Professional Documents
Culture Documents
Course name: Construction Technology, Contract and Pre/co requisite (course name None
Estimating and code, if applicable):
Credit hours: 3
Course synopsis This course emphasizes on the principles of construction in building and civil engineering works,
which consists of site preparation and layout, earthwork activities, construction of various building
elements such as foundations, floors, walls, and roofs. It also covers other important aspects in
construction i.e., formworks and scaffoldings. General concepts on industrialized building systems
including precast, pre-stressed and modular coordination in construction are also introduced. The
syllabus covers an introduction to the development process and construction contracts, types of
tenders, tendering process and the preparation of tender documents, strategy in tendering,
introduction to the methods of estimating and the preparation of the Bills of Quantities and project
estimating. At the end of the course, the students should be able to describe and distinguish the
various building elements, techniques and systems used in a construction and also to be able to
understand about contract and tendering process in construction as well as to estimate the cost of
the building elements. The students should also be able to demonstrate capability of working in a
team and some acquirement of contemporary knowledge.
Course Dr. Khairulzan b. Yahya
coordinator (if
applicable)
Name: Dr. Khairulzan Yahya Name: Mr. Abdul Rahim Abdul Hamid
Signature: Signature:
Course name: Construction Technology, Contract and Pre/co requisite (course name None
Estimating and code, if applicable):
Credit hours: 3
Mapping of the Course Learning Outcomes (CLO) to the Programme Learning Outcomes (PLO), Teaching & Learning (T&L)
methods and Assessment methods:
UTM CIDU.CI.V3.2020
School/Faculty: Civil Engineering/Engineering Page: 3 of 5
Course name: Construction Technology, Contract and Pre/co requisite (course name None
Estimating and code, if applicable):
Credit hours: 3
Weekly Schedule:
Week 1 Introduction to Construction Industry and Sustainable Construction
Industrialised Building System
Week 2 Site layout – introduction and the importance of site layout
Information and preparation processes – entrance access, temporary road and parking
Temporary buildings, storage area, hoarding and preliminary works
Week 3 Introduction to construction plants and machineries
Earthwork – earthwork activities and types of plants and machineries
Week 4 Introduction to foundations
Shallow and deep foundations
Week 5 Temporary structures: Formwork and scaffolding.
Week 6 Building elements: floors, walls, roof, and ceiling
Week 7 External works: roads, paving, drainage, and turf
Assignment/Project Presentation
Week 8 Mid-Semester Break
Week 9 Introduction to contract
Contracting process.
Introduction to tender
Week 10 Type of tenders: Pre- qualification, open tender, selective /restricted tender, negotiation Tender
Tendering process and procedures
Strategy in tendering
Week 11 Contractor evaluation and selection
Estimating process
Introduction to estimating methods
Week 12 Contractor evaluation and selection
Contract administration
Types of construction contract
Week 13 Build-up rates: Introduction
Build-up rates: plants
Build-up rates: excavation
Week 14 Build-up rates: concrete
Introduction to building measurements
TEST 1
Week 15 Measurements of quantities for excavation
Measurements of quantities for concrete
Measurements of quantities for reinforcement
Transferable skills (generic skills learned in course of study which can be useful and utilised in other settings):
Team working
Written communication
UTM CIDU.CI.V3.2020
School/Faculty: Civil Engineering/Engineering Page: 4 of 5
Course name: Construction Technology, Contract and Pre/co requisite (course name None
Estimating and code, if applicable):
Credit hours: 3
CLO L T P O
CLO 1 15h 5h 19h
CLO 2 4h 16h 5h 24h
CLO 3 12h 16h 5h 32h
CLO 4 8h 24h 5h 36h
Total SLT 39h 56h 20h 115h
Special requirement to deliver the course (e.g: software, nursery, computer lab, simulation room):
None
Learning resources:
Text book (if applicable)
UTM CIDU.CI.V3.2020
School/Faculty: Civil Engineering/Engineering Page: 5 of 5
Course name: Construction Technology, Contract and Pre/co requisite (course name None
Estimating and code, if applicable):
Credit hours: 3
None
Main references
Chudley, R., Construction Technology, 5th Edition. Pearson, 2011.
Chudley, R., Advanced Construction Technology, 5th Edition 2002. Pearson, 2012
Ahamad Abdullah, Anggaran Kos Kerja Bangunan, Edisi Kedua. Pearson Malaysia Sdn. Bhd.,2006.
