage Effect
PD (Pws-Pwf)

1000
1 10 100
Shut-in time, (hours)

Figure (C-34): Log-Log plot of pressure drop vs. shut-in time

291
Appendix-C Well: B -45(1972)

Log-Log Plot
1000

Radial Flow
PD'

100

10
1 10 100
Shut-in time, (hours)

Figure (C-35): Log-Log plot of pressure derivative vs. shut-in time

292
Appendix-C Well: B -45(1972)

Horner Plot
2950 500
m = 160.88 psi/cycle
2900

2850 400

2800
300
2750

PD'
Pws

2700
200
2650

2600 100
2550

2500 0
1000 10000 100000
Horner time

Figure (C-36): Horner plot

293
Appendix-C Well: B -45(1983)

Log-Log Plot
1000
PD (Pws-Pwf) & PD'

100

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-37): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

294
Appendix-C Well: B -45(1983)

Log-Log Plot
1000

Unit Slope

Wellbore
PD (Pws-Pwf)

Storage Effect

100

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-38): Log-Log plot of pressure drop vs. shut-in time

295
Appendix-C Well: B -45(1983)

Log-Log Plot
1000
PD'

100 Radial
Flow

10
0.01 0.10 1.00 10.00 100.00
Shut-in time, (hours)

Figure (C-39): Log-Log plot of pressure derivative vs. shut-in time

296
Appendix-C Well: B -45(1983)

Horner Plot
3300 700
m = 29.89 psi/cycle
3200 600

3100
500
3000
400

PD'
Pws

2900
300
2800
200
2700

2600 100

2500 0
1000 10000 100000 1000000 10000000
Horner time

Figure (C-40): Horner plot

297
Appendix-C Well: B -45(1984)

Log-Log Plot
1000
PD (Pws-Pwf) & PD'

100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-41): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

298
Appendix-C Well: B -45(1984)

Log-Log Plot
1000

Unit Slope

NO Wellbore
PD (Pws-Pwf)

Storage Effect

100
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-42): Log-Log plot of pressure drop vs. shut-in time

299
Appendix-C Well: B -45(1984)

Log-Log Plot
1000
PD'

Radial Flow
100

10
0.1 1.0 10.0 100.0
Shut-in time, (hours)

Figure (C-43): Log-Log plot of pressure derivative vs. shut-in time

300
Appendix-C Well: B -45(1984)

Horner Plot
3400 m =43.70 psi/cycle 700

3300 600

3200
500
3100
400

PD'
Pws

3000
300
2900
200
2800

2700 100

2600 0
1000 10000 100000 1000000 10000000
Horner time

Figure (C-44): Horner plot

301
Appendix-C Well: A -67(1996)

Log-Log Plot
10000.00

1000.00
PD (Pws-Pwf) & PD'

100.00

10.00

1.00

0.10

0.01
0.001 0.010 0.100 1.000 10.000 100.000
Shut-in time, (hours)

Figure (C-45): Log-Log plot of pressure drop and pressure derivative vs. shut-in time

303
Appendix-C Well: A -67(1996)

Log-Log Plot
10000.00

1000.00

100.00
PD (Pws-Pwf)

10.00 Unit Slope

1.00
NO Wellbore
Storage Effect
0.10

0.01
0.001 0.010 0.100 1.000 10.000 100.000
Shut-in time, (hours)

Figure (C-46): Log-Log plot of pressure drop vs. shut-in time

304
Appendix-C Well: A -67(1996)

Log-Log Plot
10000

1000
Linear Flow
Radial Flow
PD'

100

10

1
0.001 0.010 0.100 1.000 10.000 100.000
Shut-in time, (hours)

Figure (C-47): Log-Log plot of pressure derivative vs. shut-in time

305
Appendix-C Well: A -67(1996)

Linear Plot
6500 2500
mL =18.32 psi/hr0.5
6400

6300 2000

6200

6100 1500
Pws

6000

5900 1000

5800

5700 500

5600

5500 0
4 5 6 7 8 9 10
t + Δt - Δt

Figure (C-48): Linear plot of Shut-in pressure and pressure derivative vs. shut-in time

306
Appendix-C Well: A -67(1996)

Horner Plot
6500 2500
m =33.14 psi/cycle
6400

6300 2000

6200

6100 1500
Pws

6000

5900 1000

5800

5700 500

5600

5500 0
1 10 100 1000 10000
Horner time

Figure (C-49): Horner plot

307
Appendix-D
Appendix-D .

Figure (D-1): Miller-Dyes-Hutchinson dimensionless pressure for circular and square drainage area.

309
Appendix-D .

Figure (D-2): Matthews-Brons-Hazebroek dimensionless pressure for a well in the center of equilateral
drainage areas.

310
Appendix-D .

Figure (D-3): Matthews-Brons-Hazebroek dimensionless pressure for well locations in a square drainage
area.

311
Appendix-D .

Figure (D-4): Matthews-Brons-Hazebroek dimensionless pressure for different well locations in a 2:1
rectangular drainage area.

312
Appendix-D .

Figure (D-5): Matthews-Brons-Hazebroek dimensionless pressure for different well locations in 4:1 and 5:1
rectangular drainage areas.

313
Appendix-D .

0.9

R=Measured Slope Of Build-Up Data /


0.8

Theoretical Slope Of Build-up Data


0.7

0.6

0.5

0.4

0.3

0.2

0.1

0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Fracture Length / Well Spacing (Lf/D)

Figure (D-6): Correction factor for slope of pressure build-up data because of vertical fracture.

314
References
. References

References

1. Urayet, A. A.: "Advanced Topics in Transient Pressure


Analysis", Part of the Technical Program Organized for the
Petroleum Research Center, Tripoli, 2004.

2. Urayet, A. A.: "Transient Pressure Analysis", Part of the


Technical Program Organized for the Petroleum
Engineering Department, Al Fateh University, Tripoli, 2000.

3. Matthews: "Pressure Buildup and Flow Tests in Wells", pp.1-


114, 1967.

4. Tarek Ahmed and Paul D. McKinny, "Advanced Reservoir


Engineering", pp. 1-162, 2005.

5. Amanat U. Chaudhry: "Oil Well Testing Handbook",


Advanced TWPSOM Petroleum Systems, Inc, Houston,
Texas, pp.13-365, 2004.

6. Dominique Bourdet: "Well Test Analysis: the use of


Advanced Interpretation Models, pp.1-302, 2002.

316

You might also like