Alan Ashworth, Contractual Procedures in Construction Industry, 6th Edition, 2013
Additional references
Nunnally, S.W., Construction Method and Management, 8th Ed. Pearson Education, 2013
Peurifoy, R.L. and Schexnayder, C.J., Construction Planning, Equipment, and Methods. 8th Ed. McGraw Hill Education,
2010.
Brian Greenhalgh, Introduction to Construction Contract Management, 2017
Mastura Jaafar, Elementry Estimating for Building Works, Penerbit USM, 2013
Geddes, Spence, Estimating for Building and Civil Engineering, 9th Edition, Spon Press, 2013
Pratt, David. Fundamentals of Construction Estimating, Englewood, DELMAR CENGAGE Learning, 2010
Online
http://elearning.utm.my
Disclaimer:
All teaching and learning materials associated with this course are for personal use only. The materials are intended
for educational purposes only. Reproduction of the materials in any form for any purposes other than what it is
intended for is prohibited.
While every effort has been made to ensure the accuracy of the information supplied herein, Universiti Teknologi
Malaysia cannot be held responsible for any errors or omissions.
UTM CIDU.CI.V3.2020
WELCOME TO SEAA 3123
Contract
and
tendering
ASSESMENT
Overview of Construction Industry
CONSTRUCTION
The art and science to form objects, systems, or
organizations
PROJECT
“ A series of activities with a specific purpose, a starting point
and a clear end point to effectively achieve a set of objectives
by using the limited resources provided “
(Punmia P.C. & Khandelwal K.K, 1989)
Construction
General
Classification •building
•Industrial/commercial
•infrastructure
Specialized
•Electrical work
•Air conditioning
•Plumbing
•Fire resistance
Maintenance
Renovation
CATEGORIES
Demolition Rehabilitation
Petroleum & Gas
Industrial
Power
Transportation
Construction
Water Supply
Project
Category Infrastructure
Structure
Geotechnical
Building Services
Raw material
Plant &
Human Machineries
Resources
Component
Technology &
Technique Financial
DESIGN CONSIDERATION
Environment
Law
Land
contour
Available
Physical Land size
facilities
Environment
Law
Local Authority
Requirements (Local
Council)
Building
orientation Environment Building rule
Nearby land/building
DESIGN CONSIDERATION
Environment
Law
Law
• Legislation:
Uniform Building By Laws 1984
Street, Drainage and Building Act 1974
• Must comply with legal (Act 133)
Environment
Law
• The designer needs to
conduct a site visit to Site condition
see the physical
condition of the site. • Site consideration include
• Space
• Altitude
• Need to take into • Latitude and longitude positions
account the size of the • Soil Content
site, the condition of • Water content
adjacent buildings and • Nearby structures
the access road to the • Price
• Disorganized organization
• Communication status
CHARACTERISTIC OF CONSTRUCTION
INDUSTRY
• Inaccurate data
• Fluctuations in production
• Various technologies
LACK OF CO-ORDINATIONS
CONFLICT OF
INFORMATION !!
CURRENT SCENARIO OF CONSTRUCTION
INDUSTRY
• Damage
• High cost
• Project delay
The private sector continued to impel the construction activity with 53.7
per cent share or RM15.2 billion of the total value of construction work
done, as compared to the public sector with 46.3 per cent share (RM13.1
billion).
For the first half 2021, the value of construction work done
recorded RM59.6 billion, with a 8.7 per cent growth as compared to
same period last year.
CONTRIBUTION OF THE
CONSTRUCTION INDUSTRY
ENGINEER
SURVEYOR STAKEHOLDERS
CONTRACTOR
AUTHORITY
LABOUR FORCE
SUPPLIER
Construction Project Implementation Process
Construction Phase
Conceptual
Construction
PROJECT LIFE CYCLE
Occupation/
Maintenance
Post Contract
Construction
Tender
Pre Contract
Design
Project Time
PROJECT LIFE CYCLE
Project Conceptual Detail Construction Construction Operation
Feasibility Program
Phase Design Design Planning
Sketches
Data Specifi- Estimate As-Built
Output Report Drawings Drawings
cations Schedule Drawings
& Input
The Principle of Engineering
for Sustainable Development
• Measuring sustainability
• Designing for sustainability
• Optimising for sustainability
Conclusions
1
Definition
• The Industrialised Building Systems (IBS)
is a construction process that utilises
techniques, products, components, or
building systems which involve
prefabricated components and on-site
installation.
2
Introduction
4
In Malaysia, Construction Industry Development
Board (CIDB) has classified the IBS system into 5
categories as follows:
Balcony
Beams
10
Pre- cast
Concrete
Components
11
Structural Category of IBS
Group 2: Steel Formwork Systems
12
Group 2
Tilt-up system
13
Structural Category of IBS
Group 3: Steel Framing Systems
14
Structural Category of IBS
Group 4: Prefabricated Timber
Framing Systems
15
Structural Category of IBS
Group 5: Block Work Systems
16
Pre-cast Concrete
Concrete cast into
desired shapes prior
to placement in a
structure
17
Pre-cast Concrete
18
Prestressed Concrete
19
Erection
The assembly of parts put together in different
ways to form the total building fabric
The parts meet at joints or connections
Joint refers to the space between components
whether or not they are in contact
20
Frame Joints
21
Precast Frame Joints
22
Advantages of Pre-cast concrete
system (1)
High level mechanisation thus precision
No delay due to bad weather and manpower
Application of modular design in standardising
dimensions
Work done concurrently at factory and at site thus
speed up construction
Low site workers requirement due to simplified
construction methods
Quality controlled and highly aesthetic end products
Reduction of construction materials at sites
Save costs
23
Advantages of Pre-cast concrete
system (2)
25
Why MC
Provide a coherent method for coordinating the
position and dimension of components in the
planning and design of buildings
Improve productivity in building industry. MC
facilitate achievement of industrilisation
Provide guide to component sizes thus reduce
work on site eg trimming and shaping hence
reduce wastage and labour
Standardisation simplify site operation by
rationalising setting out, positioning and
assembly of building components
26
Examples: IBS
The construction of Police Station in
Senawang Negeri Sembilan:
Comprises of 1 unit of Police Station Office
Block, 4 units of Class F Quarters and 2
Units of Class G Quarters and the External
works
27
THE CONSTRUCTION OF QUARTERS G
The Block comprises of 5 Storey Building
as shown in the picture
QUARTERS G
28
NUMBERS OF PANELS USED
Precast Wall Precast Slab
Level Block Block Block Block G2
G1 G2 G1
1 91 91 0 0
2 94 94 102 102
3 94 94 102 102
4 94 94 102 102
Upper 1 1 0 0
Roof
468 468 408 408 29
CONSTRUCTION PROCESS USING PRECAST PANELS
PILING
PILE CAP
cast insitu
FLOOR SLAB
cast insitu
COLUMN
31
PREPARATION OF PILE CAP (CAST INSITU)
32
PREPARATION OF COLUMN STUMP (CAST INSITU)
33
34
35
INSTALLATION OF ‘300 MM x 25 MM DIA.- DOWEL BAR’ AT GROUND BEAM
36
CONSTRUCTION OF GROUND BEAM (CAST INSITU)
Dowel
Bar
37
‘MOULD’ FOR THE PRECAST CONCRETE PANEL WAS FABRICATED IN
THE FACTORY ACCORDING TO THE DESIGN SPECIFICATIONS
INCLUDING REQUIREMENTS FOR ELECTRICAL INSTALLATION
38
‘MOULD’ FOR THE PRECAST CONCRETE PANEL
39
CASTING PROCESS IN A FACTORY
40
41
42
WORK ON CASTING IN PROGRESS IN A FACTORY
43
COMPLETED WALL PANELS
44
PANELS TO BE TRANSPORTED TO CONSTRUCTION SITES
45
THE USE OF FULL TIME CRANE FOR THE HOISTING AND INSTALLATION OF PANELS
46
47
CAST IN SITU COLUMNS READY FOR PANEL INSTALLATION
48
ONE CRANE AND 5 SKILLED WORKERS WERE USED FOR THE INSTALLATION
OF THE PRECAST CONCRETE PANELS
49
WORKS ON INSTALLATION OF WALL PANELS USING A CRANE
50
Installation of Precast Panels
DOWEL BARS WERE SLOT TO THE HOLE SLOT UNDERNEATH THE PANEL FOR CONNECTION
51
PANELS WERE HOIST THROUGH PROPER HOOKS AND FIXED
THROUGH THE PANEL CONNECTION SLOTS 52
TEMPORARY SUPPORT WRE USED IN WALL INSTALLATION FOR
VERTICAL ALIGNMENT
53
THE USE OF PANEL-SUPPORT IS TO ENSURE THE VERTICALITY IN POSITIONING OF PANELS
54
55
CONCRETE JOINTS BETWEEN COLUMN AND WALL PANELS
56
CROSS-SECTION OF PANEL JOINT DETAIL
57
GROUTING OF THE JOINTS BETWEEN WALL AND COLUMN
58
59
COMPLETED COLUMN/PANEL JOINT
GROUTING IN PROGRESS USING GROUTING
MATERIAL‘EMCRETE S’ 60
INSTALLATION OF PRECAST FLOOR SLAB PANEL
61
FLOOR SLAB PANELS FIXED TO POSITION
62
PREPARATION OF FLOOR SLAB CONCRETE TOPPING
(CAST INSITU)
63
COMPLETED FLOOR SLAB
64
ROOF TRUSS OF QUARTERS G
65
FINISHING AND FINAL TOUCH- UP
PAINTINGS
66
QUARTERS G NEARLY COMPLETION
67
INTERNAL VIEW OF QUARTERS G
LOUNGE
DINING
KITCHEN
68
OTHER EXAMPLE OF PRECAST
CONCRETE PANELS CONSTRUCTION
69
Components delivered for this project
are as below:
Hollow Core Slab 1927.0 m2
71
SOME COMPLETED PROJECT PHOTOS USING
PRECAST CONCRETE STRUCTURE
Velodrome, Nilai
72
SOME COMPLETED PROJECT PHOTOS USING PRECAST
CONCRETE STRUCTURE
73
74
Issues And Challenges in the
Implementation of
Industrialised Building Systems
in Malaysia
• The IBS systems as mentioned
previously are not new in Malaysia. For
example, precast wall system has been
adopted in Malaysia as early as in the
late 60s.
• Lack of knowledge in
structural analysis and
design of pre-fabricated
components.
• Poor connection system.
• Steel framed buildings that
are designed to imitate the
conventional reinforced
concrete structural system
results in serviceability
problems.
Successful Implementation of IBS
Projects
• With the advanced knowledge
in computer aided design, IBS
buildings can be designed and
visualised analytically prior to
the actual construction.
• Standardisation may
lead to improvement in
quality, decrease
variability and increase
the ease of
manufacturing.
2. Investment on Heavy
Equipment for
Mechanized Construction
System
• The awareness
campaigns may include
seminars and short
courses.
4. Knowledge
• Specialized and additional
engineering knowledge will be
required to design, manufacture
and construct a good IBS
system.
Answer:
Definition: Sustainable development is development that meets the needs of
the present, without compromising the ability of future generations to meet
their own needs
(1 mark)
Answer
Brief explanation any 4 of the following challenges:
Answer:
Short explanation on any 5 of the impacts in the following on construction
activities at any construction phase
Materials
Energy
Air Pollution
Water Pollution
Waste
Resource depletion
Global warming
Ozone depletion
Acidification
Biodiversity toxicity
The cost of building green as proposed in sustainable
approach might be higher than conventional. Explain the 7
role of Civil Engineer in order to promote sustainable marks
construction despite the higher cost?
Answer:
Definition: “Sustainable construction is a practice of creating structures and using
processes that are environmentally responsible and resource-efficient”
(1 mark)
Elaboration: “High cost of building green may attribute to high initial cost for construction
which can be economically unattractive to contractor. However, building green is
important because currently, we have a very limited non-renewable resources” (2 marks)
#1 Example: “As civil engineer, cost management for building green must be planned
thoroughly, a good cost distribution can minimize the size of a building’s mechanical
systems, which saves money in the short and long terms” (2 marks)
•Introduction
•Definition
•Knowledge of the site
•Planning Site Layouts
•Conclusion
•Problem Based Learning
–Proposed Site Layout
Introduction
• The construction of a building can be considered as
production with temporary ‘factory’
• The building site being the ‘factory’ in which the building
contractor will make the product
• The building site have to be carefully controlled so that:
– The operatives have the right machines in the most advantageous
position
– The materials stored so that they are readily available and not
interfering with general site circulation
– Adequate storage space for construction materials
– Site accommodation and facilities for staff
Definition
What is Site Layout?
Site Layout can be defined as:
Site Space Allocation for
• material storage
• working areas
• units of accommodation
• plant positions
• general circulation areas
• Access and egress for deliveries and emergency
services
Knowledge of the site
• It is important to acquire the knowledge of the
site before setting out the site layout.
• The knowledge about the site can be obtained
from:
• Contract document
• Site investigation
• Information from local authority
Knowledge of the site
Knowledge from contract document:
• Plant schedule
– This can be prepared in the form of a bar chart and method statements
showing requirements and utilization which will help in deciding
equipment and space for plant accommodation will be needed on site
• Material Schedule
– Basic data can be obtained from the bill of quantities. The contractor can
predict the delivery periods and the amount of site space and/or
accommodation required.
• Labour summary
– Basic data obtained from the bill of quantities and pre-tender bar chart
programme to establish number of subcontract trades required. Also the
quantity and type of site personnel accommodation required.
Knowledge of the site
Knowledge from site investigation:
• Access to site
– On and off-site access, road and rail facilities, distances involved
and bridge weight or height limitations on approach routes.
• Staff
− Travel distances, availability of local trade contractors, specialist
contractors, local rates of pay and facilities to be provided e.g.
site accommodation, catering, health and safety equipment.
• Temporary Services
– Available power and water supplies together with rates of
payment or services already on site, diversion required and the
time element involved in carrying out any necessary diversion
together with cost implications.
Knowledge of the site
Knowledge from site investigation (Cont.):
• Security
– Local vandalism and pilfering record, security contractors
facilities, need for night security, fencing hoarding requirements
to prevent trespass and to protect people in the vicinity.
• Site clearance and demolition
– neighbouring properties, preservation orders, trees, demolition
problems and special insurance considerations.
• Ground composition
– General site conditions such as nature of soil, height of water
table, flooding risks, tidal waters
Knowledge of the site
Knowledge from local authority (planning, highways,
building departments)
◦ Permission to develop
◦ To ascertain the viability of the proposal
◦ Access roads and facilities are adequate
◦ Proposed alteration and improvement are acceptable
◦ Follow outline approval
◦ Detail planning application is necessary
Site Work and setting out
Task of preparing for and setting out the building can
be grouped under three headings
◦ Clearing the site
◦ May involve demolition of existing building, grubbing out bushes and
trees, removal of soil
• Site Activities
• Efficiency
• Facilities & Accommodation
Planning Site Layouts
Site Activities
• The time needed for carrying out the principal activities can be estimated
i. the data obtained previously for preparing the material
e.g. rate of placing concrete will be determined by the output of the mixer
ii. labour requirements
e.g. speed of transporting the mix to the appropriate positions.
• Alternatives which can be considered are:
– More than one mixer, regulated supply of ready mix concrete or on large
contracts, pumping the concrete to the placing position
• All alternatives methods for any activity will give different requirements for
staff numbers, material storage, access facilities and possibly plant types and
numbers
Planning Site Layouts
Efficiency
• To achieve maximum efficiency the site layout must aim at
maintaining the desired output of the planned activities. This
will depend largely upon the following factors:
• Avoidance, as far as practicable of double handling materials
• Walking distance are kept to a minimum to reduce the non productive
time spent in covering the distance between working, rest and storage
areas
Planning Site Layouts
Efficiency (Cont…)
• Avoidance of loss by the elements
– provide adequate protection for unfixed material on site, thereby
preventing time loss and cost of replacing damage materials
– Proper store keeping arrangements to ensure that the materials are of
the correct type, in the correct quantity and are available when
required
Efficiency (Cont…)
◦ Avoidance of loss by theft and vandalism
– provide security arrangements by having adequate hoardings and
fences.
◦ Avoidance of loss due to pilfering by site staff
– provide adequate system of stores’ requisition and material checking
procedures
◦ Minimising on-site traffic congestion
– plan delivery arrivals,
– provide adequate parking facilities for staff cars and mobile machinery
when not in use,
– provide sufficient turning circle room for the type of delivery vehicles
likely to enter site
Planning Site Layouts
Facilities & Accommodation
The main contractor is obliged to provide a safe, healthy
place of work and safe system of work, plant and equipment
which are not a risk to health:
• A safe place of work
• Safe access and egress from place of work
• Safe system of work
• Safe items of plant and equipment
• Suitable and adequate training, supervision and instruction in the use
of equipment
• Suitable and appropriate PPE
• Material and substances which are safe to use
Planning Site Layouts
Facilities & Accommodation
Apart from legislative necessities, the main area of concern will
be sizing, equipping and assigned a location to the various units
of accommodations such as:
• Mess Hut
• Toilets
• First aid rooms
• Offices – Contractor’s supervisory staff, Clerk of work, Reception of
material or security
• Lock up store
• Storage compound for major materials
• Timber store and formwork fabrication area
• Reinforcement store and fabrication area
• Scaffold store
Planning Site Layouts
Facilities & Accommodation (Cont…)
2. Type of operations
• New work or restoration.
3. Construction method
• Prefabricated or on site work.
4. Time allowed
• Contract period and finishing date.
.
SELECTION
5. Staff availability
• Competent person to select type of plant
• Plant operator must be a trained man
• Trained person for maintenance and schedule for the
plant maintenance must be followed.
SELECTION
6. Soil conditions
• Wet sites require plant with caterpillar
tracks
• Dry sites are suitable for track and
wheeled vehicles.
7. Access to site
• Congested town sites limit use of many
types of machineries and plant
• Allowable weight and height of
machineries to be transported to site.
SELECTION
8. Safety
• Governed by law eg Health and Safety at work
• Construction regulations
9. Noise emission
• Under health and safety at work provision is
made for the protection of workers against noise
• Local authority requirements
• The type of machineries prohibited
• Hours during which works may be carried out
• Level of noise permitted during specific hours.
DECISION ON BUYING
OR HIRING
• Advantage of buying
• Plant is available when required
• Cost of idle time caused by inclement weather, work being behind planned
programme or delay in deliveries of material will generally be less on owned plant
than hired
• Builders can apportion the plant costs to the various contracts using the plant.
DECISION ON BUYING
OR HIRING
Bulldozer Earth movers and other heavy equipment help to speed not
only earth work but also materials handling, demolition, and
Tractor construction.
Slung scaffold
Building
Foundations
Foundation systems
• The foundation system for a building is the critical link in the
transmission of building loads down to the ground.
Function
• Transfer loads to under layer ground
BUILDING DESIGN
FOUNDATION TYPES
1 SETTLING
2 WATER
3 FROST
SETTLING
• As a building bears down on the supporting
soil, some settlement is to be expected.
• A properly designed and constructed
foundation system should minimize
settlement Uneven or "differential" settlement
that can cause a building to shift out of plumb
causing cracks in the foundation, structure, or
finish.
• Extreme differential settlement can lead to
failure of a building's structural integrity.
• The cause of settlement is typically due to a
reduction in the volume of air voids in the soil.
WATER
• Ground water can create lateral pressure (called
Equivalent Fluid Pressure) and can penetrate
foundation walls and ground slabs below grade,
especially if they lie below the water table.
• In cohesive soles, ground water may rise through
capillary action and penetrate a building's ground
slab.
• Granular base materials and vapor barriers are
used to control capillary action.
• Dewatering a foundation site is often required
prior to beginning construction.
Factors for Foundation Design
Having ascertained the nature and bearing capacity of the
subsoil, the width of the foundation can be determined by one of
the following methods:
For example, if the total load is 40 kN/m and the subsoil safe
bearing capacity is 80 kN/m2, then the foundation width is: = 0.5
m or 500 mm
SOIL
LOAD COST CONDITION TECHNOLOGY
Factors for Foundation Design
LIVE LOAD/VARIABLE
ACTION
DEAD LOAD/PERMANENT
ACTION WIND LOAD
LOAD
Factors for Foundation Design
COST
Factors for Foundation Design
CHEMICAL CONTENT
SOIL
CONDITION
Factors for Foundation Design
TECHNOLOGY
Foundation types
SHALLOW DEEP
Combined Footings
Isolated
• constructed for two or more columns
when they are close to each other and
their foundations overlap
TIMBER + CONCRETE
DRIVEN
IN SITU
ROTARY
BORED
Type of Piles
JETTING
HAMMERED
Pile materials
Pile Foundation – load transfer
Friction pile End-bearing pile
Good bearing
capacity layer
Pile Testing
• To make sure the
design load for the pile
is sufficient
• Normally, minimum
number of testing is
one.
• Best position of pile will
be selected to be tested
• Load will be imposed
onto the pile for at least
50% or more from the
actual load
• The total load will be
remained impose onto
the pile for 24 hours
SEAA 3123
BUILDING ELEMENTS
1
BUILDING ELEMENTS
3 ROOF
4 CEILING
1 FLOOR
5
EXTERNAL 2 WALL
WORKS
<a href='https://www.freepik.com/vectors/city'>City vector created by freepik - www.freepik.com</a>
2
FLOOR
<a href='https://www.freepik.com/vectors/background'>Background vector created by vectorpocket - www.freepik.com</a>
3
FLOOR: CONTENT
FUNCTION
Strength and Stability
Durability
Fire Protection
Sound Insulation
Thermal Insulation FINISHES
Under floor Services Hard flooring
Soft flooring
• Various use of the building should be
Floor function taken account in the design work of
floor
• The main important function of all
the type of floor is that throughout
its life time, it should safely support
the loads placed on it and could
maintained its strength and stability
Strength • The load of floor is made up of:
• Dead load or “self-weight” of the floor
(including the weights of the various
and materials used in the construction of
the floor)
stability
• Superimposed load (weight of building
users, plus their belongings such as
furniture, equipment, or machinery)
5
• Generally, water tight ground
Floor function floors on solid base and
suspended floors secured by walls
and roof must be durable for the
life of the structure and require
slight maintenance, repair or
improvement.
• Durability and free from
maintenance of floors are rely on
the nature of materials applied
and the wear they are exposed to.
• The material used must have a
Durability reasonable life to avoid premature
replacement with resultant extra
cost and inconvenience
6
• An adequate degree of fire
Floor function resistance is required by a floor,
especially relates mainly to
multistory block of flat, and in
building where parts are in
different ownerships, where there
are many occupants or where
large quantities of combustible
goods are stored.
Fire • Large building usually are split by
Protection floor (compartment) to limit the
spread of fire.
7
• In multi- story buildings it is sometimes
Floor function necessary to limit the amount of impact
noise transmitted through a floor to
rooms below. e.g. hotels and apartment
buildings.
• Sound transmission may be either
caused by direct impact or by airborne.
• Impact sound transmission occurs only
downwards generated by footsteps
and/or machinery. It is transmitted as
structure-borne vibration. Through
8
• In some situation, it is important
Floor function that a floor should function in
such a way as to prevent loss or
gain of heat to the room above or
below it.
• There has various type of
controlling the thermal in the
building such electrically warmed
floor, radiant floor heating - dry
Thermal system hydronic and hot-water
heated floor.
insulation
9
• Floors are frequently used for the
Floor function distribution of electrical and
communications wiring -
especially in areas that are wide
and have few fixed partitions.
• If the needs for electrical and
telephone services are minimal
Under
and predictable, an economical
solution to the horizontal
distribution of these services is for
floor wiring in conventional conduits of
metal tubing that are cast into in-
services situ concrete floor slabs (or
screeds - where pre-cast slabs are
used).
10
Under floor
services
However, in most
commercial buildings
greater flexibility is
required to
accommodate wiring
changes that will occur
through the life of the
building.
There are several
alternative systems for
creating this flexibility:
• cellular raceways
• poke-through
systems
• raised access flooring
• under-carpet wiring
11
Pre cast hollow
Composite
Ground floor
Beam and Block
Upper floor
Pre cast
Suspended concrete
timber
POWERPOINT
TEMPLATE
Partial access
Solid ground
Hollow block
Full access and waffle
Raised access
Types of floors
Floor finishes
Like other interior finish components, floor finishes must also be selected with the
following in mind: combustibility, fire resistance ratings and the structural loads they
will place on the building. The finishing materials must be designed to deal with: skid
resistance, sanitation, noise reduction between floors and electrical conductivity.
15
WALL: CONTENT
CLASSIFICATION
Load bearing
Non Load bearing
MATERIAL
Timber
Block
Brick
Curtain wall
Pre cast panel
FUNCTION Metal/Alloys
Internal influences
External influences
Functional requirement
Internal Influences on the wall
• Radiation or conduction
19
Wall classification
20
Load Bearing Walls
Load
bearing
wall
Non load bearing
wall
01
TIMBER
02 03
BRICK BLOCK
WALL
MATERIAL
CURTAIN
METAL/
WALL
ALLOYS
04 PRECAST 05
PANEL
06
ROOF
27
Is necessary in order to provide a
STRUCTURAL means of support for the roof
covering
STABILITY The roof structure or framework
must be of adequate strength to
carry its own weight together with
the loads of wind, snow and foot
Joint deflect
traffic.
span too great
The strength of a roof depends on
the characteristic of the materials
from which it constructed and the
way they put together in the form
of a flat platform or some form of
triangulated frame.
Must take into account the span of
structural members. If the span of a
joist or other structural member is
too great, it will bend
28
GOOD The roof might be a major visual
element in the design of a
APPEARANCE building.
30
The degree of sound insulation offered
SOUND by roofs of domestic building is usually
adequate to reduce external noise ( such
INSULATION as aircraft ) to an acceptable level
31
A roof could contribute to the
spread of fire either: FIRE
Within a building
PROTECTION
Some factory roofs consist of a
covering material, separated by an
air space from a layer of insulation From one building to another
material. Fires within such
buildings could spread through Roof constructions are
the air space causing burning designated with two letter A
pieces of insulation material to fall
elsewhere in the building. (good) to D (poor) in
Measure design to combat this accordance British Standard
problem include : Test (BS 476: PART 3: 1958)
• Using non-combustible
insulation material • To resistance to external
• Restricting the area of air gap penetration from fire.
• Fixing the insulation in such a • To resistance to spread of
way that no air gap exists
flame over the outer
32
Pitched roof
DRAINAGE During heavy storms, large
SYSTEM quantities of water fall on a roof.
Water falling down the surface of
a pitched roof is collected at the
lower end in a gutter.
Flat roof
Flat roofs are designed and built
to slope slightly in one direction.
This slope is known as the ‘Fall” of
a roof. At the lower end of the fall,
a gutter and down pipe
33
ROOFING STYLE….
34
MANSARD
A couple planed hip roof.
HIP ON GABLE
A partial hip applied to the peak of gable roof
SHED
A roof that starts at the eaves of the existing
roof and continues at a lower pitch
GABLE
Two pitch roof, back to back,forming a
35
rectangular roof.
GAMBREL ROOF
A gable type roof with breaks in the
planes
PYRAMID
A hip roof built on a square base with
eaves of the same length
37
Cross Gable
This is like the gable roof, but has two parts that cross.
38
Flat
A flat roof is exactly that - flat. It is easy to build and uses
few materials.
39
Mansard
A French gable roof. The difference is that the mansard has a
flat area at the top instead of being perfectly triangular.
These are common in French Chateau houses and Second
Empire style houses.
40
Hipped
A low-pitched roof that Cross Hipped
allows rain and snow to Similar to a hipped
run off easily, the hipped roof, but this roof
roof also allows for large has two parts that
eaves on a building. cross .
41
Pyramidal
A hipped roof that forms a pyramid shape.
42
Barrel vault
Barrel vault are commonly installed in commercial and
industrial buildings as well as large public buildings such as
hall and factory.
43
Shed
Similar to a gable roof, as it allows rain and snow to run
off easily. This is one of the easiest roofs to build.
44
Saltbox
Similar to a gable roof, but the two sides of
it are not symmetrical.
Gambrel
This roof looks more bell-like than triangular when viewed from the
side. It is like a flattened gable roof. Many farms have gambrel
roofs.
45
Roof Classification
46
SIM ROOF
47
CEILING
48
Content
49
FUNCTIONS OF CEILINGS
• They help control the diffusion of light and sound about a room
50
FUNCTIONS OF CEILINGS
Ceilings are frequently used to The visual impact of ceilings is
distribute: influenced by the following
• conditioned air aspects:
• artificial light • colour
• electrical energy
• texture
• water supply
• water supply for sprinkler systems • pattern
• water waste disposal • shape
• communications wiring
• Sound insulation
51
Suspended
Tightly
Ceilings
Attached
Ceilings
Exposed POWERPOINT
Structural and
Mechanical TEMPLATE
Interstitial
Components Ceilings
Types of ceiling
EXTERNAL WORKS
54
CONTENT
01 DRAINAGE
ROADS AND
02 PAVINGS
04 FENCING - SECURITY
Examples of External Works
56
Drainage
57
Principles of Good Drainage
58
Surface Water Drainage
Struts at 3 meters
centers
Rubble walling
Rubble-pitching drain
60
Sewage Drainage
Pipes:
• Choice of pipes: most common is clay and concrete
• Size of pipe: design calculation
• Pipe bedding – design of correct bedding for pipe is
necessary before construction:
Bearing capacity of ground
superimposed load
61
Pipe laying
62
Manholes
63
Manhole construction for sewage
64
Roads and Pavings
65
Road Junctions
66
Terminations
67
Road layout
• Considerations:
• Width of road according to traffic flow
• Major layout problem at junctions and terminations of cul-de-sac roads
• Triangulated sight lines – to provide clear view of approaching vehicles
• Suitable radius to manoeuvre – governed by vehicle types
• At cul-de-sac planned to allow vehicles to turn round
68
Road Joint Details
69
Road Joint Details
70
Rigid pavement
71
Rigid pavement
Advantages:
• Properly constructed rigid pavement can give a long and
maintenance-free surface
• It can be used on weaker subgrades due to its own strength
72
Rigid pavement
Disadvantage:
• It tends to crack and break up easily with any settlement of support
• Ingress of water cannot drain through the layers
• Repairs are more difficult than flexible pavement therefore more
costly
73
Flexible Pavement
74
Flexible pavement
75
Flexible pavement
Advantages:
• Easier to lay
• Able to deflect without cracking
• Top layer is virtually water-proof to protect the remainder layers
below from the effects of water and frost
• Patching and total replacement is easy
• Cheaper to construct
76
Flexible pavement
Disadvantages:
• The surface tend to wear more quickly than rigid surface
• Once punctured can peel off from next layer
• Require more maintenance
• Surface polishing by moving vehicles creating skidding problem
77
Road Construction
78
Road Construction
• surfacing only to be
applied lastly after the
completion of other
construction
79
Details of a Carriageway and Footway
80
Road Gully
• Means of connection to
drainage system
• Situated along the road
at intervals
81
Road Gully
82
Service Trench Detail
83
Site Protection and Reinstatement
84